Rashmi Metaliks Limited -...
Transcript of Rashmi Metaliks Limited -...
Rashmi Metaliks Limited Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PRE-FEASIBILTY REPORTS
FOR
PRODUCTION CAPACITY ENHANCEMENT OF DUCTILE IRON PIPE PLANT
FROM 2, 00,000 TPA TO 5, 50,000 TPA
AT
VILLAGE- GOKULPUR, P.O – SHYAMRAIPUR, P.S – KHARAGPUR (L)
DISTRICT – WEST MEDINIPUR, WEST BENGAL
Project Execution By
RASHMI METALIKS LIMITED
PREMLATA BUILDING, 6thFLOOR
39, SHAKESPEARE SARANI, KOLKATA – 700 017
WEST BENGAL
Ph No.–033 – 22894255/56
Rashmi Metaliks Limited Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
CONTENTS
Page No.
Chapter -1 -Executive Summary
1.1- Introduction 01
1.2- Present Project 04
1.3- Market Demand 05
1.4- Process Concept & Technology 06
1.5- Capital Cost 07
1.6- Project Schedule 07
Chapter -2 - Introduction of the Project
2.1- Identification of Project & Project Proponent 08
2.2- Brief Description of nature of the Project 10
2.3- Need for Project & Its Importance 10
2.4- Demand Supply Gap 10
2.5- Import Vs Indigenous Product 16
2.6- Export Possibility 16
2.7- Domestic Export Market 17
2.8- Employment Generation 18
Chapter -3 – Project Description
3.1 Type of Project 19
3.2 Process Concept 19
3.3 Raw Material Requirement Detail 25
3.4 Availability of Power, Water & its Sources 26
3.5 Quality Assurance 28
Chapter -4 – Site Analysis
4.1 Connectivity 29
4.2 Land form, Land use and Land Ownership 29
4.3 Location of Map 30
4.4 Alternative Site Selection 32
Rashmi Metaliks Limited Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
Page No.
4.5 Topography (With Map) 33
4.6 Existing Land Use Pattern 34
4.7 Soil Classification 34
4.8 Climate Data from Secondary Sources 35
4.9 Social Infrastructure availability 36
Chapter -5– Planning Brief
5.1 Planning Concept 37
5.2 Population Projection 38
5.3 Land Use Planning 38
5.4 Assessment of Infrastructure Demand 38
5.5 Amenities/ Facilities 39
Chapter -6 – Proposed Infrastructure
6.1 Industrial Area 40
6.2 Residential Area 40
6.3 Green Belt 40
6.4 Social Infrastructure 41
6.5 Connectivity 42
6.6 Sewerage System 42
6.7 Industrial Waste Management 42
6.8 Solid Waste Management 43
6.9 Power Requirement & Supply/ Source 44
Chapter -7 – Environment Management Plan
7.1 EMP During Construction Phase 45
7.2 EMP During Operational Phase
7.2.1 Air Pollution Management Plan 46
7.2.2 Noise Pollution Management Plan 50
7.2.3 Water Pollution Management Plan 51
7.2.4 Pathway of Pollutant 52
7.2.5 Solid Waste Management Plan 52
Rashmi Metaliks Limited Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
Page No.
7.3 Occupational Health Management Plan 53
7.4 Green Belt Development Plan 55
7.5 Rain Water Harvesting 56
7.6 Road Connectivity 56
7.7 Monitoring Scheme 56
Chapter -8– Rehabilitation and Resettlement (R & R) Plan
8.1 Introduction 57
Chapter -9– Project Schedule & Cost Estimates
9.1 Detail 58
9.2 Estimate Project Cost 58
Chapter -10– Project Schedule & Cost Estimates
10.1 Financial and social benefits 60
Annexure-I- Plant Layout
Annexure-II- Green Belt Development
Annexure-III- Existing Rain Water Harvesting Facility
Annexure-IV- CSR Activities carried in past by RML
Annexure-V- Water Extraction Permission
Annexure-VI- Stack/ Ambient Analysis Report
Annexure-VII- Valid CFO, NOC & EC Detail
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 1
1. Executive Summary
1.1 Introduction
M/s Rashmi Metaliks Limited has an Integrated Steel Plant & Ductile Iron Pipe
Plant and has already obtained EC on 12.06.2008 ; 01.06.2012 from MoEF, New
Delhi for integrated steel plant and on 09.10.2009 for Ductile Iron Pipe Plant of
2,00,000 TPA from SEIAA West Bengal and necessary NOC, CFO for running its unit.
Its registered office is at Premlata Building, 6th Floor, 39-Shakespeare Sarani, Kolkata
– 700 017 in West Bengal.
M/s Rashmi Metaliks Limited at present operating Sinter Unit (50,000 TPM), Mini
Blast Furnace (14,000 TPM), SMS (15,500 TPM), Rolling Mill (9600 TPM), Ductile Iron
Pipe (11833 TPM), Pellet Plant-I (75,000 TPM), Coal Gasifier (6000 Nm3/hr) at village -
Gokulpur, P.O. Shyamraipur, Kharagpur. District Paschim Mednipur in West Bengal.
It is important to note that by virtue of Hon‟ble Calcutta High Court order for
demerger, as on date the complete Sponge Iron Plant, Captive Power Plant, MBF ( 1 X
320 m2), Pellet Plant-II (0.6 MTPA), Pellet Plant-III (0.6 MTPA), Iron Ore Beneficiation
Plant and Producer Gas Plant got transferred to M/s Orissa Metaliks Private Limited
(OMPL). The name of plant units of RML is given in Table 1.1. The name of plant
units of OMPL is given in Table 1.2.
Table 1.1 Name of Units with Rashmi Metaliks Limited
Name of the Units Size of Units
under Operation
Production
Capacity
Name of Product
Mini Blast Furnace 1 x 215 m3 168000 TPA Molten Iron
Sinter Plant 2 x 25 m2 600000 TPA Sinter
Pig Casting Machine
- 120000 TPA Pigs
SMS - 378000 TPA Steel
Pellet Plant 0.9 MTPA 900000 TPA Pellets
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 2
Ductile Iron Pipe Plant 0.14 MTPA 140000 TPA Pipe
Rolling Mill TMT 8 - 32 mm
Wire Rod 5.5 mm
- 12 mm
120000 TPA TMT Bar
Table 1.2 Name of Units with Orissa Metaliks Private Limited (By Virtue of Hon’ble Calcutta High Court Order)
Name of the Units Size of Units
under Operation
Production
Capacity
Name of Product
DRI kilns 6 x 100 TPD +
1 x 350 TPD
321000 TPA Sponge Iron
Iron Ore Beneficiation
Plant
1.5 MTPA Iron ore concentrate
Pellet Plant 2 x 0.6 MTPA 120000 TPA Pellets
Producers Gas Plant 10 x 7500 Nm3/ h
- Producer gas for pellet
making
CPP-WHRB DRI based WHRB &
AFBC
28 MW Electricity
After transferred of units to M/s Orissa Metaliks Private Limited the status of
units in the company name as follows.
Units under the company Name Orissa
Metaliks Private limited
Units under the Company Name Rashmi
Metaliks Limited
Under EC No J-11011/227/2010-IA-II (I) dated 12th, June, 2008 of MoEF, New Delhi
DRI (10 X100 TPD; 3 X350 TPD) WITH
WHRB
SINTER PLANT : 70 sqM (0.84MTPA)
MBF : 320 sqM (0.3MTPA) STEEL MELTING SHOP : 0.5 MTPA
OXYGEN PLANT : 60 TPD
LIME CALCINATION : 1200 TPD
F. No. J – 11011/372/2014-IA II (I) dated 12.02.2015. of MoEF, New Delhi
PELLET PLANT-I -0.9 MTPA
Under EC. No. EN/256/T-II-I/047/2009 dated 09.10.2009. of SEIAA, West Bengal
DUCTILE IRON PIPE PLANT -2,00,000 TPA
Under EC No J-11011/604/2010-IA-II (I) dated 1st, June, 2012’ of MoEF, New Delhi
I/O BENEFICATION PLANT-1.5 MTPA
PELLET PLANT (0.6 MTPA x2) 1.2 MTPA
PRODUCER GAS PLANT ( 10 X 7500 NM3/hr)
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 3
As a strategic decision the company has decided to expand their business model by
enhancing the capacity of Ductile Iron Pipe Plant from 2,00,000 TPA to 5,50,000 TPA
in phase wise at Mouza – Nandarchak (J.L. No.-124), Sujatpur (J.L. No.-139) &
Khidipur(J.L. No.-140) Village – Gokulpur, P.O – Shyamraipur, P.S – Kharagpur (L),
Dist. Paschmi Mednipur in the state of West Bengal.
Rashmi Group founded in 1966 really got impetus from its real promoter. Rashmi
Group of companies is a fast growing Group in the field of manufacturing steel and
cement. The company has developed core competence in minerals, steel and cement
with 40 years of experience. The Group‟s turnover is around Rs.2100 Crores and net
worth is Rs.2139 Crores. Rashmi Group awarded „Ultra Mega Project‟ status by Govt.
of West Bengal. The Group is also engaged in import/export of Mineral & Mineral
based products. The growth of the group during last few years has been phenomenal
and fast catching the attention of bankers, professionals and industry as a whole.
The group has grown from merely a re-rolling mill to a fully fledged Cement Grinding
unit having capacity of 0.18 MTPA and group have already obtained EC from the
SEIAA, W.B. in favour of Rashmi Cement Limited (Cement Division) vide letter no.
1276/EN/T-II-1/044/2014 on 27.05.2015 for expansion from 0.18 MTPA to 0.96
MTPA which is under commissioning stage at Jhargram in West Bengal.
In addition to this, the Group also has a Sponge Iron Plant in the name of Rashmi
Cement Limited (Steel & Power Division) for which EC (File No. J-11011/227/2007-
1A.II (I)) had obtained from MoEF, Delhi on 12.02.2009 for expansion of capacity from
3, 00,000 TPA TO 6, 00,000 TPA, Ferro alloy with capacity 72,000 TPA & Power Plant
25 MW and at present we are having operation capacity of 4, 00,000 TPA Sponge Iron,
Ferro alloy 24,000 TPA & Captive Power Plant WHRB based 28 MW at village -
Jitusole, P.O. Jhargram, District Paschim Mednipur in West Bengal.
Also , Rashmi Group is going to set up another 1.0 million TPA Steel Plant and 200
MW power plant at Jamuria, Dist.-Burdwan in West Bengal by the name of Rashmi
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 4
Cement Limited, for this MOEF, Delhi has already issued the Environmental
Clearance (File No. J -11011/112/2010-IA II (I)) dated 26th August 2014.
