Realtime Utility Engineers - SOQ

18
8417 Excelsior Dr., Madison, WI 53717 Ph: 800-297-1478 608-664-2008 Fax 608-664-2009 www.rue-inc.com S Su u b b s s t t a a t t i i o o n n E En n g g i i n n e e e e r r i i n n g g & Transmission Line Engineering Engineering Tomorrow’s Power - Today

description

Statement of Qualifications for Realtime Utility Engineers

Transcript of Realtime Utility Engineers - SOQ

Page 1: Realtime Utility Engineers - SOQ

8417 Excelsior Dr., Madison, WI 53717 • Ph: 800-297-1478 • 608-664-2008 • Fax 608-664-2009 • www.rue-inc.com

SSuubbssttaattiioonn EEnnggiinneeeerriinngg &&

TTrraannssmmiissssiioonn LLiinnee EEnnggiinneeeerriinngg

EEnnggiinneeeerriinngg TToommoorrrrooww’’ss PPoowweerr -- TTooddaayy

Page 2: Realtime Utility Engineers - SOQ

8417 Excelsior Dr., Madison, WI 53717 • Ph: 800-297-1478 • 608-664-2008 • Fax 608-664-2009 • www.rue-inc.com

SSuubbssttaattiioonn EEnnggiinneeeerriinngg

TTrraannssmmiissssiioonn && DDiissttrriibbuuttiioonn SSuubbssttaattiioonnss

NNeeww SSuubbssttaattiioonnss SSuubbssttaattiioonn EExxppaannssiioonnss

• Substation Engineering Electrical / Physical Design • Protection & Control Engineering • SCADA & Automation Engineering

SSuubbssttaattiioonn DDeessiiggnn EEnnggiinneeeerriinngg Realtime’s experienced substation engineers provide complete electrical and physical pre-design scoping services. To meet the client’s requirements, we prepare an engineering scope-of-work in complete conformance of the highest effective standards. We then follow-up by providing an original design, or adapting one of many proven past designs. Realtime has expertise in upgrading/expanding existing substations of all shapes and sizes. Project types include high voltage transmission substations; distribution substations; switching stations; industrial substations. Extensive experience enables us to work with both complex upgrades/retrofits and standard Greenfield projects.

Page 3: Realtime Utility Engineers - SOQ

8417 Excelsior Dr., Madison, WI 53717 • Ph: 800-297-1478 • 608-664-2008 • Fax 608-664-2009 • www.rue-inc.com

SSuubbssttaattiioonn EEnnggiinneeeerriinngg

TTrraannssmmiissssiioonn && DDiissttrriibbuuttiioonn SSuubbssttaattiioonnss ((ccoonnttiinnuueedd))

PPrree--DDeessiiggnn PPllaannnniinngg

• Project Scope Development • Create Specifications and Schedules • Relay Recommendations • Environmental Assessments and Real Estate Support

DDeessiiggnn

• Civil Design • Station Layout and Site Design • Electrical / Physical Design • Grounding Systems • Conduit and Cable Systems • Control Building Layouts • AC and DC Distribution Systems • Relay and Control Panels • Metering and Instrumentation • SCADA / RTU • Equipment Specifications and Procurement • As-Built Drawings and Documents

“Realtime always have a

quick/correct answer to the

field questions and

concerns… definitely made

our jobs easier. Thanks!”

