REDUCING PROJECT COSTS THROUGH EFFECTIVE
CONSTRUCTABILITY REVIEWS
REDUCING PROJECT COSTS THROUGH EFFECTIVE
CONSTRUCTABILITY REVIEWS
A Pre-Construction Best Management Practice
Presenters:Troy Pyles, PE, Project DirectorJim Barger, Deputy Director of Review ServicesVanir Construction Management, Inc.
NWCCC Conference - November 8, 2006
![Page 2: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/2.jpg)
Vanir Construction Management Inc. 2
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Experience has shown that the ability to reduce project cost is much greater early in the life of a project
• Much of the opportunity is past once the project is out for bid.
• Constructability review during the design phase is a key to project success.
OVERVIEW
![Page 3: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/3.jpg)
Vanir Construction Management Inc. 3
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
![Page 4: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/4.jpg)
Vanir Construction Management Inc. 4
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• A structured review of the project and design documents to ensure:– Feasibility of construction– Design as represented in the plans and
specifications is biddable and constructible
WHAT IS A CONSTRUCTABILITY REVIEW?
![Page 5: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/5.jpg)
Vanir Construction Management Inc. 5
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Site Constraints– Access– Lay down areas– Availability of
utilities– Height restrictions
TWO TYPES OF REVIEWS
• Schedule Constraints– Duration– Allowable work hours– Sequencing– Time of year– Weather impacts
Feasibility Review – Early In Design
![Page 6: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/6.jpg)
Vanir Construction Management Inc. 6
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Resource Constraints– Materials– Labor– Equipment
TWO TYPES OF REVIEWS
Feasibility Review (cont.)
![Page 7: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/7.jpg)
Vanir Construction Management Inc. 7
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Bidable & Buildable• Looking for
– errors – omissions – ambiguities – conflicts
• Coordination
Detailed Document Review – Later In Design
TWO TYPES OF REVIEWS
• Complete instructions• Inclusion of:
– Permit requirements– Geotechnical study
recommendations– LEED analysis– Hazmat report
Sometimes referred to as a Bidability Review
![Page 8: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/8.jpg)
Vanir Construction Management Inc. 8
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Constructability Review– Looks at how the design is represented to the contractor– Is the contractor provided complete and unambiguous
instructions on what to build?
CLARIFICATION
• Design / Peer Review– Looks at the design per se– Is the design correct per engineering, architectural,
regulatory, and code standards & requirements?
• Coordination Review– Coordination of disciplines only
![Page 9: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/9.jpg)
Vanir Construction Management Inc. 9
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
A design is a unique, one time endeavor requiring scores of individuals making hundreds of decisions on thousands of building components. It does not have the benefit of product testing. A perfect design will not result.
A third party review will help!
WHY DO CONSTRUCTABILITY REVIEWS?
![Page 10: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/10.jpg)
Vanir Construction Management Inc. 10
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
WHY DO CONSTRUCTABILITY REVIEWS?
![Page 11: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/11.jpg)
Vanir Construction Management Inc. 11
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
WHY DO CONSTRUCTABILITY REVIEWS?
![Page 12: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/12.jpg)
Vanir Construction Management Inc. 12
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
Primary Benefits
• Reduces RFIs• Reduces change orders• Reduces likelihood of impact claims• Reduces impossible and impracticable
requirements
WHY DO CONSTRUCTABILITY REVIEWS?
Savings = $6 to $27 for each $1 invested in the review
![Page 13: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/13.jpg)
Vanir Construction Management Inc. 13
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
Primary Benefits (cont.)
• Cleaner contract documents =– More attractive project– More bids– Lower bids – less contingency
WHY DO CONSTRUCTABILITY REVIEWS?
More Savings!!
![Page 14: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/14.jpg)
Vanir Construction Management Inc. 14
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
Side Benefits• Less RFIs and Changes =
– More management on construction– Better relationships– Better attitudes
• Better quality• Better schedules• VE suggestions
WHY DO CONSTRUCTABILITY REVIEWS?