As a strategic decision, the management has decided to expand their business model
by enhancing the capacity of Ductile Iron Pipe Plant from 2,00,000 TPA to
5,50,000 TPA by the name of M/s Rashmi Metaliks Limited in phase wise, the
detail is given in Table-1.3 at Mouza – Nandarchak (J.L. No.-124), Sujatpur (J.L. No.-
139) & Khidipur(J.L. No.-140) Village – Gokulpur, P.O – Shyamraipur, P.S –
Kharagpur (L), Dist. Paschmi Mednipur in the state of West Bengal.
Table 1.3- Proposed Expansion Project Detail
Sr. No Plant Existing
(TPA)
Proposed (TPA) Total
(TPA) Phase-I Phase-II
1 Ductile Iron Pipe 2,00,000 1,50,000 2,00,000 5,50,000
1.2 Present Project
The proposed project, after obtaining the „EC‟ & „NOC‟ project works will be started at.
Management has decided to enhance the capacity of Ductile Iron Pipe Plant from
2,00,000 TPA to 5,50,000 TPA in phase wise at Mouza – Nandarchak (J.L. No.-124),
Sujatpur (J.L. No.-139) & Khidipur(J.L. No.-140) Village – Gokulpur, P.O –
Shyamraipur, P.S – Kharagpur (L), Dist. Paschmi Mednipur in the state of West
Bengal for following reason:
Raw Materials availabilities like Hot Metal which will be obtaining from RML
and adjacent unit i.e. OMPL
Close to high growth deficient markets
Economies of scale will result in lower operating cost
Offers freight advantage vis-à-vis competitors
Excellent export opportunities to South Asian countries
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 5
The markets in the East & North-East are potential territories for Ductile Cast Iron
Pipe & offer great opportunity to market this product, which is well accepted in other
parts of the country.
1.3 Market Demand
India is one of the fastest developing economies in the world. Infrastructure lacuna
has been an anathema to India's growth. Not surprisingly, India lags behind water
infrastructure and sewerage development with only 33% of the total population having
access to improved sanitation. In rural areas, where 72% of India's population lives,
only 22% has better coverage for sanitation.
The Indian pipes business has been growing rapidly since the past several years
mainly due to increasing demand for pipes in the irrigation sector, for crude oil, real
estate industry and growth in Gross domestic product (GDP) of the country. Among
the several varieties of pipes available in the market, the demand for plastic pipes
such as PVC, CPVC in particular, is on a rise due to its low cost, high quality and
high durability. Other types of pipes, like steel pipes and ductile iron pipes also have
major demand. Nationwide infrastructural development, urbanization, government‟s
focus on real estate, irrigation to drive agricultural growth have been identified as
major factors facilitating the growth of the pipes industry in the country.
The Government of India is launching new schemes in the irrigation and the real
estate sector for significant investments. It is evident here that the focus of Indian
government is on water supply for housing sector, which will only be fulfilled with
effective use of pipelines. Therefore, this end-user is a major demand driver of pipes.
Furthermore, strong demand for crude oil transportation is also adding to the demand
of pipes across the country.
The major grades demanded in the Indian markets is the K7 and K9 series, the
governmental authorities and waste water authorities majorly demand DN 80 mm to
DN 1000 mm diameter or sizes of specifications. The major feature of this market is
that it is 100 % organized as the commissioning of project is routed through EPC
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 6
contractors and vendor selection criteria by the government is completely based on
Quality of the DI pipes and robust quality standards with regards to ISO and British
Standards
The Ductile Iron pipes market in India is set to grow in the short term and medium
term (2 – 5 years) clocking consistent growth rates, with major players ramping up
their operations along with a sudden surge in demand in the Indian markets as well
as export markets like South Asia, Middle East and North Africa.
In the medium term and long term (7 to 10 years) we predict a demand supply gap in
terms of excess supply in the Indian markets over demand as a result of established
infrastructural waste water and water projects, and India would have prime focus to
export to developing & underdeveloped regions which lacks infrastructural
development in waste water & water infrastructure.
This proposed production enhancement project of Ductile Iron Pipe Plant from
2,00,000 TPA to 5,50,000 TPA by the name of M/s Rashmi Metaliks Limited in
phase wise at Mouza – Nandarchak (J.L. No.-124), Sujatpur (J.L. No.-139) &
Khidipur(J.L. No.-140) Village – Gokulpur, P.O – Shyamraipur, P.S – Kharagpur (L),
Dist. Paschmi Mednipur in the state of West Bengal shall be partially fulfilling the
demand of the Ductile Iron Pipe in India & Global market.
1.4 PROCESS CONCEPT & TECHNOLOGY
The existing DI pipe plant is based on state of the art technology with respect to
energy efficiencies and environmental protection. In Blast Furnace Hot Metal carbon
percentage 4.2 to 4.3 but in DI pipe, carbon percentage is 3.6 %. Therefore steel scrap
with 0.3% carbon is to be added by about 12% to 15 % for chemistry correction. After
that hot metal is treated with Magnesium and taken for Centrifugal casting.
Successfully casting pipes are sent for heat treatment, Zn-coating, Hydraulic Pressure
Test, Cement Motor Lining and Bitumen Coating respectively. Bag Filters, Suction
Hoods are using for Induction as well as Annealing Furnaces to control of dust
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 7
emissions for main processing equipments. For Fugitive emissions control from
various transfer points/storage areas etc, by Bag filters, Suction Hoods, dust collector
systems and dust suppression systems
1.5 CAPITAL COST
The estimated capital cost, for the proposed production enhancement project works
out to about Rs. 165 crores including Machineries, Building construction, Road
construction, Green Belt Development etc.
1.6 PROJECT SCHEDULE
This project would be designed by Capex Projects Management division of RASHMI
GROUP and will be executed by M/s Rashmi Metaliks Limited project division, which
is located at Kolkata, West Bengal. The entire project will be completed within 60
months from the date of obtaining of Environment Clearance & Consent to establish.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 8
2. Introduction of the Project
2.1 Identification of Project and Project Proponent
M/s Rashmi Metaliks Limited has an Integrated Steel Plant & Ductile Iron Pipe
Plant and has already obtained EC on 12.06.2008 ; 01.06.2012 from MoEF, New
Delhi for integrated steel plant and on 09.10.2009 for Ductile Iron Pipe Plant of
2,00,000 TPA from SEIAA West Bengal and necessary NOC, CFO for running its unit.
Detail Enclosed as Annexure- VII. Its registered office is at Premlata Building, 6th
Floor, 39-Shakespeare Sarani, Kolkata – 700 017 in West Bengal.
M/s Rashmi Metaliks Limited at present operating Sinter Unit (50,000 TPM), Mini
Blast Furnace (14,000 TPM), SMS (15,500 TPM), Rolling Mill (9600 TPM), Ductile Iron
Pipe (11833 TPM), Pellet Plant-I (75,000 TPM), Coal Gasifier (6000 Nm3/hr) at village -
Gokulpur, P.O. Shyamraipur, Kharagpur. District Paschim Mednipur in West Bengal.
It is important to note that by virtue of Hon‟ble Calcutta High Court order for
demerger, as on date the complete Sponge Iron Plant, Captive Power Plant, MBF ( 1 X
320 m2), Pellet Plant-II (0.6 MTPA), Pellet Plant-III (0.6 MTPA), Iron Ore Beneficiation
Plant and Producer Gas Plant got transferred to M/s Orissa Metaliks Private Limited
(OMPL).
As a strategic decision the company has decided to expand their business model by
enhancing the capacity of Ductile Iron Pipe Plant from 2,00,000 TPA to 5,50,000 TPA
in phase wise at Mouza – Nandarchak (J.L. No.-124), Sujatpur (J.L. No.-139) &
Khidipur(J.L. No.-140) Village – Gokulpur, P.O – Shyamraipur, P.S – Kharagpur (L),
Dist. Paschmi Mednipur in the state of West Bengal.
Rashmi Group founded in 1966 really got impetus from its real promoter. Rashmi
Group of companies is a fast growing Group in the field of manufacturing steel and
cement. The company has developed core competence in minerals, steel and cement
with 40 years of experience. The Group‟s turnover is around Rs.2100 Crores and net
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 9
worth is Rs.2139 Crores. Rashmi Group awarded „Ultra Mega Project‟ status by Govt.
of West Bengal. The Group is also engaged in import/export of Mineral & Mineral
based products. The growth of the group during last few years has been phenomenal
and fast catching the attention of bankers, professionals and industry as a whole.
The group has grown from merely a re-rolling mill to a fully fledged Cement Grinding
unit having capacity of 0.18 MTPA and group have already obtained EC from the
SEIAA, W.B. in favour of Rashmi Cement Limited (Cement Division) vide letter no.
1276/EN/T-II-1/044/2014 on 27.05.2015 for expansion from 0.18 MTPA to 0.96
MTPA which is under commissioning stage at Jhargram in West Bengal.
In addition to this, the Group also has a Sponge Iron Plant in the name of Rashmi
Cement Limited (Steel & Power Division) for which EC (File No. J-11011/227/2007-
1A.II (I)) had obtained from MoEF, Delhi on 12.02.2009 for expansion of capacity from
3, 00,000 TPA TO 6, 00,000 TPA, Ferro alloy with capacity 72,000 TPA & Power Plant
25 MW and at present we are having operation capacity of 4, 00,000 TPA Sponge Iron,
Ferro alloy 24,000 TPA & Captive Power Plant WHRB based 28 MW at village -
Jitusole, P.O. Jhargram, District Paschim Mednipur in West Bengal.
Also , Rashmi Group is going to set up another 1.0 million TPA Steel Plant and 200
MW power plant at Jamuria, Dist.-Burdwan in West Bengal by the name of Rashmi
Cement Limited, for this MOEF, Delhi has already issued the Environmental
Clearance (File No. J -11011/112/2010-IA II (I)) dated 26th August 2014.
As a strategic decision, the management has decided to expand their business model
by enhancing the capacity of Ductile Iron Pipe Plant from 2,00,000 TPA to
5,50,000 TPA by the name of M/s Rashmi Metaliks Limited in phase wise, the
detail is given in Table-2.1 at Mouza – Nandarchak (J.L. No.-124), Sujatpur (J.L. No.-
139) & Khidipur(J.L. No.-140) Village – Gokulpur, P.O – Shyamraipur, P.S –
Kharagpur (L), Dist. Paschmi Mednipur in the state of West Bengal.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 10
Table 2.1- Proposed Expansion Project Detail
Sr. No Plant Existing
(TPA)
Proposed (TPA) Total
(TPA) Phase-I Phase-II
1 Ductile Iron Pipe 2,00,000 1,50,000 2,00,000 5,50,000
2.2 Brief Description of Nature of The Project
The proposed project, after obtaining the „EC‟ & „NOC‟ project works will be started at.
