Rate-Tariff Sheets

46
10/01/2021 Rate-Tariff Sheets

Transcript of Rate-Tariff Sheets

Page 1: Rate-Tariff Sheets

10/01/2021

Rate-Tariff Sheets

Page 2: Rate-Tariff Sheets
Page 3: Rate-Tariff Sheets
Page 4: Rate-Tariff Sheets
Page 5: Rate-Tariff Sheets
Page 6: Rate-Tariff Sheets
Page 7: Rate-Tariff Sheets
Page 8: Rate-Tariff Sheets
Page 9: Rate-Tariff Sheets
Page 10: Rate-Tariff Sheets
Page 11: Rate-Tariff Sheets
Page 12: Rate-Tariff Sheets
Page 13: Rate-Tariff Sheets
Page 14: Rate-Tariff Sheets
Page 15: Rate-Tariff Sheets
Page 16: Rate-Tariff Sheets
Page 17: Rate-Tariff Sheets
Page 18: Rate-Tariff Sheets
Page 19: Rate-Tariff Sheets
Page 20: Rate-Tariff Sheets
Page 21: Rate-Tariff Sheets
Page 22: Rate-Tariff Sheets
Page 23: Rate-Tariff Sheets
Page 24: Rate-Tariff Sheets
Page 25: Rate-Tariff Sheets
Page 26: Rate-Tariff Sheets
Page 27: Rate-Tariff Sheets
Page 28: Rate-Tariff Sheets
Page 29: Rate-Tariff Sheets
Page 30: Rate-Tariff Sheets
Page 31: Rate-Tariff Sheets

MISCELLANEOUS CHARGE AMOUNTS Page 2 (Continued from Sheet No. 16.0)

RETURNED CHECKS:

Current Returned Check Table

Check Amount Fee Less than or equal to $50 $25 Greater than $50 but less than or equal to $300 $30 Greater than $300 but less than or equal to $800 $40 Greater than $800 5% of check amount

METER TEST: Each meter test (over once per year)

Third Revised Sheet No. 16.01 Cancels Second Revised Sheet No. 16.01

$ 50.00

UNAUTHORIZED RECONNECT, METER TAMPERING or CURRENT DIVERSION: $250 plus the applicable reconnect fee, plus expenses, plus the estimated cost of lost revenue.

UNDERGROUND DIFFERENTIAL: Members requesting underground electric distribution facilities will pay the calculated differential installed cost between the underground facilities and the suitable overhead facilities.

DORMANT FACILITIES CHARGE: 75% of monthly customer charge for applicable rate schedule payable annually 12 months in advance.

SURGE PROTECTION LEASE PROGRAM: Installation charge (less than 300 amp): Installation charge (300 amp or greater): Monthly service fee :

Service is provided for a minimum of 12 months. $ 25.00 $100.00 $ 5.95

EV CHARGER LEASE PROGRAM: Service is provided for a minimum of3 months. Installation charge: $ 50.00 Monthly service fee : $ 14.50

PAYMENT ARRANGEMENT CHARGE: $5.00 processing fee for all payment arrangements made outside of the Cooperative's Interactive Voice Response system

FEE for EXCESS MONTHLY PAYMENTS ON PREPAID METERING RATE: $3 .00 transaction fee for all payments received in excess of 5 payments during a calendar month.

Effective October I, 2021 Issued by: James P. Duncan, CEO

Page 32: Rate-Tariff Sheets
Page 33: Rate-Tariff Sheets

Third Revised Sheet No.Cancels Second Revised Sheet No.

16. I

16. I

LINE EXTENSION CHARGES

PURPOSE:The purpose of this policy is to define a uniform method by which Contributions In Aid ofConstruction (CIAC) will be computed for member/applicant whose electrical servicerequirements necessitate extension of the Cooperative's distributionfocilities.

POLICY:

A. APPLICABILITY

This policy shall apply to all member/applicants in all rate classifications who request a designof new or revised services or extensions of the Cooperative's distribution facilities after the

ffictive date of this policy.

B. ENGINEERING SERVICE FEE

l. When a member/applicant requests new or revised services, the initial consultation isfree. If the member/applicant then requests a design/layout, on engineering service fee inthe amount of $100 will be collected prior to the design of saidfacilities.