American Transmission

Company (ATC)

Page 4: Realtime Utility Engineers - SOQ

8417 Excelsior Dr., Madison, WI 53717 • Ph: 800-297-1478 • 608-664-2008 • Fax 608-664-2009 • www.rue-inc.com

TTrraannssmmiissssiioonn LLiinnee EEnnggiinneeeerriinngg

TTrraannssmmiissssiioonn LLiinnee EEnnggiinneeeerriinngg

•• RRaattiinngg AAnnaallyyssiiss ffoorr LLiinnee UUppggrraaddeess •• SSttrruuccttuurraall AAnnaallyyssiiss •• TTrraannssmmiissssiioonn LLiinnee DDeessiiggnn

Realtime’s experienced transmission line engineers provide overhead transmission line design to electric utilities nationwide. Our transmission line engineering staff is comprised of civil and structural engineers, designers, and GIS technicians as well as PLS-CADD experts and a registered land surveyor. Realtime provides utilities with the data and analysis needed to assess existing transmission lines. Realtime has worked on over 10,000 miles of transmission level voltage line projects. From providing rapid survey data collection, to completing final construction drawings, Realtime’s engineers will take a transmission line engineering project from inception to completion. SSttrruuccttuurraall AAnnaallyyssiiss

• Lattice Towers

• Existing Steel Poles

• Wood Frame Structures

• Existing Foundations

• New Foundation Design

“We are pleased with

Realtime’s performance on

our projects. They delivered

on time and were

responsive to requests and

flexible in meeting changing

project requirements” -

NSTAR

Page 5: Realtime Utility Engineers - SOQ

8417 Excelsior Dr., Madison, WI 53717 • Ph: 800-297-1478 • 608-664-2008 • Fax 608-664-2009 • www.rue-inc.com

TTrraannssmmiissssiioonn LLiinnee EEnnggiinneeeerriinngg

RRaattiinngg AAnnaallyyssiiss ffoorr LLiinnee UUppggrraaddeess • Field Surveys & LiDAR Rapid Data Collection • Rating Studies • Existing Line Conditions • Maximum Operating Capacity of the Line • Clearance Violation Reports • Design Alternatives • Structural and Foundation Analysis • Opinion of Probable Cost • Project Schedule • Design Criteria Development

TTrraannssmmiissssiioonn LLiinnee DDeessiiggnn

• Reconductor • Rebuild • New Line Design • Line Optimization • Construction Specifications • Structure Drawings • Material Lists and Procurement Assistance • Plan and Profile Drawings • Field Surveys & LiDAR Rapid Data Collection

DDeessiiggnn SSooffttwwaarree EExxppeerrttiissee • Complete PLS Design Software Suite • MFAD Foundation Design • Microstation • AutoCAD

Page 6: Realtime Utility Engineers - SOQ

8417 Excelsior Dr., Madison, WI 53717 • Ph: 800-297-1478 • 608-664-2008 • Fax 608-664-2009 • www.rue-inc.com

EEnnggiinneeeerriinngg ffoorr WWiinndd EEnneerrggyy

PPrree--CCeerrttiiffiiccaattiioonn EEnnggiinneeeerriinngg

• Facility and Impact Studies • Generation Requests • Power Flow Analysis

PPrree--DDeessiiggnn CCoonnssuullttiinngg SSeerrvviicceess

• Detailed Project-Cost Estimating • Design Engineering Criteria • Detailed Project Schedule

IImmpplleemmeennttaattiioonn EEnnggiinneeeerriinngg

• Substation Design • Collector Systems Design • Transmission Line Design

Page 7: Realtime Utility Engineers - SOQ

8417 Excelsior Dr., Madison, WI 53717 • Ph: 800-297-1478 • 608-664-2008 • Fax 608-664-2009 • www.rue-inc.com

FFiieelldd SSeerrvviicceess

CCoommmmiissssiioonniinngg,, TTeessttiinngg,, MMaaiinntteennaannccee,, aanndd CCoonnssttrruuccttiioonn MMaannaaggeemmeenntt Realtime’s team of experienced Protection Engineers, Senior SCADA Technicians, Senior Relay Technicians, and Relay Technicians provide extensive commissioning, testing and maintenance services for distribution and transmission substations and switchyards. Realtime installs, troubleshoots, and checks out substation SCADA, annunciation, recording, telecommunication and protective relay systems.

