RECAPP Facility Evaluation Report - Alberta...Evaluator Name: Tobias Link The building is a single...
Transcript of RECAPP Facility Evaluation Report - Alberta...Evaluator Name: Tobias Link The building is a single...
Report run on: March 12, 2013 11:02 AM
RECAPP Facility Evaluation Report
Centennial Centre - Marion HouseB0636DPonoka
Alberta Health Services-Central
Report run on: March 12, 2013 11:02 AM Page 2 of 22
B0636DBuilding Id:
Centennial Centre - Marion HBuilding Name:
PonokaLocation:46 Street ( South Of HighwayAddress:
986.00Gross Area (sq. m): $5,412,154Replacement Cost:1990Construction Year:
Evaluation Date: December 17 2012
Golder AssociatesEvaluation Company:
Tobias LinkEvaluator Name:
The building is a single storey structure providing accommodation for up to 16 patients of the adjacent Brain InjuryUnit. It was built in 1990 and has an approximate gross floor area (GFA) of 986m². The building is still in its original state and no additions and modifications have been made since its originalconstruction. The building is in overall acceptable condition.
General Summary:
Structural Summary:The building was reported to have cast-in-place (CIP) wall foundation most likely with spread footing and with a standardconcrete slab on grade. The structural frame of the building was reported to be a wood frame construction with wood studs The pitched roof construction was concealed, but has been reported to be constructed of wood joists sheathed withplywood. No actions are anticipated in respect to the building structure within the next five years. The buildings structural systems are in overall acceptable condition.
Envelope Summary:The exterior walls are clad with a masonry brick veneer with some concrete showing on the foundation. The building is provided with partly operable double pane aluminum windows and aluminum shop front doors with asidelight. Some wood exterior doors with glazing are provided on the east and west side. The roof is provided with asphalt shingles and metal rain gutters and downspouts. No actions are anticipated in respect to the envelope within the next five years. The buildings envelope is in overall acceptable condition.
Interior Summary:All rooms and corridors typically are provided with resilient sheet flooring throughout. The only exception are themechanical rooms which are provided with painted concrete floors. All interior walls are wood stud walls with painted drywall sheathing. A suspended T-bar ceiling with acoustic tiles is provided in the hallways and the rest of the building has painted
2.10%5 year Facility Condition Index (FCI):
Facility Details Evaluation Details
Total Maintenance Events Next 5 years: $113,700
Ponoka - Centennial Centre - Marion House (B0636D)
Report run on: March 12, 2013 11:02 AM Page 3 of 22
gypsum board ceilings. No actions are anticipated within the next five years. The buildings interior finishes are in overall acceptable condition.
Mechanical Summary:Stainless steel sinks are provided in the kitchens. The bathrooms are equipped with vitreous china lavatories andwater closets as well as with fibreglass shower enclosures. The domestic water distribution is assumed to be copper and the waste water piping is ABS plastic. Domestic hotwater is provided by three natural gas fired water heaters located in two different mechanical rooms. Heat getssupplied using five natural gas fired furnaces also located in the two mechanical rooms. The sprinkler system was reported to be a dry pipe system. Work is anticipated to be required to the water heaters within 5 years of writing this report. Overall the mechanical systems are in acceptable condition.
Electrical Summary:Electrical service is provided to the Central Distribution Panel (CDP) 2 and 4 located in the Halvar Johnson Centre forBrain Injury (BIU) via buried conductors from the exterior 1000 KVA Transformer 2. Primary power distribution to theMarion House is provided via CDP 2 & 4 located in the BIU electrical room. Secondary distribution is provided by fournormal and four emergency ITE 120/208V 3 Phase 4 Wire electrical panels located in the Marion House electricalroom. Emergency power is supplied to the emergency electrical panels from the backup emergency generator locatedin the BIU mechanical room. Electrical branch wiring in the building is standard copper wire in conduit. Flexible conduit and cable are provided forfinal connections to mechanical equipment. All interior and exterior plug-ins are ground fault circuit interrupter (GFCI)protected. The major of interior lighting throughout the building consists of T-8 fluorescent lamps with electronic ballasts. Otherinterior lighting consist of incandescent hospital supplied lamps provided in the bedrooms. Exterior lighting consist ofwall-mounted high-pressure sodium fixtures around the building perimeter. Emergency lighting is provided by the BIUemergency power generator connected to a portion of the fluorescent lighting throughout the building. Emergency exitsigns are generally LED fixtures throughout. Securitron key-switches are provided in the interior and exterior of the exit doors. A My-Call duress alarm for the long-term care staff is provided with wireless pendants No work is anticipated to be required within 5 years of writing this report. The electrical components are in overall acceptable condition.
