National Cyclone Risk Mitigation Project (NCRMP) Revenue (DM) Department Government of Andhra Pradesh THIRD PARTY QUALITY AUDIT (TPQA) in Joint Venture with

Transcript of Quarterly Progress Report - Jan-March 2013

Page 1: Quarterly Progress Report - Jan-March 2013

National Cyclone Risk Mitigation Project (NCRMP)

Revenue (DM) Department Government of Andhra Pradesh

THIRD PARTY QUALITY AUDIT (TPQA)

in Joint Venture with

Page 2: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

INDEX

1.0 Project Background 02

1.1 Third Party Quality Audit Consultant 03

1.2 Mobilization of Team 04

1.3 Setting up offices and logistics for the consultant teams 07

2.0 Review Meetings and Other Activities 08

3.0 Status of TPQA Visits 08

4.0 Progress of NCRMP works 09

5.0 District wise status of tests conducted by TPQA 27

6.0 Details of Quality Control Audit Reports Submitted During this 3 Months 28

7.0 Details of Environmental and Social Reports Submitted During this 3 Months 35

8.0Details of Consolidated Environmental and Social Reports Submitted During

this 3 Months 43

9.0 Inspections and Site Visits of TPQA During this 3 months 95

Photographs of site visits of TPQA 122

Page 1 of 198

Page 3: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1.0 Project BackgroundAndhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road network in the

state, the nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and

September-December, cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions,

the catastrophic events are increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is

enormous. In the 97 years ranging from 1892 to 1989, there were as many as 67 cyclones within the State.

It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or

disaster due to natural calamities such as cyclones and associated tidal waves and storm surges. The project is

formulated based on experiences of Government of Andhra Pradesh in mitigating such disasters during the past and

also keeping in view the existing facilities available in the project area in Andhra Pradesh.

The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development

Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply the

proceeds to payments for goods, works, related services and consulting services under this Project.

National Cyclone Risk Mitigation Project (NCRMP) – Project Implementation Unit (PIU), Andhra Pradesh,

headquartered at Hyderabad has invited the consultants to submit proposals for providing the consultancy services

for Third Party Quality Audit for 9 coastal districts namely Srikakulam, Vijayanagaram, Visakhapatnam, East Godavari,

West Godavari, Krishna, Guntur, Prakasam and Nellore. The project “Construction of Multipurpose Cyclone

Shelters, Roads to Cyclone Shelters, and Roads to habitations and Roads & Bridges under NCRMP” is

funded by International Development Association and received through Government of India. This consultancy is

envisaged to audit the quality of works being implemented by various line departments working under PIU. The

number of works under progress / for which agreements are concluded in each district is shown in the table below.

District

No. of works(Under ConcludedAgreements) No. of works Completed No. of works under Progress

No.

of w

orks

not

star

ted

RH

B

RC

S

MPC

S

Brid

ges

Roa

ds (R

&B

)

Tota

l

RH

B

RC

S

MPC

S

Brid

ges

Roa

ds (R

&B

)

Tota

l

RH

B

RC

S

MPC

S

Brid

ges

Roa

ds (R

&B

)

Tota

l

Srikakulam 6 8 2 4 1 21 3 8 0 3 1 15 3 0 2 1 0 6 0

Vizianagaram - - - 2 1 3 0 0 0 1 1 2 0 0 0 1 0 1 0

Visakhapatnam 8 6 7 - - 21 8 6 0 0 0 14 0 0 6 0 0 6 1

East Godavari 2 8 3 - - 13 2 7 0 0 0 9 0 0 3 0 0 3 1

West Godavari 10 - - - - 10 10 0 0 0 0 10 0 0 0 0 0 0 0

Krishna 5 3 - - - 8 5 3 0 0 0 8 0 0 0 0 0 0 0

Guntur 3 12 - 2 - 17 3 11 0 1 0 15 0 1 0 1 0 2 0

Prakasham 14 7 2 1 - 24 14 7 2 1 0 24 0 0 0 0 0 0

Nellore 16 10 - - - 26 16 8 0 0 0 24 0 2 0 0 0 2 0

64 54 14 9 2 143 61 50 2 6 2 121 3 3 11 3 0 20 2

Page 2 of 198

Page 4: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1.1 Third Party Quality Audit Consultant.

To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone

Shelters, Roads to Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9

coastal districts The Commissioner for Disaster Management & Project Director, Project Implementation

Unit (PIU) NCRMP has selected Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.

On 31st May’2011, the Contract for Consultancy Service was signed between The Commissioner for

Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and the Egis

International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.

Page 3 of 198

Page 5: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1.2 Mobilization of Team

In accordance with the Contract for Consultant Services, executed on 31st May’2011, by The

Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP

and the Egis India, professional services were authorized to commence work. The detail of team

mobilization and organization chart is shown below.

Sr.No. Name Designation Date Of

JoiningLast Day

ofWorking

NCRMP Project Office, Hyderabad

1 Bhavanna Rao Project Manager 01.06.2011

2 Dr. Surjit Singh Deepak Environmental Management Expert 09.06.2011

3 Dr. Sudesh Kaul Social Management Expert 01.06.2011

4 Mrityunjay Kumar MIS Expert 01.06.2011

5 V.Ravi Kumar Electrical 06.06.2011

6Ch.Giridhar Electrical 02.06.2011 13.12.2012

Prakash Rao Electro Mechanical 17.12.2012

7 Hari Shankar Prasad Field Staff - Environmental Engineer 09.06.2011

8 M. Venkata Ramana Field Staff - Social Expert 04.07.2011

9Viraj Premi Office Manager HYD 01.06.2011 31.03.2012

Suchan Kumar K P Office Manager HYD 02.04.2012

VISHAKAPATANAM

10 Ch.V.S.Sivakumar DPM / Vishakapatnam 28.09.2011

11 K.Siva Ramprasad Site Engineer 02.06.2011

12 Mallela Shyam sunder Site Engineer 07.07.2011

13 B.Srinivasulu Reddy Site Engineer 06.06.2011 22.09.2012

14 H.Venugopal Site Engineer 06.06.2011

15Siva Kishore Vedula Site Engineer 09.06.2011 04.01.2012

Sivaji Raju Site Engineer 13.02.2012

16Srinivas.Y Site Engineer 27.06.2011 06.01.2012

Venkateshwara Prasad Site Engineer 13.02.2012

17 Babu.G Office Manager 01.06.2011 19.06.2012

Page 4 of 198

Page 6: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

KNVS.Malleswara Swamy Office Manager 20.06.2011 14.11.2012

N.Ramakrishana Office Manager 17.11.2012

ELURU

18M. Manohar DPM / Eluru 27.06.2011

R. Sathi Babu Randhi Deputy Project Manager 02.06.2011

19 Gudla Rama Naresh Site Engineer 06.06.2011

20 Nakka Jayasimha Site Engineer 06.06.2011

21 K. Jyothi Prasad Site Engineer 06.06.2011

22P.Durga Rao Site Engineer 06.06.2011 02.01.2012

Sridhar G Site Engineer 27.02.2012

23 N.Srinivas Site Engineer 01.07.2011

24 Vijaya Bhaskar Nalli Site Engineer 01.03.2012

25 Avinash Babu Gunnam Office Manager 01.06.2011

ONGOLE

26 Arun Kumar DPM / Ongole 22.02.2012

27P.Ramesh Reddy Site Engineer 06.06.2011 13.03.2012

T.SreeVishnu Site Engineer 14.03.2012

28Shaik Zaheer Ahamad Gori Site Engineer 02.06.2011 31.08.2012

S.Narendar Site Engineer 10.09.2012

29 K. Rama Rao Site Engineer 22.06.2011

30 Suresh Babu.P Site Engineer 06.06.2011

31 R.Balakrishna Reddy Site Engineer 02.06.2011

32Mallikarjuna Rao Site Engineer 02.06.2011 01.03.2012

Ravinder Reddy Site Engineer 15.07.2011

33 Neelakantan Office Manager 01.06.2011

Page 5 of 198

Page 7: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Organization Chart of TPQA, NCRMP

Page 6 of 198

Page 8: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1.3 Setting up offices and logistics for the consultant teams

We have established a Main office at Hyderabad, where all the necessary expertise that is required for this project.

There is a core team of national experts to monitor the project activities and discipline specialist will appropriately

support this core team. These experts will again be supported from the respective home office. Other than the

experts, support staff is also be stationed in this office. This office will be the base office during the project period of

consultants.

The details of our site offices are given in table below. These offices are provided with required communication

equipment, transportation facilities and necessary infrastructure. The offices are also equipped with computers with

basic software programs, printers, and other electronic gadgets like telephone, fax machines, etc. as felt needed.

Apart from the above PM and DPM offices, we have established site offices in all other districts

PM Office – Hyderabad

9-1-77/3, No.31, Third Floor

S.D. Road, Secundrabad – 500 003

Fax:=91-04-40179496

E- mail: [email protected]

DPM Office – Vishakhapatnam

Pavan Residency, Dr. No. 31-7-2/73,

Flat NO 503Kurmannapalem,

Opp to Bus Depot,

Vishakhapatnam - 530046

DPM Office – Eluru

Flat No. 504, Fourth Floor,

Yemireddy Residency Apartment,

Shekar Street, Gandhinagar,

Eluru, West Godavari Dist. A.P.

DPM – Ongole Office

H. No. 6-277, 2nd lane

Beside computer Centre

Maruthi Nagar

Ongole - 523002

Site Office for Krishna Dist.

D. No. 20-516-3/4,NGO Colony,

Frenchpet, Machilipatnam,Krishna Dist.,

Site Office for Srikakulam Dist.

Flat No T-1,3rd Floor Indiranagar Colony,

Ganesh Apartments,Srikakulam - 532421

Site Office for Guntur Dist.

H.No. 10-32,

Opposite Bhaskar Theatre,

Tenali road,Cherukapalli, Guntur-522309.

Site Office for East Godavari Dist.

D. No. 70-6-19/1,Upstairs,

Nagendragudi Veedhi,Ramanayyapet, Kakinada, E G Dist

Site Office for Nellore Dist.

Door No.23/218,2nd Floor Ravichettu Centre,

Fathekhanpet, Nellore – 524 003

Site Office for Krishna Dist.

Door No.20/516-27/8, NGO Colony,Parasupeta,Machilipatnam, Krishna District.

Page 7 of 198

Page 9: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

2.0 Review Meetings and Other Activities

S.No. Place Date Activity

1 Hyderabad 07.01.2013 Attended Review meeting of TPQA at H Block in AP Secretariat with Commissionerand PD

2 Hyderabad 08.01.2013 Attended Review meeting of EPTRI at H Block in AP Secretariat withCommissioner and PD

3 Hyderabad 31.01.2013 Attended Review meeting at H Block in AP Secretariat with Commissioner and PD

4 Hyderabad 13.02.2013 Attended NCRMP State Level Committee review meeting conveyed by AP ChiefSecretary in ‘C’ Block of AP Secretariat.

5 Hyderabad 26.02.2013 Attended NCRMP Review meeting by World Bank Social Experts ‘H’ Block of APSecretariat.

6 Machilipatnam 27.02.2013 Attended to the Inspection of Saline Embankment and Bridge site in Krishnadistrict by World Bank Social Experts.

7 Hyderabad 14.03.2013 Attended NCRMP Review meeting by Hon’ble Minister Revenue in J Block, 7th

Floor of AP Secretariat.

3.0 Status of TPQA Visits:

The following table shows the details of TPQA visits to sites in respective districts.

DistrictTotal Number of Visits

TotalJan.'2012 Feb.'2012 Mar.'2012

Srikakulam 31 28 21 80

Vizianagaram 1 05 5 11

Vishakhapatnam 53 11 48 112

East Godavari 16 32 15 63

West Godavari 26 13 16 55

Krishna 5 14 0 19

Guntur 19 21 18 58

Prakasam 31 17 16 64

Nellore 18 13 13 44

Page 8 of 198

Page 10: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

4.0 Progress of NCRMP works:

Third Party Quality Audit by Egis – India consulting servicesSummary of Activities

S.No. District

Agreements forPackages Communicated Status of works

PR R&B completed Progress Not Started/Deleted

1 Srikakulam 16 5 15 6 0

2 Vizianagaram - 3 2 1 0

3 Visakhapatnam 21 0 14 6 1

4 East Godavari 13 0 9 3 1

5 West Godavari 10 0 10 0 0

6 Krishna 8 0 8 0 0

7 Guntur 15 2 15 2 0

8 Prakasam 23 1 24 0 0

9 Nellore 26 0 24 2 0

Total 132 11 121 20 2

Total Packages for which Agreements are received 79

Total Number of works in the above packages 143

No. of Visits by TPQA

Page 9 of 198

The district wise progress of works is shown below.

Page 11: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

TPQA STATUS REPORT FOR NCRMP WORKS TO THE END OF MARCH 2013

S.No.

District

Packages /Works

entrustedStatus of Works

Fin

al Q

ual

ity

Au

dit

repo

rts

subm

itte

d Total Visits up toMarch'13

Tota

l No.

of

QC

test

s do

ne

NCRs

Au

dit

Rep

orts

Iss

ued

Envi

ron

men

tal &

Soc

ial

Rep

orts

Iss

ued

Elec

tric

al R

epor

tsIs

sued

PR

R&

B

Star

ted

Not

Sta

rted

Del

eted

Pro

gres

s

Com

plet

ed

Civ

il Si

teEn

gin

eers

Env

& S

ocia

lTe

am

Elec

tric

alEn

gin

eers

Issu

ed

clos

ed

Pen

din

g

1 Srikakulam 16 5 21 0 0 6 15 10 524 80 15 1614 54 54 0 86 76 4

2 Vizianagaram - 3 3 0 0 1 2 2 82 15 - 521 3 3 0 11 12 -

3 Visakhapatnam 21 - 20 1 0 6 14 14 505 69 37 2585 25 25 0 86 61 11

4 East Godavari 13 - 12 0 1 3 9 8 695 49 17 1257 28 28 0 65 39 5

5 West Godavari 10 - 10 0 0 0 10 10 494 50 - 349 20 20 0 62 47 -

6 Krishna 8 - 8 0 0 0 8 8 304 38 - 88 3 3 0 43 29 -

7 Guntur 15 2 17 0 0 2 15 1 426 69 - 6668 14 14 0 65 48 -

8 Prakasam 23 1 24 0 0 0 24 12 470 76 20 1961 36 36 0 132 74 10

9 Nellore 26 - 26 0 0 2 24 23 369 104 - 1238 32 32 0 136 72 -

Total 132 11 141 1 1 20 121 88 3869 550 89 10281 215 215 0 686 458 30

Page 10 of 198

Page 12: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN SRIKAKULAM DISTRICT AT THE END OF MARCH-2013

Category

Packages allottedunder Phase - 1

Names of works under eachpackage

AgreementNo. / Date Work Status Remarks

RHB

NCRMP/B-W/AP/RHB/PRED/

01/Santhabommali/003

Road from DPN R&B road toUddandapalem

/2010-11, Dt.30.04.2011 Work completed working estimate approval not received

Road from K. Umilada Junction toKoduru (Link Road)

/2010-11, Dt.30.04.2011 Work completed working estimate approval not received

Road from Borubhadra, Malagam toKollipadu via Seepuram, Gantapeta

/2010-11, Dt.30.04.2011 Work completed EOAT and working estimate approval not

received

NCRMP/B-W/AP/RHB/PRED/

01/Polaki/006

Road from R&B road Mobagam toDuubakavanipeta viaGajapathinagaram

/2010-11, Dt.30.04.2011 Work in Progress

300 mts CC road completed, GSB layingcompleted, GII spreading progress,

formation width vary from 6.00mts to7.50mts

Road from Talasamudram to DolaRegulator

/2010-11, Dt.30.04.2011

Work stopped dueto insufficientroad width.

