Innovative Approach to Decentralised Energy System Pays ...
Transcript of Innovative Approach to Decentralised Energy System Pays ...
How Armstrong Helped the UK Police Arrest Their Energy Losses
Innovative Approach to Decentralised Energy System Pays Huge Dividends
NHS Sustainability Event – February 2012
MBS Retrofit Case Study
NHS Sustainability Event – February 2012
MBS Retrofit Case Study
Lancashire Constabulary
- established in 1839
- covers an area of 1189 sq miles
- population of 1,500,000
Hutton Hall County HQ
Police Training Centre- Firing Range and Sports Hall
- Teaching Blocks
- Accomodation Blocks
- Canteens
National Police Computer Database HQ
NHS Sustainability Event – February 2012
Starting Conditions
Old centralised oil fired heating plant
Oversized
Very inefficient
Expensive to run
- Fuel consumption averaged 417,000 litre/yr or £293,000 yr
- Maintenance costs were huge
Unreliable
NHS Sustainability Event – February 2012
Project Challenges
A new system was required but...
the site couldn’t be closed or disrupted in any way
heating and hot water generation had to continue 24/7
the new solution had to be cost effective – max 3 year payback
the new solutions had to be environmentally friendly –Lancashire Constabulary were committed to reducing their carbon emissions
NHS Sustainability Event – February 2012
Options
a) Change fuel from oil to gas but retain
existing boilers
b) Change fuel from oil to gas and replace boilers
and associated plant
c) Decentralise the system and install new plant
close to the demand
NHS Sustainability Event – February 2012
Options
a) Change fuel from oil to gas but retain existing boilers
Pros
Relatively inexpensive to do
Relatively quick to do
Result in fuel cost savings of around 50%
Payback around 2 years
Cons
Boiler shells over 30 years old and well past normal life cycle
System still oversized and thus inefficient
Ageing underground distribution piping would remain
System energy losses would still be high
Maintenance costs would still be high
Could only be done one at a time during the summer
NHS Sustainability Event – February 2012
Options
b) Change fuel from oil to gas and replace boilers and associated plant
Pros
Result in fuel cost savings of around 60%
Payback around 3 years
Boilers could be “right sized” to suit the reduced demand
Boiler/burner maintenance costs would be reduced
Cons
Ageing underground distribution piping would remain
System energy losses would still be high
Maintenance costs for the distribution piping would still be high
Could only be done one at a time during the summer
NHS Sustainability Event – February 2012
Options
c) Decentralise the system and install new plant closer to the demand
Pros
Result in fuel cost savings of around 75%
Payback around 2.5 years
Boilers could be “right sized” to suit the reduced demand
Plant maintenance costs would be greatly reduced
New plant should mean frequent breakdowns were a thing of the past
Underground distribution piping would be eliminated
Cons
Could only be done during the summer
NHS Sustainability Event – February 2012
Advanced 3D Design
NHS Sustainability Event – February 2012
Solution Elements
4 – MBS Integrated Plant Rooms
1) 160kW serving the firing range and sports hall
2) 320kW serving the Lancastrian
building – HQ offices and canteen
3) 320kW serving the Ellis building –
training rooms and lecture theatres
4) 240kW serving the Langdale building –
training rooms
NHS Sustainability Event – February 2012
Installation
NHS Sustainability Event – February 2012
Installation
NHS Sustainability Event – February 2012
Installation
NHS Sustainability Event – February 2012
Project Benefits
Energy Consumption and Cost
Environmental
Construction
NHS Sustainability Event – February 2012
Project Benefits
Energy Consumption and Cost
Consumption reduced from 4,503,600kWh pa to 2,550,730kWh pa. A saving of 1,952,870kWh or 43%
Cost saving of kWh reduction of £126,937 in first full year of operation
Cost saving on change of fuel £118,696
Total energy cost saving of £245,633 in the first full year alone
based upon an oil cost of £0.065 per litre and natural gas at £0.02 per kWh
NHS Sustainability Event – February 2012
Project Benefits
Environmental
Carbon emissions (based on kWh reduction) reduced by 525 tonnes pa
Carbon emissions (based on change of fuel (217 tonnes pa)
Total carbon savings 744 tonnes per year
Best in Class low Nox emissions – less than 20mg/kWh
NHS Sustainability Event – February 2012
Project Benefits
ConstructionTimescale: MBS systems assembled offsite concurrently with
excavations and installation of gas network cutting 3 months off the programme
Disruption: Existing plant could continue to function during the new installation programme ensuring continuous heating and hot water availability
Safety: Manufacturing the plant rooms in a purpose designed factory minimised the health and safety risks associated with site work
Security: Offsite manufacture meant that 15 less personnelwere required on a sensitive site
Environment: Offsite manufacture reduced the number of site deliveries by over 40 %
NHS Sustainability Event – February 2012
Customer Satisfaction
What Ed said about the project...
“It was only when we analysed the energy consumption at the end of the first year that we realised just how much money the packaged plant rooms had saved the taxpayer. The equipment has paid for itself in just a year, and will continue to deliver cost savings throughout it’s life.”
