Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

25
Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012 Thomas Blaser – Director Department of Transportation

description

Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012. Thomas Blaser – Director Department of Transportation. Transportation Headlines. Location & Design Public Hearing Route 28 (Linton Hall Road to Fitzwater Drive) Wednesday, April 25, 2012 7:00 pm to 9:00 pm - PowerPoint PPT Presentation

Transcript of Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

Page 1: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

Quarterly Transportation Report

2nd Quarter 2012April 17, 2012

Thomas Blaser – DirectorDepartment of Transportation

Page 2: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|2|Quarterly Transportation Report | Tuesday, April 17, 2012

Transportation Headlines

Location & Design Public HearingRoute 28 (Linton Hall Road to Fitzwater Drive)

Wednesday, April 25, 20127:00 pm to 9:00 pmPatriot High School

10504 Kettle Run RoadNokesville, VA 20181

Page 3: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|3|Quarterly Transportation Report | Tuesday, April 17, 2012

University Boulevard PPTA(Prince William Parkway to Sudley Manor Drive)

Accomplishments Hornbaker Road design has been completed and

approved by VDOT University Boulevard design has been approvedIssues R-O-W negotiations with adjacent developmentsTimeline Construction activities began in January 2012 on

Hornbaker Road with majority of activities starting in the Spring of 2012

Construction to be complete by December 26, 2013

Page 4: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|4|Quarterly Transportation Report | Tuesday, April 17, 2012

University Boulevard PPTA(Prince William Parkway to Sudley Manor Drive)

Page 5: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|5|Quarterly Transportation Report | Tuesday, April 17, 2012

Route 1 – Joplin to Bradys Hill

Accomplishments Project activities and billing are 89%

complete Median work with stamped concrete

and grass is 60% complete Paving is ongoing and is 70% complete

Issues Timing of Inn Street connection

Timeline Construction on-schedule for

completion June 2012

Page 6: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|6|Quarterly Transportation Report | Tuesday, April 17, 2012

Route 28 (Linton Hall Road to Fitzwater Drive)

Accomplishments Design has initiated with survey work underway Citizen Information Meeting held on October 11, 2011 Project Value Engineering has been completed Environmental Assessment Document approvedIssues Construction phasing to expedite completion Impacts to septic fields and R-O-W acquisitionTimeline Public Hearing scheduled for April 25, 2012 Anticipated Final Construction Plans – January 2013 Construction Advertisement for Phase I (Linton Hall Road to Realigned

Vint Hill Road) anticipated for Spring 2013 Phase II to follow contingent on funding availability

Page 7: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|7|Quarterly Transportation Report | Tuesday, April 17, 2012

Route 28 (Linton Hall Road to Fitzwater Drive)

Page 8: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|8|Quarterly Transportation Report | Tuesday, April 17, 2012

Fuller Rd./Fuller Heights Rd. (Quantico Marine Corps Base Entrance)

Accomplishments Coordination with Marine Corps Base Quantico (MCBQ) regarding design

concerns has been concluded Environmental Permitting is completed R-O-W and easement requested from MCBQ on 3/30/12 R-O-W plans submitted to VDOT for authorizationIssues Maintenance of traffic during construction Access Management waivers Flood Plain and CLOMR/LOMR RequirementsTimeline R-O-W authorization from VDOT anticipated by Summer 2012

Page 9: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|9|Quarterly Transportation Report | Tuesday, April 17, 2012

Fuller Rd./Fuller Heights Rd. (Quantico Marine Corps Base Entrance)

Page 10: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|10|Quarterly Transportation Report | Tuesday, April 17, 2012

Telegraph Road Commuter Lot

Accomplishments Final grading activities ongoing for Phase I (Commuter Lot) Temporary SWM activity is complete Demolition of pavement is complete Storm sewer pipes are 90% completeIssues Coordinate with adjacent developers Utility Relocations Opening of Phase ITimeline Lot construction (Phase I) scheduled for completion – August 31, 2012 Final R-O-W plan approval for road improvements – February 2012 Construction advertisement for road improvements (Phase II) – May 2012 Construction for road improvements anticipated to be complete –

Summer 2013

Page 11: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|11|Quarterly Transportation Report | Tuesday, April 17, 2012

Telegraph Road Commuter Lot

Page 12: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|12|Quarterly Transportation Report | Tuesday, April 17, 2012

Old Bridge Road Pedestrian Improvements (Mohican Road to Dillingham Square)

AccomplishmentsDesign of the project incorporating the VDOT

Safety Project is in progressProject is in coordination with VDOT Safety

ProjectIssuesNoneTimelineConstruction is anticipated to start Fall 2012

Page 13: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|13|Quarterly Transportation Report | Tuesday, April 17, 2012

Prince William Parkway (Old Bridge Road to Minnieville Road)

Accomplishments Preliminary Design/Build Plans completed by AMT Project to be financed through Bond funding and use

of State Revenue Sharing funds RFP advertised – February 2012Issues R-O-W Impacts Utility relocationTimeline Bid opening on May 23, 2012 Award Design/Build contract Summer of 2012

Page 14: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|14|Quarterly Transportation Report | Tuesday, April 17, 2012

Rollins Ford Road

Accomplishments Design for roadway extension has been submitted to VDOT

for approvalIssues Project construction will include two phases and two Notice

To Proceeds (NTPs) Improvements at Vint Hill Road to meet current standards Coordination with Park ProjectTimeline Advertisement for construction for roadway extension

anticipated for Spring 2012

Page 15: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|15|Quarterly Transportation Report | Tuesday, April 17, 2012

Route 1 – Dale Blvd. to Featherstone Rd.