![Page 15: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/15.jpg)
Vanir Construction Management Inc. 15
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
REVIEW FORMATS
• Workshop– Better for VE– May catch big issues
• Independent Study– More detailed– Will find more issues
![Page 16: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/16.jpg)
Vanir Construction Management Inc. 16
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Compile documents• Team orientation• Site visit• Document review• A/E Review and Respond• Reconciliation Meeting• Back Check• Final Report
REVIEW PROCESS
![Page 17: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/17.jpg)
Vanir Construction Management Inc. 17
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Three sizes of generators• Leland Stanford’s tree• Overhead power line interference• Backflow preventer• Wrong soil elevation• Conflicting permits
EXAMPLE CONSTRUCTABILITY ISSUES
![Page 18: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/18.jpg)
Vanir Construction Management Inc. 18
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Civil pad elevations• Civil utility plans/plumbing site plans• Civil utility plans/landscape plans• Structural beams/HVAC ducts• Structural top of steel elevations• Structural/architectural• Gridlines & dimensions
EXAMPLE CONSTRUCTABILITY ISSUES
![Page 19: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/19.jpg)
Vanir Construction Management Inc. 19
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Site visit critical– As-builts poor– Designer & constructor perspectives differ
• Say it once – Say it right• Need to budget & schedule the review• Don’t hide the results
LESSONS LEARNED
![Page 20: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/20.jpg)
Vanir Construction Management Inc. 20
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Back check to get maximum value• Need qualified reviewers• Need a developed Review Methodology• Review with “eyes of a contractor”• Review team needs all disciplines
LESSONS LEARNED (con’t)
![Page 21: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/21.jpg)
Vanir Construction Management Inc. 21
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Benefits designer• Quality of documents is decreasing
– Less principal involvement– Cut and paste details– Workload too high
• There is no industry standard definition of “constructability review”
LESSONS LEARNED (con’t)
![Page 22: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/22.jpg)
Vanir Construction Management Inc. 22
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Why do a constructability review? I’m already paying the designer for good plans and specs.
FAQs
![Page 23: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/23.jpg)
Vanir Construction Management Inc. 23
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Should owner pay to have the designer make the corrections?
FAQs
![Page 24: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/24.jpg)
Vanir Construction Management Inc. 24
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• How much does a constructability review cost?
FAQs
![Page 25: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/25.jpg)
Vanir Construction Management Inc. 25
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• How long does a constructability review take?
FAQs
![Page 26: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/26.jpg)
Vanir Construction Management Inc. 26
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Can’t you just do a quick review and find all the big problems?
FAQs
![Page 27: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/27.jpg)
Vanir Construction Management Inc. 27
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• When is the best time to do a review?FAQs
![Page 28: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/28.jpg)
Vanir Construction Management Inc. 28
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Our change order rate is only 10%, so why should we do constructability reviews?
FAQs
![Page 29: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/29.jpg)
Vanir Construction Management Inc. 29
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• Do you spell it “constructability” or “constructibility”?
FAQs
![Page 30: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/30.jpg)
Vanir Construction Management Inc. 30
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews
• While there will never be a perfect set of plans and specs, a constructability review will help improve the quality.
• A constructability review should be viewed as an investment, not an expense.
CONCLUSIONS
![Page 31: REDUCING PROJECT COSTS THROUGH EFFECTIVE CONSTRUCTABILITY ... · Vanir Construction Management Inc. 2 Reducing Project Costs Through Effective Constructability Reviews •Experience](https://reader035.fdocuments.in/reader035/viewer/2022062908/5aed318d7f8b9ab24d9117ed/html5/thumbnails/31.jpg)
Vanir Construction Management Inc. 31
Reducing Project Costs Through Effective Constructability ReviewsReducing Project Costs Through Effective Constructability Reviews