400mts length of road was not taken updue insufficient road width on canal bund.Approval of WE with alternative proposal is

awaited. 1.1 KM completed

NCRMP/B-W/AP/RHB/PRED/01/P

olaki/005

Road from R&B road Edulavalasa -Killam to Jonnam viaTalasamudram

/2011-12, Dt.30.04.2011 Work in Progress

BT layer completed from Km 5/670 to Km7/270, and WBM Gr- III metal collection isin progress from Km 5/000 to Km 5/670

Bridges

NCRMP/B-W/AP/Br/R&B/01/

Patnavanipeta/001

Construction of bridge at Km 11/6-8 of NH-5 to PatnavanipetaConnecting Sundarapalem

46/2011, Dt.17.12.2010 Work completed working estimate approval not received

NCRMP/B-W/AP/Br/R&B/01/Surampeta/003

Construction of Minor Bridge at Km12/2-4 of NH-5 to Surampeta Roadvia Naruva, Mentada

45/2010-2011,Dt17.12.2010 Work completed -

NCRMP/B-W/AP/Br/R&B/

01/Bendigedda/004

Construction of High level bridgeacross Bendigedda at KM 4/10 ofPundi-Parlakimidi road

1/2010,Dt.11.11.2010 Work completed working estimate approval not received

Page 11 of 198

Page 13: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/Br/R&B/01/Uppu

gedda/002

Construction of High level bridgeacross Uppugedda at KM 7/6 ofSrikakulam muncipal limits toPukkalapeta via Killipalem inSrikakulam Dt, A.P.

47/2010-2011,Dt17.12.20

10Work in Progress Foundation completed, Shuttering for

Aboutment and Piers is in progress

RoadsNCRMP/B-

W/AP/RD/R&B/01/Nowpada/006)

Improvesments Naupada-Venkatapuram road from0/0to15/0km

43/2010-11,17.12.2010 Work completed Working Estimates approved but ATRs are

pending

RCS

NCRMP/B-W/AP/RCS/PRED/01/V.

KOTTURU/002

Road from NP road to URKpuram G.o rt No 451 dt06.04.2010 Work completed Working Estimates approved but ATRs are

pendingRoad from Deppuru, Bahadapalliroad to Onkuluru & to cycloneshelter

G.o rt No 451 dt06.04.2011 Work completed Working Estimates approved but ATRs are

pending

Road from R&B road toDevunthalada

G.o rt No 451 dt06.04.2012 Work completed Working Estimates approved but ATRs are

pending

Road from pollada to Komarthalada& to cyclone shelter

G.o rt No 451 dt06.04.2013 Work completed Working Estimates approved but ATRs are

pending

NCRMP/B-W/AP/RCS/PRED/01/E

TCHERLA/005

Road from Koyyam R&B Road toMoosavanipeta

G.o rt No 451 dt06.04.2010 Work completed

Road from Mentada to Dovupeta G.o rt No 451 dt06.04.2010 Work completed

Road from Kotcherela road toKollibhemavaram & cyclone shelter

G.o rt No 451 dt06.04.2010 Work completed

Road from Kotcherla road toPathasundarapalem

G.o rt No 451 dt06.04.2010 Work completed

MPCSNCRMP/B_W/AP/MPCS/PRED/01/Santhabom

malli/005

Construction of Cyclone shelter atKollipadu

G.o rt No 451 dt06.04.2010 Work in Progress Silt floor level slab completed. First floor

slab shuttering is in progress

Construction of Cyclone Shelter atRunku

G.o rt No 451 dt06.04.2010 Work in Progress 1st floor Slab Shuttering for concrete in

progress

Page 12 of 198

Page 14: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN VIZIANAGARAM DISTRICT AT THE END OF MARCH-2013

Category Packages allottedunder Phase - 1 Names of works under each package Agreement

No. / DateWorkStatus Remarks

Bridges

NCRMP/B-W/ AP/ Br/R&B/ 02/Puligadda/

007

Construction of Minor Bridge at Km. 7/2 nearPuligedda of Konada – Ramatheertham R&B Road to

Konathalapalem via Yerukonda, Pasupam,Kollayavalsa (Z.P. Road)

31/2010-2011Dt.

01.12.2010

Workcompleted

NCRMP/B-W/ AP/ Br/R&B/ 02/

Chakaligadda /008

Construction of Minor Bridge at Km 15/2 nearChakaligadda of Konada Ramatheertham R&B road to

Konathalapalem (via) Yerukonda, Pasupam,Kollayavalsa (ZP Road)

34/2010-2011Dt.

08.12.2010

Workcompleted

working estimate approvalnot received

RoadNCRMP/B-

W/AP/RD/R&B/ 02/Konada/009

Improvements to Road from Konada Ramatheertham(R&B) Road to Konathalapalem (Via) Pasupam,

Yerukonda, Kollayavalsa from Km 12/0 to 16/5 (Km0/0 to 4/0 i.e. up to NH-5 crossing)

33/2010-2011Dt.

08.12.2010

Workcompleted

Page 13 of 198

Page 15: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF TOTAL WORKS IN VISAKHAPATNAM DISTRICT AT THE END OF MARCH-2013

Category

Packages allottedunder Phase - 1 Names of works under each package Agreement No. /

Date Work Status Remarks

MPCS

NCRMP/B-W/AP/MPCS/PRED

/03/Payakaraopeta/003

Construction of cyclone shelter atGajapathinagaram

/2011-12, Dt.03.10.2011

Nearingcompletion

expected to be completedby 30.03.2013

Construction of cyclone shelter atRatnayampeta

/2011-12, Dt.03.10.2011

Nearingcompletion

expected to be completedby 30.03.2013

NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

Construction of cyclone shelter atPatimeeda

/2011-12, Dt.03.10.2011 work in progress finishing stage

Construction of cyclone shelter atMullaparra

/2011-12, Dt.03.10.2011 work in progress finishing stage

Construction of cyclone shelter atBangarampeta

/2011-12, Dt.03.10.2011 work in progress finishing stage

NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004

Construction of cyclone shelter atVenkayyapalem

/2011-12, Dt.03.10.2011 work in progress Slabs completed, brick

work to be taken up

NCRMP/B-W/AP/MPCS/PRED/03/Parawada/001

Construction of cyclone shelter atThikkavanipalem

/2011-12, Dt.07.10.2011

Work not starteddue to siteproblem

-

RCS

NCRMP/B-W/AP/RCS/PRED

/03/Anandapuram/001Road from NH-5 to Ramarayadupalem /2011-12, Dt.

15.09.2011 Work completed

NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002

Road from R & B road to Rajakoduru /2011-12, Dt.15.09.2011 Work completed

Road from R & B road to Kattubolu toMarripalem

/2011-12, Dt.15.09.2011 Work completed

Page 14 of 198

Page 16: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Road from R & B road to Krishnampalem /2011-12, Dt.15.09.2011 Work completed

NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003

Road from R&B road to Pedatheernala toChinatheernala

/2011-12, Dt.15.09.2011 Work completed

Road from Upmaka Rajayyapeta R&B roadto Janakayyapeta

/2011-12, Dt.15.09.2011 Work completed

RHB

NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001

Road from Vempudi to Patimeeda /2010-11, Dt.11.01.2011 Work completed

Road from R&B road to Mullaparra up toBeach end

/2010-11, Dt.27.01.2011 Work completed

NCRMP/B-W/AP/RHB/PRED/

03/Anandapuram/003

Road from R&B B.P Kallalu toMatchvanipalem

/2010-11, Dt.10.03.2011 Work completed

NCRMP/B-W/AP/RHB/PRED/03/Paravada/004

Road from R & B road toPothurajanapalem

/2010-11, Dt.28.03.2011 Work completed

Road from R & B road to Jalaripeta /2010-11, Dt.28.03.2011 Work completed

NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006

Road from R & B road to Venkayyapalem /2010-11, Dt.11.01.2011 Work completed

NCRMP/B-W/AP/RHB/PRED/

03/Atchutapuram/007

Road from R&B road to Ava- Somavaram /2011-12, Dt.27.04.2011 Work completed

Road from R&B Road to Avarajam /2011-12, Dt.27.04.2011 Work completed

Page 15 of 198

Page 17: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF TOTAL WORKS IN EAST GODAVARI DISTRICT AT THE END OF MARCH-2013

Category

Packages allottedunder Phase - 1

Names of works under eachpackage

AgreementNo. / Date

WorkStatus Remarks

RCS

NCRMP/B-W /RCS/PRED/04/Karapa/001

Approach Road to cyclone Shelter atAdivipudi

32/2011-12Dt:20.05.2011

Workcompleted -

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Road toP.Chodipallipeta CS

73/2011-12Dt:07.09.2011

Workcompleted -

NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

Road from R&B Road toK.Chodipallipeta CS

73/2011-12Dt:07.09.2011

Workcompleted -

NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

Road from R&B Road to HukumpetaCS

73/2011-12Dt:07.09.2011

Workcompleted -

NCRMP/B-W/AP/RCS/PRED/04/Uppalaguptam/0

03

Road from R&B Road toChinaraghavulapeta Cyclone Shelter

74/2011-12Dt: 23.09.2011

Workcompleted Working Estimates & ATRs are pending

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Road to GaddipetaCS

73 /2011-12Dt:07.09.2011

Workcompleted -

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Road to DanavaipetaCS

73 /2011-12Dt:07.09.2011

Workcompleted -

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Road toG.Musalayyapeta CS

73/2011-12Dt:07.09.2011

Workdeleted -

RHB NCRMP/B-W/AP/RHB/PRED/04/Karapa/001

Road from Gurjanapalli toBandulavaripalem

24/2011-12Dt:27.04.2011

Workcompleted -

Page 16 of 198

Page 18: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/

Road from PR roads toDasarivanipeta and to Cyclone

Shelter

18/2011-12Dt:27.04.2011

Workcompleted -

MPCSNCRMP/B-

W/AP/MPCS/PRED/ 04/Uppalaguptam/002

Construction of Cyclone Shelter atPedaraghavulapeta of Uppalaguptam

Mandal

78/2011-12Dt:17.10.2011

Work inProgress

Terrace floor Beam and slabCompleted. Stilt floor & First floor

Plastering and Brick work is inprogress.

MPCS

NCRMP/B-W /AP/MPCS/PRED/04/ Thondangi/001

Construction of Cyclone Shelter atLakshmanudipeta in Thondangi

77/2011-12Dt:07.09.2011

Work inProgress

Finishing Stage, white wash inprogress

NCRMP/B-W /AP/MPCS/PRED/ 04/Thondangi/001

Construction of Cyclone Shelter atAvulamanda

77/2011-12Dt:07.09.2011

Work inProgress

Finishing Stage, white wash inprogress

Page 17 of 198

Page 19: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN WEST GODAVARI DISTRICT AT THE END OF MARCH-2013

Category

Packages allotted underPhase - 1 Names of works under each package Agreement

No. / DateWorkStatus Remarks

RHB

NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/

001

Road from NH 214 A at Ranga Statue center to Harijanawadaof Kalipatnam (E) (Mogalthuru Mandal)

16 /2011-12Dt.27.04.2011

Workcompleted -

R&B road at Panchayat Office to Pulaparthivarithota viaBadava (Mogalthuru Mandal W.G.Dist.)

Workcompleted -

Mogalthuru Vempa R&B Road at Uchintha Kalava Bridge toGogulamma Harijanapeta (Mogalthuru Mandal)

Workcompleted -

From Narsapur Mogalthuru R&B road to Dayadaldaspeta viaVenkateshwara Swamy temple (Mogalthuru Mandal)

Workcompleted -

Road from NH 214 A road to Harijanapeta of Kothota Workcompleted -

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/

002

R&B road to Indira Nagar (via) Pochamma temple (NarsapurMandal)

21 /2011-12Dt.09.05.2011

Workcompleted -

Road from R&B road to Pedalanka (Narsapur MandalW.G.Dist.)

Workcompleted -

Road from LB Cheria CC road to Chillapalem of LB Cheria. Workcompleted -

NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

From A-U R&B Road to Satyanarayanapuram (Kalla Mandal) 25/2011-12Dt.26.05.2011

Workcompleted -

From A-U R&B Road to Mekaladibba (Kalla Mandal W.G.Dist.) Workcompleted -

Page 18 of 198

Page 20: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN KRISHNA DISTRICT AT THE END OF MARCH-2013

Category Packages allotted underPhase - 1 Names of works under each package Agreement No.