Management has decided to enhance the capacity of Ductile Iron Pipe Plant from
2,00,000 TPA to 5,50,000 TPA in phase wise at Mouza – Nandarchak (J.L. No.-124),
Sujatpur (J.L. No.-139) & Khidipur(J.L. No.-140) Village – Gokulpur, P.O –
Shyamraipur, P.S – Kharagpur (L), Dist. Paschmi Mednipur in the state of West
Bengal.
2.3 Need For the Project and Its Importance to the Country and/or Region
&
2.4 Demand- Supply Gap
Economic Growth
Indian economy is likely to grow in the range of 5.4 to 5.9 per cent in 2014-15 and the
outlook is very positive. The average consumer spending has increased significantly
which has fuelled demand for quality infrastructure services like roads, electric power,
transportation, water supply, sanitation, communication, etc.
Demand for Water
Water is a precious resource in India because the country accounts for 16% of the
world population as against just 4% of global water resources. The water use
efficiency is low in the country compared to international standards. As in the
previous years, agriculture will continue to be the major demand segment for water in
India. However, the demand from industries is expected to grow faster than the
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 11
demand from agriculture and domestic sectors. It is understood that the use of water
in Indian industries is high due to a combination of factors such as obsolete process
technology, poor recycling and reuse practices, and poor wastewater treatment. Use of
water in industries is closely linked to the economy of a country. The major water
guzzling industries are pulp and paper units, thermal power plants, fertilizer units,
iron and steel plants, sugar plants, and textile units. Estimates vary with respect to
the requirement of water for industries. According to the Ministry of Water Resource
(MoWR), the requirement will increase from 30 billion cubic metre in 2000 to 120
billion cubic metre by 2025. According to the World Bank, the water demand for
industrial uses and energy production will touch 228 billion cubic meters by 2025. As
per the Tenth Plan, the stipulated norms are 40 liters per capita per day (lpcd) of safe
drinking water within a walking distance of 1.6 km and at least 1 hand pump for
every 250 persons. The norm will be relaxed to 55 lpcd in states where the 40-lpcd
norm has been achieved already. The above-mentioned norms are quite reasonable
because it is reported that in many large cities, water withdrawal amounts to 300 to
600 lpcd. In contrast, the consumption in the developed countries of Europe and
North America had already touched 500-1000 lpcd by the turn of the last century.
Water demand projection varies from agency to agency. Consumption of water by
2020 in different sectors as projected by Water Resources Division, Planning
Commission is given below.
According to a WHO-UNICEF Sponsored Study (India Assessment 2002-Water Supply
& Sanitation), the total water requirement by 2050 will be 1,422 billion cubic meter.
Tata Energy Research Institute (TERI) has estimated that the overall water demand
will virtually double from 564 billion cubic meters in 1997 to 1,048 billion cubic meter
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 12
in 2047. MoWR has assessed the water requirement at 694 cubic km in 2010, 784
cubic km in 2025, and 973 cubic km in 2050. As against the projected demand, the
availability of water in 2050 is estimated at 996 cubic km.
At the national level, it will be a difficult to increase the availability to the projected
levels as most of the water resources are concentrated in a few river basins.
Transporting huge quantity of water from like rivers, lakes, wells, and treatment
plants to millions of homes would require a reliable pipeline system that will serve for
years without leaks and contamination. The increase in demand for water will call for
enormous efforts to capture, preserve, and distribute available water equitably.
Urbanization
It is estimated that by the end of the 12th Plan in 2017, approximately 40% of the
country‟s population will live in cities and towns. This fast pace of urbanization will
increase the demand for piped water supply. Thus, the increase in population
accompanied by the fast pace of urbanization will together contribute for the growth
in demand for pipes.
Improvement in Water and Sanitation Coverage of Government to provide drinking
water & sanitation to100% of the population:
Thrust of government to provide drinking water & sanitation to100% of the population
Government‟s focus to improve the urban infrastructure has increased significantly
during the last 10 years. The investment allocation to water supply & sanitation
during five year plan is INR 423 Bn.
• The year wise fund allocation growth rate in this five year plan is 21% which is
higher than the year wise growth rate of 15% during last five year plan.
• The JNNURM scheme commenced during the five year plan is the main driver for
urban infrastructure development. JNNURM scheme is focused towards strengthen
the infrastructure in 63 cities, the other schemes UIDSSMT & AUWSP focuses on
other cities/towns.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 13
• Water PPP‟s have emerged during the last 10 years & are fairly successful in India;
the central Government has planned to increase the number of PPP projects in order
to support state water authorities in improving the system efficiency
• The depletion of fresh water sources is driving the need of desalination projects &
these projects are expected to drive the growth of urban water infrastructure in the
coming years. The desalination projects are being planned & ongoing in certain
coastal cities
Source: JNNURM Website & Frost & Sullivan Primary Research & Analysis
Demand Analysis for DI Pipes
The demand drivers for pipes in general and DI pipes in particular are:
Economic growth
Demand for water
Urbanization
Improvement in water supply and sanitation coverage
Awareness on safety and hygiene
Investment by the Central and State Governments in Water and Sanitation
schemes
Assistance from external agencies
Inter-linking of rivers
Export potential
Investment in Water Projects and Role of Government Bodies
The central government had given thrust to improve the urban infrastructure during
the last 10 years and have been implementing various programs & schemes in the
WSS sector. Apart from the state governments also funds & undertake various
schemes. The funds for certain WSS projects are pooled from international banks &
financial institutions (World Bank, JICA, ADB etc. Key WSS Programs in India
JNNURM (Jawaharlal Nehru National Urban Renewal Mission) UIDSSMT (Urban
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 14
Infrastructure Development Scheme for Small and Medium Towns) AUWSP
(Accelerated Urban Water Supply Programme) Program Description
Flagship program for improving urban infrastructure
Focuses on 63 mission cities
Program covers the cities & towns which are not covered under JNNURM
Focuses on improvement on urban infrastructure facilities & PPP projects
Aimed at extending WSS services in smaller cities & towns
Partly funded by central government & partly by state government/municipal
bodies
Government/municipal bodies: It is estimated that at the current rate of growth, in
about two decades, water demand in India and China together will be thrice the
world‟s current consumption. Budgetary outlay for Indian government‟s 12th 5-yr
plan 2012-17 for water supply and sanitation is more than Rs. 255,310 crores which
is significantly higher than previous plan.
Increasing investment of government in water and sanitation projects, the main driver
for DI pipe demand is evident from the figure below.
External Aid
Water resources projects in India are supported by multilateral or bilateral aid,
grants, loans, and commodity aid from foreign countries as well as donor agencies
such as the International Bank of Reconstruction and Development (IBRD) commonly
known as the World Bank. During 2013, the Sian Development Bank has sanctioned
projects worth Rs 8800 crores for projects to improve drinking water and sanitation in
major cities like Delhi and Kolkata along with projects in Rajasthan. The National
Ganga River Basin Authority (NGBRA) has received one Billion USD financing from
the World Bank.
The Ministry of Water Resources, Government of India assists the state governments
in tying up external assistance from different funding agencies to fill up the resource
gaps.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 15
Water resources projects have also been funded through bilateral support of France,
Australia, Canada, Germany, and the Netherlands
Industry Analysis
While the purchase of pipes in general has increased, the share of DI pipes in the total
purchase of pipes has increased significantly from 33% to 52%. The share of other
pipes has been either declining or stagnant. The plastic pipes used are predominantly
PVC pipes and recent increase in use of HDPE pipes in competition for PVC pipes. The
other pipes include GRP, BWSCC pipes, Hume pipes, stoneware pipes, etc. GRP pipes,
RCC pipes, and stoneware pipes are used predominantly in sewerage applications.
The increasing share of DI pipes obviously indicates its rising acceptance by
customers and its growing popularity. The increasing share of DI pipes indicates that
DI pipes are gradually replacing all other pipes, especially steel pipes. The government
bodies have virtually stopped purchase of CI pipes for potable water supply and the
existing CI pipelines are increasingly being replaced by DI pipes. Plastic pipes and
cement pipes (AC/RCC/PSC) are also being replaced in urban and semi-urban areas;
however, in rural water supply schemes they still exist due to the low initial
investment.
Preference of Pipe Materials
The choice of the pipe material, on technical grounds, is governed by two major
factors: the pipe diameter and the area of application, i.e., transmission or
distribution. The general preference of pipe materials for water supply projects are
available in three different diameter ranges and used in urban, semi-urban, and rural
areas. DI pipes are widely preferred in urban and semi-urban areas. In urban and
semi-urban areas, uncovered water is considered unsafe and it is mandatory to
provide piped water supply to prevent pollution and contamination of drinking water.
Moreover, in the urban and semi-urban areas, DI pipes are preferred because they are
the best suited in places where heavy traffic loads, digging for cable laying and
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 16
bridges/flyover, etc. are quite common. In diameter sizes above 600 mm, MS pipes are
preferred because the initial investment is less as compared to that of DI pipes. DI
pipes are preferred in the lower diameter sizes, for both high-pressure transmission
and low-pressure distribution system. However, the users are increasingly considering
the life cycle cost (LCC) rather than just the initial investment because this factor is
being focused in tender evaluation as well. The government departments and
organizations are well aware of the long-term economic benefits of using DI pipes in
water supply and sanitation projects.
Inter Linking of Rivers (ILR) Project
Inter Linking of Rivers (ILR) project is Government of India‟s proposal to link 37 rivers
through 30 links, dozens of large dams and thousands of miles of canals, making it
the largest water project in the world. Once this project is set in motion, there will be
an unprecedented demand for not only DI pipes and fittings, but also services for
design, implementation, project management, and maintenance.
The project offers an excellent opportunity for M/s Rashmi Metaliks Limited (RML)
enhance its production capacity from 2, 00,000 TPA to 5, 50,000 TPA in same
premises.
2.5 Imports vs. Indigenous Production:
India is self sufficient to meet the demands of the market with the GDP projected at
10 % in the coming decades and in view of the infrastructure. Facilities going across
the region the growth rate of demand will increase to meet the expansion of new
proposal are muted.
2.6 Export Possibility
Total global DI pipe production is about 5.4 million TPA, out of which dependence on
import by various countries is about 500,000 TPA. Export ratio is 10 – 40%. Middle
East and Asia is everybody‟s target. Low domestic capacity and production has been
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 17
the major constraint that inhibited exports of DI pipes from India. India has the
competitive advantage of being strategically located to cater to Asian, South Asian,
and Middle East countries. The Middle East is a very prospective region for DI pipes
because being water scarce, as the countries in the Middle East give special focus on
water supply and sanitation. During the last four years, India exported DI pipes to as
many as 37 countries of which the regular destinations have been Algeria, Brunei,
Hong Kong, Qatar, Singapore, Spain, Sri Lanka, Sultanate of Oman, and UK. Thus, DI
pipes will continue to be in good demand in these countries in the forthcoming years
as well.