Accomplishments Three unsolicited design-build proposals received for the

project Selection committee selected the firm of Lane Construction to

move forward with project negotiation

Issues Project Funding Waterline Construction

Timeline Award of design-build contract – Spring 2012

Page 16: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|16|Quarterly Transportation Report | Tuesday, April 17, 2012

Minnieville Road – Spriggs Rd. to Rte. 234

Accomplishments Three unsolicited design-build proposals received for the

project

Issues Selection committee rejected all PPTA proposals

Timeline Issuance of RFP for project design – Summer 2012

Page 17: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|17|Quarterly Transportation Report | Tuesday, April 17, 2012

Mountain Road Improvements (Revenue Sharing/TRIP)(Bear Hollow Trail to Jackson Hollow Road)

Accomplishments Notice to Proceed has been issued to NOVEC Project has been advertised for construction R-O-W and easements have been acquired Environmental Permit issued Utility Relocation is in progressIssues None Maintenance of traffic during construction – Road closure during

Summer monthsTimeline Utility relocation completion anticipated by end of Spring 2012 with

construction to follow Bid opening on April 13, 2012

Page 18: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|18|Quarterly Transportation Report | Tuesday, April 17, 2012

Mountain Road Improvements (Revenue Sharing/TRIP)(Bear Hollow Trail to Jackson Hollow Road)

Page 19: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|19|Quarterly Transportation Report | Tuesday, April 17, 2012

Logmill Road Improvements

Accomplishments Preliminary plan design is in progress Project Day meeting with VDOT, JMT and PWC DOT held in

November 2011 Meeting held with property owners concerning grade at Parnell

Court Profile to proceed with balanced cut and fill for optimum

constructionIssues Possible temporary road closure and management of traffic during

constructionTimeline Intermediate Plan submission scheduled for Summer 2012 Advertisement for construction – Spring 2013 Construction completion anticipated for Fall 2013

Page 20: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|20|Quarterly Transportation Report | Tuesday, April 17, 2012

Fuller Heights Rd. Sidewalk –Bethlehem Church Rd. to Potomac Crest Dr. (TRIP)

Accomplishments R-O-W acquisition is completed Construction by County forces is in progressIssues Coordination during construction of sewer line Drainage design affecting adjacent properties Project BudgetTimeline Construction completion is anticipated in Summer of

2012

Page 21: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|21|Quarterly Transportation Report | Tuesday, April 17, 2012

Hoadly Road Trail – Spriggs Road to Dale Boulevard (TRIP)Accomplishments Plans submitted to VDOT Comments received from VDOT and Development

Services are being addressedIssues R-O-W and easement constraints Possible design waiverTimeline Plans expected to be re-submitted to VDOT in April

2012

Page 22: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|22|Quarterly Transportation Report | Tuesday, April 17, 2012

Gideon Drive Sidewalk – Dale Blvd. to Opitz Blvd. (TRIP)

Accomplishments Notice to Proceed with preliminary design has been issued to

RDA Task Order to RDA has been modified to accommodate use of

Federal CMAQ funding on project for constructionIssues R-O-W and easement constraints Utility RelocationsTimeline Preliminary design scheduled for submission to VDOT – May

2012

Page 23: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|23|Quarterly Transportation Report | Tuesday, April 17, 2012

Glenkirk Road Sidewalk

Accomplishments County request to administer project approved by VDOT County/Sate Agreement has been received and funding

budgeted and appropriated Federal design task order has been issued to Dewberry

Issues Expedited construction schedule

Timeline Advertise for construction in Fall 2012

Page 24: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|24|Quarterly Transportation Report | Tuesday, April 17, 2012

Mine Road @ Van Buren Road Intersection Improvements

Accomplishments County request to administer project approved by VDOT County/Sate Agreement has been received and funding

budgeted and appropriated Federal design task order has been issued to Dewberry

Issues None

Timeline Advertise for construction in Fall 2012

Page 25: Quarterly Transportation Report 2nd Quarter 2012 April 17, 2012

|25|Quarterly Transportation Report | Tuesday, April 17, 2012

Panther Pride Drive Sidewalk

Accomplishments County request to administer project approved by VDOT County/Sate Agreement has been received and funding

budgeted and appropriated Federal design task order has been issued to Dewberry

Issues None

Timeline Advertise for construction in Fall 2012