RReeaallttiimmee pprroovviiddeess::

• Line Protective Relay Testing • Substation Protective Relay Testing • Current Transformer Testing • Capacitive Coupled Transformer Testing • CT and PT Circuit Checkout • Control Circuit Checkout • Power Line Carrier Tuning • Wave Trap Testing • Satellite Synchronized End-to-End Testing • Relay Simulation to test relays under actual conditions • SCADA / RTU Checkout and Verification • Double Power Factor Testing • SF6 and Oil Circuit Breaker Testing • Upon request, Realtime can also provide: Ground Grid and Earth

Resistivity Testing, Battery and UPS Testing, Transformer Oil Sampling, and Infrared Inspection

Page 8: Realtime Utility Engineers - SOQ

8417 Excelsior Dr., Madison, WI 53717 • Ph: 800-297-1478 • 608-664-2008 • Fax 608-664-2009 • www.rue-inc.com

FFiieelldd SSeerrvviicceess

CCoommmmiissssiioonniinngg,, TTeessttiinngg,, MMaaiinntteennaannccee,, && CCoonnssttrruuccttiioonn MMaannaaggeemmeenntt ((ccoonnttiinnuueedd)) CCoonnssttrruuccttiioonn MMaannaaggeemmeenntt Realtime provides experienced construction management for substation and transmission line upgrades and Greenfield designs. Our expertise includes estimating, budgeting, specifying equipment, creating and implementing master schedules, selecting and coordinating contractors, adhering to all national and local codes, and overseeing all construction. Realtime manages complex, multiple construction projects simultaneously at different locations.

CCoommmmiissssiioonniinngg EEqquuiippmmeenntt::

• Doble 6150 Test Set • ProTest Software • Doble M4100 Insulation Test set and TDR9000 Breaker TIMER • Westinghouse Phase Angle Meter • Fluke Scopemeter and Multimeter • SignalCrafter Model 60, Attenuator, Model 70, Model 110 • Simpson VOM • 100kV DC Hipot • AVO Micro-Ohmeter • Biddlel TTR, 5kV Megger • GE Oil Dielectric Tester, ABB Test Plugs, 240 Volt Variac • 4-20 mA Transducer Calibrator/Tester • SEL 5010, SEL 5601, SEL 5020 Software

Page 9: Realtime Utility Engineers - SOQ

Bass Creek Substation Bass Creek Substation, Janesville, WI Replacement of an existing 69kV Substation Project Scope: Replace an existing (2) line 69kV substation with a 69/138kV substation consisting of (2) 69kV lines, (2) 138kV lines, (1) 100 MVA 69/138kV transformer with oil containment, and a new 24’ X 36’ control building. The existing equipment was removed and the site was re-graded and enlarged. Special environmental consideration was given to an adjacent wetland area and creek. The substation equipment footprint had to be compressed as much as possible and a retention pond installed to capture storm water runoff. Major savings to the client were realized by utilizing spare equipment from various other client substations. This required extra research and confirmation that the used equipment met the requirements of the new substation and in the case of the reused steel structures, was properly modified to fit the new use. Realtime provided all engineering for the substation including; grading, grounding grid, raceways, foundations, steel structures, bus, equipment specification including a 24’ X 36’ control building, and protection and control. Design Completion Date: September 2010 Client: American Transmission Company

Page 10: Realtime Utility Engineers - SOQ

Comerford Substation Comerford Substation, Monroe, NH 230kV Switchyard Revitalization Project Scope: This project included (2) separate project scopes:

• 230kV Switchyard Revitalization • 230kV Disconnect Switch Replacement at TransCanada’s Request.

The Comerford Generation Station is a (4) turbine, 160 MW hydroelectric station, located along the Connecticut River. There are four, two-winding generator step-up transformers which step up the 13.8kV generator output, to supply the 230kV switchyard. Each pair of GSUs are connected to the 230kV bus, via motor operated disconnect switches, to a common breaker position in a breaker and a half arrangement. Engineering, Design, and Construction Support Services Includes:

• Replace all (11) Mineral Oil Dielectric Fluid (MODF) filled and live tank circuit breakers with SF6 breakers.