Kharagpur being nearer to both Orissa and Jharkhand states, the select plant
location is ideal for growing markets especially East & North East states. Further,
proximity to the Haldia port is ideal for export of DI pipe to neighbouring country and
Middle East. Also company has own private Railway siding for raw materials inwards
and finished goods outwards.
2.7 Domestic / Export Markets
There are number of units engaged in the manufacture of DI pipes in India and the
total installed capacity (as on June 2015) is around 2.42 MnT & the production
during 2015– 16 is estimated to be 1.51 Million MT.
The average capacity utilization is around 57%, which may go up to 70% during 2016-
17 and the production is likely to go up to 1.70 MnT during 2016-17.
The investment allocation to water supply & sanitation during the 12th five year plan
is INR 255319 crores. Based on prior experience, it is estimated that 13% of this
expenditure to be on DI pipes.
Considering domestic demand and the requirement from the export market, Pipes
demand is expected to reach 1.99 MnT by 2016 – 17. The detail about the demand
supply gap is given in Table-2.2.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 18
Table-2.2- Demand Supply Gap
With the demand growing and the supply scenario showing incremental growth, the
demand supply gap is set to increase to 0.29 MnT.
The investment in water supply and sanitation sector by the Central and State
governments registered a compound annual growth rate of 18.5% from the end of the
8th Five Year Plan to the end of the 11th Five Year Plan.
Supply constraints in the past have inhibited market expansion and the industry is
yet to pick up momentum. DI pipes being at the beginning of its product life cycle, it is
expected that the growth trajectory will be very buoyant at least in the next decade or
so after which it may mature to a stable level.
2.8 Employment Generation (Direct & Indirect) due to the project:
The project will create the direct employment of 300 Peoples during the construction
phase and around 600 Peoples will be involve during operational period. Skilled and
unskilled people on daily average will be employed. RML will give preference to the
local peoples during construction and operation phase of the project depending upon
the skill, job requirement and capability. Several others around 200 indirect
employment opportunities will be created in the surrounding areas by transport,
business, vehicle drivers and attendants, workshops, grocery and retails, medical, etc.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 19
3. PROJECT DESCRIPTION
3.1 Types of Project
M/s Rashmi Metaliks Limited, is going to enhance the production capacity of
Ductile Iron Pipe Plant from 2,00,000 TPA to 5,50,000 TPA phase wise (the detail
is given in Table-3.1) at Mouza – Nandarchak (J.L. No.-124), Sujatpur (J.L. No.-139)
& Khidipur(J.L. No.-140) Village – Gokulpur, P.O – Shyamraipur, P.S – Kharagpur (L),
Dist. Paschmi Mednipur in the state of West Bengal within the same premises near to
the existing DIP Unit.
Table 3.1- Proposed Expansion Project Detail
Sr. No Plant Existing
(TPA)
Proposed (TPA) Total
(TPA) Phase-I Phase-II
1 Ductile Iron Pipe 2,00,000 1,50,000 2,00,000 5,50,000
3.2 Process Concept and Technology
a) Process Concept and Technology
Ductile Irons Pipe‟s Manufacturing Process consists of various processes; they are
1. Molten Hot Metal preparation and Chemistry correction
2. Magnesium treatment
3. Centrifugal Casting
4. Core Making
5. Mold Maintenance
6. Heat Treatment by Annealing Furnace
7. Zinc Coating
8. Hydraulic Pressure Testing
9. Cement Motor Lining
10. Bitumen Coating
11. Finishing
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 20
A ductile iron pipe is produced with centrifugal casting method. The molten ductile
iron is poured into a rapidly spinning water-cooled mould and centrifugal force results
in an even spread of iron around the circumference.
A schematic process flow diagram is given in Figure-3.1.
Each process will explained in below
1. Molten Hot Metal Preparation: In Blast Furnace Hot Metal, Carbon percentage
(%) is usually 4.2 % to 4.3 %. But in DIP, Carbon percentage is 3.6 %. Therefore
Steel Scrap with 0.3 % Carbon is to be added by about 12 % to 15 % of BF Hot
Metal.
2. Magnesium Treatment: During this process, molten Hot metal treated with
Ferro Alloys, like Silico-Manganese, Magnesium, carbon etc. and melted with
14600-15200 C of temperature. The sphere-iodization process has been carried
out in the crucibles at about 1500 °C by tundish treatment and it was
performed by means of 2,1 % of Fe-Si-Mg. Next, molten iron will be poured to
the cast process.
3. Centrifugal Casting: Centrifugal casting requires water cooling metallic and
centrifugal casting machine that works automatically. Types of the machine are
divided as the pipe dimension (DN). Here For example, there are machine for
DN80-300mm, machine for DN400-700mm or machine for DN700-1000mm.
During the process, the molten iron will be poured to the volumetric ladle.
When the molten iron entered the mould spinning, it needs water high speed
spin through the long through for the water cooling system. During this
process, the solidification process will be started. Finally, the extractor will
extract the pipe after it solidified completely.
4. Core Making: Core making equipment consists of manual machine and
automatic machine known as core-making jets. Silicon sand, solidifying agent
and resin will be mixed and rolled. Then it‟s moved to the hopper of the core-
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 21
making jets machine with a conveyor. Core making process will be started by
jetting that material into core box. When it‟s solidified completely core will be
made and tested. Next, core will be conveyed to casting process.
5. Mould Maintenance: To remove the rust in the internal surface of a mould, it
will be grounded with sand wheel before it‟s dotted with penning head to
increase its crack resistance. If cracks found on the mould surface, it will be
removed by turning the mould and welding the turning area. Next grinding and
penning will accomplish the maintenance.
6. Annealing/ Heat Treatment : The process consists of heating section, heat
holding section, slow cooling section and fast cooling section. Ductile iron pipe
will be entered to this 52 meters long machine and rolled on it. Certainly its
temperature will be controlled.
7. Zinc Coating: Adhesive molten zinc will be extracted to external surface of pipe.
EN 545/598 mandates a minimum zinc content of 130 g/m2 (with local minima
of 110 g/m2 at 99.99% purity), and a minimum average finishing layer
thickness of 20 µm .
8. Finishing and Hydrostatic Testing: Pipe dimension will be checked here and
it‟s important to remove the fins on the external and internal surface. A
Hydrostatic checking will be done in 10 seconds with proper pressure refers to
the dimension.
Hydraulic pressure for hydrostatic testing
Nominal Diameter (mm) Hydraulic Pressure (Mpa):
80≤DN≤300, 200≤DN≤600, 700≤DN≤1000, 1100≤DN≤2000
9. Cement Lining: Pipe will be rolled with low speed and it will be sprayed with
material. This material includes cement, sand, and water. Pipe will be rolled
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 22
with high speed to move excessive water and deposit cement. Nature cure will
be given to cement lining. Grinder will smooth its surface
10. Bitumen Coating: As zinc coating, bitumen will be sprayed to pipe. But it will
be done to internal and external surface. Bitumen will reduce the corrosive on
the internal surface.
11. Finishing: This process includes marking (trade mark), painting if it‟s required
and packing. It will pack with thick wood and bundled with steel belt.
Ductile Iron Metallurgy: Ductile Iron is an iron with elementary alloy such as
carbon, Si, Mn and Mg. Commonly, the carbon content on its structure is 3 % or
more. Ductile iron is one of the most important engineering materials, in view of its
excellent cast-ability, significantly better mechanical properties and low cost. Simply,
it‟s similarly to steel in strength, toughness, ductility and hardness.
Figure-3.1 Process Flow Sheet for Ductile Iron Pipe Manufacturing
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 23
Production Capacity/Batch Time Calculation:
Double Track Induction Furnace 2 Nos = 2 x 15 T with 6 crucibles (4 in operation and 2 stand by)
Induction Furnace Batch time -45 minutes
Operational Time-15 hours in a day
Maximum production- 60 Ton/Batch
No of working days in a year-300 days
Total Batch in a day-(15*60)/45 = 20 (Max.)
Therefore, annual Production =Batch per day x Maximum Production x No. of working
days in a year
= 20*60*300
= 3, 60,000 TPA
Considering breakdown /time lapse the annual production will be 3, 50,000 TPA
b) List of Machineries for the proposed Activities: -
The capacity enhancement of proposed plant will have a capacity to produce 5, 50,000
TPA of DI pipes in Phase Wise having a size range of DN 80 to DN 600.The detail is
given below:
Sr. No Plant Existing
(TPA)
Proposed (TPA) Total
(TPA) Phase-I Phase-II
1 Ductile Iron Pipe 2,00,000 1,50,000
Size of Pipe
(SDP I)
DN(80- 300
mm ) x 5.5 m
2,00,000
Size of Pipe
(SDP II)
DN(200- 600
mm ) x 5.5 m
5,50,000
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 24
The plant will comprise of the main plant & machinery indicated in following Table
3.2.
Table-3.2 List of the machineries required to be added to enhance production
Sr. No Machinery Quantity
(No.)
1 15 T Induction Furnace with 3 crucible ( 2 in operation & 1 stand by)
02
2 Annealing Furnace of 30 TPH for making SDP of Dimension
(DN-80-300 mm) x 5.55 m ; (DN 200-600) x 5.5 m
02
3 Magnesium Converter of 18 TPH 02
4 Zinc Coating Machine of 10 TPH 01
5 Centrifugal Casting machine of 5 TPH 10
6 Hydraulic Pressure Testing Machine 02
7 Cement Mortar Lining/ Curing System of 15 TPH 03
8 Bitumen Coating Machine with preheating & post heating
furnace
02
9 Pipe Socket Grinding/ Mould Grinding 02
10 Sand Drying & Conveying System 01
11 Finishing Line 02
Table-3.3 List of the machineries existing and proposed for achieving 5, 50,000 TPA productions
Sr. No Main Plant & Machinery Quantity (No.)
Existing Proposed Total
1 8 T Induction Furnace with 3 crucible ( 2 in operation & 1
stand by)
2 NIL 02
2 15 T Induction Furnace with 3
crucible ( 2 in operation & 1 stand by)
NIL 02 02
3 Annealing Furnace of 30 TPH 02 02 04
4 Magnesium Converter of 18 TPH 02 02 04
5 Zinc Coating Machine of 10 TPH 05 01 06
6 Centrifugal Casting machine of 5
TPH
10 10 20
7 Hydraulic Pressure Testing
Machine
05 02 07
8 Cement Mortar Lining/ Curing
System of 15 TPH
05 03 08
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 25
9 Bitumen Coating Machine with preheating & post heating furnace
05 02 07
10 Pipe Socket Grinding/ Mould Grinding
03 02 05
11 Sand Drying & Conveying System 02 01 03
12 Finishing Line 08 02 10
13 Core Shooter Machine 04 NIL 04
3.3 Raw Material required along with estimated quantity, likely source,
marketing area of final products/s, mode of transport of raw material and
finished product.