“If a new system isn’t commissioned properly, all of the inherent energy efficiency of the system can be lost. But I was really impressed with the Armstrong engineers’ ability to get the equipment working at it’s full potential – right from the beginning.”
NHS Sustainability Event – February 2012
Industry Acknowledgment
Energy Manager of the Year Award 2008
“Innovation and imagination were two key qualities that helped Ed Palmer, Energy Manager for Lancashire Constabulary, win this year’s Energy Manager of the Year Award. Sponsored by the Energy Services & Technology Association (ESTA), this annual award recognises outstanding achievement in saving energy and reducing carbon emissions.”
ESTA press release May 2008
NHS Sustainability Event – February 2012
Key Success Factors
48% of the energy savings were due to the change in fuel –relatively easy and obvious fix.
52% of the energy savings were due to the change in the system – something worthy of a little more investigation.
NHS Sustainability Event – February 2012
Energy Insights
HEATING
IS
A
PART LOAD
APPLICATION
NHS Sustainability Event – February 2012
Energy Insights
For 36% of the heating season the system is running at only 15% of the load
for 45% of the heating season the system is running at only 30% of the load
for only 19% of the heating season the system is running at 100% of the load
Source: Part L of the UK Building Regulations 2010
ȠOSBE = 0.36Ƞ15% + 0.45Ƞ30% + 0.19Ƞ100%
NHS Sustainability Event – February 2012
Energy Insights
300kW boiler system running at 30% of the load
NHS Sustainability Event – February 2012
Energy Insights
NHS Sustainability Event – February 2012
Energy Insights
300kW boiler system running at 30% of the load
NHS Sustainability Event – February 2012
Energy Insights
Weather compensation or outdoor reset
Variable primary pumping
Integrated gas meter with digital outputs
Remote alarms functions
Building Automation System (BAS) ready
All from one source, taking total responsibility
NHS Sustainability Event – February 2012
Installation Highlights
Completed on time
On budget
Exceeded savings and payback predictions
Installation proceeded without causing disruption to the site
Savings from change of fuel easily won
System savings only possible through the integrations of modern technologies
NHS Sustainability Event – February 2012
Armstrong Capital Assist- Ed Rowe
NHS Sustainability Event – February 2012
What is Capital Assist?
§ Enables you to spread the cost of Armstrong Solutions for periods 3 – 10 years.
§ Shifts capital expenditure to your revenue budget.
§ Aims to be self-funding via energy/maint savings.
§ Utilises money already being spent on inefficient plant.
§ Enables you to upgrade/ retrofit immediately.
§ First payment can be deferred until new Financial Year
NHS Sustainability Event – February 2012
NHS – The Challenge?
§ Ageing & inefficient plant
§ Substantial carbon reduction targets.
§ Insufficient Capital resources to invest in new plant.
§ Estates often loses out to clinical demands for capital allocation.
§ How to improve energy efficiency whilst retaining clinical demand as top priority for available capital.
NHS Sustainability Event – February 2012
Implications
§ Increasing energy & maintenance costs as systems age.
§ Increased risk of failure.
§ Difficulty in achieving carbon reduction targets.
§ Significant amounts being wasted from operating budgets on inefficient plant.
NHS Sustainability Event – February 2012
The Solution?
§ Upgrade / Retrofit with new energy efficient Armstrong Solutions – without the need for capital
§ Spread cost over appropriate period ( 3 to 10 years ).
§ Use energy & maintenance savings to cover monthly payments.
§ Monthly payments from operating budget ( Revenue ).
§ Use ARMSTRONG CAPITAL ASSIST.
NHS Sustainability Event – February 2012
Benefits
§ Realise immediate energy & maintenance savings.
§ No capital outlay required.
§ Use savings to fund monthly payments.
§ Monthly costs fixed for easier budgeting.
§ Avoid obsolete plant.
§ Reduce backlog maintenance.
§ Improve site efficiency & lifecycle costs.
NHS Sustainability Event – February 2012
CAPITAL ASSIST EXAMPLE for Lancashire Constabulary MBS retrofit over 3 years
Capital cost of works £359,000
Rental period 3 years
Monthly rental (fixed) £11,000
Est. annual energy savings £245,633
Est. net savings over rental period £340,899
Payback period 2.72yrs (33mths)
Est. net savings over 10 years £2,060,330
NHS Sustainability Event – February 2012
CAPITAL ASSIST EXAMPLE for Lancashire Constabulary MBS Retrofit over 5 years with 1st
payment deferred for 12 months
Capital cost of works £359,000
Rental period 5 years in arrears
Monthly rental (fixed) £7,479
Est. annual energy savings £245,633
Est. net savings over rental period £779,425
Payback period 4yrs (48mths)
Est. net savings over 10 years £2,007,590
NHS Sustainability Event – February 2012
CAPITAL ASSIST EXAMPLE for Upgrade to Optivisor all variable plant controller
Capital cost of works £84,000
Rental period 3 years
Monthly rental (fixed) £2597
Est. annual energy savings £66,976
Est. net savings over rental period £107,436
Payback period 2.15 yrs (26 mths)
Est. net savings over 10 years £576,268
NHS Sustainability Event – February 2012
Thank you
Please share your questions