Redesign of South Bend Airport Rail Connection › files › library ›...
Transcript of Redesign of South Bend Airport Rail Connection › files › library ›...
Redesign of South Bend Airport Rail Connection
Timothy MacaskillTuesday, Sept. 11th, 2007, 8:30am
Redesign of South BendAirport Rail Connection
1
Tim Macaskill – Quick background• A little bit more about me
Redesign of South BendAirport Rail Connection
2
Tim Macaskill – Quick background• A little bit more about me
Redesign of South BendAirport Rail Connection
3
Tim Macaskill – Quick background
• A little bit more about me
Redesign of South BendAirport Rail Connection
4
Tim Macaskill – Quick background• A little bit more about me
Redesign of South BendAirport Rail Connection
5
Tim Macaskill – Quick background• I’m “Car free”……….. not “car less”
Redesign of South BendAirport Rail Connection
6
Overview
• Project background• Coordination with all parties• New layout concept and plan and profile production• Simulation of time savings
Redesign of South BendAirport Rail Connection
7
Project Background
• Client: NICTD – Northern Indiana Commuter Transportation District
• Project: South Bend Airport NICTD relocation
• Tasks: • Produce conceptual plan to explore
shorter NICTD routes to the South Bend Airport.
• Produce plan and profile sheets of four proposed alignments.
• Coordinate with adjacent highway projects
• Create RailSim TPC (Train Performance Calculator) simulation runs to compare forecast run times against existing run times.
Redesign of South BendAirport Rail Connection
8
Project Background
Redesign of South BendAirport Rail Connection
9
Project Background
• The benefits of this relocation include:• a reduction in running time by reducing the length of alignment• reducing slow speed zones• elimination of 25 grade crossings, several of which can be hazardous.
Redesign of South BendAirport Rail Connection
10
Coordination with all parties
• Coordination with proposed highway elements• Early goal to build on strong social justice principals
• Cemetery• Adjacent residential structures• Other social / environmental receptors
• Proposed runway extension coordination
Redesign of South BendAirport Rail Connection
11
New layout concept and plan and profile production
Redesign of South BendAirport Rail Connection
12
New layout concept and plan and profile production
A True “Multi-Modal” Facility:
• Commercial passenger air service – 5 providers, 14 gates
• NICTD commuter rail service
• Local bus service – city transit provider
• Regional bus service – charter and daily service to Chicago and O’Hare
• National bus service – Greyhound
• Rental Car service – 6 providers
• Taxi and Limo service – 9 providers
Redesign of South BendAirport Rail Connection
13
New layout concept and plan and profile production
Redesign of South BendAirport Rail Connection
14
New layout concept and plan and profile production
Redesign of South BendAirport Rail Connection
15
New layout concept and plan and profile production
Redesign of South BendAirport Rail Connection
16
New layout concept and plan and profile production
Redesign of South BendAirport Rail Connection
17
Simulation of time savings
• The goal is to produce TPC output the client can:
1. Understand.
2. Utilize in their decision making process.
Redesign of South BendAirport Rail Connection
18
Simulation of time savings
• TPC input: Train and Train Composition.
Redesign of South BendAirport Rail Connection
19
Simulation of time savings
• The path to TPC output.1. Basemap – concepts
typically utilize aerial photo or aerial topo, projects moving to full design typically utilize aerial topo and piecemealed survey at critical points.
2. Narrow alternatives, concept P&P in CAD. Set speeds for alignment based upon geometrics, equipment, crossings, etc.
Redesign of South BendAirport Rail Connection
20
Simulation of time savings
• TPC output: Summary
Redesign of South BendAirport Rail Connection
21
Simulation of time savings
• Utilizing that TPC output.A. Organize the data – raw output is in CSV file format, must be converted into Excel format.B. Interpret the data into something the client can understand.C. Comparison with existing conditions using charts, and or graphics.
Redesign of South BendAirport Rail Connection
22
Summary
• Project background• Coordination with all parties• New layout concept• Simulation of time savings• Plan and profile production
Redesign of South BendAirport Rail Connection
23
Happy to answer any questions
Questions?