Raw Material Requirement
The major raw materials for DI Pipe manufacture is liquid pig iron, also known as hot
metal. 1.07 t of hot metal is required per tonne of DI pipe. The charge-mix will be 90%
hot metal and 10 % solids comprising of purchased steel scrap and reject pipes. Raw
materials to be sourced must fulfill the quality requirements demanded by process,
equipment and technological parameters. The annual requirement of raw materials
including other materials for the 5, 50,000 TPA capacity DI Pipe Plant is presented in
Table 3.3.
Table 3.3-Raw Materials** Requirement Detail
Sr.No.
Name of the Raw
Materials
Source (TPA) Mode of
Transportation
Estimated
Quantity
(TPA)
1 Pig Iron/ Hot Metal Rashmi Metaliks Ltd,
Kharagpur; Orissa
Metaliks Pvt. Ltd. ,
Kharagpur Plant
Through Crane/
conveying
System
3,75,000
2 Mold Powder Local Market Road 949
3 Refractory (WH-A+K) Local Market Road 2065
4 Ferro Silico Rashmi Cement
Limited, Jhargram
Rail/ Road 1050
5 Inoculants Local Market Road 336
6 Magnesium Local Market Road 595
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 26
7 Slag Coagulant Local Market Road 485
8 Zinc Local Market Rail/ Road 662
9 Runner Coat Local Market Road 1789
10 Bitumen/ Epoxy Paint WRAS Approved
Vendor
Rail/ Road 1472 KL
** The above quantities are likely to vary in narrow range as the quality of inputs to
have variations.
Table 3.5-Materials Balanced For the Proposed Project
Name of the Input Materials
Quantity input in (TPA)
Name of the output Materials Quantity output in (TPA)
Hot Metal from B.F 3,75,000 D I Pipes 3,50,000
Mold Powder 949 Slag 10500
Refractory (WH-A+K) 2065 Dust & Sludge 8403
Ferro Silicon 1050 LOI, etc 15500
Inoculants 336
Magnesium 595
Runner Coat 1789
Slag Coagulant 485
Zinc 662
Bituminous Solution 1472 KL/ Year
Total 384403 384403
3.4 Availability of Water, Energy /Power Requirement & Its Sources
POWER:
The power required for the proposed production enhancement project will be 10 MW
sourced from WBSEDCL.
Table 3.6-The Power Requirement for the production enhancement project is as:
SR NO PRODUCT GROSS CAPACITY SPECIFIC
POWER CONSUPMTION
TOTAL CONSUMED
POWER
LOAD FACTOR
CONNECTED LOAD
TPA TPD TPH IN KWH IN KWH IN KWH
1 DIP 350000 1166 49 158.8 7781.2 0.80 9726.5
2 OFICE , STREET LIGHT
4
POWER REQUIRED IN KWH 7781.2 0.80 9730.5 IN MWH 7.78 9.73
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 27
TABLE 3.7-The Total Power Requirement
Sr. No Utility Existing
Requirement
Additional
Requirement
Total Source
1 Power 5.5 MW 9.73 15.23 West Bengal State
Electricity Distribution
Company Limited
WATER:
The existing plant water is 20 m3/hr (480 KLD) and additional water requirement for
the proposed expansion project is about 34.5 m3/hr (830 KLD). The break-up of water
required for existing and proposed is given in Table-3.8.
This requirement will be met from the River “Kasai‟ & ground water sources by bore
wells and Rain Water Harvesting pond. Rashmi Metaliks Limited has already obtained
permission for withdrawal of 1 MGT water from „Kasai‟ river & 0.6 MGT from bore well
and has already made another application for obtaining permission for additional 1
MGT withdrawal from‟ Kasai‟ River to SWID for industrial uses and it is in final stage
of approval. The water withdrawal permission is enclosed as Annexure-V. So, it is
clear that required water will be managed by River „Kasai‟, Bore Well and Rain Water
Harvesting pond.
Table 3.8-The Total water Requirement for the complete project (existing &
proposed) is as:
Sr. No Utility Existing
Requirement
(KLD)
Additional
Requirement
(KLD)
Total after
Expansion
(KLD)
1 Induction furnace 126 230 356
2 Centrifugal Casting 233 380 613
3 Annealing Furnace 64 64 128
4 Zinc Coating Machine 3 18 21
5 Hydraulic Pressure Testing Machine
35 62 97
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 28
6 Cement Mortar Lining Machine
10 45 55
7 Bitumen/ Epoxy Coating 4 22 26
8 Green Belt Development/ Dust Suppression
2 5 7
9 Domestic Use 3 4 7
Total 480 830 1310
3.5 Quality Assurance
DI pipes need to conform to stringent quality standards as they are used to transmit
drinking water. Pipes are produced according to the stipulations of applicable quality
standards as below:
Indian standard - IS 8329: 2000, and
International standards – ISO:2531
International standards - BS EN 545: 2002
In order to attain stipulated specifications, stringent quality assurance measures will
be enforced at every stage of production which will include chemical analysis, visual
inspection, pressure testing, pipe thickness measurement, cement lining thickness
measurement, bitumen coating thickness measurement, physical testing, etc.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 29
4. SITE ANALYSIS
4.1 Connectivity
The project site is well connected to Howrah (110 Kms), Kharagpur and to Tata Nagar
(120 Kms) via Ghatsila. It is nearest city Kharagpur is at a distance of 4.5 Kms and
Jhargram Town 30 kms. The nearest Railway station Gokulpur railway station at a
distance of about 1.0 kms is the railway station on broad gauge line of South Eastern
Railway connecting Howrah and Jamshedpur. This distance chart of major cities and
towns in WB from the project Site is as below.
M/s Rashmi Metaliks Limited, is going to enhance the production capacity of
Ductile Iron Pipe Plant from 2,00,000 TPA to 5,50,000 TPA phase wise (the detail
is given in Table-3.1) at Mouza – Nandarchak (J.L. No.-124), Sujatpur (J.L. No.-139)
& Khidipur(J.L. No.-140) Village – Gokulpur, P.O – Shyamraipur, P.S – Kharagpur (L),
Dist. Paschmi Mednipur in the state of West Bengal within the same premises near to
the existing DIP Unit.
4.2 Land form, Land use and Land Ownership
The proposed capacity enhancement project will be carried out within the existing
plant area and around 10 acres of land will be required. The required 10 acres land is
already in possession by Rashmi Group in the name of M/s Rashmi Metaliks Ltd.
To Distance in kms (Approx.)
Jhargram 30
Kharagpur 4.5
Howrah 110
Tata Nagar 120
Durgapur 125
Medinipur 6.5
Haldia (Port) 92
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 30
As per existing land used pattern, land is generally flat and no major earth filling is
required for the proposed capacity enhancement project within the same premises
near to the existing DIP Unit.
4.3 Location of the Project
M/s Rashmi Metaliks Limited, is going to enhance the production capacity of
Ductile Iron Pipe Plant from 2,00,000 TPA to 5,50,000 TPA phase wise (the detail
is given in Table-3.1) at Mouza – Nandarchak (J.L. No.-124), Sujatpur (J.L. No.-139)
& Khidipur(J.L. No.-140) Village – Gokulpur, P.O – Shyamraipur, P.S – Kharagpur (L),
Dist. Paschmi Mednipur in the state of West Bengal within the same premises near to
the existing DIP Unit.
Total land requirement is 10 acres which is already in possession by Rashmi Group in
the name of M/s Rashmi Metaliks Ltd.
The proposed plant will be located at longitude 87017‟46.89”E and latitude
22021‟40.44”N and elevation 112 feet from mean sea level at village-Gokulpur, Dist.
Paschim Medinipur, West Bengal.
The nearest airport is Netaji Subhash Chandra Bose International Airport at distance
of about 123 KM from the proposed project site.
The proposed plant site is at distance of around 4.5 Km from Kharagpur Junction
Railway Station on Howrah- Mumbai broad gauge railway line of South-Eastern
Railway and Gokulpur Railway line is only 1.5 KM away from the project site.
Nearest port is Haldia Port which is around 135 KM away from the proposed project
site. Private Railway siding of RML is around 2 KM from the proposed project site and
generated power will be consumed the existing unit operation.
This site is favourable for proposed capacity enhancement project for following
reasons
1. Availability of adequate Land
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 31
2. Availability of Railway Siding which is only 1 KM from the proposed project site.
3. Availability of Raw Materials like hot metal which will be obtained from Rashmi
Metaliks Limited and from adjacent unit i.e. OMPL.
Pic.4.1: LOCATION OF THE PROPOSED PROJECT SITE
District wise State Map of West Bengal Kharagapur Block – I
Pic.4.2-Satellite Google Imaginary for the proposed project site
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 32
Pic.4.3-Toposheet of Project site
4.4 ALLTERNATIVE SITE SELECTION
In this case, have no option to select the alternative site because this project is an
expansion project within the existing plant premises. Hence, no alternative site where
examined.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 33
4.5 Topography (along with map)
Based on the contour map, the Digital Elevation Model has been prepared. The
nearest neighbour method has been used to interpolate the elevation data to develop
the elevation model. This map gives clear picture that the South-Western part of the
area having higher elevation ranges from 50-79 m. Eastern part of the area has lowest
range of elevation from 22-50m. Remaining area shows the medium elevation from
35-55m.
The Digital Elevation Model for the area in 10 km radius from the proposed site is
shown below.
Pic 4.4-Satelite Immage in 10 km radius
Site Location: Village Gokulpur, Mouja-Nandarchak, Sujatpur, Khidirpur Tehsil-
Kharagpur (Block), District Paschim Medinipur, West Bengal
Site Co-ordinate:
Latitude 22˚21′40.44″N & Longitude 87˚17′46.89″E, MSL- 112 ft.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 34
4.6 Existing Land used Pattern
Proposed plant site does not falls under the CRZ area or notified industrial area. Its
graphical coordinates longitude 87˚17′46.89″E and latitude 22˚21′40.44″N and
elevation 112 feet from mean sea level (MSL). River Kangsabati are passing approx. 4
km distance in the northern side w.r.t the project site. The project site is generally
flat, infertile, non-irrigated land. Land Use Pattern of 10KM area shown below:
Land Use Pattern Of T Area
4.7 Soil Classification
Predominantly the texture of the soil is clay. Sand, slit and clay percentage ranges
form 22-27%, 32-35% and 40-43% respectively.
Sl.