Ponoka - Centennial Centre - Marion House (B0636D)
Condition Rating Performance1 - Critical Unsafe, high risk of injury or critical system failure.2 - Poor Does not meet requirements, has significant deficiencies. May have high operating/maintenance costs.
3 - Marginal Meets minimum requirements, has significant deficiencies. May have above average operating maintenance costs.4 - Acceptable Meets present requirements, minor deficiencies. Average operating/maintenance costs.
Rating Guide
5 - Good Meets all present requirements. No deficiencies.6 - Excellent As new/state of the art, meets present and foreseeable requirements.
Report run on: March 12, 2013 11:02 AM Page 4 of 22
A1010 Standard Foundations*
A1030 Slab on Grade*
B1010.02 Structural Interior Walls Supporting Floors (or Roof)*
B1020.01 Roof Structural Frame*
B1020.03 Roof Decks, Slabs, and Sheathing*
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
Rating
1990
1990
1990
1990
1990
Installed
Installed
Installed
Installed
Installed
0
0
0
0
0
Design Life
Design Life
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Updated
Updated
Ponoka - Centennial Centre - Marion House (B0636D)S1 STRUCTURAL
The building is provided with standard cast-in-place (CIP) foundations with spread foootings.
The building is provided with a slab on grade.
The interior load bearing structure is concealed, but has been reported to be a wood framing structure.
The roof construction is concealed, but has been reported to be a wood framing structure.
Roof sheathing concealed, but consists most likely of ply wood sheathing.
Report run on: March 12, 2013 11:02 AM Page 5 of 22
B2010.01.02.01 Brick Masonry: Ext. Wall Skin*
B2010.01.09 Expansion Control: Ext. Wall*
B2010.01.11 Joint Sealers (caulking): Ext. Wall**
B2010.02.05 Wood Framing: Ext. Wall Const.*
B2010.03 Exterior Wall Vapour Retarders, Air Barriers, and Insulation*
B2010.06 Exterior Louvers, Grilles, and Screens*
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
Rating
Rating
1990
1990
1990
1990
1990
1990
Installed
Installed
Installed
Installed
Installed
Installed
0
0
20
0
0
0
Design Life
Design Life
Design Life
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Updated
Updated
Updated
Replace Joint Sealers (~510m)
Lifecycle Replacement 2016 $16,400 Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)S2 ENVELOPE
Event:
Type Year Cost Priority
Updated: MAR-13
The exterior wall skin is constructed of masonry bricks.
Standard expansion control is provided on the exterior wall skin.
Joint sealers are provided on the exterior wall.
The exterior wall construction is concealed, but has been reported to be constructed of wood framing.
Concealed, no issues have been observed and reported.
Louvers are provided on the little roof towers containing the chimneys.
Report run on: March 12, 2013 11:02 AM Page 6 of 22
B2020.01.01.02 Aluminum Windows (Glass & Frame)**
B2030.01.01 Aluminum-Framed Storefronts: Doors**
B2030.01.10 Wood Entrance Door**
B3010.01 Deck Vapour Retarder and Insulation*
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
1990
1990
1990
1990
Installed
Installed
Installed
Installed
40
30
30
0
Design Life
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Updated
Replace Aluminum Windows (~105m²)
Replace Sore Front Doors (4 units)
Replace Wood Doors (4 units)
Lifecycle Replacement
Lifecycle Replacement
Lifecycle Replacement
2030
2020
2020
$110,900
$14,800
$7,800
Unassigned
Unassigned
Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)
Event:
Event:
Event:
Type
Type
Type
Year
Year
Year
Cost
Cost
Cost
Priority
Priority
Priority
Updated:
Updated:
Updated:
MAR-13
MAR-13
MAR-13
Insulated aluminum windows are provided throughout the building.