/ Date Work Status Remarks

RHB

NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/001

Road connecting R&B road throughGantlammapalem

8/2011-12/27.04.2011 Work completed -

NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002

Road from R & B Road to B.V Thota 7/2011-12/27.04.2011 Work completed -

Road from Potalapalem Z.P road toChikativanipalem

7/2011-12/27.04.2011 Work completed -

NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

Road from Intheru R&B Road to Rangaraopet 9/2011-12/27.04.2011 Work completed -

Road from R&B road to Cyclone Shelter atChandala

9/2011-12/27.04.2011 Work completed -

RCS NCRMP/B-W /AP/RCS/PRED/06/Machilipatnam/001

Road from Bhogireddypalli R&B Road toRamakhandam

32/2011-12/Dt.02.09.2011 Work completed -

Road from R&B Road Chinnapuram toGundupalem

32/2011-12/27.04.2011 Work completed -

Road from Potlapalem Z.P road to Pothepalli. 32/2011-12/Dt.02.09.2011 Work completed -

Page 19 of 198

Page 21: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN GUNTUR DISTRICT AT THE END OF MARCH-2013

Category

Packages allottedunder Phase - 1 Names of works under each package Agreement

No. / DateWorkStatus Remarks

RHB

NCRMP/B-W/AP/RHB/PRED/07/Karlapalem/001

Road to Kesavapuri ST Colony 7/2011-1227.04.2011

Workcompleted

working estimate approval notreceived

NCRMP/B-W/AP/PRED/07/Nagaram/002

R/f R&B Road to Mohammad Alipalem8/2011-1227.04.2011

Workcompleted

working estimate approval notreceived

R/f R&B Road to Katurivaripalem Workcompleted

working estimate approval notreceived

Bridges

NCRMP/B-W/AP/Br/R&B/07/Bapatla/010

Reconstruction of High-level Bridge @Km5/2 ofBapatla-Suryalanka Road across perali drain

79/2010-111.12.2010

Workcompleted -

NCRMP/B-W/AP/Br/R&B/07/Bapatla/011

Reconstruction of HLB @Km2/4 of Bapatla-Pandurangapuram Road across perali drain

78/2010-111.12.2010

work inprogress Approaches is in progress

RCS

NCRMP/B-W/AP/RCS/PRED/07/PV Palem/001

Road from R&B road to Mandevaripalem

2011-20121.11.2011

Workcompleted

working estimate approval notreceived

Road from R&B Road Alluru to Yadavapalem work inprogress

From Km 0.071 to km 0.125 andkm 0.373 to km 1.046 CC

completed. From km 0.125 km0.373 CC road to be done

NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002

Road from Ganapavaram R&B Road toPedamarpuvaripalem 2011-2012

1.11.2011

Workcompleted

working estimate approval & ATRnot received

Road from R&B Road to Chinapuluguvaripalem Workcompleted

working estimate approval & ATRnot received

Page 20 of 198

Page 22: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

From R&B road to Yaramvaripalem Workcompleted

working estimate approval & ATRnot received

Road from R&B Road to Pedagollapalem CS Workcompleted

working estimate approval & ATRnot received

Pedagollapalem PR road to Bonthagoralapalem Workcompleted

working estimate approval & ATRnot received

RCS

NCRMP/B-W/AP/RCS/PRED/

07/Nizampatnam/003

Road from R&B Road to Gurunadhanagar

2011-201217.10.2011

Workcompleted

working estimate approval & ATRnot received

Road from R & B Road to Adavala H/OBavajipalem

Workcompleted

working estimate approval notreceived

Road from R & B Road to Atlavaripalem Workcompleted

working estimate approval & ATRnot received

NCRMP/B-W/AP/RCS/PRED/07/Bapatla/004

Road from R & B Road to Hanumathanagar2011-201227.10.2011

Workcompleted

working estimate approval notreceived

Road from R & B Road to Adarsh nagar Workcompleted

working estimate approval notreceived

Page 21 of 198

Page 23: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN PRAKASAM DISTRICT AT THE END OF MARCH-2013

Category

Packages allottedunder Phase - 1

Names of works under eachpackage

Agreement No. /Date

WorkStatus Remarks

BRIDGES

NCRMP/B-W/AP/Br/R&B/08/ Kanaparthy/012

Construction of High level Bridge at Km16/10 of Naguluppapadu – Kanaparthyroad

76/2010-11Dated1/12/2010

Workcompleted

Work completed & Final bill paid. Quadrantialrevetment & slopes are damaged duringNeelam cyclone, Because of its height

retaining walls and revetment is necessary.Which are not provided in the original

agreement. The Field officers informed that aseparate estimate for the protection workswould be got sanctioned under state funds

for the slope protection works.

RHB

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001

Road from Pakala ZP Road toAulavaripalem Cyclone shelter

Dated25.04.2011

Workcompleted -

Road from R&B Road to Somarajupalli Dated25.04.2011

Workcompleted -

Road from R&B road to Narravaripalem Dated25.04.2011

Workcompleted -

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

Road from NH5 to Mulaguntapadu dated10/02/2011

Workcompleted working estimate approval not received

Road from R&B road toChalivendradibba

dated -10/02/2011

Workcompleted working estimate approval not received

Road from Pakala R&B road toMosanaladinne

dated10/02/2011

Workcompleted working estimate approval not received

Road from R&B road to BinginapalliHarijanawada Cyclone Shelter

dated10/02/2011

Workcompleted working estimate approval not received

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003

Road from R&B Road Allur to M T Rajucolony

Dated27/04/2011

Workcompleted -

Page 22 of 198

Page 24: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004

Road from KEM R&B Road toSankuvarigunta

Dated27/04/2011

Workcompleted -

Road from KEM R & B Road toPullareddypalem

Dated27/04/2011

Workcompleted -

NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07

Road from MC Road to SubbarayuduSatram

dated27/04/2011

Workcompleted -

RHB

NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/08

Road from R&B road Tettu toRamayapatnam

dated27/04/2011

Workcompleted -

NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09

Road from R&B road Pellur toVasepallipadu

dated16/03/2011

Workcompleted -

NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10 Road from R&B road to Kesupalem dated

19/04/2011Work

completed -

RCS

NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001

Road from R&B road to Vijayanagarcolony cyclone shelter

dated30.09.2011

Workcompleted working estimate approval not received

Road from NH road to Challareddypalem Workcompleted working estimate approval not received

Road from R&B road to jeevarakshnagar colony cyclone shelter

Workcompleted working estimate approval not received

Road from R&B road to Ramnagarcolony cyclone shelter

Workcompleted working estimate approval not received

Road from R&B road to cyclone shelterat Mankenavaripalem

Workcompleted working estimate approval not received

NCRMP/B-W/AP/RCS/PRED/08/Chirala/002

Road from R&B Road toKeerthivaripalem cyclone shelter dated

27.08.2011

Workcompleted working estimate approval not received

Road from R&B Road to Devinuthulacyclone shelter of Chirala Mandal

Workcompleted working estimate approval not received

Page 23 of 198

Page 25: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

MPCS

NCRMP/B-W/APMPCS/PRED/08/Ulavapadu/001

Chakicharla cyclone shelter in UlavapaduMandal

Workcompleted -

NCRMP/B-W/APMPCS/PRED/08/NG Padu/003

Kanaparthy cyclone shelter inNaguluppapadu Mandal prakasamdistrict

Workcompleted working estimate approval not received

Page 24 of 198

Page 26: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN SPSR NELLORE DISTRICT AT THE END OF MARCH-2013

Category

Packages allotted underPhase - 1 Names of works under each package

Agreement No. /Date

Work Status Remarks

RHB

NCRMP/B-W/AP/RHB/PRED/09/

BOGOLO/RHB/001

1. Road from NH5 to Sambasiva Puram

1/19/2011

Work completed -

Road from 9/6 of Juvvaladinne R&B Road to 11/0 ofJuvvaladinne R&B Road Via Venkateshpalem Work completed -

NCRMP/B-W/AP/RHB/PRED/09/BOGOLU/002

Road from 1/6 of Zuvvaladinne R&B Road to TellaguntaKM to 2/720 07.02.2011 Work completed -

NCRMP/B-W/AP/RHB/PRED/09/

CHITTAMURU/003

Road from R&B Road to Muttambeka Via Pittuvanipalla18.01.2011

Work completed -

Road from R&B Chittamur to Soma Samudram Work completed -

NCRMP/B-W/AP/RHB/PRED/09/RHB/KAVALI

/004

Road from5/8 of Chennayapalem Road to Gummadibandla

17.01.2011

Work completed -

Road from pedattapupalem R&B road to ChennayapalemH.wada Work completed -

Road from K.T R&B Road to Alliguntapalem Work completed -

NCRMP/B-W/AP/RHB/PRED/09/

VIDAVALURU/005

Road from KT R&B road to Alaganipadu to Vavilla

27.04.2011

Work completed working estimateapproval not received

Road from R&B road Kancharapalem HW toAlaganipadu. Work completed working estimate

approval not received

NCRMP/B-W/AP/ PRED/09/MUTHUKUR/RHB/ 006 Road from R&B road to Patuvari Kandriga 25.4.11 Work completed -

NCRMP/B-W/AP/RHB/PRED/09/

V.CHALEM/RHB/ 007

Road from Survepalli-Pudiparthi road to Srikanth Colony

27.04.2011

Work completed -

providing BT Surface to the road from R&B road toEdagali Kandriga Work completed -

Page 25 of 198

Page 27: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RHB/PRED/09/Allur/009

Road from R&B road Alluru to Galidibbalu (via)Chukavani dibba 24.01.2011 Work completed -

RHBNCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012

Ring Road to TP Gudur- Salipeta R & B Road via CSPuram and Mandapam Vill. 19.05.2011

Work completed -

Road from R & B Road C S Puram to Sivaramapuram Work completed -

RCS

NCRMP/B-W/AP/PRED/09/kota/RCS /001

Road from R&B road to A.S PURAM10.05.2011

Work completed -

Road from GD Road to Vavilla Palem Work completed -

NCRMP/B-W/AP/ PRED/09/MUTHUKUR/RCS/ 002

Road from R&B Road kappaladoruvu to bandla PalemH.wada 21.04.2011 Work completed -

NCRMP/B-W/AP/PRED/09/Chillakur/RCS/004 Road from Kakuvaripalem R&B road to Vellapalem 23.05.2011 Work completed -

NCRMP/B-W/AP/RCS/PRED/09/

T.P.GUDUR/005

Road from7/2 M.C Road to VenkannapalemPattuapalem 17.05.2011 Work completed -

NCRMP/B-W/AP/RCS/PRED/09/ KAVALI/006

Road Connecting R&B Road through Voturu Village inSPSR Nellore District. 21.09.2011 Work completed working estimate

approval not received

NCRMP/B-W/AP/RCS/PRED/09/ KAVALI/007

Road from Kotha satram R&B to Indrsanagar (via)Thumalapenta palam, Patharavadu palam, Ramudupalam, Karaduvari palam & Sreeramapuram

29.08.2011 Work completed -

NCRMP/B-W/AP/ PRED/09/D.V.SATRAM/RCS/ 008

Road from R&B road to Sullurpeta Mallam toBerijengalapalli cyclone shelter 09.05.2011 Work completed -

NCRMP/B-W/AP/RCS/PRED/ 09/TADA/009

Providing BT road to Pedapannamgadu in Tada Mandal14.09.2012

work in progress Road furniture isbalance

Road from @ 56/8 to C.K road to Periyavettu kuppamcyclone shelter work in progress Sub grade work in

progress

Page 26 of 198

Page 28: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

5.0 District wise status of tests conducted by TPQA:

Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at various

stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards. These tests are

carried out in the site itself and in some cases samples are collected and testing done in outside laboratories. The details of

tests conducted in the field till end of December 2012 are presented.

Summary of QC Tests - Up to 31.03.2013

S.No. District

No. TestsConductedduring the

Month

Total no. of Tests Cumulative TestsDone

Total no. of Tests up to31.03.2013

Passed Failed Passed Failed

1 Srikakulam 51 51 0 1614 1608 6

2 Vizianagaram 14 14 0 521 521 0

3 Visakhapatnam 132 132 0 2585 2539 46

4 East Godavari 48 48 0 1257 1257 0

5 West Godavari 0 0 0 349 349 0

6 Krishna 0 0 0 88 88 0

7 Guntur 9 9 0 668 657 11

8 Prakasam 6 6 0 1961 1957 4

9 Nellore 23 23 0 1238 1217 21

Total 283 283 0 10281 10193 88

Page 27 of 198

Page 29: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

6.0 Details of Final QARs & Quality Control Audit Reports Submitted during this 3 months:

6.1 Details of Final QARs & QCA Reports Submitted during the month of January-2013:

a) QCRs Submitted

Package Number Name of Work District

NCRMP/BW/AP/RHB/PRED/09/vidavalur/005

Road from R&B road Kancharapalem HW toAlaganipadu of SPSR Nellore Dt. Nellore

NCRMP/B-W/AP/RCS/PRED/08/VETAPALEM/001

Road from NH to Challareddypalem InPrakasam District Prakasam

NCRMP/BW/AP/RCS/PRED/07/Karlapalem/002.

Road from Pedagollapalem PR Road toBonthagorlapalem Prakasam

NCRMP/B-W/AP/RCS/PRED/ 07/PVPalem/001

Road from R&B Road Alluru to Yadavapalemin Guntur DT. Guntur

NCRMP/B-W/AP/RCS/PRED/09/TADA/009

Providing BT Road to Peda Pannam Gadu inTada Mandal of Nellore Dt. Nellore

NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003

Providing Road from R&B B.P Kallalu toMatchvanipalem in Visakhapatnam Dt. Visakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001

Providing B.T to the Road from NH-5 toRamaraidupalem in Visakhapatnam Dt. Visakhapatnam

NCRMP/BW/AP/RHB/PRED/09/vidavalur/005

Road from R&B road Kancharapalem HW toAlaganipadu of SPSR Nellore Dt. Nellore

NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of cyclone shelter at Kollipadu inSanthabommali Mandal in Srikakulam Dt. Srikakulam

b) Final QARs submitted

NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

Road from Interu ZP road to Rangaraopeta inKrishna Dt. Krishna

NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001

Road from Bhogireddypalli R&B road toRamakhandam in Krishna Dt. Krishna

NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001

Road from Potlapalem ZP road to Potepalli inKrishna Dt. Krishna

NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002

Road from R&B road to B.V.Thota in KrishnaDt. Krishna

NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001

Road from Chinnapuram R&B road toGundupalem in Krishna Dt. Krishna

NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/001

Road connecting R&B road throughGantalammapalem in Krishna Dt. Krishna

Page 28 of 198

Page 30: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

Road from R&B road to Cyclone shelter atChandala in Krishna Dt. Krishna

NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002

Road from Potlapalem Z.P road toChikativanipalem in Krishna Dt. Krishna

NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

R&B Road at Panchayat office toPulaparthivarithota via Badava of Mogalthuru

Mandal in West Godavari Dt.West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Narasapur/002

Road from R&B road to Pedalanka of NarsapurMandal in West Godavari District. West Godavari

NCRMP/B-W/AP/RHB/ PRED/05/Narasapur/002

R&B road to Indira Nagar (via) Pochammatemple of Narsapur Mandal in West Godavari

Dt.West Godavari

NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

Road from NH 214 A road to Harjanawada ofkothota of Mogalthuru Mandal in West

Godavari Dt.West Godavari

NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

Road from NH 214 A at Ranga statue centerto Harijanawada of Kalipatnam (E) of

Mogalthuru MandalWest Godavari

NCRMP/B-W/AP/RHB/PRED/05/Narasapur/002

Road from LB Cherla CC road to Chillapalemof LB Cherla of Narsapur Mandal in West

Godavari Dt.West Godavari

NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

Mogaltur Vempa R&B Road at Uchintha kalavaBridge to Gogulamma Harijanapeta of

Mogalthuru Mandal in West Godavari Dt.West Godavari

NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

From Narsapur Mogaltur R&B road toDayaldaspeta via Venkateshwara SwamyTemple of Mogalthuru Mandal in West

Godavari Dt.