No Class
Area
(km2)
Area
(%)
1 Forest 29.90 9.51
2 Village Orchard
70.33 22.38
3 Farmland:
Fallow
119.4
2 38.00
4 Farmland:
Cropped 13.71 4.36
5
Culturable
Waste
(mainly
grass)
35.43 11.27
6
Wasteland
(mainly
laterite)
7.63 2.43
7 Urban Area
/ Paved 23.76 7.56
8 Sand 8.83 2.81
9 Water 5.28 1.68
Total of all
classes 314.29 100.00
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 35
4.8 Climate Data from Secondary Sources
A meteorological station was also established earlier at Plant site to generate site-
specific meteorological data on hourly wind speed, wind direction, ambient
temperature and relative humidity. Measurement techniques, instruments,
specification of measurements and accuracy of instruments for meteorological
parameters from the Indian Standard: 8829-1978 "Guidelines for Micrometeorological
Techniques in Air Pollution Studies" were followed for data generation. The site-
specific wind-rose generated during summer season.
Temperature – December and January constitutes winter months with daily mean
minimum temperature around 12.8oC and daily mean maximum temperature around
26.4oC. May is the hottest month with daily mean maximum temperature at 38.4oC
and daily mean minimum temperature at 25.9oC. During the study period the daily
mean minimum temperature was found to be 24.3oC and daily mean maximum
temperature around 38.7oC.
Relative Humidity – The air is generally dry in the region except during monsoon.
April and May are driest with relative humidity between 43-66%. The maximum
humidity during rainy season is 84% and minimum was 70%. High humidity is found
during daytime and low humidity values during night time in all the months. During
the study period the humidity levels were found to be 40 –71 %.
Rainfall – The annual total rainfall is 1478 mm. Over 80% of the total annual rainfall
is received during the monsoon period between July to September.
Wind Speed– The wind speed was mostly between 3.1 – 9.0 km/hour for all the
months.
WIND - The wind speed during summer season was mostly between 6.8 – 9.0 km/hr,
during rainy season it was between 5.0 – 6.8 km/hr and in winter months wind speed
ranges between 3.1 – 3.3 km/hr.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 36
Wind Direction – The predominant wind direction is from South and South West for
all months except winter season. During winter the wind flows from north and North
West direction. The wind direction (dominant) during the study period was from south
west direction.
4.9 Social Infrastructure availability:
All infrastructure facilities such as Education, Health facilities and other Social
facilities are adequate at Kharagpur town which is around 4.5 KM and district head
quarter Medinipur is 6 KM from the proposed project site. Entire area is enjoying the
modern facilities. RASHMI Group always tries to socio-economic up liftmen of entire
area since 2006.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 37
5.0 Planning Brief
5.1 Planning Concept (types of industries, facilities, transportation etc) Town
and Country planning/Development authority Classification
During planning phase of the proposed project the following steps will be carried out:
1. Feasibility studies
2. Technical appraisal and due diligence
3. Project development planning, permitting and consenting
4. Environmental audits and impact assessments
5. Financial and thermal modelling, business planning
6. Tariff studies, power purchase agreement
7. Conceptual and pre-engineering design
8. Implementation planning and cost estimating
9. Special studies and risk assessment
The proposed project is for enhancing the capacity of Ductile Iron Pipe Plant from
2,00,000 TPA to 5,50,000 TPA by the name of M/s Rashmi Metaliks Limited in
phase wise, at Mouza – Nandarchak (J.L. No.-124), Sujatpur (J.L. No.-139) &
Khidipur(J.L. No.-140) Village – Gokulpur, P.O – Shyamraipur, P.S – Kharagpur (L),
Dist. Paschmi Mednipur in the state of West Bengal.
The rail and road will be developed/strengthened around the plant for
transportation of raw materials. This will also enhance the transportation facilities
of the area.
As the project is envisaged to employ 200 indirect employees during construction and
operation phase and 300 direct employees so the basic infrastructure facilities like
medical facilities, schools, playground, drinking facilities, bank, post offices etc. will
be developed and the same can also be used by nearby villages.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 38
5.2 Population Projection
The increasing in production capacity of Ductile Iron Pipe Unit from 2, 00,000 TPA to
5, 50,000 TPA in phase wise would aid in the overall social and economic development
of the region. The plant will give direct employment to about 300 people; in addition
there will be indirect employment to many more people in the form of out sourcing
jobs, business opportunities, service facilities etc. This will enhance the economic
status of the local region. Apart from the jobs, the company will provide medical and
educational facilities to the employees which can also be availed by the people around
the plant.
The Demographic and Socio economic characteristics with regards to demography,
literacy and occupational status will be describe in EIA report.
5.3 Land use Planning
Sr. No. Particulars Existing
(Acres)
Proposed
(Acres)
Total Area
(Acres)
1 Ductile Iron Pipe Unit 4 6.7 11.7
2 Raw Material Yard 2 -- 2
3 Storage Yard 2 1 2
4
Administrative Building/
Canteen 0.5 -- 0.5
5 Reservoir 1.0 -- 1.0
6 Road 0.5 -- 0.5
7 33% Green Belt 5 3.3 8.3
TOTAL AREA 15 10 25
5.4 Assessment of Infrastructure Demand
Adequate physical and social facilities are available in this area for the proposed
production Capacity enhancement project of Ductile Iron Pipe Plant from 2, 00,000
TPA to 5, 50,000 TPA in phase wise
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 39
5.5 Amenities / Facilities
All infrastructure facilities such as education, health facilities and other social
facilities are adequate at district headquarter which site makes the region adequate in
amenities.
RML will take the initiative to develop the roads of the villages to provide better
connectivity to the nearest State and National highways. Apart from this the following
amenities will be developed:
A. Street Light and Avenue Trees
B. Well Maintained park with Children‟s Play area
C. Educational Institutions
D. Primary Health Centres / Hospital
E. Healthy camps and free medical check-up should be encouraged for local
population.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 40
6 Proposed Infrastructure
6.1 Industrial Area
Layout of the proposed capacity enhancement project has been optimized considering
the space requirements of the all the equipment and systems, buildings and
structures, green belt etc.
All facilities of the plant area will be laid out in close proximity to each other to the
extent practicable so as to minimize the extent of land required. The layout is also
facilitating the movement of men and materials between the various units both during
construction and subsequent operation and maintenance to entire project.
The general layout plan of the plant is attached in Annexure – I.
6.2 Residential Area
Residential colony does not required for the proposed production enhancement project
of Ductile Iron Pipe Plant from 2,00,000 TPA to 5,50,000 TPA in phase wise at Mouza
– Nandarchak (J.L. No.-124), Sujatpur (J.L. No.-139) & Khidipur(J.L. No.-140) Village
– Gokulpur, P.O – Shyamraipur, P.S – Kharagpur (L), Dist. Paschmi Mednipur in the
state of West Bengal because the local unskilled worker will be engaged, they will
work at plant from their own residence and the company has existing Guest house
there qualified expert will get the accommodation.
6.3 Green Belt
Extensive afforestation has been taken in the past by Rashmi Metaliks Limited (copy
of the same is enclosed as Annexure-II) at plant and will be undertaken for this
proposed capacity enhancement project which would not only act as long space in the
area but would also improve aesthetics. Local, fast growing species will be used for
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 41
Green Belt Development keeping in view the guidelines and directions of MOEF, Govt.
of India and W.B.P.C.B as well C.P.C.B.
6.4 Social Infrastructure
M/s Rashmi Metaliks Limited has well-defined ESR policy under which will Carry out
social development and welfare measures in the surrounding villages. The detail of the
ESR activities carried in the past by management of Rashmi Metaliks is briefed in
Annexure-IV. Under ESR activity RML to create partnership with its local
communities, RML under its Enterprise Social Responsibility (ESR) will take up
initiatives on three-focus areas
Education
Health & Sanitation
Sustainable Livelihood
The purpose of the ESR is to bring qualitative improvements in the lives of the
community residing in the vicinity of its activity of the activities. In addition to this,
RML focuses on sports and youth development programme, environment protection
drives and executes infrastructure development projects.
Keeping in mind the infrastructure needs of the area RML would focuses on the
following areas
Improving medical facilities in the village around the project area
Improving awareness and providing sufficient training in hygiene , sanitation
and proper diet
Encouraging people to send children to school and also educate themselves
through adult literacy programs
Improving education infrastructure by providing better teaching aid and
training for teaching faculty
Building skills among villagers as per skills requirements of the project during
constructing as well as during the operation time
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 42
Encourage entrepreneurial spirit among people and supporting such initiative
by conducting training programmes to acquire and enhance skill
Creating awareness about long term financial planning
2.5 % of the proposed project cost (Rs 4.125 Crore) will be earmarked for ESR
and will be spend in 10 year after proper planning.
6.5 Connectivity
The plant site is well connected by Road, Rail, Air and Water way. Plant is connected
to NH - 6 by a well maintained road which is passing at a distance of 15 KM from the
project site in East direction. Access road and internal roads are constructed within
the plant premises and maintained regularly.
Road Connectivity: The Plant site is well connected with NH-6 which is passing very
closed from the proposed project site.
Rail Connectivity: Nearest Railway Station is at Gokulpur, about 1.5 KM in north-
east and Kharagpur junction Railway station is around 5.0 KM from the plant site in
south-East direction.
Airport: Nearest Air Kolkata Netaji Subhash Chandra Bose International Airport
which is about 130 KM from the project site in North-East direction.
Port: Nearest port is at Haldia about 135 KM from project site in South-East
direction.
6.6 Sewerage System
Sewage from the various building in the plant as well as nearby locality will be routed
through sewage treatment aeration tanks; domestic waste water discharge will be
treated separately and used for green belt development within the premises.
6.7 Industrial Waste Management
The water treatment system of the project comprises of Water Pre-treatment Plant,
Water Dematerializing Plant, Chlorination Plant, Cooling Water Treatment Plant.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 43
6.8 Solid Waste Management
The present practice being used for solid waste management by RML is:
From Induction Furnace solid waste is generated in the form of slag which is
utilized in Road Filling and Land Reclamation.
From Magnesium converter slag is generated which is utilized for Road Filling and
Land Reclamation.
The Runner Scrap is re melted.
Magnesium dust is used in our existing Sinter Plant.
Core sand in Casting Area as well as the same from the Annealing Furnace is used
in Land Filling and reclamation now, and will be recycled in the future.
Zinc Dust is sold to PCB certified Paint manufacturer.
Cement slurry is taken to the Effluent Treatment Plant from which the water is
recycled and the solid is either be used to manufacture brick/cement tiles or is
sold to a manufacturer of the same.
Waste oil, used oil and other hazardous wastes will be safely stored in
drums/tanks/covered shed and sold to authorized recyclers.
Organic waste will be used as organic manure in the green areas. The municipal
waste will be given to authorized agencies for suitable disposal. The detail of solid
waste management is given in Table-6.1.