Aluminum framed storefront doors are provided at the entrances.
Wood doors with glazing are provided on the patio exits.
Concealed, no issues have been observed and reported.
Report run on: March 12, 2013 11:02 AM Page 7 of 22
B3010.02.01.01 Asphalt Shingles**
B3010.08.02 Metal Gutters and Downspouts**
4 - Acceptable
4 - Acceptable
Rating
Rating
2010
1990
Installed
Installed
25
30
Design Life
Design Life
MAR-13
MAR-13
Updated
Updated
Replace Asphalt Shingles (for ~986m² GFA)
Replace Metal Gutters and Downspouts
Lifecycle Replacement
Lifecycle Replacement
2035
2020
$50,800
$6,200
Unassigned
Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
MAR-13
MAR-13
Not visible at time of assessment due to snow coverage.
Metal gutters and downspouts are provided around the building. The installation date of the gutters and downspouts couldnot be confirmed. For the purpose of this report the installation date is to be assumed 1990.
Report run on: March 12, 2013 11:02 AM Page 8 of 22
C1010.01 Interior Fixed Partitions*
C1020.01 Interior Swinging Doors (& Hardware)*
C1020.07 Other Interior Doors*
C1030.01 Visual Display Boards**
C1030.05 Wall and Corner Guards*
C3010.04 Gypsum Board Wall Finishes (Unpainted)*
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
Rating
Rating
1990
1990
1990
1990
1990
1990
Installed
Installed
Installed
Installed
Installed
Installed
0
0
0
20
0
0
Design Life
Design Life
Design Life
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Updated
Updated
Updated
Replace Whiteboards (4 units)
Lifecycle Replacement 2016 $2,000 Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)S3 INTERIOR
Event:
Type Year Cost Priority
Updated: MAR-13
Concealed, but reported to be framed partitions (Studs).
Wood doors in wood frames are provided throughout the building.
Metal utility doors are provided for the mechanical rooms.
White boards are provided in the building.
Painted wood wall and corner guards provided in the hallways.
Gypsum board walls are provided on the interior partitions.
Report run on: March 12, 2013 11:02 AM Page 9 of 22
C3010.06 Tile Wall Finishes**
C3010.11 Interior Wall Painting*
C3020.01.02 Painted Concrete Floor Finishes*
C3020.07 Resilient Flooring**
C3030.04 Gypsum Board Ceiling Finishes (Unpainted)*
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
Rating
1990
1990
1990
1990
1990
Installed
Installed
Installed
Installed
Installed
40
0
0
20
0
Design Life
Design Life
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Updated
Updated
Replace Ceramic Wall Tiles (~30m²)
Replace Resilient Flooring (~900m²)
Lifecycle Replacement
Lifecycle Replacement
2030
2016
$8,200
$79,300
Unassigned
Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
MAR-13
MAR-13
Ceramic wall tiles are provided in the washrooms.
Interior partitions are painted throughout the building.
Painted concrete floors are provided in the mechanical/electrical rooms.
Resilient sheet flooring is provided throughout the building.
Gypsum board ceilings are provided in most parts of the building.
Report run on: March 12, 2013 11:02 AM Page 10 of 22
C3030.06 Acoustic Ceiling Treatment (Susp. T-Bar)**
C3030.07 Interior Ceiling Painting*
4 - Acceptable
4 - Acceptable
Rating
Rating
1990
1990
Installed
Installed
25
0
Design Life
Design Life
MAR-13
MAR-13
Updated
Updated
Replace T-Bar Ceiling (~150m²)
Lifecycle Replacement 2016 $7,700 Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)
Event:
Type Year Cost Priority
Updated: MAR-13
A suspended T-bar system with acoustic tiles is provided for the hallways.
Gypsum board ceilings are painted throughout the building.