West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

From A-U R&B Road to Satyanarayanapuramof Kalla Mandal in West Godavari Dt. West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

From A-U R&B Road to Mekaladibba of KallaMandal in West Godavari Dt. West Godavari

6.2 Details of Final QARs & QCA Reports Submitted During the Month of February-2013:

a) QCRs submitted

Package Number Name of Work District

NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

Construction of cyclone shelter atBangarrampeta in Nakkapalli Mandal in

Visakhapatnam Dt.Visakhapatnam

NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004

Construction of cyclone shelter atVenkayypalem in Rambilli in Visakhapatnam

Dt.Visakhapatnam

Page 29 of 198

Page 31: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/BW/AP/BR/R&B/001/Uppugedda/002

Construction of High level bridge acrossUppugedda at KM 7/6 of Srikakulam Municipal

limits to Pukkalapeta via KillipalemSrikakulam

NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

Construction of cyclone shelter at Mullaparrain Nakkapalli Mandal. Visakhapatnam

NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001

Construction of Cyclone Shelter atLakshamanudipeta in Thondangi Mandal, East

Godavari District.East Godavari

NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001

Construction of Cyclone Shelter atAvulamanda in Thondangi Mandal, East

Godavari District.East Godavari

NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002

Construction of Cyclone Shelter atPedaraghavulapeta in Uppalaguptham Mandal,

East Godavari District.East Godavari

NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

Construction of cyclone shelter at Patimeedain Nakkapalli Mandal, Visakhapatnam District. Visakhapatnam

NCRMP/B-W/AP/RCS/PRED/09/Kavali/006

Road Connecting R&B Road through VotturuVillage in SPSR Nellore District SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/09/TADA/009

Providing BT Road to Peda Pannam Gadu inTada Mandal in SPSR Nellore District SPSR Nellore

NCRMP/BW/AP/RHB/PRED/09/Vidavalur/005

Road from R&B road Kancharapalem HW toAlaganipadu in SPSR Nellore District SPSR Nellore

NCRMP/B-W/AP/Br/R&B/07/Bapatla/010/2010

Reconstruction of HLB@Km 5/2 of Bapatla-Suryalanka Road across Perali drain. Guntur

b) Final QARs submitted

NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006

Providing BT surface to the Road from R&Broad to Venkayyapalem in Rambilli Mandal Visakhapatnam

NCRMP/B-W/AP/RHB/PRED/08/Tangatur/10

R&B Road to Kesupalem in Tangatur MandalPrakasam District. Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09

Road from R&B Road Pellur to Vasepallipadu-Tangutur (M) Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/007

Road from M.C Road to Subbarayudu Satramin Ulavapadu Mandal Prakasam

NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

Road from 7/2 M.C Road to Venkannapalampattapupalem of T.P Gudur in Nellore Dt. SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/09/KAVALI/007

Road from Kotha satram R&B to Indrsanagar(via) Thumalapenta palam, Patharavadu

palam, Ramudu palam, Karaduvari palam &Sreeramapuram

SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/09/D.V.Satram/008

Road from R&B Road Sullurpeta-Mallam toBerijangalapalli Cyclone Shelter SPSR Nellore

Page 30 of 198

Page 32: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RHB/09/T.P.GUDUR/012

Ring Road to T.P.Gudur-Salipeta R&B Road viaC.S.Puram and Mandapam Village. SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001

Road from R&B road to Narravaripalem inPrakasam District Prakasam

NCR MP/B-W/AP/RHB/PRED/09/Bogolu/002

Road from 1/6 of Zuvvaladinne R&B Road toTellagunta SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/008

Road from R&B Road Tettu to Ramayapatnamin Ulavapadu Mandal in Prakasam District Prakasam

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001

Road from R&B Road to Somarajupalli inPrakasam District Prakasam

NCRMP/B -W/AP/RHB/PRED/09/Bogolu/001

Road from 9/6 of Juvvaladinne R&B Road to11/0 of Juvvaladinne R&B Road via

Venkateshpalem of SPSR Nellore DistrictSPSR Nellore

NCRMP/B-W/AP/RHB/PRED/08/Singarayakonda/001

Road from Pakala ZP Road to AulavaripalemCyclone Shelter Prakasam

NCRMP/B -W/AP/RHB/PRED/09/Bogolu/001

Road from NH5 to Sambasivapuram in SPSRNellore District SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/09/Kota/001

Road from R&B road to A.S.Puram in SPSRNellore District SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003

Road from R&B Road to Allur to M.T.Rajucolony in Kothapatnam Mandal Prakasam

NCRMP/B-W/AP/RCS/PRED/09/Kota/001

Road from GD road to Vavillapalem in VakaduMandal. SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/T.P.GUDUR/012

Road from R&B C.S.Puram to Siva RamaPuram of SPSR Nellore District SPSR Nellore

NCRMP/BW/AP/RH/PRED/03/Nakkapalli/001

Providing Bt Surface To The Road FromVempudi To Patimeeda in Nakkapalli Mandal. Visakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003

Road from R&B road to Pedatheernala toChinatheernala in Visakhapatnam District Visakhapatnam

NCRMP/B-W/AP/RCS/PRED/09/Chillakur/004

Road from Kakuvaripalem R&B Road toVellapalem in Chillakur Mandal SPSR Nellore

NCRMP/BW/AP/RHB/PRED/09/V.Chalem/007

Providing BT Surface to the road from R&Broad to Edagalikandriga. SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004

KEM R&B Road to Pullareddypalem villageKothapatnam Mandal in Prakasam District Prakasam

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004

Road from KEM R&B Road to Sankuvariguntavillage Kothapatnam Mandal Prakasam

NCRMP/BW/AP/RHB/PRED/09/V.Chalem/007

Providing BT Surface to the Road fromSurvepalli-Pudiparthi road to Srikanth Colony. SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003

Road from Upmaka Rajayyapeta R &B Road toJanakayyapeta Visakhapatnam

Page 31 of 198

Page 33: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RHB/PRED/09/Chittamuru/003

Road from R&B to Muttembaka (via)Pittuvanipalli in SPSR Nellore District SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Chittamuru/003

Road from R&B Chittamuru to SomaSamudram in SPSR Nellore District SPSR Nellore

NCRMP/BW/AP/RHB/PRED/09/Muthukur/006

Road from R&B Road to Patuvari Kandriga inSPSR Nellore District SPSR Nellore

NCRMP/B-W/AP/MPCS/PRED/08/Ulavapadu/001

Construction of Cyclone shulter at Chakicherlain Ulavapadu mandal in Prakasam District Prakasam

NCRMP/B-W/AP/RHB/PRED/09/Allur/009

Road from R&B road Alluru to Galidibbalu(via) Chukkavani dibba of Nellore Dt. SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/03/Paravada/004

Road from R&B Road to Jalaripeta of ParvadaMandal in Visakhapatnam District Visakhapatnam

NCR MP/B -W/AP/RCS/PRED/09/Muthukur/002

Road from R&B Road Kappaladoruvu toBandlapalem H.wada SPSR Nellore

NCRMP/B-W/AP/MPCS/PRED/08/Ulavapadu/001

Construction of Minor bridge At KM 12/2-4 ofNh-5 to Surampeta road via Naruva, Mentada Srikakulam

NCRMP/B-W/AP/RHB/PRED/03/Paravada/004

Road from R&B Road to Pothurajanapalem ofParavada Mandal in Visakhapatnam District Visakhapatnam

NCRMP/B-W/AP/Br/R&B/07/Bapatla/010/2010

Reconstruction of Hlb@Km 5/2 of Bapatla-Suryalanka Road Across Perali Drain Guntur

NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002

Providing BT surface to the Road from R&BRoad to Krishnampalem in Rambilli Mandal Visakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002

Providing BT surface to the Road from R&BRoad to Kattubolu to Marripalem in Rambilli

MandalVisakhapatnam

NCRMP/BW/AP/RHB/PRED/03/Nakkapalli/002

Providing BT Surface to the Road from R&BRoad to Mullaparra up to Beach End in

Nakkapalli MandalVisakhapatnam

NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005

Road from Kotcherla road to Kollibhemavaram& Cyclone Shelter of Ranasathalam Mandal Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005

Road from Kotcherla road toPatasundarapalem of Ranasathalam Mandal Srikakulam

NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002

Providing BT surface to the Road from R&BRoad to Raja Koduru in Ramibilli Mandal Visakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Achutapuram/007

Road from R & B Road to Ava Rajam inAchutapuram Mandal Visakhapatnam

NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005

Road from Koyyam R&B Road toMoosavanipeta in Etcherla Mandal Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005

Road from Mentada to Dovupeta inRanasathalam Mandal of Srikakulam Dt. Srikakulam

Page 32 of 198

Page 34: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

6.3 Details of Final QARs & QCA Reports Submitted During the Month of March-2013:

a) QCRs submitted

Package Number Name of Work District

NCRMP/BW/AP/RCS/PRED/07/Karlapalem/002

Road from Ganapavaram R&B Road toPedamarpuvaripalem Guntur

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

Road from NH5 to Mulaguntapadu village inSingarayakonda Mandal Prakasam

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

Road from Pakala R&B road to Mosanaladinne inSingarayakonda Mandal Prakasam

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

Road from R&B Road to Chalivendradibba inSingarayakonda Mandal Prakasam

NCRMP/B-W/AP/RHB/PRED/09/KOTA/023

Road from at km 22/5 of Yamadinnepalem roadto Gunnampadia of Kota Mandal SPSR Nellore

NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of Cyclone Shelter at Runku inSanthabommali Mandal Srikakulam

NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of Cyclone Shelter at Kollipadu inSanthabommali Mandal Srikakulam

NCRMP/B-W/AP/RCS/PRED/ 07/PVPalem/001 Road from R&B Road Alluru to Yadavapalem Guntur

NCRMP/B-W/AP/RHB/PRED/09/V.Chalam/021

Road from Thirumalammapalem R&B road toGajulapalli Koneru of Venkatachalam Mandal SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/09/TADA/009

Providing BT road to Peda Pannam Gadu in TadaMandal. SPSR Nellore

NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001

Construction of Cyclone Shelter at Avulamanda inThondangi Mandal East Godavari

NCRMP/B-W/AP/MPCS/PRED/04/Thondangi/001

Construction of Cyclone Shelter atLakshamanudipeta in Thondangi Mandal East Godavari

NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002

Construction of Cyclone Shelter atPedaraghavulapeta in Uppalaguptham Mandal East Godavari

NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004

Construction of cyclone shelter at Venkayypalemin Rambilli Mandal Visakhapatnam

NCRMP/B-W/AP/RHB/PRED/09/KOTA/023

Road from at km 22/5 of Yamadinnepalem Roadto Gunnampadia of Kota Mandal SPSR Nellore

b) Final QARs submitted

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004 Road from R&B Road to Danavaipeta East Godavari

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Road to Gaddipeta of ThondangiMandal in East Godavari Dt. East Godavari

Page 33 of 198

Page 35: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Road to Hukumpeta CycloneShelter East Godavari

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Road to K. Chodipallipeta ofThondangi Mandal in East Godavari Dt. East Godavari

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004 Road from R&B Road to P.Chodipallipeta East Godavari

NCRMP/B W/AP/RHB/PRED/09/Kavali/004

Road from pedattapupalem R&B road toChennyapalam H.wada SPSR Nellore

NCRMP/BW/AP/RHB/PRED/09/Kavali/004 Road from KT R&B Road to Alliguntapalem SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/04/Karapa/001

Road from Approach Road to Cyclone Shelter atAdavipudi of Karapa Mandal East Godavari

NCRMP/B-W/AP/RHB/PRED/04/Karapa/001

Road from Gurajanapalli to Bandulavaripalem ofKarapa Mandal East Godavari

NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003

Road from PR Road to Dasarivanipeta and toCyclone Shelter of Katrenikona Mandal East Godavari

NCRMP/B-W/AP/RHB/PRED/09/Kavali/004

Road from 5/8 of Chennayapalem Road toGummadi bandla SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Kavali/004

Road from R&B Road to Ava Somavaram inAchutapuram Mandal Visakhapatnam

NCRMP/B-W/AP/RD/R&B/02/Konada/009

Improvements to Road from KonadaRamatheertham (R&B) Road to Konathalapalem(Via) Pasupam, Yerukonda, Kollayavalasa fromKm 12/0 to 16/5 (Km 0/0 to 4/0 i.e. upto NH-5

crossing).