Table-6.1-Solid Waste Management
Sr. No. Particulars Existing
(TPA)
Proposed
(TPA) Disposal Scheme
1 Core Sand & Slag
5429 9500 Used for land filling
2 Cement Slurry 572 1000 Sold, Brick Manufacturing
3 From APC Devices –Mg & Zn Dust
4800 8403 Used in Sinter Plant,
4 Scrap Variable -- Used in Process
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 44
The waste generated due the capacity enhancement will be handled as per the existing
practices. Sewage will be treated in existing sewage treatment plant.
6.9 Power Requirement & Supply / Source
POWER:
The power required for the proposed production enhancement project will be 10 MW
sourced from WBSEDCL.
Table 6.2-The Power Requirement for the production enhancement project is as:
SR NO PRODUCT GROSS CAPACITY SPECIFIC
POWER CONSUPMTION
TOTAL CONSUMED
POWER
LOAD FACTOR
CONNECTED LOAD
TPA TPD TPH IN KWH IN KWH IN KWH
1 DIP 350000 1166 49 158.8 7781.2 0.80 9726.5
2 OFICE , STREET LIGHT
4
POWER REQUIRED IN KWH 7781.2 0.80 9730.5 IN MWH 7.78 9.73
TABLE 6.3-The Total Power Requirement
Sr. No Utility Existing
Requirement
Additional
Requirement
Total Source
1 Power 5.5 MW 9.73 15.23 West Bengal State
Electricity Distribution
Company Limited
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 45
7 Environment Management Plan
Environmental Management Plan is the key to ensure a safe and clean environment.
Our plant may have taken proper pollution control measures but without a
management plan to assure its proper function, the desired results may not be
obtained.
7.1 EMP during Construction Phase
The impacts of the proposed construction phase on the environment would be
basically of transient nature and are expected to wear out gradually on completion of
the construction program. However, once the construction of the units will be
completed and its operations started, these operation stage impacts would overlap the
impacts due to the construction activities.
In order to mitigate such impacts and restrict them within tolerable levels, the
Authorities would adopt the following measures:
i) Designation and demarcation of sites for construction camps and ensuring due
provision of necessary infrastructural services as water supply, sewerage and
drainage facilities and electrification.
ii) Implementation of necessary drainage facilities, inclusive of catch pits or
sedimentation basins for the drainage of construction wastewater, prior to discharge.
iii) Regular sprinkling of water around vulnerable areas of the construction sites from
trucks or through installation of water sprinklers or any other suitable methods, to
control fugitive dust as and when required.
7.2 EMP during Operation Phase
The present practice being used by RML management in order to keep the pollution
load within the permissible limit is:
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 46
7.2.1 Air Pollution Management Plan
Fugitive Emission control :
All pollution control systems are connected to energy meters and the records
are maintained for run hours, failure time and efficiency.
Clean technologies/measures are implemented in the following way.
Flue gases are used for drying the Green pellet.
De-dusting is provided for product handling area.
Fugitive emissions are suppressed by using dust suppression system
Every possible effort is made to conserve the raw materials, energy and water
consumption to match with the international standards.
Good housekeeping practices are maintained
Raw Materials Handling Plant :
All vibrating screens are already covered to preventing the leakages of Dust
Dust suppression system (Pulse jet Bag Filter with Silicon coating bags) is
adopted to control the fugitive dust emanated during extra quantity of raw
materials unloading operations.
Raw Materials Storage system :
All discharge and feed points wherever the possibility of dust generation is there,
are provided with dust suppression system.
All material transfer points are connected with dust suppression water nozzles to
avoid the pollution
Control of Point Emission :
Clean gases having less than 150 mg/Nm3 of dust content are exhausted
through a stack of height 35 m height.
The Detail of Existing APC devices are mentioned in Table 7.1 and their
characteristics in Table-7.2.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 47
Sr. No. Details Installation capacity as
per EC, & NOC Awarded
Existing Machineries
Air Pollution Control System
Stack Detail
1 Induction Furnaces
2 X 8 MT with 6 Crucibles
2 X 8 MT with 4 Crucibles
Swivelling Hood, Spark Arrestor, Bag Filter & ID Fan.
Bag filter- Capacity
60,000 m3/hr
Existing Common Stack Height:- 35 meter from GL
2 Centrifugal
Casting machine
10 X 5 TPH 10 x 5 TPH Not Required Not Required
3 Magnesium Converter
2 X 18 TPH 2 X 18 TPH Common Bag Filter With one in Stand By Mode.
Existing Common Stack Height:- 35 meter from GL
4 Annealing Furnaces
2 X 30 TPH 2 X 30 TPH Not Required Existing Common Stack Height:- 35 meter from GL
5 Zinc Coating Machines
5 X 10 TPH 3 X 10 TPH Common Bag Filter
Bag filter- Capacity 25,000 m3/hr
Existing Common Stack Height:- 35 meter from GL
6 Cement Motor Lining & Cement Curing system
5 X 15 TPH 4 X 15 TPH Not Required Existing Common Stack Height:- 30 meter from GL
7 Bitumen Coating Machine with per-heating & Post-heating Furnaces
5 X 15 TPH 4 X 15 TPH Not Required Existing Common Stack
Height:- 35 meter from GL
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 48
Characteristic of Pollutant Emission Source: Table-7.2
Source Pollutants Control measures
A. Air pollution
B. Domestic wastewater
C. Solid Waste
Dust and Fumes
Waste water
Dust
Bag / cascade filters would be provided
in various sections of material handling and processing units for controlling air
pollution. The waste gases would be discharged through tall stacks to ensure adequate dispersion and
dilution of pollutants.
To be used for green belt.
Collected dust from the control devices
will be recycled in the process.
8 Sand Drying & conveying system
02 Nos. 02 Nos. Existing Common Stack Height:- 15 meter from GL
9 D.G. Set 01 x 725 KVA 01 x 725 KVA
All DG Sets are acoustically enclosed and as per CPCB norms
Existing Common Stack Height:- 10.5
meter from GL
10 Core Making
Machine
03 Nos. 02 Nos. Not Required Not Required
11 Hydraulic
Pressure Testing
Machine
05 Nos. 04 Nos. Not Required Not Required
12 Mould Grinding
and Arc Welding
machines
03 Nos. 02 Not Required Not Required
13 Core shooter
Machine
04 Nos. 02 Not Required Not Required
14 Finishing Unit 08 Nos. 05 Not Required Not Required
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 49
The detail of proposed APC devices for the capacity enhancement project is mentioned
in Table-7.3
Table – 7.3-Proposed APC Devices for Expansion project
Sr. No. Particulars Quantity/ capacity
Name of the APC Devices
Proposed Stack Height
1 15 t Induction furnace
02 Nos. with 6 crucibles (4 in operation & 2 stand by)
Pulse Jet Bag Filter of sufficient capacity, Swivelling Hood, Spark Arrestor, ID Fan for individual Induction Furnace
35 Meter Individual
2 Annealing Furnace
02 x 30 TPH Not Required 35 Meter Individual
3 Magnesium Converter
02 x 18 TPH Bag Filter 35 Meter Individual
4 Zinc Coating Machine
01 x 10 TPH
Bag Filter 35 Meter
5 Centrifugal Casting Machine
10 x 5 TPH
Not Required 35 Meter
6 Hydraulic Pressure Testing Machine
02 Nos.
Not Required -----
7 Cement Mortar Lining/ Curing Machine
03 x 15 TPH Not Required 35 Meter
8 Bitumen Coating Machine
02 x 15 TPH Not Required
35 Meter
9 Mould Grinding/ Pipe socket Grinding
02 Nos. Not Required -----
10 Sand Drying & Conveying System
01 No. Not Required 15 m
11 Finishing Line 02 Nos. Not Required -----
Existing APC DEVICE pictures are shown as Figure7.1
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 50
7.2.2 Noise Pollution Management Plan
Noise will be minimized through regular maintenance of equipment / machines. Low
noise generating equipment is being used for the plant. Proper vibration dampening
arrangement is being provided to minimize the noise generation. It is ensured that the
noise level at plant boundary compiles with the standards of 75 dB (A) during day
time and 70 dB (A) during night time. The layout of the plant and greenbelt is
designed appropriately to achieve the standard. In other case enclosure or sheds is
constructed. Ear plugs / ear muffs are provided to personal working near high noise
areas to ensure that no plant personnel are over exposed. Sound absorbing material is
provided in rooms where both the noise source and plant personal is present so that
the reflecting sound is absorbed.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 51
7.2.3 Water Pollution Management Plan
Waste water disposal method of septic tank is being followed as per the standard
regulations of PHED W.B. Neutralized water is let into the factory‟s general drainage
network. Outlet of the general drainage network is sent to the Effluent Treatment
Plant for further neutralization and recirculation. We also have a storm water
drainage network in place separately where the water is taken for Rain water
Harvesting.
Effluent Treatment Plant:
At present solid waste of around 106 kg/day coming out of the cement lining
process. This slurry is pumped into sedimentation chambers of the E.T.P. The
sediments thus deposited into the sedimentation chambers. These sediments are
periodically removed with the help of a Mechanical shovel or Excavator. The solid
waste thus collected is removed to a drying bed and dried. After that it is
converted to brick or tiles or is sold to a manufacturer of the same. The turbid water
is taken for further neutralization since the ph value is around 12 and adequate
acid dozing is done to bring the ph nearer to 7. The said neutralized water is re-
circulated into the process. The detail of existing ETP plant is shown in Figure 7.2.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 52
7.2.4 Pathway of Pollutants (Seepage into Groundwater)
Raw materials stock pile, open dump yard is made inside the plant premises, which
have the potential to contaminate the groundwater level through seepage. Following
mitigation measures are recommended to avoid any groundwater contamination:
1. Stockpiles of all raw materials and coal is made on pucca platform (preferably
concrete / clay compacted) and provided with garland drains and sedimentation
pit.
2. Stockpiles preferably being covered using tarpaulin, etc.
3. Wind breakers in the form of tin sheds are installed around open stock yard.
7.2.5 Solid Waste Management Plan
The present practice being used for solid waste management by RML is:
From Induction Furnace solid waste is generated in the form of slag which is
utilized in Road Filling and Land Reclamation.
From Magnesium converter slag is generated which is utilized for Road Filling and
Land Reclamation.
The Runner Scrap is re melted.
Magnesium dust is used in our existing Sinter Plant.
Core sand in Casting Area as well as the same from the Annealing Furnace is used
in Land Filling and reclamation now, and will be recycled in the future.
Zinc Dust is sold to PCB certified Paint manufacturer.
Cement slurry is taken to the Effluent Treatment Plant from which the water is
recycled and the solid is either be used to manufacture brick/cement tiles or is
sold to a manufacturer of the same.