2. If constructed, the engineering service fee will be applied towards the CIAC. If notconstructed, the fee will be retained by SECO.

C. CIAC FOR OVERHEAD FACILITIES

l. For members/applicants in rate classes that do not include separately computed demandcharges, the CIAC shall be calculated as follows:

C|AG=CF-4[(kWh"xE")]

2. For members/applicants in rate classes that include both per kWh energt charges andper kW demand charges, the CIAC shall be calculated as follows:

GIAC = CF - 4[(kwh" x E")] + 4kW"[(D" - (Do x DF)l

CF represents installed cost ofnew poles and conductors and appropriate fixtures to provideservice, excluding transformer, service drops, and meters

kWh" represents customer's annual expected kWH usage

Es represents difference between SECO's current retail energy charge per kWH and currentwholesale energy charge per kWH including PCA charges

kW" represents customer's cumulative monthly demand for a one-year period

D" represents SECO's current monthly demand charge per kW

D, represents SECO's wholesale demand expense per kW

DF represents the average demand coincidence factor of the rate class of the new member

(Continued on Sheet No. 16.2)

Effective June 1,2015Issued By: James P. Duncan, CEO

t I

Page 34: Rate-Tariff Sheets

Fourth Revised Sheet No. 16.2Cancels Third Revised Sheet No. 16.2

LINE EXTENSION CHARGESPage 2 (Continued from Sheet No. l6.l)

D. CIAC F'OR UNDERGROUND FACILITIES

l. When a member/applicant requests underground electric facilities, the member/applicantshall pay SECO the full cost of facilities to be installed, including underground feederbackbone and/or additional facilities.

2. The CIAC for the cost differential between the overhead and underground facilities isnon-refundable. The remaining CIAC balance is refundable on a prorated basis. Theproration will be straight-line over 48 months based on the individual additions ofpermanent member accounts in a quarter. At the end of 48 months, any balanceremaining will be retained by SECO. The Cooperative will refund the proratedcollections to the member/applicant (builder/developer) who paid the cost of thefacilities installation.

E. CIAC FOR SERVICE AT PRIMARY VOLTAGE OR TRANSMISSIONVOLTAGE

Members/applicants requesting service at the distribution voltage level or transmissionvoltage level shall pay a CIAC based upon the cost to serve them less an appropriate credit fortaking delivery at the higher voltage level.

F. LINE EXTENSIONS WITH MORE THAN ONE MEMBER/APPLICANT

In cases where two or more members/applicants are to be served by a line extension, the

Cooperative will prorate the CIAC over the number of members/applicants expected to be

served within a four-year period by the line extension.

G. OUTDOOR LIGHTING SYSTEMS

Member/applicants requesting the installation of outdoor lighting systems in residentiol andcommercial developments shall pay a CIAC based on the total cost to provide such service.

H. DEFINITIONS

1. Cooperative

Sumter Electric Cooperative, Inc.

(Continued on Sheet No. 16.3)

Effective June l, 2015Issued By: James P. Duncan, CEO

-J: t I

Page 35: Rate-Tariff Sheets
Page 36: Rate-Tariff Sheets
Page 37: Rate-Tariff Sheets

Rev.11/18/2016 Page1of6

InterconnectionAgreement

ForCustomer-ownedRenewableGenerationSystems(1-1,000kW)