Report run on: March 12, 2013 11:02 AM Page 11 of 22
D2010.04 Sinks**
D2010.05 Showers**
4 - Acceptable
4 - Acceptable
Rating
Rating
1990
1990
Installed
Installed
30
30
Design Life
Design Life
MAR-13
MAR-13
Updated
Updated
Replace Kitchen Sinks (2 units)
Replace Service Sink (1 unit)
Replace Fibreglass Showers (4 units)
Lifecycle Replacement
Lifecycle Replacement
Lifecycle Replacement
2020
2020
2020
$3,600
$2,800
$17,700
Unassigned
Unassigned
Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)S4 MECHANICAL
Event:
Event:
Event:
Type
Type
Type
Year
Year
Year
Cost
Cost
Cost
Priority
Priority
Priority
Updated:
Updated:
Updated:
MAR-13
MAR-13
MAR-13
A floor mounted service sink is provided in the janitorial room. The kitchen is provided with stainless steel sinks.
Fibreglass showers are provided in the washrooms.
Report run on: March 12, 2013 11:02 AM Page 12 of 22
D2010.10 Washroom Fixtures (WC, Lav, Urnl)**
D2020.01.01 Pipes and Tubes: Domestic Water*
D2020.01.02 Valves: Domestic Water**
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
1990
1990
1990
Installed
Installed
Installed
35
0
40
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Replace lavatories (2 units)
Replace water closets (4 units)
Replace valves (~12 units)
Lifecycle Replacement
Lifecycle Replacement
Lifecycle Replacement
2025
2025
2030
$4,000
$10,500
$6,000
Unassigned
Unassigned
Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)
Event:
Event:
Event:
Type
Type
Type
Year
Year
Year
Cost
Cost
Cost
Priority
Priority
Priority
Updated:
Updated:
Updated:
MAR-13
MAR-13
MAR-13
Water closets are vitreous floor mounted flush valve units. Lavatories are enamel steel.
Distribution piping is copper throughout the building.
Domestic gate and ball valves are provided on plumbing fixtures.
Report run on: March 12, 2013 11:02 AM Page 13 of 22
D2020.01.03 Piping Specialties (Backflow Preventers)**
D2020.02.06 Domestic Water Heaters** - 1990
D2020.02.06 Domestic Water Heaters** - 2002
D2030.01 Waste and Vent Piping*
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
1990
1990
2002
1990
Installed
Installed
Installed
Installed
20
20
20
0
Design Life
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Updated
Replace Backflow Preventer (1 unit)
Replace Water Heaters (1 unit)
Replace Water Heaters (2 units)
Lifecycle Replacement
Lifecycle Replacement
Lifecycle Replacement
2016
2016
2022
$6,100
$2,200
$4,400
Unassigned
Unassigned
Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)
Event:
Event:
Event:
Type
Type
Type
Year
Year
Year
Cost
Cost
Cost
Priority
Priority
Priority
Updated:
Updated:
Updated:
MAR-13
MAR-13
MAR-13
A backflow preventer is provided ion the water main. The installation date could not be confirmed. For the purpose of thisreport the installation date is to be assumed 1990.
One natural gas fired water heater is provided in the east mechanical room. The capacity is assumed to be 45,000BTU/hr each with a recovery of 37.8G/hr.
Two natural gas fired Bradford White hot water tanks are provided in the west mechanical room. Each tank has acapacity of 45,000 BTU/hr with a recovery rate of 37.8G/hr.
Concealed. Assumed to be ABS plastic.
Report run on: March 12, 2013 11:02 AM Page 14 of 22
D3010.02 Gas Supply Systems*
D3020.03.01 Furnaces**
D3020.03.02 Chimneys (& Comb. Air): Furnace*
D3040.01.04 Ducts: Air Distribution*
D3050.01.03 Packaged Terminal Air Conditioning Units*
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
Rating
1990
2009
1990
1990
1990
Installed
Installed
Installed
Installed
Installed
0
25
0
0
0
Design Life
Design Life
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Updated
Updated
Replace Furnace (5 units)
Lifecycle Replacement 2034 $21,500 Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)
Event:
Type Year Cost Priority
Updated: MAR-13
Concealed, but assumed to be black steel.
Three natural gas fired furnaces in west mechanical room. Two gas fired Lennox (99,000 BTU) furnaces are provided in the east mechanical room.