• Install a new SF6 breaker. • Replace (28) motor-operated disconnect switches. • Install line traps for (5) lines. • Replace dead-end insulators supporting main and cross buses. • Install CCVTs on (3) lines. • Replace CCVT’s on (3) lines. • Design of a new control house incorporating:

Control, relay, and communication equipment required to operate the outdoor switchyard, including provision for Bulk Power Conversion.

Station AC and DC auxiliary services, and standby generator. HVAC. Heat detection system. Primary and emergency lighting system. Operator’s desk.

• Switchyard Grounding: Analyze and modify the existing ground grid design to meet present National Grid standards. Extend the existing ground grid design to connect to the new equipment, control house, and the expanded fence.

• Redesign the fenced area around the control building and new line positions. • Provide material lists and revise cable schedules. • Provide structural and electrical calculations and design.

Design Completion Date: November 2011 Client: National Grid

Page 11: Realtime Utility Engineers - SOQ

Staff Substation Staff Substation, Cambria, WI New Greenfield 138kV Switching Station

Project Scope: Realtime Engineers’ involvement began with finalizing the transmission company’s Facilities Study and Exhibits within the pending generation interconnection agreement. The substation was a greenfield site, ultimately consisting of a ring bus arrangement. It is initially to be operated with (3) 138kV lines, with future expansion to (6) 138kV lines. The station will serve as a system tie between a wind farm and the local utility’s transmission grid. After about two years of planning and design, the new 138kV switchyard is into construction with an in service date of May 2011. Our original scope was to design a three termination straight bus, looping an existing transmission line through the bus and providing a tap to an adjacent wind farm collector station. Around the time of this design’s completion, our scope changed to designing a ring bus arrangement. Realtime expanded the design and completed the design package within schedule to meet the original in service date. Changing gears and incorporating the ring bus design into the construction issue saved the client about $460,000 in overall project cost. Realtime provided all engineering for the switchyard including; grading, grounding grid, raceways, foundations, steel structures, bus, equipment specification including a 24’ X 36’ control building, and protection and control. Realtime also provided the line loop-through scoping, design engineering, procurement support, and construction support for two new 90’ steel corner poles within existing ROW. We closed our work by providing new records for creation of a newly designated line. Some interesting challenges included: Coordinating efforts with the generation owner for a single, common and jointly beneficial ground grid system of the switch station and the collector substation. Also, designing an integrated SCADA communications system that satisfied the requirements of multiple Utility stakeholders. Design Completion Date: March 2011 Client: American Transmission Company Client Commentary: “… this job was done with very little confusion, minor rework, and overall a design job well done. You (Realtime) always have a quick/correct answer to the field questions and concerns… definitely made my job easier than normal. Thanks!”

Page 12: Realtime Utility Engineers - SOQ

500kV - 502 Junction Substation 502 Junction Substation, Mount Morris, PA New Greenfield 500kV Substation Project Scope: Realtime engineered this 500kV greenfield substation, consisting of (4) 500kV lines, designed with future expansion to (6) 500kV lines and future transformation to 138kV. This design required the movement of over 2 million cubic yards of materials, as well as removal of over 80 feet of mountain top, for the ultimate substation layout. Realtime was responsible for the engineering of the (4) line terminal 500kV switchyard, which consisted of (8) 500kV breakers installed in a double breaker-double bus configuration. Space was included for installation of a fifth and sixth 500kV line terminal, also with a double breaker-double bus configuration. The substation was also graded for the future 500/138kV step-down transformation and 138kV facilities. An approximate 40’ x 120’ metal control building was installed to house the substation electrical controls, metering, and communications equipment. The building also houses the 125VDC storage battery and charger, and is climate controlled, complete with well and septic facilities. A 52’ x 32’ maintenance building was designed and installed, as well as a separate 16’ x 24’ emergency generator building. Realtime also engineered a new SCADA system which has been installed. Additional scope included the design of a new family of 500kV steel structures, for use by the client, as standards for future projects. This project invested over three years of planning and design, and the new 500kV switchyard step down Substation for Trans-Allegheny Interstate Line Company (TrAILCo) at 502 Junction is in-service. All substation engineering, except site and grading, were performed by Realtime for 502 Junction. Completion Date: December 2010 Client: Kenny Construction Co. on behalf of TrAILCo and Allegheny Energy