ThisInterconnectionAgreementforCustomer-OwnedRenewableGenerationSystems("InterconnectionAgreement")ismadethis_____dayof_______________20____,byandbetweenSECOEnergy("Cooperative")and_____________________("theCustomer")locatedat_______________________________________,Florida,referredtohereinindividuallyasa“Party”andcollectivelyasthe“Parties.” RECITALSWhereas,aRenewableGenerationSystem(“RGS”)isanelectricgeneratingsystemthatusesone or more of the following fuels or energy sources: hydrogen, biomass, solar energy,geothermalenergy,windenergy,oceanenergy,wasteheat,orhydroelectricpowerasdefinedinSection377.803,FloridaStatutes,ratedatnomorethan1,000kilowatts(kW)alternatingcurrent (AC) power output and is primarily intended to offset part or all of a Customer'scurrentelectricityrequirements.Whereas,theCustomerhasrequestedtointerconnectitsRenewableGenerationSystemof_____kW(AC)totheCooperative'selectricalservicegridattheCustomer'spresentlymeteredlocation;andWhereas,theCooperativeandSeminoleElectricCooperative,Inc.("Seminole")haveenteredintothatcertainWholesalePowerContract("WPC"),effectiveasofJuly30,1975,which,asamended, provides, among other things, that the Cooperativemay allownetmetering forrenewableenergyresourceswhicharelocatedonacustomer'spremises;andWhereas, the Cooperative and Seminole have entered into that certain Net MeteringAgreement,whichprovidesthestandardinterconnectionrequirementsforacustomer'sRGSinstallation;andWhereas, the Customer acknowledges the complexity and integrated nature of theCooperative'selectricsystem,towhichtheCustomerdesiresinterconnectionandwithwhichCustomerdesiresparalleloperation;andWhereas, the Customer acknowledges the important safety issues and financialconsequencesontheCooperative'selectricsystemthatcouldresultfromanydeviationbytheCustomerfromtherequirementsofthisAgreement.Now,Therefore,inconsiderationofthemutualcovenantsandagreementshereinsetforth,thePartiesdoherebyagreeasfollows:1) Inordertocommencetheprocessforinterconnection,theCustomershallprovidethe

Cooperative a completed “Application Form”, attachedhereto asAttachment 1 andincorporatedherein.

Page 38: Rate-Tariff Sheets

Rev.11/18/2016 Page2of6

2) TheCustomeragreestoprovidetheCooperativewithwrittencertificationthattheRGSinstallationhas been inspectedby the local code officialwhohas certified that theinstallation was permitted and has been approved and has met all electrical andmechanicalrequirements.SuchcertificationshallbedeliveredtoCooperativepriortotheoperationoftheRGS.

3) TheCustomershall,priortooperationoftheRGS,provideequipmentspecificationsto

the Cooperative identifying and certifying in writing that the RGS, inverters andassociated equipment design, and installation and operation adhere to IEEE-1547Standards,UL-1741Standards,theNationalElectricCode,and,ifapplicable,hasbeenapprovedbytheFloridaSolarEnergyCenter(FSECStd203-10).

4) The Customer is responsible for the inspection, maintenance, and testing in

accordancewiththemanufacturer'sinstructionsandapplicablecodes,standards,andregulationsto insurethattheRGSandassociatedequipmentareoperatedcorrectlyandsafely.

5) TheCustomeragreestopermittheCooperativeand/orSeminole,ifitshouldsochoose,

to inspect the RGS and its component equipment and the documents necessary toensure compliance with various sections of this Interconnection Agreement bothbeforeandaftertheRGSgoesintoserviceandtowitnesstheinitialtestingoftheRGSequipment and protective apparatus. The Cooperative shall provide the Customerwithasmuchnoticeasreasonablypracticable,eitherinwriting,e-mail,facsimileorbyphone,astowhentheCooperativemayconductinspectionordocumentreview,andthe Customer shall provide the Cooperative with as much notice as reasonablypracticable regarding the testing of the RGS equipment and protective apparatus.Uponreasonablenotice,oratanytimewithoutnoticeintheeventofanemergencyorhazardous condition, Customer agrees to provide the Cooperative access to theCustomer'spremisesforanyreasonablepurposeinconnectionwiththeperformanceof theobligations imposedby this InterconnectionAgreement. TheCustomershallnotifytheCooperativeatleastten(10)dayspriortothein-servicedateoftheRGStoprovidesufficientnoticefortheCooperativetobeabletobepresent,ifitsochooses,whentheRGSisplacedinservice.SeminoleshallhavethesamerightsanddutiesofinspectionastheCooperative;however,nothinghereinobligatestheCooperativeorSeminoletoinspect,andthefailureoftheCooperativeand/orSeminoletoinspector,uponinspection,todetectaproblemordeficiencyshallnottransferresponsibilitytoCooperativeorSeminolenorrelieveCustomerofitsdutieshereunder.