Vizianagaram

NCRMP/B-W/AP/Br/R&B/02/Puligadda/007

Construction of Minor Bridge at Km. 7/2 nearPuligadda of Konada – Ramatheertham R&B Road

to Konathalapalem via Yerukonda, Pasupam,Kollayavalasa (Z.P. Road)

Vizianagaram

NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP road to URK Puram. Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B Road to Devunthalada. Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002

Road from Deppuru, bhadapalli road to Onkuluru& cyclone shelter Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002

Road from Pollada to Komaralthada cyclonicshelter. Srikakulam

NCRMP/BW/AP/RHB/PRED/09/Vidavalur/005

Road from R&B road Kancharapalem HW toAlaganipadu SPSR Nellore

NCRMP/BW/AP/BR/R&B/001/Patnavanipeta/001

Construction of HLB Act KM 11/6-8 of NH-5 topatnavanipeta Road Via Tamada connecting

Sundarapalem.Srikakulam

NCRMP/BW/AP/RHB/PRED/09/Vidavalur/005

Road from R&B road Alaganipadu to Vavilla ofVidavalur SPSR Nellore

Page 34 of 198

Page 36: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

7.0 Details of Environmental and Social Reports Submitted During this 3 Months:

7.1. Details of Environmental and Social Reports Submitted During the Month January 2013:

Package Number Name of Work District

Nil Nil Nil

7.2. Details of Environmental and Social Reports Submitted During the Month February 2013:

Package Number Name of the Work District

NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001 Road from NH-5 to Ramarayadupalem Vishakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R & B road to Rajakoduru. Vishakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B road Kattubolu to Marripalem Vishakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R & B road to Krishnampalem. Vishakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003

Road from R&B road Pedateernala toChinateernala in Nakkapalli Mandal. Vishakhapatnam

NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003

Road from Upmaka Rajayyapeta R&B Road toJanakayyapeta in Nakkapalli Mandal Vishakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001 Road from Vempudi to Patimeeda Vishakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/002

Road from R&B Road to Mulapura up to Beachend. Vishakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Anandpuram/003 Road from R&B B.P Kallulu to Matchavaniplem. Vishakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 Road from R&B road to Pothurajannapalem. Vishakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 Road from R&B road to Jalaripeta. Vishakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006 Road from R&B road to Venkayyapalem. Vishakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/007 Road from R&B road to A.Somavaram. Vishakhapatnam

NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/007 Road from R&B road to Avarajam. Vishakhapatnam

NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Bangarampeta. Vishakhapatnam

Page 35 of 198

Page 37: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Mulaparra. Vishakhapatnam

NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Patimeeda. Vishakhapatnam

NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

Construction of cyclone shelter atGajapathinagaram. Vishakhapatnam

NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Ratnayampeta. Vishakhapatnam

NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004

Construction of Cyclone Shelter at Venkayyapalemin Rambilli Mandal. Vishakhapatnam

NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002

Deppuru Bahadpalli Road to Onkuluru & to CycloneShelter Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 R&B Road to Devunaltada Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Pollada to Komraltada & to Cyclone shelter Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002

Road from Koyyam R&B Road to Moosavanipeta ofSrikakulam Dt. Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Mentada Dovupeta Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005

Road from Kotcherla Road to Kollibheemavaram &Cyclone Shelter Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Kotcherala road to Pathasundarapalem Srikakulam

NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003

of Road from Borubhadra, Malagam to Kollipaduvia Seepuram, Gantapeta Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/Santhabommali/003 Road from DPN R&B Road to Udandapalem Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/Santhabommali/003

Road from K. Umilada Junction to Koduru(Link Road) Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/Polaki/005

Road from R&B Road Edulavalsa Killam to Jonnamvia Talasamudram Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/Polaki/006

Road from R&B Road Mobagam toDubbakavanipeta via Gajapatinagram Srikakulam

NCRMP/B-W/AP/RCS/PRED/01/Polaki/006 Road from Talasamudram to Dola Regulator Srikakulam

NCRMP/B-W/AP/Br/R&B/01/Patnavanipeta/001

Construction of bridge at Km 11/6-8 of NH-5 toPatnavanipeta Connecting Sundarapalem Srikakulam

NCRMP/B-W/AP/Br/R&B/01/Surampeta/003

Construction of Minor Bridge at Km 12/2-4 of NH-5to Surampeta Road via Naruva, Mentada Srikakulam

Page 36 of 198

Page 38: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/Br/R&B/01/Bendigaada/004

Construction of High level bridge acrossBendigedda at KM 4/10 of Pundi-Parlakimidi Road Srikakulam

NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005 Construction of Cyclone Shelter at Runku Srikakulam

NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005 Construction of Cyclone Shelter at Kollipadu Srikakulam

NCRMP/B-W/AP/RCS/PRED/05/Mogaltur/001

Road from NH 214 A at Ranga Statue Centre toHarijanawada of Kalipatnam (E) West Godavari

NCRMP/B-W/AP/RCS/PRED/05/Mogaltur/001

R&B Road at Panchayat office toPulaparthivarithota via Badava West Godavari

NCRMP/B-W/AP/RCS/PRED/05/Mogaltur/001

Mogaltur Vempa R&B Road at Uchinta KalavaBridge to Gogulamma Harijanapeta West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/001

Narsapur mogaltur R&B Road to Dayadaldaspetavia Venkateshwara Swamy Temple West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/001

Road from NH 214 A to Harijanapeta of Kothota inWest Godavari District West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/002

Road from R&B Road to Indiranagar (Via)Pochamma Temple West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/002 Road from R&B Road Pedalanka West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/002

Road from LB Cheria CC Road to Chillapalem of LBCheria West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Kalla/003 Road from A_U Road to Satyanarayanapuram West Godavari

NCRMP/B-W/AP/RHB/PRED/05/Kalla/003 Road from A_U Road to Mekaladibba West Godavari

NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001

Road from R&B road to cyclone shelter atMankenavaripalem Prakasham

NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001

Road from R&B road to jeevaraksha nagar colonycyclone shelter Prakasham

NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001

Road from R&B road to Vijaynagar colony cycloneshelter. Prakasham

NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001

Road from R&B road to Ramnagar colony cycloneshelter. Prakasham

NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001 Road from NH Road to Challreddypalem. Prakasham

NCRMP/B-W/AP/RCS/PRED/08/Cheerala/002

Road from R&B Road to Devinuthula cycloneshelter. Prakasham

NCRMP/B-W/AP/RCS/PRED/08/Cheerala/002

Road from R&B Road to Keerthivaripalem cycloneshelter. Prakasham

NCRMP/B-W/AP/RCS/PRED/08/S.Konda/001

Road from Pakala ZP Road to AulavaripalemCyclone shelter. Prakasham

Page 37 of 198

Page 39: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RCS/PRED/08/S.Konda/001 Road from R&B Road to Somarajupalli . Prakasham

NCRMP/B-W/AP/RCS/PRED/08/S.Konda/001 Road from R&B Road to Narravaripalem. Prakasham

NCRMP/B-W/AP/RCS/PRED/08/S.Konda/002 Road from NH-5 to Mulgantapadu Prakasham

NCRMP/B-W/AP/RCS/PRED/08/S.Konda/002 Road from R&B Road to Chalivendradibba Prakasham

NCRMP/B-W/AP/RCS/PRED/08/S.Konda/002

Road from R&B Road to Mosanaladinne ofPrakasam Dt. Prakasham

NCRMP/B-W/AP/RCS/PRED/08/S.Konda/002

Road from R&B Road to Binginapalli HarijanwadaCyclone Shelter of Prakasam Dt. Prakasam

NCRMP/B-W/AP/RCS/PRED/08/Kothapatnam/003 Road from R&B Road Allur to MT Raju colony. Prakasam

NCRMP/B-W/AP/RCS/PRED/08/Kothapatnam/004 Road from KEM R&B road to Sankuruvarigunta Prakasam

NCRMP/B-W/AP/RCS/PRED/08/Kothapatnam/004 Road from KEM R&B road to Pullareddypalem Prakasham

NCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/07 Road from MC Road to Subarayaudu satram. Prakasam

NCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/08 Road from MC Road to Tettu to Ramyapatnam. Prakasam

NCRMP/B-W/AP/RCS/PRED/08/Tangutur/08 Road from R&B Road Pellur to Vasepallipadu Prakasam

NCRMP/B-W/AP/RCS/PRED/08/Tangutur/10 Road from R&B Road to Kesuplem Prakasam

NCRMP/B-W/AP/RCS/PRED/09/Kota/001 Road from R&B Road to A.S.Puram Nellore

NCRMP/B-W/AP/RCS/PRED/09/kota/001 Road from GD road to Vavillapalem Nellore

NCRMP/B-W/AP/RCS/PRED/09/Muthukur/002

Road from R&B Road to Kappaladoruvu toBandlapalem H.Wada Nellore

NCRMP/B-W/AP/RCS/PRED/Chillakur/004 Road from Kakuvaripalem R&B road to Vellapalm Nellore

NCRMP/B-W/AP/RCS/PRED/09/T.P.Gudur/005

Road from 7/2 M.C. Road to VenkannapalemPattapupalem Nellore

NCRMP/B-W/AP/RCS/PRED/09/Kavali/006 Road connecting R&B Road through Votturu Village Nellore

NCRMP/B-W/AP/RCS/PRED/09/Kavali/007

Road from Kotha satram R&B to Indrsanagar (via)Thumalapenta palam, Patharavadupalam,

Ramudupalam, Karaduvari palam &Sreeramapuram

Nellore

NCRMP/B-W/AP/RCS/PRED/09/D.V. Satram/008

Road from R& B road to Sullurpeta Mallam toBerijengalapalli Cyclone Shelter Nellore

Page 38 of 198

Page 40: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RHB/PRED/09/Bogole/001 Road from NH5 to Sambasiva Puram Nellore

NCRMP/B-W/AP/RHB/PRED/09/Bogole/001

Road from 9/6 to 11/0 of Juvvaladinne R&B Roadvia Venkatespalem Nellore

NCRMP/B-W/AP/RHB/PRED/09/Bogole/002

Road from 1/6 of Zuvvaladinne R & B Road toTellgunta Nellore

NCRMP/B-W/AP/RHB/PRED/09/Chittamur/003

Road from R&B Road to Muttambeka ViaPittuvanipalli Nellore

NCRMP/B-W/AP/RHB/PRED/09/Chittamuru/003 Road from R&B Chittamur to Somasamudram Nellore

NCRMP/B-W/AP/RHB/PRED/09/Kavali/004 Road from KT R&B Road to Alliguntapaem Nellore

NCRMP/B-W/AP/RHB/PRED/09/Kavali/004

Road from KM 5/8 of Chennayapalem Road toGummadibandala Nellore

NCRMP/B-W/AP/RHB/PRED/09/Kavali/004

Road from Pedapattupalem R&B Road toChennyapalam H.Wada Nellore

NCRMP/B-W/AP/RHB/PRED/09/Vidavalur/005

Road from KT R&B Road to Alaganipadu to VavillaGC Nellore

NCRMP/B-W/AP/RHB/PRED/09/Vidavalur/005

Road from R&B road Kancharlapalam HW toAlaganipadu. Nellore

NCRMP/B-W/AP/RHB/PRED/09/Muthukur/006 Road from R&B road to Patuvari Kandriga. Nellore

NCRMP/B-W/AP/RHB/PRED/09/Muthukur/006

Road from Survepalli – Pudiparthi Road to SrikanthColony Nellore

NCRMP/B-W/AP/RHB/PRED/09/V.Chalam/007 Road from R&B Road to Edagil Kandriga Nellore

NCRMP/B-W/AP/RHB/PRED/09/Allur/009

Road from R&B Road Allur to Galidibbalu (Via)Chilkaruvanidibba. Nellore

NCRMP/B-W/AP/RHB/PRED/09/Allur/009

Road from R&B Road to CS Puram and MandapamVillage Nellore

NCRMP/B-W/AP/RHB/PRED/09/T.P.Gudur/012 Road from R&B road CS Puram to Sivarampuram. Nellore

7.3. Details of Environmental and Social Reports Submitted During the Month March 2013:

NCRMP/B-W/AP/RCS/PRED/09/Kota/001 Road from R&B Road to A.S.Puram SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/09/kota/001 Road from GD road to Vavillapalem SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/09/Muthukur/002

Road from R&B Road to Kappaladoruvu toBandlapalem H.Wada SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/Chillakur/004 Road from Kakuvaripalem R&B road to Vellapalm SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/09/T.P.GUDUR/005

Road from 7/2 M.C. Road to VenkannapalemPattapupalem SPSR Nellore

Page 39 of 198

Page 41: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RCS/PRED/09/Kavali/006 Road connecting R&B Road through Votturu Village SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/09/Kavali/007

Road from Kotha satram R&B to Indrsanagar (via)Thumalapenta palam, Patharavadu palam, Ramudu

palam, Karaduvari palam & SreeramapuramSPSR Nellore

NCRMP/B-W/AP/RCS/PRED/09/D.V. Satram/008

Road from R& B road to Sullurpeta Mallam toBerijengalapalli Cyclone Shelter SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Bogole/001 Road from NH5 to Sambasiva Puram SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Bogole/001

Road from 9/6 of Juvvaladinne R&B Road to 11/0 ofJuvvaladinne R&B Road via Venkatespalem SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Bogole/002

Road from 1/6 of Zuvvaladinne R & B Road toTellgunta SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Chittamur/003

Road from R&B Road to Muttambeka ViaPittuvanipalli SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Chittamuru/003 Road from R&B Chittamur to Somasamudram SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Kavali/004 Road from KT R&B Road to Alliguntapaem SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Kavali/004

Road from KM 5/8 of Chennayapalem Road toGummadibandala SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Kavali/004

Road from Pedapattupalem R&B Road toChennyapalam H.Wada SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Vidavalur/005 Road from KT R&B Road to Alaganipadu to Vavilla GC SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Vidavalur/005

Road from R&B road Kancharlapalam HW toAlaganipadu. SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Muthukur/006 Road from R&B road to Patuvari Kandriga. SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Muthukur/006

Road from Survepalli – Pudiparthi Road to SrikanthColony SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/V.Chalam/007 Road from R&B Road to Edagil Kandriga SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Allur/009

Road from R&B Road Allur to Galidibbalu (Via)Chilkaruvanidibba. SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/Allur/009

Road from R&B Road to CS Puram and MandapamVillage SPSR Nellore

NCRMP/B-W/AP/RHB/PRED/09/T.P.Gudur/012 Road from R&B road CS Puram to Sivarampuram. SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/ 07/PVPalem/001 Road from R&B Road to Mandevaripalem Guntur

NCRMP/B-W/AP/RCS/PRED/07/PV Palem/001 Road from R&B Road Alluru to Yadavapalem Guntur

NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002

Road from Ganapavaram R&B Road toPedamarpuvaripalem Guntur

NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002 Road from R&B Road to Chinapuluguvaripalem Guntur

NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002 Road from R&B Road to Yaramavaripalem Guntur

NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002

Road from R&B Road Peddagollapalem CycloneShelter Guntur

Page 40 of 198

Page 42: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002

Road from Peddagollapalem P.R Road toBothagorlapalem Guntur

NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/003 Road from R&B Road to Adavala H/O Bavajipalem Guntur

NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/003 Road from R&B Road to Atalavaripalem Guntur

NCRMP/B-W/AP/RCS/PRED/07/Baptala/004 Road from R&B Road to Hanuamathnagar Guntur

NCRMP/B-W/AP/RCS/PRED/07/Baptala/004 Road from R&B Road to Adarshnagar Guntur

NCRMP/B-W/AP/RHB/PRED/07/Karlapalem/001

Road from Ganapavaram R&B Road to Kesavapuri STcolony Guntur

NCRMP/B-W/AP/RHB/PRED/07/Nagaram/002 Road from R&B Road to Mohammad Alipalem Guntur

NCRMP/B-W/AP/RHB/PRED/07/Nagaram/002 Road from R&B Road Katuvanipalem Guntur

NCRMP/B-W/AP/Br/R&B/07/Bapatla/010

Reconstruction of HLB at Km. 5/2 of Bapatla-Suryalanka Road. Guntur

NCRMP/B-W/AP/Br/R&B/07/Perali/011

Reconstruction of HLB at Km. 2/4 of Bapatla-Pandurangapuram across Perali Drain. Guntur

NCRMP/B-W/AP/Br/R&B/02/Puligadda/007

Minor Bridge at Km. 7/2 near Puligadda of Konada –Ramatheertham R&B Road to Konathalapalem viaYerukonda, Pasupam, Kollayavalasa (Z.P. Road)

Vizianagaram

NCRMP/B-W/AP/Br/R&B/02/Chakaligadda/008

Minor Bridge at KM15/2 near chakaligadda of Konda-Ramatheertham R&B Road to Konathalapalem (via)