Waste oil, used oil and other hazardous wastes will be safely stored in
drums/tanks/covered shed and sold to authorized recyclers.
Organic waste will be used as organic manure in the green areas. The municipal
waste will be given to authorized agencies for suitable disposal. The detail of solid
waste management is given in Table-7.1.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 53
Table-7.1-Solid Waste Management
Sr. No. Particulars Existing
(TPA)
Proposed
(TPA) Disposal Scheme
1 Core Sand & Slag
5429 9500 Used for land filling
2 Cement Slurry 572 1000 Sold, Brick Manufacturing
3 From APC Devices –Mg & Zn Dust
4800 8403 Used in Sinter Plant,
4 Scrap Variable -- Used in Sinter Plant,
7.3 Occupational Health Management Plan
Exposure problems to noise, dust, heat and gases are the main occupational hazards
identified in this project. Silicosis, Bronchitis and Noise induced hearing loss are the
occupational health hazards identified from the plant. Workers involved in raw
material handling activity, dust and ash handling are exposed to high dust levels.
Over a long period of time such exposure is likely to result in respiratory problems
and occupational health problems.
Engineering measures is implemented to reduce the dust generation at the originating
point by installing appropriate control devices and / or regular water sprinkling.
Regular monitoring of work environment for humidity, heat, illumination, metal
fumes, gases, dust, etc is carried out and shall be done in near future also. Plant
personnel working in dust prone areas are encouraged to wear personnel protective
equipment like air filters over their nose.
Job rotation schemes are practiced for over-exposed persons, including heat stress.
Proper illuminations are maintained at each and every nook and corner of the work
places.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 54
Regular advice is/ will be given to the workers through special campaigns and
illustrations related to safe work practices so that they do not develop any muscular
strain or fatigue during their work schedules. It is/ will be ensured that workers are
not exposed above the threshold noise levels through suitable administrative controls.
PPE like earplugs and muffs are provided and administrative pressure applied for
using them. Auditory examination by qualified doctors upon the first employment and
thereafter periodic examination are conducted which include determination of
auditory threshold for pure tones.
Medical check-up of all the employees will be done during pre-employment. The
healths of workers are regularly monitored under an occupational surveillance
programme. Under this programme, all the employees are subject to detailed medical
examination at the time of employment. The medical examination covers the following
tests.
General Physical Examination and Blood Pressure
X-Ray Chest and ECG
Sputum Examination
Routine Blood and Urine Examination
Lung Function Test
Eye Test
Audiometric Test
The medical histories of all the employees will be maintained in a standard format.
Thereafter the employees are subjected to medical examinations on annual basis. The
following tests results will upgrade the data base of medical history of the employees.
The recommended medical examinations are shown in following Table.
Recommended Medical Examination for Employees
Sr. No. Disease Tests to be conducted
1. Heart Disease ECG, blood for lipid profile, stress test, 2D-Echo and other tests are required
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 55
2. Lung Diseases Total Count (WBC Count), Differential Count, Sputum examination, X-ray Chest, Alveolar macrophage
3. Respiratory Disorders Differential Count, ESR, X-ray chest, Lung Function Tests (Spirometry) and Sputum examination
4. Diabetes Random blood sugar, urine sugar, if positive, BSL-Fasting / pp, Diabetic profile
5. Hypertension Blood Pressure reading, if required Renal profile, ECG and stress test
6. Abdomen Pain Routine Urine for Albumin, Sugar bile salts, Liver function test
7. Ear, Nose, Throat Routine Eye Test, Fungus examination, retinopathy test, color blindness, nose infections, auditory threshold for pure tones.
Plant personnel working in dust prone areas will be encouraged to wear personnel
protective equipment like air filters over their nose. Job rotation schemes will be
practiced for over-exposed persons. It will be ensured that workers are not exposed
above the threshold limits prescribed above through suitable administrative controls.
PPE like earplugs and muffs will be provided and administrative pressure applied to
the workers to using them despite uncomforted. Workers exposed to mechanical
accident-prone areas will be given personal protective equipment (PPE). The non-
respiratory PPE includes tight rubber goggles, safety helmets, welders hand shields
and welding helmets, plastic face shields, ear plugs, ear muffs, rubber aprons, rubber
gloves, shoes with non-skid soles, gum boots, safety shoe with toe protection. All
safety and health codes prescribed by the Bureau of Indian Standards are
implemented. Safety data sheets of the hazardous chemicals are displayed at specific
locations. The data is in English, Hindi and Bengali language / script.
7.4 Greenbelt Development Plan
RML has developed 20-25 % AS GREEN BELT copy of the same is enclosed as
Annexure -II. While selecting trees species following things will/ are be considered:
The tree species to be selected for the plantation will be pollutant tolerant, fast
growing, and wind firm, deep rooted. A three tier plantation is proposed comprising of
an outer most belt of taller trees which will act as barrier, middle core acting as air
cleaner and the innermost core which may be termed as absorptive layer consisting of
trees which are known to be particularly tolerant to pollutants.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 56
7.5 Rain Water Harvesting Plan
RML has 02 nos. rain water harvesting pond having 95,000 cubic meter water storage
capacity. Copy of the same is enclosed as Annexure-III. Surface runoff from the plant
area is collected in the water reservoir located inside the plant. This stored water is
used inside the plant. The groundwater depth at the site is minimum 5 m during
post-monsoon season. Due to presence of Kasai River and their nalas the natural
recharge rate is high by nature.
Further it is proposed that the rain water harvesting and ground water recharge
structure may also be constructed outside the plant premises after the consultation /
permission with local gram Panchayat and village head to augment ground water level
of the area.
7.6 Road Connectivity
A proper road is available for daily use, transportation of raw materials and finished
product The Plant site is well connected with NH-6 which is passing very closed from
the proposed project site.
7.7 Monitoring Scheme
Monitoring of the stacks of existing stacks of Dip Units is done frequently by WBPCB
on quarterly or half yearly basis. Third party monitoring for ambient, fugitive, noise &
water will be carried out once in a year by WBPCB approved laboratory/
NABEL/MoEF approved lab. Copy of the same is enclosed as Annexure-VI.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 57
8. Rehabilitation and Resettlement (R & R) Plan
8.1 Introduction
Total land requirement is 10 acres which is already in possession by Rashmi Group in
the name of M/s Rashmi Metaliks Ltd.
There was no residential habitat, so Rehabilitation and Resettlements (R&R) plant is
not required.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 58
9. Project Schedule & Cost Estimates
9.1 Likely date of start of construction and likely date of completion (time
schedule for the project to be given)
Successful execution of the project largely depends on the coordinated approach of
the project implementing agencies. Proper co-ordination between the various project
execution agencies, monitoring of project schedules, appropriate mobilization of
manpower and other resources can achieve cost control and timely completion of the
project.
The proposed enhancement project of Ductile Iron Pipe Plant from 2, 00,000 TPA to 5,
50,000 TPA in phase wise at Mouza – Nandarchak (J.L. No.-124), Sujatpur (J.L. No.-
139) & Khidipur (J.L. No.-140) Village – Gokulpur, P.O – Shyamraipur, P.S –
Kharagpur (L), Dist. Paschmi Mednipur in the state of West Bengal is expected to be
commissioned within 60 months from the date of Environment Clearance issued by
WBPCB.
Civil work including building and equipment foundations are to be completed before
the equipment arrives at site.
All auxiliary system, plant water system needed for commissioning the plant should
be completed so as to match the schedule for initial trial of the main equipment.
9.2 Estimated project cost along with analysis in terms of economic viability
of the project
The Capital costs have been worked out on the basis of prices prevailing today and do
not include any provision for future escalation in costs during implementation period.
The various assumptions are made while estimating the capital cost estimation. The
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 59
cost estimate is based on the data available from similar type of steel projects. The
Estimated cost break up is given below:
Sr. No. Particulars of facilities Capacity Estimated Cost (Rs. Cores)
1. Ductile Iron Pipe Unit- PHASE-I
1,50,000 TPA 75
2. Ductile Iron Pipe Unit- PHASE-II
2,00,000 TPA 90
Total 165
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 60
10. ANALYSIS OF PROPOSAL
10.1 Financial and social benefits with special emphasis on the benefit to
the local people including tribal population, if any in the area.
Based on the growing demand in the state of West Bengal over the next 10 years, the
proximity of the project location is an advantage with respect sustainable growth of
the Rashmi Group. The financial viability also shows a good Rate of return from the
project for Rashmi Group. The project is environmental friendly as it is using the
Green Field Clean Technology. Considering the above, RML is planning to go-ahead
with the project, once it gets all the statutory approvals.
Employment: Preference will be given for locals for employment based on
qualifications &requirement
Medical facilities: Medical facilities will be provided for employees as well
as people of nearby villages
Educational facilities: Basic educational and vocational facilities will be provided
for the children of employees as well as nearby villagers
Infrastructure facilities: Approach roads will be developed at par with plant roads
Additional Facilities: The establishment of project will facilitate additional
auxiliary facilities like banking, post office & recreation facilities etc.
Other Tangible Benefits:
The overall quality of life of the people will improve due to better means of
transportation and communication. As a result, mobility will increase, which will
substantially increase job opportunities. The social exposure of the villagers will be
enhanced and will be able to related better to the outside world.
*********************************************
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 61
ANNEXURE NO. – I
PLANT LAYOUT
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 62
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 63
ANNEXURE NO. – II
Green Belt Development
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 64
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 65
ANNEXURE NO. – III
Existing Rain Water Harvesting
Facility
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 66
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 67
ANNEXURE NO. – IV
ESR Activities Carried in Past By
RML
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 68
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 69
ANNEXURE NO. – V
Water Extraction Permission
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 70
Certificates
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 71
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 72
ANNEXURE NO. – VI
Stack & Ambient Analysis Report
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 73
STACK GAS ANAYSIS REPORT
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 74
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 75
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 76
.
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 77
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 78
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 79
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 80
AMBIENT AIR ANALYSIS REPORT
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 81
ANNEXURE NO. – VII
Valid CFO, NOC & EC Detail
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 82
Valid CFO
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 83
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 84
NOC
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 85
NOC Amendment
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 86
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 87
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 88
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 89
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 90
EC Detail
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 91
EC Amendment
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 92
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 93
EC COPY
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 94
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 95
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 96
Rashmi Metaliks Limited
Proposed Feasibility Report for RML_ DIP Division _ Production Capacity Enhancement at village – Gokulpur, P.O – Shyamraipur P.S – Kharagpur (Local), District: Paschim Medinipur, W.B.
PFR for Production Capacity Enhancement of DIP Pipe Unit from 2, 00,000 TPA to 5, 50,000 TPA Page 97