6) TheCustomerisresponsibleforprotectingtheRGS,inverters,protectiondevices,and

othersystemcomponentsfromthenormalandabnormalconditionsandoperationsthatoccurontheCooperative'selectricalsystemindeliveringandrestoringsystempower.TheCustomercertifiesthattheRGSequipmentincludesautility-interactiveinverter or interconnection systemequipment that ceases to interconnectwith theutility upon a loss of utility power. The inverter shall be considered certified forinterconnectedoperationifithasbeensubmittedbyamanufacturertoanationally-recognized testing laboratory (NRTL) to complywithUL1741. TheNRTL shall beapprovedbytheOccupationalSafety&HealthAdministration(OSHA).

Page 39: Rate-Tariff Sheets

Rev.11/18/2016 Page3of6

7) The Customer shall not energize the Cooperative's systemwhen the Cooperative'ssystemisde-energized.Thereshallbenointentionalislanding,asdescribedinIEEE1547,betweentheCustomer'sandtheCooperative'ssystems.

8) ForanRGSwithacapabilityoften(10)kWorless,theCustomershallnotberequired

tomaintainGeneralLiabilityInsuranceforPersonalandPropertyDamage,andforanRGSwith a capability of greater than ten (10)kW, theCustomer shall provide andmaintainnotlessthanonemilliondollars($1,000,000)ofGeneralLiabilityInsurancefor Personal and Property Damage. Proof of said insurance, if applicable, shall beprovidedby theCustomer and attached to this InterconnectionAgreement, and allpolicyrenewalsshallbeprovidedtotheCooperative.

9) The Customer shall, at the Customer's expense, install and maintain a manual

disconnectswitchtoprovideaseparationpointbetweentheACpoweroutputoftheRGSandanyCustomerfacilitiesconnectedtotheCooperative'selectricalsystem.ThemanualdisconnectswitchshallbemountedseparatelyfromthemetersocketandshallbereadilyaccessibleatalltimestotheCooperativeandshallbecapableofbeinglockedin the open position by the Cooperative. The Cooperativemay open and lock theswitch,isolatingtheRGSfromtheCooperative'selectricalservicegridwithoutpriornoticetotheCustomer.Totheextentpractical,theCooperativewillattempttonotifythe Customer of its intent to disconnect the RGS from the Cooperative's electricalservicegrid,butshallhavenoliabilityforfailuretodoso.

10) "Gross power rating" (“GPR”) means the manufacturer's AC nameplate generating

capacity of theRGS thatwill be interconnected to and operate in parallelwith theCooperative’s distribution facilities. For inverter-based systems, the GPR shall becalculatedbymultiplyingthetotalinstalledDCnameplategeneratingcapacityby.85inordertoaccountforlossesduringtheconversionfromDCtoAC.ItistheCustomer'sresponsibility to notify the Cooperative of any change to the GPR of the RGS bysubmittinganewapplicationforinterconnectionspecifyingthemodificationsatleastthirty(30)dayspriortomakingthemodifications.Ifsuchmodificationsareapprovedby the Cooperative, an amendment to this Interconnection Agreement shall beexecutedbythePartiesandtheCustomerrecognizesandagreesthatanincreaseinGPR to greater than ten (10) kW may impose additional requirements on theCustomer.

11) TheRGSmusthaveaGPRthatdoesnotexceedninetypercent(90%)oftheCustomer's

utilitydistributionserviceratingattheCustomer'slocation.IftheGPRdoesexceedthatninetypercent(90%)limit,theCustomershallberesponsibletopaythecostofupgradesforthatdistributionservicetoaccommodatetheGPRcapacityandtoensuretheninetypercent(90%)thresholdisnotbreached.

12) The Cooperative will furnish, install, own and maintain metering equipment to

measurekilowatt-hours(kWh)ofenergyand,ifapplicable,thekWofdemandandtimeofuseofsaidenergyanddemand.TheCustomer'sserviceassociatedwiththeRGSwillbemeteredatasinglemeteringpoint,andthemeteringequipmentshallbecapableofmeasuringthenetenergydeliveredbytheCooperativetotheCustomerandthenetenergy delivered by the Customer to the Cooperative on a monthly basis. The

Page 40: Rate-Tariff Sheets

Rev.11/18/2016 Page4of6

Customeragreestoprovidesafeandreasonableaccesstothepremisesforinstallationofthisequipmentanditsfuturemaintenanceorremoval.

