RDI Status Report: EUP Consortium October 26, 2010

19
RDI Status Report: EUP Consortium October 26, 2010 Steve Brodeur- PMP Nate De Winkle- CAPM

description

RDI Status Report: EUP Consortium October 26, 2010. Steve Brodeur- PMP Nate De Winkle- CAPM . Agenda. Overview Purpose of Project Management What is Collected How information is collected Status Overview Implementation Status Professional Development Status Teacher Survey - PowerPoint PPT Presentation

Transcript of RDI Status Report: EUP Consortium October 26, 2010

Page 1: RDI Status Report: EUP Consortium October 26, 2010

RDI Status Report:EUP Consortium

October 26, 2010

Steve Brodeur- PMPNate De Winkle- CAPM

Page 2: RDI Status Report: EUP Consortium October 26, 2010

Agenda• Overview• Purpose of Project Management• What is Collected • How information is collected• Status Overview

– Implementation Status– Professional Development Status

• Teacher Survey – Introduction and Purpose– Results

• Upcoming Events/Reminders

10/26/2010- RDI EUP Status Report 2

Page 3: RDI Status Report: EUP Consortium October 26, 2010

PM Quote Corner

Project Management is… The art of creating the illusion that any outcome is the result of a series of predetermined, deliberate acts when, in fact, it was dumb luck.

-Harold Kerzner, 1995

10/26/2010- RDI EUP Status Report 3

Page 4: RDI Status Report: EUP Consortium October 26, 2010

PM’s Role• Provide (or help to provide) a clear understanding of

stakeholder expectations• Provide a clear definition of project scope and budget• Track well defined milestones and master schedule• Continually review and update a project plan• Help the leadership team in setting priorities• Maintain project communication• ‘Tell the story of the RDI project.’

10/26/2010- RDI EUP Status Report 4

Page 5: RDI Status Report: EUP Consortium October 26, 2010

What is Collected• Data on Data Warehouse Integration

– Districts Integrated– Schools Integrated – User Accounts Created– Number of users accessing the system in the last month

• Data on Professional Development– Training Sessions Scheduled– Training Sessions Held– Attendees

• Data on Budget– Spend down

10/26/2010- RDI EUP Status Report 5

Page 6: RDI Status Report: EUP Consortium October 26, 2010

How Data Is Collected• Monthly Status Updates

– The Google Form you are asked to complete.

• Surveys– Professional Development Provider Questionnaire– Professional Development Pre-Post Survey

10/26/2010- RDI EUP Status Report 6

Page 7: RDI Status Report: EUP Consortium October 26, 2010

Project Status

10/26/2010- RDI EUP Status Report 7

Page 8: RDI Status Report: EUP Consortium October 26, 2010

EUP Project Status

10/26/2010- RDI EUP Status Report 8

Page 9: RDI Status Report: EUP Consortium October 26, 2010

Status AnalysisData Warehouse

• The numbers indicate progress, Good Work.• However there are reporting inconsistencies:

– Not everyone reports everything all the time:– E.g. the districts integrated number is for Q3 was carried over from Q2

because there should not have been a drop. – E.g. Not every one reports number of schools integrated every

reporting period.

• Please report these numbers consistently so that we can tell the RDI Story

10/26/2010- RDI EUP Status Report 9

Page 10: RDI Status Report: EUP Consortium October 26, 2010

Status AnalysisProfessional Development

• Over the Course of the Grant:– 64 events reported on monthly status reports – 34 PD Provider Surveys Completed

• Please continue to use the surveys for reporting. • For all PD Events we are asking that PD Providers complete

the PD Provider survey.– www.surveymonkey.com/s/rdipdproviders

• For PD funded by RDI, participants need to complete the Before and After Survey.– www.surverymonkey.com/s/pre-postsurvey

10/26/2010- RDI EUP Status Report 10

Page 11: RDI Status Report: EUP Consortium October 26, 2010

Project Evaluation:Why Evaluate

• $11.5 Million ARRA Grant: An evaluation is required.• Ensures progress is adequately tracked and recognized. • Helps make the case for future funding requests around

classroom data use

10/26/2010- RDI EUP Status Report 11

Page 12: RDI Status Report: EUP Consortium October 26, 2010

Project Evaluation:Evaluation Methods

• Project Status reports are used to evaluate implementation.• Surveys are used to evaluate program effectiveness.

– Surveys are divided into 3 levels– Level 1: Statewide Teacher Survey

• Survey: RDI Participant Self-Assessment

– Level 2: PD funded by RDI Grant• Survey: Pre-Post Professional Development Assessment• Survey: RDI Professional Development Provider Survey

– Level 3: Data Related PD not funded by RDI• Survey: RDI Professional Development Provider Survey

10/26/2010- RDI EUP Status Report 12

Page 13: RDI Status Report: EUP Consortium October 26, 2010

Project Evaluation:State-Wide Teacher Survey

• Responsible: RDI Consortium/ISD Leads– RDI Leadership Team will provide an email containing a link the

survey, we ask that you forward it to educators and administrators in your ISD.

• Data Collection Required:– RDI Participant Self-Assessment– Will be sent to teachers 4 times over the course of the grant

• End of June-September 2010• November 2010• February 2011• May 2011

• Teachers will receive .3 SB-CEUs each time they complete a survey . – These will be awarded in time for certificate renewal next year.

10/26/2010- RDI EUP Status Report 13

Page 14: RDI Status Report: EUP Consortium October 26, 2010

Project Evaluation:SB-CEUs

• Goal is to help the state seed the SB-CEU Secure Central Registry.– Seeded with Teacher Name, PIC, Email Address, and School

Association.

• Permission was granted by CEPI to use Data4SS REP file for this purpose.

• This process has already been completed.• The SB-CEUs will be given FREE OF CHARGE.

– For individuals completing the teacher survey.

10/26/2010- RDI EUP Status Report 14

Page 15: RDI Status Report: EUP Consortium October 26, 2010

Project Evaluation:Teacher Survey Results

10/26/2010- RDI EUP Status Report 15

Page 16: RDI Status Report: EUP Consortium October 26, 2010

Project Evaluation:Teacher Survey Results

10/26/2010- RDI EUP Status Report 16

Page 17: RDI Status Report: EUP Consortium October 26, 2010

Teacher Survey:Summary

• Good response given short lead time and process changes• Thank you for all your work• Look for an email detailing the Second opening of the Survey

next week. – Please forward this to your teachers and administrators

• People who did not complete the first survey CAN STILL PARTICIPATE.

10/26/2010- RDI EUP Status Report 17

Page 18: RDI Status Report: EUP Consortium October 26, 2010

Reminders• For all PD Events we are asking that PD Providers complete

the PD Provider survey.• www.surveymonkey.com/s/rdipdproviders • For PD funded by RDI participants need to complete the

Before and After Survey.• www.surverymonkey.com/s/pre-postsurvey • Continue to complete the RDI Status Reports

10/26/2010- RDI EUP Status Report 18

Page 19: RDI Status Report: EUP Consortium October 26, 2010

Reminders• Upcoming events

– 2nd Teacher survey Launches Nov 1. – Status Reports are due Nov. 19– Research project symposium- May 2011

• What information to expect from the project management team– Details on Second Survey Implementation

10/26/2010- RDI EUP Status Report 19