PHASE ONE, PART FOUR: MOVING THE DEPOT APRIL 2015 Remington Historic Freight Depot Project

Transcript of Remington Historic Freight Depot · Final preparations are made at the depot’s new site,...

Page 1: Remington Historic Freight Depot · Final preparations are made at the depot’s new site, including a gravel base between the piers. Freight Depot Preparation April 28, 2015 Ready

PHASE ONE, PART FOUR:

MOVING

THE DEPOT

APRIL 2015

Remington Historic Freight Depot Project

Page 2: Remington Historic Freight Depot · Final preparations are made at the depot’s new site, including a gravel base between the piers. Freight Depot Preparation April 28, 2015 Ready

Remington Historic Freight Depot

April 27, 2015 Ayers House Movers of Fredericksburg completes the process of supporting the building with a network of steel beams. Jason Ayers checks a small shim.

Page 3: Remington Historic Freight Depot · Final preparations are made at the depot’s new site, including a gravel base between the piers. Freight Depot Preparation April 28, 2015 Ready

Freight Depot Depot Move April 27, 2015

Final preparations are made at the depot’s new site, including a gravel base between the piers.

Page 4: Remington Historic Freight Depot · Final preparations are made at the depot’s new site, including a gravel base between the piers. Freight Depot Preparation April 28, 2015 Ready

Freight Depot Preparation

April 28, 2015

Ready to go!

Page 5: Remington Historic Freight Depot · Final preparations are made at the depot’s new site, including a gravel base between the piers. Freight Depot Preparation April 28, 2015 Ready

Freight Depot Move April 29, 2015

The depot rolls across Main Street, Remington, driven by Jason Ayers (in yellow safety vest) using a remote control.

Page 6: Remington Historic Freight Depot · Final preparations are made at the depot’s new site, including a gravel base between the piers. Freight Depot Preparation April 28, 2015 Ready

Freight Depot Move April 29, 2015

The building clears Main Street, but must pause to allow safe passage of a Norfolk Southern freight train.

Page 7: Remington Historic Freight Depot · Final preparations are made at the depot’s new site, including a gravel base between the piers. Freight Depot Preparation April 28, 2015 Ready

Freight Depot Move April 29, 2015

Ready to turn and cross the spur track, leaving Norfolk Southern’s right-of-way for good.

Page 8: Remington Historic Freight Depot · Final preparations are made at the depot’s new site, including a gravel base between the piers. Freight Depot Preparation April 28, 2015 Ready

Freight Depot Move April 29, 2015

Crossing the spur tracks with the wheels rolling over steel plates.

Once off the right-of-way, the depot travels across a back yard.

Page 9: Remington Historic Freight Depot · Final preparations are made at the depot’s new site, including a gravel base between the piers. Freight Depot Preparation April 28, 2015 Ready

Freight Depot Move April 29, 2015

After the back yard, the Groves Hardware lumberyard is navigated through.

Page 10: Remington Historic Freight Depot · Final preparations are made at the depot’s new site, including a gravel base between the piers. Freight Depot Preparation April 28, 2015 Ready

Freight Depot Move April 29, 2015

Crossing the ditch, which was temporarily filled with steel beams.

We wish to thank Bryan Hughey, Carl Faller, and Paul Groves for allowing the freight depot to cross their respective properties.

To be continued...