Galvanized steel chimneys for the furnaces are provided in each mechanical room.
Galvanized ducting is provided throughout the building for air distribution.
One ground mounted outdoor AC unit is provided on the south side of the building. Not accessible at time of assessment,no further information known.
Report run on: March 12, 2013 11:02 AM Page 15 of 22
D3050.03 Humidifiers**
D3060.02.01 Electric and Electronic Controls**
D4010 Sprinklers: Fire Protection*
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
2009
1990
1990
Installed
Installed
Installed
25
30
0
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Replace Humitifiers (5 units)
Replace Electric Controls (for ~986m² GFA)
Lifecycle Replacement
Lifecycle Replacement
2034
2020
$4,500
$3,200
Unassigned
Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
MAR-13
MAR-13
A humidifier is attached to each furnace.
Electronic thermostats are provided throughout the building.
A dry sprinkler system is provided in the building.
Report run on: March 12, 2013 11:02 AM Page 16 of 22
D5010.05 Electrical Branch Circuit Panelboards (Secondary Distribution)**
D5020.01 Electrical Branch Wiring*
D5020.02.01 Lighting Accessories: Interior (Lighting Controls)*
D5020.02.02.01 Interior Incandescent Fixtures*
D5020.02.02.02 Interior Fluorescent Fixtures**
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
Rating
1990
1990
1990
1990
1990
Installed
Installed
Installed
Installed
Installed
30
0
0
0
30
Design Life
Design Life
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Updated
Updated
Replace 8 Secondary Distribution Panels
Replace T8 Fluorescent Lighting. (~800m²/gfa)
Lifecycle Replacement
Lifecycle Replacement
2020
2020
$41,700
$70,000
Unassigned
Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)S5 ELECTRICAL
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
MAR-13
MAR-13
A total of eight, four normal and four emergency, ITE secondary distribution panels are provided throughout the building.All secondary distribution panels are 225 Amps, 120/208 Volts, 3 phase 4-wire at approximately 50% capacity.
Branch wiring is copper in conduit throughout the building.
Line voltage switches provided throughout.
Incandescent light fixtures are provided in approximately 20% of the building installed in various areas.
T-8 fluorescent lighting is provided throughout the majority of the building.
Report run on: March 12, 2013 11:02 AM Page 17 of 22
D5020.02.03.01 Emergency Lighting Built-in*
D5020.02.03.03 Exit Signs*
D5020.03.01.04 Exterior H.P. Sodium Fixtures*
D5020.03.02 Lighting Accessories: Exterior (Lighting Controls)*
D5030.01 Detection and Fire Alarm**
D5030.02.01 Door Answering*
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
Rating
Rating
1990
1990
1990
1990
2003
1990
Installed
Installed
Installed
Installed
Installed
Installed
0
0
0
0
25
0
Design Life
Design Life
Design Life
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Updated
Updated
Updated
Replace Detection and Fire Alarm. (~1000m²/gfa)
Lifecycle Replacement 2028 $23,500 Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)
Event:
Type Year Cost Priority
Updated: MAR-13
It was reported that a portion of the lighting is supported by the emergency generator located in the Halvar JohnsonCentre for Brain Injury building.
Powered LED exit signs are provided throughout the building and at interior and exterior exit doors .
Wall-mounted high pressure sodium light fixtures are provided around the building.
The exterior lighting control is provided by photocell receptor.
Fire detection and alarm is provided throughout the building complete with pull station, audible alarm, strobes, heat andsmoke detectors.
A door answering system monitored by the receptionist is provided at the entrance of the building.
Report run on: March 12, 2013 11:02 AM Page 18 of 22
D5030.02.03 Security Access**
D5030.04.01 Telephone Systems*
D5030.04.03 Call Systems**
D5030.04.04 Data Systems*
D5030.06 Television Systems*
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
Rating
2003
1990
2003
2003
2003
Installed
Installed
Installed
Installed
Installed
25
0
25
0
0
Design Life
Design Life
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Updated
Updated
Replace the Securitron Key-switches (4 Units)
Replace the Duress System (Main Panel and 10Units)
Lifecycle Replacement
Lifecycle Replacement
2028
2028
$2,500
$15,550
Unassigned
Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
MAR-13
MAR-13
Securitron key-switches are provided at the two exit doors.