Yerukonda, Pasupam, Kollayavalasa (Z.P.Road)Vizianagaram

NCRMP/B-W/AP/Br/R&B/02/Konda/009

Improvements to Road from Konda Ramatheertham(R&B) Road to Konathalapalem (Via) Pasupam,

Yerukonda, Kollayavalasa from Km. 12/0 to 16/5 (Km.0/0 to 4/0 i.e., upto NH-5 crossing)

Vizianagaram

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004 Road from R&B Road to G.Musalayyapeta East Godavari

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004 Road from R&B Road to Danavaipeta East Godavari

NCRMP/B-W/AP/RCS/PRED/4/Thondangi/004 Road from R&B Road to Gaddipeta Cyclone shelter East Godavari

NCRMP/B-W/AP/RCS/PRED/4/Thondangi/004 Road from R&B Road to Hukumpeta Cyclone shelter East Godavari

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Road to K. Chodipallipeta Cycloneshelter East Godavari

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Road to P.Chodipallipeta Cycloneshelter East Godavari

NCRMP/B-W/AP/RHB/PRED/04/Karapa/001 Road from Gurjanpalli to Bandualavaripalem East Godavari

NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003

Road from PR Road to Dasarivanipeta and to CycloneShelter East Godavari

NCRMP/B-W/AP/MPCS/PRED/08/Ulavapadu/001 Construction of Cyclone Shelter at Chakicherla. Prakasam

NCRMP/B-W/AP/MPCS/PRED/08/NG Padu/003 Construction of Cyclone Shelter at Kanaparthy. Prakasam

Page 41 of 198

Page 43: Quarterly Progress Report - Jan-March 2013

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/Br/R&B/08/Kanaparthy/012 Construction of HLB @ Km.16/10 of Nagulapapadu Prakasam

NCRMP/B-W /AP/RCS/PRED/06/Machipatnam/001 Road from Potlapalem Z.P road to Pothepalli. Krishna

NCRMP/B-W /AP/RCS/PRED/06/Machipatnam/001 Road from Chinnapuram R&B Road to Gundupalem. Krishna

NCRMP/B-W /AP/RCS/PRED/06/Machipatnam/001

Road from Bhogireddipalli R&B Road toRamakhandam. Krishna

NCRMP/B-W /AP/RHB/PRED/06/Machipatnam/001

Road Connecting R&B Road throughGantalammapalem. Krishna

NCRMP/B-W /AP/RHB/PRED/06/Machipatnam/002 Road from R&B Road to B.V.Thota. Krishna

NCRMP/B-W /AP/RHB/PRED/06/Machipatnam/002 Road from Potalapalem Z.P Road to Chikativanipalem. Krishna

NCRMP/B-W /AP/RHB/PRED/06/Kruthivenu/003 Road from Intheru Z P Road to Rangaraopeta. Krishna

NCRMP/B-W /AP/RHB/PRED/06/Kruthivenu/003

Road from Intheru Z P Road to Cyclone shelter atChandala Krishna

Page 42 of 198

Page 44: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

8.0 Consolidated E&S Reports during this 3 Months:

8.1 Consolidated E&S Report for Srikakulam, Visakhapatnam, West Godavari, Prakasam & SPSR Nellore Districts in the Month ofFebruary 2013:

Third Party Quality Audit for Construction of Cyclone Shelters, Roads to CycloneShelters & Habitations, Bridges and Culverts under NCRMP (Details of SrikakulamDistrict during February, 2013)

Sl.No Activity Measures to be implemented by the contractor Complied Not

CompliedNot

Applicable Total

1Work Plan forEMPimplementation

The Contractor’s Project Manager shall be responsible for implementation of EMPprovisions and will coordinate the over-all implementation of the said plan. Alongwith the Work Programme, the Contractor shall submit a plan including methodstatement and timeline about specific actions that will be taken by him to implementthe provisions laid out in the EMP

16 16

2RegulatoryPermissionsand Consents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consent forplants, water and extraction and borrow areas operations. This includes:

Consent for establishment and operation of plant (for concrete work) from SPCB. 16 16

PUC certification for all vehicles/equipment used for/during construction. 16 16Permission/consent of the District Administration/Mining Department/otheragencies for quarrying and/or borrowing operations for materials like sand andearth.

16 16

Permission for water extraction, if applicable in the local area context. 16 16

The Contractor shall abide by all conditions laid out in the said clearances. 16 16

Page 43 of 198

Page 45: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3

ConsultationandCommunityConsent

The Contractor shall consult and obtain written consents oflandowners(individual/Panchayat/govt. agency) for temporary use of land for allconstruction related activities including:a) Setting-up and operation of construction camp including labour camps, stockyards etc. 16 16

b) borrow areas and 16 16c) Disposal of debris and other waste material. 16 16

4 Construction/Labour Camp

a) Location: The camp and plant site/s location and establishment shall be done ina manner that does not interfere or disturb the activities of local inhabitants,particularly those of schools and health facilities. Written permission (no objectioncertificate) shall be taken from the Gramsabha and the land owner prior to locationselection and a copy shall be submitted to the Engineer approval.

16 16

b) Camp site shall not be located within 250mts. From a water body includingvillage ponds. 16 16

c) A distance of at least 500mts. Shall be maintained from designated/protectednatural habitats (such as National Parks, Sanctuaries, Biosphere Reserves,Reserve Forests and Ramsar Sites) and Coastal Regulation Zone.

16 16

b) Accommodation and Basic Amenities: All weather shelter with the requiredtenement size and toilets shall be provided, as per provisions of Labour Laws.Separate toilet facilities shall be provided for women workers. If a common mess isnot provided/operated additional space for cooking shall be provided. Thecontractor shall ensure that hygienic conditions are maintained during the operationof such camps/facilities.

16 16

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is not used as acooking medium in the construction /labour camp. 16 16

d) Potable water supply: Drinking water supply of at least 40Ipcd with the requiredsupply points shall be provided. 16 16

e) Fire Safety: Adequate fire safety precautions shall be taken and required firesafety equipment (such as fire extinguishers) shall be provided by the contractor. 16 16

5 Site Clearancea) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s (includingthose from Forest Dept., if required) are obtained prior to cutting of such trees.

16 16

Page 44 of 198

Page 46: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

b) The non-timber grade trees are to be stacked and possession is to be given toEmployer/concerned Govt. Department. 16 16

c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. The top soilshall be reinstated in the cyclone shelter compound after the construction is over.

16 16

6Protection ofProperties andResources

The Contractor shall take due care to protect and prevent damages to the followingresources during preparatory and construction work:a) Water supply lines 16 16b) Irrigation canals 16 16c) Cart, cattle and/or foot trail/tracks 16 16d) Cultural properties and sites/structures of religious importance 16 16e) Houses, Farmlands, Orchids and/or Trees. 16 16f) School and other existing buildings adjacent to the site of construction. 16 16In case of damage due to construction activity, the restoration/repairs shall becarried out by the contractor at his own cost. 16 16

7 QuarryOperations

The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.

16 16

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractor following thestipulations given below: The finalisation of all such locations shall be dependenton the approval of the Engineer on technical and environmental grounds. Thisincludes on-site verification to cross-check the accuracy of details provided by thecontractor. Only after receipt of the written approval from the Engineer, theContractor shall enter into a formal agreement with landowner.

16 16

b) The Contractor shall not procure any kind of construction material (such asaggregates, sand and earth) from ecologically protected areas. 16 16

c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to be doneon an agricultural land, top-soil stripping, stacking and preservation is must.

16 16

2. Borrow pits shall not be located within a distance of 100mts. From any NH, SHor other roads. 16 16

Page 45 of 198

Page 47: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 16 16

4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centers. 16 16

5. No borrow area shall be opened with in 500mts. from a reserved or protectedforest area, protected sites, wildlife movement zone and cultural heritage site. 16 16

6. No tree cutting shall be undertaken. 16 167. Borrow area near any surface water body will be at least 100mts. away. 16 16d) Operation 161. Area up to which material will be extracted shall be cleared demarcated onground. 16 16

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 16 163. Borrowing of earth should be preferably limited to a depth of 1.5mtr from theexisting ground level. 16 16

4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 16 16

e) Rehabilitation of Borrow Areas: 16 161. Rehabilitation shall be satisfactory undertaken immediately after the use hasceased and at least three weeks prior to monsoon 16 16

2. Preserved top soil has be spread uniformly over land (except in cases whereborrow area is developed as a water body) used as a borrow area. 16 16

9 WaterExtraction /Use

Water for construction and for use at construction camps (including labour camps)is to be extracted with prior written permission of(a) the individual owner, in casethe source is private well/tube well; (b) Gram Panchayat in case the source belongsto community: and (c) Irrigation Department in case the source is an irrigation canalor river.

16 16

10

Safety of RoadUsers andLocalResidents

a) Traffic safety arrangements (including provision of warning signage, speedbreakers etc.) shall be made by the contractor to ensure safety of road users andlocal people, particularly in the internal village roads which will be used fortransporting materials.

16 16

b) Material shall be covered during transportation to prevent spillage, accidentsand pollution. 16 16

Page 46 of 198

Page 48: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

c) All required measures to ensure safety of local residents including childrenand other near-by residents shall be taken up by the Contractor. This shall includeprovisions to prevent un authorised entry into the construction.

16 16

11 Worker’sSafety

a) All measures required for ensuring safety and health of the workers shall betaken up by the Contractor. This includes provision and enforcement of appropriatepersonal protective equipment; first aid facility; emergency response arrangement;proper storage of hazardous/toxic and polluting materials and; measures forensuring fire electrical and mechanical safety arrangements in camp and in worksite.

16 16

b) All methods steps and measures are required for ensuring safety of workers,particularly those needed while undertaking work in or around excavations;workings at height; and; while handling inflammable, toxic and/or hazardousmaterials shall be ensured by the contractor.

16 16

c) Material safety data sheet record of fuel and other inflammable chemicalsshall be maintained at the site. 16 16

12 Air pollution a) Wind barriers or screens shall be provided in the downwind direction at airpollution causing sources like plant sites and fine material storage stock yards

16 16

b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover on materials,based on activity and site conditions.

16 16

c) All plants and equipment shall comply with pollution control norms. 16 16d) Water shall be sprinkled at least twice during dry day on haulage roadspassing through or near settlements(including at least 100m before the settlement)

16 16

13 Water Pollution

a) All measures (including provision of temporary silt fencing to control sedimentrun-off) required for avoiding adverse impacts to water bodies (such as ponds,streams, canals and rivers), water sources (such as hand pumps and wells) andadjacent farmland shall be undertaken by the Contractor.

16 16

b) Storage of materials like fuel, chemicals, and cement shall be done in amanner (with impervious layer on bottom and a covered shed on top) that does notcontaminate land and ground/surface water.

16 16

14 Noise Pollution

a) All noise causing activities shall be stopped during night time (9.00 PM to6.00 AM). The Contractor shall schedule construction works in consultation withlocal Panchayat Authority and School Principal to ensure least disturbance toschool children and other adjacent residents.

16 16

Page 47 of 198

Page 49: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

b) Ear plugs shall be provided to the labour facing risk from high noise pollutionsuch as plant site and those working near generators, heavy equipment/machinery.

16 16

c) Appropriate noise controlling devices including acoustic generators shall beused to minimize noise during construction work and operation of camp. 16 16

15 DisposalDebris/ wastes

a) Debris and other construction waste, if any, shall be disposed in locationspre-approved by the Engineer in a manner that it does not contaminate theenvironment.

16 16

b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In no case,debris shall be disposed within 500mts. of ecologically sensitive areas, includingforests, wetlands and protected natural habitats.

16 16

16

RestorationandRehabilitationof Sites

All work sites and areas under temporary use (including construction and labourcamps, plant, sites, haul roads and borrow areas) shall be restored/rehabilitated toa better condition (if not at least to its original condition) and to the satisfaction ofthe Engineer and land owner upon completion of construction work by theContractor.

16 16

Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps, plants,in and around the construction site; disposal of debris/construction wastes at pre-approved locations and; restoration of borrow areas and other sites/ locations usedfor material sourcing.

16 16

17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram Panchayat ( including those related to temporary use of land, waterextraction and disposal of debris) shall be settled by the Contractor.

16 16

Third Party Quality Audit for Construction of Cyclone Shelters, Roads to CycloneShelters & Habitations, Bridges and Culverts under NCRMP (Details ofViskhapatnam District during February, 2013)

Sl.No Activity Measures to be implemented by the contractor Complied Not

CompliedNot

Applicable Total

Page 48 of 198

Page 50: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1Work Plan forEMPimplementation

The Contractor’s Project Manager shall be responsible for implementation of EMPprovisions and will coordinate the over-all implementation of the said plan. Alongwith the Work Programme, the Contractor shall submit a plan including methodstatement and timeline about specific actions that will be taken by him to implementthe provisions laid out in the EMP

21 21

2RegulatoryPermissionsand Consents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consent forplants, water and extraction and borrow areas operations. This includes:

Consent for establishment and operation of plant (for concrete work) from SPCB. 21 21

PUC certification for all vehicles/equipment used for/during construction. 21 21Permission/consent of the District Administration/Mining Department/otheragencies for quarrying and/or borrowing operations for materials like sand andearth.

21 21

Permission for water extraction, if applicable in the local area context. 21 21

The Contractor shall abide by all conditions laid out in the said clearances. 21 21

3

ConsultationandCommunityConsent

The Contractor shall consult and obtain written consents oflandowners(individual/Panchayat/govt. agency) for temporary use of land for allconstruction related activities including:a) Setting-up and operation of construction camp including labour camps, stockyards etc. 21 21

b) borrow areas and 21 21c) Disposal of debris and other waste material. 21 21

4 Construction/Labour Camp

a) Location: The camp and plant site/s location and establishment shall be done ina manner that does not interfere or disturb the activities of local inhabitants,particularly those of schools and health facilities. Written permission (no objectioncertificate) shall be taken from the Gramsabha and the land owner prior to locationselection and a copy shall be submitted to the Engineer approval.

21 21

b) Camp site shall not be located within 250mts. From a water body includingvillage ponds. 21 21

Page 49 of 198

Page 51: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

c) A distance of at least 500mts. Shall be maintained from designated/protectednatural habitats (such as National Parks, Sanctuaries, Biosphere Reserves,Reserve Forests and Ramsar Sites) and Coastal Regulation Zone.

21 21

b) Accommodation and Basic Amenities: All weather shelter with the requiredtenement size and toilets shall be provided, as per provisions of Labour Laws.Separate toilet facilities shall be provided for women workers. If a common mess isnot provided/operated additional space for cooking shall be provided. Thecontractor shall ensure that hygienic conditions are maintained during the operationof such camps/facilities.

