RDR: Goals and Scope
Barry BarishFermilab
RDR Meeting13-Feb-06
ILC Design/Cost WBS
GDE RDR Meeting - Fermilab 2
13-Feb-06
Global Design Effort
– The Mission of the GDE • Produce a design for the ILC that includes a
detailed design concept, performance assessments, reliable international costing, an industrialization plan , siting analysis, as well as detector concepts and scope.
• Coordinate worldwide prioritized proposal driven R & D efforts (to demonstrate and improve the performance, reduce the costs, attain the required reliability, etc.)
GDE RDR Meeting - Fermilab 3
13-Feb-06
The GDE after Six Months
• How have we done?– We are on track – BCD produced by end of 2005
as promised. It will provide a sound basis for entering into a reference design effort, globally coordinate R&D program, begin industrialization, determine costs, etc. next year
• What’s Next?– Undertaking Design/Cost effort toward Reference
Design Report (RDR)– Assessing present R&D program to begin to
provide global guidance in the future.
GDE RDR Meeting - Fermilab 4
13-Feb-06
from my Snowmass Plenary Talk
GDE RDR Meeting - Fermilab 5
13-Feb-06
ICFA FALC
FALC Resource Board
ILCSC
GDEDirectorate
GDEExecutive Committee
GlobalR&D Program
RDR Design Matrix
GDER & D Board
GDEChange Control Board
GDEDesign Cost Board
GDE RDR / R&D Organization
GDE RDR Meeting - Fermilab 6
13-Feb-06
ICFA FALC
FALC Resource Board
ILCSC
GDEDirectorate
GDEExecutive Committee
GlobalR&D Program
RDR Design Matrix
GDER & D Board
GDEChange Control Board
GDEDesign Cost Board
GDE RDR / R&D Organization
Reporting
resourcestechnical
GDE RDR Meeting - Fermilab 7
13-Feb-06
ICFA FALC
FALC Resource Board
ILCSC
GDEDirectorate
GDEExecutive Committee
GlobalR&D Program
RDR Design Matrix
GDER & D Board
GDEChange Control Board
GDEDesign Cost Board
GDE RDR / R&D Organization
GDE
GDE RDR Meeting - Fermilab 8
13-Feb-06
ICFA FALC
FALC Resource Board
ILCSC
GDEDirectorate
GDEExecutive Committee
GlobalR&D Program
RDR Design Matrix
GDER & D Board
GDEChange Control Board
GDEDesign Cost Board
GDE RDR / R&D Organization
ILCDesignEffort
ILCR&D
Program
GDE RDR Meeting - Fermilab 9
13-Feb-06
GDE Structure and Organization
• Executive Committee for Baseline Configuration– GDE Director
• Barish
– Regional Directors • Dugan – Americas • Foster – Europe• Takasaki – Asia
– Accelerator Leaders• Yokoya - Asia• Raubenheimer - Americas• Walker - Europe
• Responsible for overall decisions and guidance of the GDE Program
GDEExecutiveCommittee
GDE RDR Meeting - Fermilab 10
13-Feb-06
GDE Structure and Organization
• GDE Groups– Design / Cost Engineers
• Shidara – Asia
• Bialowons – Europe
• Garbincius – Americas
– Siting, Civil Construction and Infrastructure• Baldy - Europe
• Enomoto – Asia
• Kuchler – Amercas
– Physics / Detectors (WWS chairs)• Brau - Americas
• Richard - Europe
• Yamamoto - Asia
– Accelerator Experts (44 GDE members)
GDE RDR Meeting - Fermilab 11
13-Feb-06
GDE Organizational Evolution for RDR
• Selected additions to the GDE following the BCD completion having needed skills in design, engineering, costing, etc
• Change Control Board– The baseline will be put under configuration control and a
Board with a single chair will be created with needed expertise.
• Design / Cost Board– A GDE Board with single chair will be established to
coordinate the reference design effort, including coordinating the overall model for implementing the baseline ILC, coordinating the design tasks, costing, etc.
• R&D Board– A GDE Board will be created to evaluate, prioritize and
coordinate the R&D program in support of the baseline and alternatives with a single chair
GDE RDR Meeting - Fermilab 12
13-Feb-06
Change Control Board (CCB) Nobu Toge (chair)
• The Change Control Board is responsible for maintaining the baseline configuration as defined in the Baseline Configuration Document. The first action of the CCB will be to finalize the BCD and put it under configuration control. In addition to maintaining the baseline, the CCB will assess R&D projects defined in the BCD that potentially can lead to improvements over the baseline in cost or performance. The CCB will define what needs to be demonstrated in these R&D projects, in order to be considered for a CCB action to replace the baseline.
• The CCB will work with the GDE EC to formalize levels for taking change control actions. Major changes in the baseline defined as changing costs by more than $100M or make significant changes in performance, schedule or risk will be recommended to the Director and GDE EC for final approval. For all other changes, the CCB will be the final authority.
GDE RDR Meeting - Fermilab 13
13-Feb-06
Change Control Board (CCB) Nobu Toge (chair)
Tom Markiewicz US
Shekhar Mishra US
Warren Funk US
Kiyoshi Kubo Asia
Masao Kuriki Asia
Carlo Pagani EU
Grahame Blair EU
Daniel Schulte EU
GDE RDR Meeting - Fermilab 14
13-Feb-06
CCB and the RDR
• The document defining the ILC configuration details at any given time is the BCD. It will evolve through change control actions.
• The RDR will have a different audience, goals and structure. The configuration descriptions in the RDR must be completely consistent with those in the BCD. (Some narrative from the BCD may be appropriate for the RDR, but this is not required).
• The RDR will emphasize the overall design and performance, project issues (costing , siting, etc.) and especially costing.