13) Once the Cooperative has received the Customer'swritten documentation that the

requirements of this Interconnection Agreement have been met and the correctoperation of the manual switch has been demonstrated to Cooperative, theCooperativewill,withinten(10)businessdays,notifythatparalleloperationoftheRGSmaycommence.

14) The Customer shall indemnify, hold harmless and defend the Cooperative and

Seminolefromandagainstanyandallliability,proceedings,suits,costorexpenseforloss, damage or injury to persons or property in any way directly or indirectlyconnectedwith,orgrowingoutofoperationoftheRGS,exceptinthosecaseswherelossoccursduetothegrosslynegligentactionsoftheCooperative.

15) TheCooperativehastheright,attheCustomer'sexpense,todisconnecttheRGSatany

time.Thismayresultfrombutisnotlimitedto:

a) Cooperativeand/orSeminole'ssystemmaintenance,operationandemergencyoperations;

b) Hazardous conditions existing on the Cooperative's and/or transmission

provider's system due to the operation of the RGS generating or protectiveequipmentasdeterminedbytheCooperativeorSeminole;

c) AdverseelectricaleffectsontheelectricalequipmentoftheCooperative'sother

electriccustomersasdeterminedbytheCooperative;d) Failure by the Customer to adhere to the terms of this Interconnection

Agreement;e) FailurebyCustomertopaysumsduetotheCooperativeforelectricserviceor

anyotherreason.16) On the termination of this Interconnection Agreement, the Cooperative, at the

Customer'sexpense,shallopenandpadlockthemanualdisconnectswitchandremoveanyadditionalCooperativeequipmentassociatedwiththeprovisionofnetmeteringservice.AttheCustomer'sexpense,theCustomeragreestopermanentlyisolatetheRGS and associated equipment from the Cooperative's electric service grid. TheCustomer shall notify the Cooperative within ten (10) working days that thedisconnectprocedurehasbeencompleted.

17) ThePartiesagreethatthesoleandproperjurisdictionandvenueforanylegalaction

brought to enforce this Interconnection Agreement or to address the rights andobligationsofthisInterconnectionAgreementshallbetheStateCourtoftheproperjurisdictionlocatedwithintheStateofFlorida.

18) In the event of any dispute hereunder for any action to interpret or enforce this

Page 41: Rate-Tariff Sheets

Rev.11/18/2016 Page5of6

Interconnection Agreement, the prevailing Party shall be entitled to recover itsreasonablecosts,feesandexpenses,including,butnotlimitedto,witnessfees,expertfees,consultantfees,attorney,paralegalandlegalassistantfees,costsandexpensesandotherprofessionalfees,costsandexpenseswhethersuitbebroughtornot,andwhetherinsettlement,inanydeclaratoryaction,attrialoronappeal.

19) Anywrittennoticerequiredorappropriatehereundershallbedeemedproperlymade,

given to,orservedon theParty towhich it isdirected,whensentbyUnitedStatescertifiedmail,ReturnReceiptRequested,addressedasfollows:

IftoCustomer: __________________________________ __________________________________ __________________________________ IftoCooperative: SECOEnergy Attn:EngineeringDepartment-RGS P.O.Box301 Sumterville,Florida33585-0301

Notice of any change in any of the above addresses shall be deemed in themannerspecifiedinthissection.

21) OtherSpecialProvisions:

The Parties acknowledge that this Interconnection Agreement is subject to the RGSAgreementandtheWholesalePowerContract,eachenteredintobetweenCooperativeandSeminoleElectricCooperative,Inc.ThisInterconnectionAgreementisintendedtobeconsistentwiththeRGSAgreementandtheWholesalePowerContract,butintheeventthatanyoftheprovisionsofthisInterconnectionAgreementshallbeheldorotherwisedetermined to be in conflict with either the RGS Agreement or theWholesale PowerContract, the parties agree that the RGS Agreement or Wholesale Power Contract,respectively,shallprevail.