21 21

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is not used as acooking medium in the construction /labour camp. 21 21

d) Potable water supply: Drinking water supply of at least 40Ipcd with the requiredsupply points shall be provided. 21 21

e) Fire Safety: Adequate fire safety precautions shall be taken and required firesafety equipment (such as fire extinguishers) shall be provided by the contractor. 21 21

5 Site Clearance

a) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s (includingthose from Forest Dept., if required) are obtained prior to cutting of such trees.

21 21

b) The non-timber grade trees are to be stacked and possession is to be given toEmployer/concerned Govt. Department. 21 21

c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. The top soilshall be reinstated in the cyclone shelter compound after the construction is over.

21 21

6Protection ofProperties andResources

The Contractor shall take due care to protect and prevent damages to the followingresources during preparatory and construction work:a) Water supply lines 21 21b) Irrigation canals 21 21c) Cart, cattle and/or foot trail/tracks 21 21d) Cultural properties and sites/structures of religious importance 21 21e) Houses, Farmlands, Orchids and/or Trees. 21 21f) School and other existing buildings adjacent to the site of construction. 21 21In case of damage due to construction activity, the restoration/repairs shall becarried out by the contractor at his own cost. 21 21

Page 50 of 198

Page 52: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

7 QuarryOperations

The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.

21 21

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractor following thestipulations given below: The finalisation of all such locations shall be dependenton the approval of the Engineer on technical and environmental grounds. Thisincludes on-site verification to cross-check the accuracy of details provided by thecontractor. Only after receipt of the written approval from the Engineer, theContractor shall enter into a formal agreement with landowner.

21 21

b) The Contractor shall not procure any kind of construction material (such asaggregates, sand and earth) from ecologically protected areas. 21 21

c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to be doneon an agricultural land, top-soil stripping, stacking and preservation is must.

21 21

2. Borrow pits shall not be located within a distance of 100mts. From any NH, SHor other roads. 21 21

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 21 21

4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 21 21

5. No borrow area shall be opened with in 500mts. from a reserved or protectedforest area, protected sites, wildlife movement zone and cultural heritage site. 21 21

6. No tree cutting shall be undertaken. 21 217. Borrow area near any surface water body will be at least 100mts. away. 21 21d) Operation 211. Area up to which material will be extracted shall be cleared demarcated onground. 21 21

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 21 213. Borrowing of earth should be preferably limited to a depth of 1.5mtr from theexisting ground level. 21 21

4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 21 21

Page 51 of 198

Page 53: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

e) Rehabilitation of Borrow Areas: 21 211. Rehabilitation shall be satisfactory undertaken immediately after the use hasceased and at least three weeks prior to monsoon 21 21

2. Preserved top soil has be spread uniformly over land (except in cases whereborrow area is developed as a water body) used as a borrow area. 21 21

9 WaterExtraction /Use

Water for construction and for use at construction camps (including labour camps)is to be extracted with prior written permission of(a) the individual owner, in casethe source is private well/tube well; (b) Gram Panchayat in case the source belongsto community: and (c) Irrigation Department in case the source is an irrigation canalor river.

21 21

10

Safety of RoadUsers andLocalResidents

a) Traffic safety arrangements (including provision of warning signage, speedbreakers etc.) shall be made by the contractor to ensure safety of road users andlocal people, particularly in the internal village roads which will be used fortransporting materials.

21 21

b) Material shall be covered during transportation to prevent spillage, accidentsand pollution. 21 21

c) All required measures to ensure safety of local residents including childrenand other near-by residents shall be taken up by the Contractor. This shall includeprovisions to prevent un authorised entry into the construction.

21 21

11 Worker’sSafety

a) All measures required for ensuring safety and health of the workers shall betaken up by the Contractor. This includes provision and enforcement of appropriatepersonal protective equipment; first aid facility; emergency response arrangement;proper storage of hazardous/toxic and polluting materials and; measures forensuring fire electrical and mechanical safety arrangements in camp and in worksite.

21 21

b) All methods steps and measures are required for ensuring safety of workers,particularly those needed while undertaking work in or around excavations;workings at height; and; while handling inflammable, toxic and/or hazardousmaterials shall be ensured by the contractor.

21 21

c) Material safety data sheet record of fuel and other inflammable chemicalsshall be maintained at the site. 21 21

12 Air pollution a) Wind barriers or screens shall be provided in the downwind direction at airpollution causing sources like plant sites and fine material storage stock yards

21 21

Page 52 of 198

Page 54: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover on materials,based on activity and site conditions.

21 21

c) All plants and equipment shall comply with pollution control norms. 21 21d) Water shall be sprinkled at least twice during dry day on haulage roadspassing through or near settlements(including at least 100m before the settlement)

21 21

13 Water Pollution

a) All measures (including provision of temporary silt fencing to control sedimentrun-off) required for avoiding adverse impacts to water bodies (such as ponds,streams, canals and rivers), water sources (such as hand pumps and wells) andadjacent farmland shall be undertaken by the Contractor.

21 21

b) Storage of materials like fuel, chemicals, and cement shall be done in amanner (with impervious layer on bottom and a covered shed on top) that does notcontaminate land and ground/surface water.

21 21

14 Noise Pollution

a) All noise causing activities shall be stopped during night time (9.00 PM to6.00 AM). The Contractor shall schedule construction works in consultation withlocal Panchayat Authority and School Principal to ensure least disturbance toschool children and other adjacent residents.

21 21

b) Ear plugs shall be provided to the labour facing risk from high noise pollutionsuch as plant site and those working near generators, heavy equipment/machinery.

21 21

c) Appropriate noise controlling devices including acoustic generators shall beused to minimise noise during construction work and operation of camp. 21 21

15 DisposalDebris/ wastes

a) Debris and other construction waste, if any, shall be disposed in locationspre-approved by the Engineer in a manner that it does not contaminate theenvironment.

21 21

b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In no case,debris shall be disposed within 500mts. of ecologically sensitive areas, includingforests, wetlands and protected natural habitats.

21 21

16

RestorationandRehabilitationof Sites

All work sites and areas under temporary use (including construction and labourcamps, plant, sites, haul roads and borrow areas) shall be restored/rehabilitated toa better condition (if not at least to its original condition) and to the satisfaction ofthe Engineer and land owner upon completion of construction work by theContractor.

21 21

Page 53 of 198

Page 55: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps, plants,in and around the construction site; disposal of debris/construction wastes at pre-approved locations and; restoration of borrow areas and other sites/ locations usedfor material sourcing.

21 21

17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram panchayat (including those related to temporary use of land, waterextraction and disposal of debris) shall be settled by the Contractor.

21 21

Third Party Quality Audit for Construction of Cyclone Shelters, Roads to CycloneShelters & Habitations, Bridges and Culverts under NCRMP (Details of WestGodavari District during February, 2013)

Sl.No Activity Measures to be implemented by the contractor Complied Not

CompliedNot

Applicable Total

1Work Plan forEMPimplementation

The Contractor’s Project Manager shall be responsible for implementation of EMPprovisions and will coordinate the over-all implementation of the said plan. Alongwith the Work Programme, the Contractor shall submit a plan including methodstatement and timeline about specific actions that will be taken by him to implementthe provisions laid out in the EMP

10 10

2RegulatoryPermissionsand Consents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consent forplants, water and extraction and borrow areas operations. This includes:

Consent for establishment and operation of plant (for concrete work) from SPCB. 10 10

PUC certification for all vehicles/equipment used for/during construction. 10 10Permission/consent of the District Administration/Mining Department/otheragencies for quarrying and/or borrowing operations for materials like sand andearth.

10 10

Page 54 of 198

Page 56: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Permission for water extraction, if applicable in the local area context. 10 10

The Contractor shall abide by all conditions laid out in the said clearances. 10 10

3

ConsultationandCommunityConsent

The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of land for allconstruction related activities including:a) Setting-up and operation of construction camp including labour camps, stockyards etc. 10 10

b) borrow areas and 10 10c) Disposal of debris and other waste material. 10 10

4 Construction/Labour Camp

a) Location: The camp and plant site/s location and establishment shall be done ina manner that does not interfere or disturb the activities of local inhabitants,particularly those of schools and health facilities. Written permission (no objectioncertificate) shall be taken from the Gramsabha and the land owner prior to locationselection and a copy shall be submitted to the Engineer approval.

10 10

b) Camp site shall not be located within 250mts. From a water body includingvillage ponds. 10 10

c) A distance of at least 500mts. Shall be maintained from designated/protectednatural habitats (such as National Parks, Sanctuaries, Biosphere Reserves,Reserve Forests and Ramsar Sites) and Coastal Regulation Zone.

10 10

b) Accommodation and Basic Amenities: All weather shelter with the requiredtenement size and toilets shall be provided, as per provisions of Labour Laws.Separate toilet facilities shall be provided for women workers. If a common mess isnot provided/operated additional space for cooking shall be provided. Thecontractor shall ensure that hygienic conditions are maintained during the operationof such camps/facilities.

10 10

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is not used as acooking medium in the construction /labour camp. 10 10

d) Potable water supply: Drinking water supply of at least 40Ipcd with the requiredsupply points shall be provided. 10 10

e) Fire Safety: Adequate fire safety precautions shall be taken and required firesafety equipment (such as fire extinguishers) shall be provided by the contractor. 10 10

Page 55 of 198

Page 57: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

5 Site Clearance

a) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s (includingthose from Forest Dept., if required) are obtained prior to cutting of such trees.

10 10

b) The non-timber grade trees are to be stacked and possession is to be given toEmployer/concerned Govt. Department. 10 10

c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. The top soilshall be reinstated in the cyclone shelter compound after the construction is over.

10 10

6Protection ofProperties andResources

The Contractor shall take due care to protect and prevent damages to the followingresources during preparatory and construction work:a) Water supply lines 10 10b) Irrigation canals 10 10c) Cart, cattle and/or foot trail/tracks 10 10d) Cultural properties and sites/structures of religious importance 10 10e) Houses, Farmlands, Orchids and/or Trees. 10 10f) School and other existing buildings adjacent to the site of construction. 10 10In case of damage due to construction activity, the restoration/repairs shall becarried out by the contractor at his own cost. 10 10

7 QuarryOperations

The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.

10 10

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractor following thestipulations given below: The finalisation of all such locations shall be dependenton the approval of the Engineer on technical and environmental grounds. Thisincludes on-site verification to cross-check the accuracy of details provided by thecontractor. Only after receipt of the written approval from the Engineer, theContractor shall enter into a formal agreement with landowner.

10 10

b) The Contractor shall not procure any kind of construction material (such asaggregates, sand and earth) from ecologically protected areas. 10 10

c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to be doneon an agricultural land, top-soil stripping, stacking and preservation is must.

10 10

Page 56 of 198

Page 58: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

2. Borrow pits shall not be located within a distance of 100mts. From any NH, SHor other roads. 10 10

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 10 10

4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 10 10

5. No borrow area shall be opened with in 500mts. from a reserved or protectedforest area, protected sites, wildlife movement zone and cultural heritage site. 10 10

6. No tree cutting shall be undertaken. 10 107. Borrow area near any surface water body will be at least 100mts. away. 10 10d) Operation 101. Area up to which material will be extracted shall be cleared demarcated onground. 10 10

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 10 103. Borrowing of earth should be preferably limited to a depth of 1.5mtr from theexisting ground level. 10 10

4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 10 10

e) Rehabilitation of Borrow Areas: 10 101. Rehabilitation shall be satisfactory undertaken immediately after the use hasceased and at least three weeks prior to monsoon 10 10

2. Preserved top soil has be spread uniformly over land (except in cases whereborrow area is developed as a water body) used as a borrow area. 10 10

9 WaterExtraction /Use

Water for construction and for use at construction camps (including labour camps)is to be extracted with prior written permission of(a) the individual owner, in casethe source is private well/tube well; (b) Gram Panchayat in case the source belongsto community: and (c) Irrigation Department in case the source is an irrigation canalor river.

10 10

10

Safety of RoadUsers andLocalResidents

a) Traffic safety arrangements (including provision of warning signage, speedbreakers etc.) shall be made by the contractor to ensure safety of road users andlocal people, particularly in the internal village roads which will be used fortransporting materials.

10 10

Page 57 of 198

Page 59: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

b) Material shall be covered during transportation to prevent spillage, accidentsand pollution. 10 10

c) All required measures to ensure safety of local residents including childrenand other near-by residents shall be taken up by the Contractor. This shall includeprovisions to prevent un authorised entry into the construction.

10 10

11 Worker’sSafety

a) All measures required for ensuring safety and health of the workers shall betaken up by the Contractor. This includes provision and enforcement of appropriatepersonal protective equipment; first aid facility; emergency response arrangement;proper storage of hazardous/toxic and polluting materials and; measures forensuring fire electrical and mechanical safety arrangements in camp and in worksite.

10 10

b) All methods steps and measures are required for ensuring safety of workers,particularly those needed while undertaking work in or around excavations;workings at height; and; while handling inflammable, toxic and/or hazardousmaterials shall be ensured by the contractor.

10 10

c) Material safety data sheet record of fuel and other inflammable chemicalsshall be maintained at the site. 10 10

12 Air pollution a) Wind barriers or screens shall be provided in the downwind direction at airpollution causing sources like plant sites and fine material storage stock yards

10 10

b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover on materials,based on activity and site conditions.

10 10

c) All plants and equipment shall comply with pollution control norms. 10 10d) Water shall be sprinkled at least twice during dry day on haulage roadspassing through or near settlements(including at least 100m before the settlement)

10 10

13 Water Pollution

a) All measures (including provision of temporary silt fencing to control sedimentrun-off) required for avoiding adverse impacts to water bodies (such as ponds,streams, canals and rivers), water sources (such as hand pumps and wells) andadjacent farmland shall be undertaken by the Contractor.

10 10

b) Storage of materials like fuel, chemicals, and cement shall be done in amanner (with impervious layer on bottom and a covered shed on top) that does notcontaminate land and ground/surface water.

10 10

Page 58 of 198

Page 60: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

14 Noise Pollution

a) All noise causing activities shall be stopped during night time (9.00 PM to6.00 AM). The Contractor shall schedule construction works in consultation withlocal Panchayat Authority and School Principal to ensure least disturbance toschool children and other adjacent residents.

10 10

b) Ear plugs shall be provided to the labour facing risk from high noise pollutionsuch as plant site and those working near generators, heavy equipment/machinery.

10 10

c) Appropriate noise controlling devices including acoustic generators shall beused to minimise noise during construction work and operation of camp. 10 10

15 DisposalDebris/ wastes

a) Debris and other construction waste, if any, shall be disposed in locationspre-approved by the Engineer in a manner that it does not contaminate theenvironment.

10 10

b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In no case,debris shall be disposed within 500mts. of ecologically sensitive areas, includingforests, wetlands and protected natural habitats.