GDE RDR Meeting - Fermilab 15
13-Feb-06
Design Cost Board (DCB) Peter Garbincius (chair)
• The Design / Cost Board will be responsible for assessing and providing guidance for the overall RDR design effort program. The DCB initial goals will be to propose the overall structure and content for the RDR document to be developed by the end of 2006. It also will provide early guidance required to enable the design / cost effort to get fully underway by the time of the Bangalore GDE meeting.
• The DCB will set goals and milestones for producing the RDR, conduct design reviews and provide guidance and assessments of the RDR effort. The DCB will report to the Director and EC regularly as the design / cost effort progresses, reporting on early evaluations of costs, problems and changes needed in the BCD, etc.
GDE RDR Meeting - Fermilab 16
13-Feb-06
Design Cost Board (DCB) Peter Garbincius (chair)
Nan Phinney US
Ewan Paterson US
Robert Kephart US
Atsushi Enomoto Asia
Tetsuo Shidara Asia
Nobuhiro Terunuma Asia
Wilhelm Bialowons EU
Jean-Pier Delahaye EU
Alex Mueller EU
GDE RDR Meeting - Fermilab 17
13-Feb-06
DCB Board and the RDR
• The DCB is responsible for determining outline of the RDR document
• The DCB is responsible for developing the WBS, the schedules and milestones to achieve the RDR
• The DCB will be responsible to review the progress and results of the design / cost effort for the RDR
GDE RDR Meeting - Fermilab 18
13-Feb-06
The Design and Cost Guidance
• The Accelerator Leaders• Yokoya - Asia
• Raubenheimer - Americas
• Walker – Europe
Provide guidance to the RDR team on acclerator design
• The Design / Cost Leaders• Shidara – Asia
• Bialowons – Europe
• Garbincius – Americas
Provide guidance to the RDR team on costing effort
GDE RDR Meeting - Fermilab 19
13-Feb-06
Parametric Approach• Parametric approach to design
– machine parameters : a space to optimize the machine
– Trial parameter space, being evaluated by subsystems
– machine design : incorporate change without redesign; incorporates value engineering, trade studies at each step to minimize costs
GDE RDR Meeting - Fermilab 20
13-Feb-06
Global R&D Board (RDB) Bill Willis (chair)
• The Global R&D Board will be responsible for assessing and providing guidance for the overall R&D program. The RDB will suggest priorities for the research facilities and R&D supporting the baseline, the R&D on alternatives to the baseline and selective R&D that could further the field in the longer term. The mission will also include global assessments and recommended priorities for the detector R&D program and evaluate the balance between accelerator and detector R&D.
• The RDB will develop a proposal driven program, structured in the sense of defined goals, and milestones, and resources evaluated on a common basis to allow comparison across different regions and national funding systems. It will conduct reviews and identify gaps in coverage of topics, resource or technical issues, duplications, and other concerns..
GDE RDR Meeting - Fermilab 21
13-Feb-06
Global R&D Board (RDB) Bill Willis (chair)
Padamsee US
Himel US
Wolski US
Hayano Asia
Higo Asia
Elsen EU
Lilje EU
Garvey EU
Damerell EU
GDE RDR Meeting - Fermilab 22
13-Feb-06
Approach to ILC R&D Program
• Proposal-driven R&D in support of the baseline design. – Technical developments, demonstration experiments,
industrialization, etc.
• Proposal-driven R&D in support of alternatives to the baseline– Proposals for potential improvements to the baseline,
resources required, time scale, etc.
• Develop a prioritized DETECTOR R&D program aimed at technical developments needed to reach combined design performance goals
GDE RDR Meeting - Fermilab 23
13-Feb-06
GDE Organization for Snowmass
•W
G1
LE
T b
dy
n.
•W
G2
Ma
in L
ina
c
•W
G3
a S
ou
rces
•W
G3
b D
R
•W
G4
BD
S
•W
G5
Ca
vity• GG1 Parameters• GG2 Instrumentation• GG3 Operations & Reliability• GG4 Cost & Engineering• GG5 Conventional Facilities• GG6 Physics Options
Technical sub-systemWorking Groups
Global Group
Provide input
GDE RDR Meeting - Fermilab 24
13-Feb-06
Technical Systems
Vacuum systems
Magnet systems
Cryomodule
Cavity Package
RF Power
Instrumentation
Dumps and Collimators
Accelerator Physics
Global SystemsCommissioning, Operations & Reliability
Control System
Cryogenics
CF&S
Installation
Area Systems
e- e+ damping RTML main BDSsource source rings linac
Cost Roll-ups
GDE RDR Meeting - Fermilab 25
13-Feb-06
GDE Groups
GDE Groups
Design / Cost Engineering
Name Telephone Email
Wilhelm Bialowons +49 40 8998 (9) 3859 (Cell) Send Email
Peter Garbincius + 1 630 840 3693 Send Email
Tetsuo Shidara +81 29-864-1171 ext. 5685 Send Email
Siting, Civil Construction and Infrastructure
Name Telephone Email
Jean-Luc Baldy + 41 22 767 33 02 Send Email
Atsushi Enomoto +81-29-864 5688 Send Email
Vic Kuchler +1 630-840-3643 Send Email
Physics / Detectors
Name Telephone Email
Jim Brau +1 541 346-4766 Send Email
Francois Richard +33 164468463 Send Email
Hitoshi Yamamoto +81 22 795 6724 Send Email
see GDE webpages for all RDR contacts
GDE RDR Meeting - Fermilab 26
13-Feb-06
From Baseline to a RDR
Jan July Dec
2006
Freeze ConfigurationOrganize for RDR
Bangalore
Review Design/Cost Methodology
Review InitialDesign / Cost Review Final
Design / CostRDR Document
Design and Costing ReleaseRDR
Frascati Vancouver Valencia