RAMBOLL ENERGY
DECENTRALISED ENERGY PROJECTS IN LONDON
ANTHONY RIDDLE - DISTRICT ENERGY TEAM LONDON
2
The London Context
The Mayor’s Climate Change Action Plan (2007) • 60% carbon reduction by 2025, 80% by 2050 • LZC Energy Supply ~ 25% by 2025
London Plan (2004, 2008, 2011) and Local Borough Policy Framework • Energy Policy for New Developments
Mayor’s Climate Changes Mitigation and Energy Strategy 2011 • Decentralised Energy Master planning Support to Local
Authorities
3
Strategic Vision for Heat Networks
• Capacity Building • Heat Mapping • OAPFs Energy Strategies & • Feasibility Appraisals
• Energy Masterplanning • Business Case Support • Legal Advice • Technical Standards • Procurement Support
Some Ramboll Projects..
• Heat mapping 9 boroughs • Barking Heat Offtake • Masterplanning for 2 LA’s • Olympic Park Scheme • Gospel Oak District Heating
Scheme • Greenwich Peninsula • Opportunities SELCHP and
Wembley • Advising GLA on Technical
Design Concept
DEMaP / DEPDU GLA Support to Local Authorities
NEWHAM ROYAL DOCKS DECENTRALISED ENERGY MASTERPLAN DISTRICT HEATING / DECENTRALISED ENERGY MASTERPLANNING 2012-2050
Location Newham, London Client Newham Council Project Value 34M
Completion Date 2012 Engineering Services strategic planning, network masterplanning, lifecycle costing, business case development
• Demand Forecasting
• Energy Production
• Network concept development
• Whole Life Costing
• Carbon Appraisal
• Implementation Strategy
• Planning Recommendations
• Risk and Procurement
appraisal
Royal Docks Strategic Masterplan
Tate and Lyle Sugar Refinery
Thames Water SPG
Beckton Waste Treatment Facility
• 106 GWh/y ~ equivalent to 30,000 Code 4 homes.
• Newtork sized for baseload capacity with embedded peaking plant
• Safeguarding for interconnection to OPDES and LTGHN
• Heat sources EfW, biomass heat, natural gas, process heat ~ future recovery from sewage effluent and industrial waste heat
Temporary Energy Centres
Commercial Delivery
Transmission
system Heat
exchanger
stations
Baseload heat
production units
Peaking Plant
Local
Energy
Centres
(No chp)
End
users
Distribution pumps
Developments
New Developments • Required through planning to
be DH ready
• Community networks with temporary energy centres if constructed prior to heat network
• Developer contributions through S106 / CIL, Allowable Solutions
Accumulators
Pre Network Post Network
Project • ~£ 34 M investment • ~ 6% IRR over 40 years • Heat purchased at ~ 1.5 to
2.0 p /kWh • Heat selling prices to undercut
BaU • SPV as TRANSo
7
Technical Concept
• etc
REDBRIDGE ENERGY MASTERPLANNING DISTRICT HEATING / DECENTRALISED ENERGY MASTERPLANNING 2012-2050
GOSPEL OAK SCHEME, CAMDEN A DISTRICT HEATING SCHEME USING SOURCE WASTE HEAT REJECTED IN THE EXHAUST GASES OF THE EXISTING TURBINE IN THE ROYAL FREE HOSPITAL (RFH).
Location Camden, London Client Undisclosed Project Value £5M
Completion Date Ongoing Engineering Services District heating, detailed design
• Heat network serving six blocks of residential dwellings, currently served by dedicated gas fired boilers using heat recovery from existing gas turbine
• Additional requirement to provide capacity in the heat network of 3.5MW to allow for future-proofing
• Full Design Services, Technical specifications Construction Supervision, Owner’s Engineer, Acceptance testing
GREENWICH PENINSULA SCHEME A LOW CARBON ENERGY INFRASTRUCTURE SERVING A MAJOR NEW DEVELOPMENT IN LONDON
Location Greenwich, London Client Pell Frischmann
Completion Date 2011 Engineering Services Heat load assessment, concept design, energy centre design, fuel supply study, district heating network design, tender preparation and appraisal, site supervision