Page 13: Realtime Utility Engineers - SOQ

500/138kV - Meadowbrook Substation Meadowbrook Substation, Winchester, VA Upgrade and Expansion of an Existing 500/138kV Substation Project Scope: Realtime was responsible for engineering design work to accommodate the 500kV substation expansion, (1) 500kV shunt capacitor addition, and the addition of a fourth 500/138kV 392 MVA autotransformer with LTC. Realtime engineered the protection and control design associated with the addition of a fourth 500/138kV 392 MVA autotransformer with LTC. To accommodate the transformer addition, new 138kV breakers were added to the breaker-and-a-half bus arrangement, and (2) 138kV lines were moved to new bus positions. The design included (3) new relay racks, plus extensive modifications to existing relay panels. Wiring diagrams were prepared for the new transformer and breakers. Existing annunciator, DFR, and LTC paralleling schemes were modified to accommodate the additions. Engineering design work to accommodate the 500kV substation expansion included extending (2) 500kV buses, adding (4) 500kV breakers, moving (1) existing 500kV line termination, and terminating (2) new 500kV lines. Realtime’s responsibility included site design, layout, bus design, foundations, steel structures, ground grid, and equipment connections. Protection and control design included new line protection schemes, as well as incorporating the new lines into the existing bus protection and synchronizing schemes. Replacement SCADA and annunciator systems were required for the existing station to accommodate the line and equipment additions. Line OPGW fiber terminations and fiber interconnection panels were also part of Realtime’s responsibilities. Realtime also provided the engineering for (1) 500kV shunt capacitor addition, consisting of a 500kV bus extension, installation of a 500kV motor-operated disconnect switch, and (1) 500kV circuit breaker (with synchronous closing), additional 500kV CVT’s, 500kV reactors, 500kV arresters, and (3) single pole manually-operated grounding switches, (1) 200/F288 MVAR shunt capacitor bank with phase and neutral imbalance detection equipment, yard lighting, and shielding. New control panels were installed in the existing control building, within an area formerly used for material storage. Modifications to the building partition wall were required. Completion Date: December 2010 Client: Kenny Construction Co. on behalf of TrAILCo and Allegheny Energy

Page 14: Realtime Utility Engineers - SOQ

138kV – New Line Route Determination North LaSalle – Fox River; Ottawa – Fox River 138kV – Transmission Line Route Evaluation Realtime evaluated 180 miles of potential Right of Way to define three alternative routes for new 138kV transmission lines for a major mid-western utility. Project Scope: Realtime performed the following tasks to establish routes for two new transmission lines:

• Provided LiDAR Aerial Surveys and video imagery of potential routes • Evaluated data to create route selection criteria • Facilitated the route selection process with the client’s Real Estate and

Transmission Line Engineering groups • Provided on-site field verification of areas of concern for the identified routes • Assisted in the development of design standards for the new line, including

equipment and material specifications • Created property-owner database for Real Estate support and notification of

affected owners • Developed graphics and participated in informational workshops for property

owners and the communities at large • Assisted in providing formal documentation for the filing with the Illinois