22) ThisInterconnectionAgreement,alongwiththeApplicationForm,whenduly

executed,constitutestheentireagreementbetweenthePartieswithrespecttomattershereincontained.

(THESIGNATUREPAGEFOLLOWS)

Page 42: Rate-Tariff Sheets

Rev.11/18/2016 Page6of6

InWitnessWhereof,thePartiesheretohavecausedthisInterconnectionAgreementtobedulyexecutedintriplicatethedayandyearfirstabovewritten._______________________________________________ _____SECOEnergy_________Customer:PrintNameorOrganizationBy:____________________________________________ By:_____________________________ Signature:AuthorizedRepresentative Signature

____________________________________________ __JamesP.Duncan,CEO__ (Print Name and Title)

Page 43: Rate-Tariff Sheets
Page 44: Rate-Tariff Sheets
Page 45: Rate-Tariff Sheets

Original Sheet No. 19.0l**\SET!O\ETERtrY=rJ-

IDLE AND DORMANT SERVICES - SCHEDULE DS

PURPOSE

To implement a method to reduce the costs offacilities seruing inqctive accounts. The costs may be

due to, but not limited to, maintenance of poles/hardware, removal of vegelation, or safely andclearance issues. sECo Energt (SECO) reserves the right to remove its facilities where

non-revenue producing services exist.

APPLICABILITY

This policy shall apply to property owners to allow them the opportunity to choose to have SECOnot permanently retire the facilities serving an ldle Service (as deJined below) for future use. This

will also provide a mechanism for SECO to recover a portion of the continuing overhead,

maintenance, and tax costs related thereto. Non-use of ser,,tice for 12 months shall make lhe lineand equipment serving the account subject to removal.

SPECIAL PROVISIONS

llith respect to ldle and Dormant Semices, the following shall apply:

1. "ldle Service " indicates any service where lines and equipment exist but the account is inactive

for a period of I 2 months .

2. " Dormant Status " refers to facilities in the feld that will be mahtained like all other facilitiesbut may not be energized or have a meter bttalled.

). At the discretion of SECO, a certified letter will be mailed to the property owner notifuinghim or her of the ldle Semice condition. The property ov)ner may elect to not have the IdleService retired by SECO and apply for Dormant Status. If no response is received by the

deadline specified in the certified letter, the fdcilities serving the ldle Service may be

removed w ithout further notiJic ation.

4. If election is made by the property oluner to retain the ldle Service, the property owner must

be or become an active member of SECO and apply for Dormant Status. In dddition, amonthly Dormant Facilities Charge will be billed as per the established rate schedule ofSECO. SECO has the right to remove the meter and the transformer. The monthly DormantFacilities Charge is subject to periodic review by the Board ofTrustees.

5. The member with the Dormant Status service will be billed under the normal billing policyof SECO. If the account becomes delinquent and subject to non-payment disconnect, the

service will be scheduled for removal without furlher notification.

6. If an ldle Service is removed and service is requested in the future dt that location, the request

will be treated as a new service. All costs associated shall be calculated in accordance withTariff Sheet No. I 6. I (Line Extension Charges) in ffict at the time of the request.

Effective January l, 2016Issu€d by: James P. Duncan, CEO

Page 46: Rate-Tariff Sheets

y'r**o\SEGO\Ef,ERTIY=r-J-

Original Sheet No. l9.l

IDLE AND DORMANT SERVICES - SCHEDULE DSPage 2 (Continued fiom Sheet No. 19.0)

7. Connecting or reconnecting any service and later disconnecting the service to avoid the

monthly fee will subject the service to the same stalus as an ldle Service. In all cases, areconnect charge will apply as per the applicable rate schedule.

MONTHLY CHARGES

Refer to Tariff Sheet No. 16.01 (Miscellaneous Charge Amounts).

TERMS OF PAYMENT

Bills are due and payable by the date shoy'n on the bill. Bills not paid by the date shown on the billare subject to a late payment fee of 1.5% of the omount of the bill, with a minimum fee of $5.00.

Effective January l, 2016Issued by: James P. Duncan, CEO