One pay-phone unit is provided in the building.
A staff duress system by My Call/Verichip is provided throughout the building. It was reported, spare parts are no longeravailable for this system.
Building is wired with CAT 5 throughout.
CATV outlets provided in various areas of the building, including the lounge and limited patient rooms.
Report run on: March 12, 2013 11:02 AM Page 19 of 22
E1090.04 Residential Equipment*
E2010.02 Fixed Casework**
E2010.03.03 Shades*
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
1990
1990
1990
Installed
Installed
Installed
0
35
0
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Replace Fixed Casework (~10m)
Lifecycle Replacement 2025 $8,800 Unassigned
Ponoka - Centennial Centre - Marion House (B0636D)S6 EQUIPMENT, FURNISHINGS AND SPECIAL CONSTRUCTION
Event:
Type Year Cost Priority
Updated: MAR-13
Residential washing machines and dryers as well as kitchen appliances are provided in the building.
Plastic laminate counter tops with wood base and upper cabinetry is provided in the kitchens.
Shades are provided for all windows throughout.
Report run on: March 12, 2013 11:02 AM Page 20 of 22
K4010.01 Barrier Free Route: Parking to Entrance*
K4010.02 Barrier Free Entrances*
K4010.03 Barrier Free Interior Circulation*
4 - Acceptable
3 - Marginal
3 - Marginal
Rating
Rating
Rating
1990
1990
1990
Installed
Installed
Installed
0
0
0
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Install automatic door openers (allowance)
Barrier Free Access Upgrade 2013 $3,500 Medium
The main entry doors are not provided with an automatic dooropener.
Concern:
Install automatic door opener.Recommendation:
Ponoka - Centennial Centre - Marion House (B0636D)S8 SPECIAL ASSESSMENT
Event:
Type Year Cost Priority
Updated: MAR-13
Barrier free parking is not available or achievable for this building.
The main entrance does not meet barrier-free guidelines.
Interior circulation appears to meet barrier-free guidelines.
Report run on: March 12, 2013 11:02 AM Page 21 of 22
K4010.04 Barrier Free Washrooms*
K4030.01 Asbestos*
K4030.04 Mould*
3 - Marginal
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
1990
0
0
Installed
Installed
Installed
0
0
0
Design Life
Design Life
Design Life
MAR-13
MAR-13
MAR-13
Updated
Updated
Updated
Install grab bar and insulate pipes (allowance)
Barrier Free Access Upgrade 2013 $1,200 Medium
The washroom is missing a grab bar directly behind the watercloset and insulation on the exposed piping under thelavatory.
Concern:
Install a proper grab bar and insulate the exposed piping.Recommendation:
Ponoka - Centennial Centre - Marion House (B0636D)
Event:
Type Year Cost Priority
Updated: MAR-13
A barrier-free common washroom is provided in the building. It includes a tilted mirror, one grab bar, adequate turningspace, lever-style faucets, wheel-chair access to the lavatory and a lever style door handle.
No concerns observed or reported. Due to the age of the building (1990) it is possible that some asbestos containing materials (ACMs) are present in thebuilding materials. However, it has been reported that an asbestos survey has been conducted with no findings.
No concerns observed or reported.
Report run on: March 12, 2013 11:02 AM Page 22 of 22
K5010.01 Site Documentation*
K5010.02 Building Documentation*
4 - Acceptable
4 - Acceptable
Rating
Rating
2013
2013
Installed
Installed
0
0
Design Life
Design Life
MAR-13
MAR-13
Updated
Updated
Ponoka - Centennial Centre - Marion House (B0636D)
The prime consultant is Golder Associates Ltd. The evaluation date was December 17th, 2012. Site description: The building is located on the Site of the Centennial Centre south of the town of Ponoka, AB. The Site information isincluded in another report.
The prime consultant is Golder Associates Ltd. The evaluation date was December 17th, 2012. The entire building was evaluated. No building documentation was provided.
Aerial view of the Marion House from Bing Maps. The buildingassessed is denoted by the yellow lines.
Exterior view of the building.