Commerce Commission

Design Challenges & Solutions: The 38 miles of new line complete a proposed transmission loop in northern Illinois. The complexity of the project included designing multiple corridors through both rural and urban areas. Realtime’s application of evaluation criteria led to the selection of a preferred route. Additionally, Realtime coordinated all of the required environmental analysis and utilized that data for site selection. Realtime also coordinated design standards unique to the owner. Client: AmerenIP

Page 15: Realtime Utility Engineers - SOQ

138kV- Rated – Transmission Line Relocation Wausau, Wisconsin

U.S. Highway 51 & South 29 Line Relocation A Wisconsin Public Service Corporation 34.5KV distribution line needed to be relocated as a result of a Wisconsin Department of Transportation highway interchange project. Incorporating a future upgrade to 138kV, Realtime engineered five new steel-pole structures to accommodate the newly constructed overpasses. Project Scope: Realtime performed the following tasks:

• Preliminary and final design of the line alignment, structures and foundations • Coordination with the Wisconsin Department of Transportation and

Wisconsin Public Service Corporation • Steel-pole structure design and specifications • Soils investigation specifications and subcontractor coordination • Drilled-pier foundation design and construction specifications • Line construction specification • Construction documentation including PLSCADD files • Field support to construction contractors • Final project close-out

Design Challenges & Solutions: Long transmission line spans and clearance requirements over new highway overpasses lead to custom poles ranging in heights up to 115 feet. Poor soil conditions resulted in deep, large-diameter drilled-pier foundations. Total Constructed Cost Approximately: $2 million Client: Wisconsin Public Service Corporation

Page 16: Realtime Utility Engineers - SOQ

69kV – Manitowoc Public Utilities Transmission Line Relocation 69kV – Line Relocation for Power Plant Expansion Realtime engineering the relocation of a 69kV transmission line at municipal power plant under extremely adverse space constraints. Project Scope: Realtime engineered the following:

• Five new steel poles on foundations • Provided structural analysis • Provided soil borings and surveying • 69kV line was designed to 138kV standards • Realtime provided specifications for all of the new equipment and poles, as well

as, construction specifications for the new line Design Challenges & Solutions: This relocation project involved an already highly congested utility area, which included a complete coal-fired power plant and storm water-sewage treatment plant, bordering Lake Michigan’s shoreline. The design area was squeezed on a prohibitively narrow strip of land, adjoining these two facilities and the lakeshore. Adverse space constraints included maintaining access requirements for semi-truck traffic and railroad traffic in and out of the coal-fired plant on a narrow, tight-fitting strip of land. Design requirements included accommodating for multi-ton loads of coal and material to be driven on soil directly adjacent to the transmission line poles’ foundations. Due to the lakeshore, soil borings and geotechnical requirements were significantly more challenging. As a result of the complexities of the plant expansion, systems coordination between contractors working on the plant build-out, substation re-design, and the additional line requirements necessitated stringent communications among all stakeholders. The combination of designing in a physically congested, high-trafficked area, while meeting aggressive timeframes and budget constraints, allowed Realtime the opportunity to provide valuable design solutions to our client. Total Constructed Cost Approximately: $650,000 Client: Manitowoc Public Utilities

Page 17: Realtime Utility Engineers - SOQ

Representative Client List

Page 18: Realtime Utility Engineers - SOQ

References

FirstEnergy/Allegheny Power Ron Dombrosky, PE Senior Consulting Engineer (724) 838-6481 [email protected] MidAmerican Energy Tom Albertson, PE Manager-High Voltage Engineering (563) 333-8155 [email protected] Northeast Utilities-PSNH Walter Bilynski Project Manager (603) 634-2878 [email protected] WE Energies Jim Prothero Manager-Substation Engineering (414) 221-5071 [email protected] New York Power Authority (NYPA) Gerry Caccavale - Project Manager 123 Main Street White Plains, NY 10601 941-287-3033 [email protected] Ameren Services Jerry Murbarger – Transmission Design Specialist 370 S. Main St. MC C-25 Decatur, IL 62523 217-424-8794 [email protected]