10 10

16

RestorationandRehabilitationof Sites

All work sites and areas under temporary use (including construction and labourcamps, plant, sites, haul roads and borrow areas) shall be restored/rehabilitated toa better condition (if not at least to its original condition) and to the satisfaction ofthe Engineer and land owner upon completion of construction work by theContractor.

10 10

Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps, plants,in and around the construction site; disposal of debris/construction wastes at pre-approved locations and; restoration of borrow areas and other sites/ locations usedfor material sourcing.

10 10

17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram panchayat ( including those related to temporary use of land, waterextraction and disposal of debris) shall be settled by the Contractor.

10 10

Page 59 of 198

Page 61: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

8.2 Consolidated E&S Report of Vizianagaram, East Godavari, Krishna, Guntur, Prakasam & SPSR Nellore Districts in the Month ofMarch 2013:

Third Party Quality Audit for Construction of Cyclone Shelters, Roads to Cyclone Shelters &Habitations, Bridges and Culverts under NCRMP (Details of Vizianagaram in March, 2013)

Sl.No Activity Measures to be implemented by the contractor Compliced Not

complicedNot

applicable Total

1 Work Plan for EMPImplementation

The Contractor’s Project Manager shall be responsible for implementation ofEMP provisions and will coordinate the over-all implementation of the saidplan. Along with the Work Programme, the Contractor shall submit a planincluding method statement and timeline about specific actions that will betaken by him to implement the provisions laid out in the EMP

3 3

2RegulatoryPermissions andConsents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consentfor plants, water and extraction and borrow areas operations. This includes:

3

· Consent for establishment and operation of plant (for concrete work)from SPCB. 3 3

· PUC certification for all vehicles/equipment used for/duringconstruction. 3 3

· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.

3 3

· Permission for water extraction, if applicable in the local areacontext. 3 3

The Contractor shall abide by all conditions laid out in the said clearances. 3 3

3Consultation andCommunityConsent

The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:a) Setting-up and operation of construction camp including labour camps,stock yards etc. 3 3

Page 60 of 198

Page 62: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

b) borrow areas and 3 3c) Disposal of debris and other waste material. 3 3

4 Construction/Labour Camp

a) Location: The camp and plant site/s location and establishment shall bedone in a manner that does not interfere or disturb the activities of localinhabitants, particularly those of schools and health facilities. Writtenpermission (no objection certificate) shall be taken from the Gramsabhaand the land owner prior to location selection and a copy shall be submittedto the Engineer approval.

3 3

b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds. 3 3

c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks, Sanctuaries,Biosphere Reserves, Reserve Forests and Ramsar Sites) and CoastalRegulation Zone.

3 3

b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for women workers.If a common mess is not provided/operated additional space for cookingshall be provided. The contractor shall ensure that hygienic conditions aremaintained during the operation of such camps/facilities.

3 3

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp. 3 3

d) Potable water supply: Drinking water supply of at least 40Ipcd with therequired supply points shall be provided. 3 3

e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall be providedby the contractor.

3 3

5 Site Clearance

a) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s(including those from Forest Dept., if required) are obtained prior to cuttingof such trees.

3 3

b) The non-timber grade trees are to be stacked and possession is to begiven to Employer/concerned Govt. Department. 3 3

Page 61 of 198

Page 63: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. Thetop soil shall be reinstated in the cyclone shelter compound after theconstruction is over.

3 3

6Protection ofProperties andResources

The Contractor shall take due care to protect and prevent damages to thefollowing resources during preparatory and construction work:a) Water supply lines 3 3b) Irrigation canals 3 3c) Cart, cattle and/or foot trail/tracks 3 3d) Cultural properties and sites/structures of religious importance 3 3

e) Houses, Farmlands, Orchids and/or Trees. 3 3f) School and other existing buildings adjacent to the site ofconstruction. 3 3

In case of damage due to construction activity, the restoration/repairs shallbe carried out by the contractor at his own cost. 3 3

7 Quarry OperationsThe Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.

3 3

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractor followingthe stipulations given below: The finalisation of all such locations shall bedependent on the approval of the Engineer on technical and environmentalgrounds. This includes on-site verification to cross-check the accuracy ofdetails provided by the contractor. Only after receipt of the written approvalfrom the Engineer, the Contractor shall enter into a formal agreement withlandowner.

3 3

b) The Contractor shall not procure any kind of construction material (suchas aggregates, sand and earth) from ecologically protected areas. 3 3

c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to bedone on an agricultural land, top-soil stripping, stacking and preservation ismust.

3 3

2. Borrow pits shall not be located within a distance of 100mts. From anyNH, SH or other roads. 3 3

Page 62 of 198

Page 64: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 3 3

4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 3 3

5. No borrow area shall be opened with in 500mts. from a reserved orprotected forest area, protected sites, wildlife movement zone and culturalheritage site.

3 3

6. No tree cutting shall be undertaken. 3 37. Borrow area near any surface water body will be at least 100mts.away. 3 3

d) Operation 31. Area up to which material will be extracted shall be cleareddemarcated on ground. 3 3

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 3 33. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level. 3 3

4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 3 3

e) Rehabilitation of Borrow Areas: 3 31. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon 3 3

2. Preserved top soil has be spread uniformly over land (except in caseswhere borrow area is developed as a water body) used as a borrow area. 3 3

9

WaterExtraction/Use

Water for construction and for use at construction camps (including labourcamps) is to be extracted with prior written permission of(a) the individualowner, in case the source is private well/tube well; (b) Gram Panchayat incase the source belongs to community: and (c) Irrigation Department incase the source is an irrigation canal or river.

3 3

10Safety of RoadUsers and LocalResidents

a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roads whichwill be used for transporting materials.

3 3

b) Material shall be covered during transportation to prevent spillage,accidents and pollution. 3 3

Page 63 of 198

Page 65: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into theconstruction.

3 3

11 Worker’s Safety

a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aid facility;emergency response arrangement; proper storage of hazardous/toxic andpolluting materials and; measures for ensuring fire electrical andmechanical safety arrangements in camp and in work site.

3 3

b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.

3 3

c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 3 3

12 Air pollution a) Wind barriers or screens shall be provided in the downwind directionat air pollution causing sources like plant sites and fine material storagestock yards

3 3

b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

3 3

c) All plants and equipment shall comply with pollution control norms. 3 3

d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100m beforethe settlement)

3 3

13 Water Pollution

a) All measures (including provision of temporary silt fencing to controlsediment run-off) required for avoiding adverse impacts to water bodies(such as ponds, streams, canals and rivers), water sources (such as handpumps and wells) and adjacent farmland shall be undertaken by theContractor.

3 3

b) Storage of materials like fuel, chemicals, and cement shall be done ina manner (with impervious layer on bottom and a covered shed on top)that does not contaminate land and ground/surface water.

3 3

Page 64 of 198

Page 66: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

14 Noise Pollution

a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal to ensureleast disturbance to school children and other adjacent residents.

3 3

b) Ear plugs shall be provided to the labour facing risk from high noisepollution such as plant site and those working near generators, heavyequipment /machinery.

3 3 3

c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operation ofcamp.

3 3

15 Disposal Debris/wastes

a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

3 3

b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In nocase, debris shall be disposed within 500mts. of ecologically sensitive areas,including forests, wetlands and protected natural habitats.

3 3

16Restoration andRehabilitation ofSites

All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

3 3

Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps,plants, in and around the construction site; disposal of debris/constructionwastes at pre-approved locations and; restoration of borrow areas andother sites/ locations used for material sourcing.

3 3

17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram panchayat (including those related to temporary use of land,water extraction and disposal of debris) shall be settled by the Contractor.

3 3

Page 65 of 198

Page 67: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Third Party Quality Audit for Construction of Cyclone Shelters, Roads to Cyclone Shelters &Habitations, Bridges and Culverts under NCRMP (Details of East Godavari in March,2013)

Sl.No Activity Measures to be implemented by the contractor Compliced Not

complicedNot

applicable Total

1 Work Plan for EMPimplementation

The Contractor’s Project Manager shall be responsible for implementation ofEMP provisions and will coordinate the over-all implementation of the saidplan. Along with the Work Programme, the Contractor shall submit a planincluding method statement and timeline about specific actions that will betaken by him to implement the provisions laid out in the EMP

8 8

2RegulatoryPermissions andConsents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consentfor plants, water and extraction and borrow areas operations. This includes:

8

· Consent for establishment and operation of plant (for concrete work)from SPCB. 8 8

· PUC certification for all vehicles/equipment used for/duringconstruction. 8 8

· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.

8 8

· Permission for water extraction, if applicable in the local areacontext. 8 8

The Contractor shall abide by all conditions laid out in the said clearances. 8 8

3Consultation andCommunityConsent

The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:a) Setting-up and operation of construction camp including labour camps,stock yards etc. 8 8

b) borrow areas and 8 8c) Disposal of debris and other waste material. 8 8

Page 66 of 198

Page 68: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

4 Construction/Labour Camp

a) Location: The camp and plant site/s location and establishment shall bedone in a manner that does not interfere or disturb the activities of localinhabitants, particularly those of schools and health facilities. Writtenpermission (no objection certificate) shall be taken from the Gramsabhaand the land owner prior to location selection and a copy shall be submittedto the Engineer approval.

8 8

b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds. 8 8

c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks, Sanctuaries,Biosphere Reserves, Reserve Forests and Ramsar Sites) and CoastalRegulation Zone.

8 8

b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for women workers.If a common mess is not provided/operated additional space for cookingshall be provided. The contractor shall ensure that hygienic conditions aremaintained during the operation of such camps/facilities.

8 8

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp. 8 8

d) Potable water supply: Drinking water supply of at least 40Ipcd with therequired supply points shall be provided. 8 8

e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall be providedby the contractor.

8 8

5 Site Clearance

a) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s(including those from Forest Dept., if required) are obtained prior to cuttingof such trees.

8 8

b) The non-timber grade trees are to be stacked and possession is to begiven to Employer/concerned Govt. Department. 8 8

c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. Thetop soil shall be reinstated in the cyclone shelter compound after theconstruction is over.

8 8

Page 67 of 198

Page 69: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

6Protection ofProperties andResources

The Contractor shall take due care to protect and prevent damages to thefollowing resources during preparatory and construction work:a) Water supply lines 8 8

b) Irrigation canals 8 8c) Cart, cattle and/or foot trail/tracks 8 8d) Cultural properties and sites/structures of religious importance 8 8e) Houses, Farmlands, Orchids and/or Trees. 8 8f) School and other existing buildings adjacent to the site ofconstruction. 8 8

In case of damage due to construction activity, the restoration/repairs shallbe carried out by the contractor at his own cost. 8 8

7 Quarry OperationsThe Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.

8 8

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractor followingthe stipulations given below: The finalisation of all such locations shall bedependent on the approval of the Engineer on technical and environmentalgrounds. This includes on-site verification to cross-check the accuracy ofdetails provided by the contractor. Only after receipt of the written approvalfrom the Engineer, the Contractor shall enter into a formal agreement withlandowner.

8 8

b) The Contractor shall not procure any kind of construction material (suchas aggregates, sand and earth) from ecologically protected areas. 8 8

c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to bedone on an agricultural land, top-soil stripping, stacking and preservation ismust.

8 8

2. Borrow pits shall not be located within a distance of 100mts. From anyNH, SH or other roads. 8 8

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 8 8

4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 8 8

Page 68 of 198

Page 70: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

5. No borrow area shall be opened with in 500mts. from a reserved orprotected forest area, protected sites, wildlife movement zone and culturalheritage site.

8 8

6. No tree cutting shall be undertaken. 8 87. Borrow area near any surface water body will be at least 100mts.away. 8 8

d) Operation 81. Area up to which material will be extracted shall be cleareddemarcated on ground. 8 8

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 8 83. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level. 8 8

4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 8 8

e) Rehabilitation of Borrow Areas: 8 81. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon 8 8

2. Preserved top soil has be spread uniformly over land (except in caseswhere borrow area is developed as a water body) used as a borrow area. 8 8

9 Water Extraction/Use

Water for construction and for use at construction camps (including labourcamps) is to be extracted with prior written permission of(a) the individualowner, in case the source is private well/tube well; (b) Gram Panchayat incase the source belongs to community: and (c) Irrigation Department incase the source is an irrigation canal or river.

8 8

10Safety of RoadUsers and LocalResidents

a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roads whichwill be used for transporting materials.

8 8

b) Material shall be covered during transportation to prevent spillage,accidents and pollution. 8 8

c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into theconstruction.

8 8

Page 69 of 198

Page 71: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

11 Worker’s Safety

a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aid facility;emergency response arrangement; proper storage of hazardous/toxic andpolluting materials and; measures for ensuring fire electrical andmechanical safety arrangements in camp and in work site.

8 8

b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.

8 8

c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 8 8

12 Air pollution a) Wind barriers or screens shall be provided in the downwind directionat air pollution causing sources like plant sites and fine material storagestock yards

8 8

b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

8 8

c) All plants and equipment shall comply with pollution control norms. 8 8d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100m beforethe settlement)

8 8

13 Water Pollution

a) All measures (including provision of temporary silt fencing to controlsediment run-off) required for avoiding adverse impacts to water bodies(such as ponds, streams, canals and rivers), water sources (such as handpumps and wells) and adjacent farmland shall be undertaken by theContractor.

8 8

b) Storage of materials like fuel, chemicals, and cement shall be done ina manner (with impervious layer on bottom and a covered shed on top)that does not contaminate land and ground/surface water.

8 8

14 Noise Pollution

a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal to ensureleast disturbance to school children and other adjacent residents.

8 8

b) Ear plugs shall be provided to the labour facing risk from high noisepollution such as plant site and those working near generators, heavy 8 8 8

Page 70 of 198

Page 72: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

equipment /machinery.

c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operation ofcamp.

8 8

15 Disposal Debris/wastes

a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

8 8

b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In nocase, debris shall be disposed within 500mts. of ecologically sensitive areas,including forests, wetlands and protected natural habitats.

8 8

16Restoration andRehabilitation ofSites

All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

8 8

Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps,plants, in and around the construction site; disposal of debris/constructionwastes at pre-approved locations and; restoration of borrow areas andother sites/ locations used for material sourcing.

8 8

17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram panchayat ( including those related to temporary use of land,water extraction and disposal of debris) shall be settled by the Contractor.

8 8

Third Party Quality Audit for Construction of Cyclone Shelters, Roads to CycloneShelters & Habitations, Bridges and Culverts under NCRMP (Details of Krishna inMarch,2013)Sl.No Activity Measures to be implemented by the contractor Compliced Not

complicedNot

applicable Total

Page 71 of 198

Page 73: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1 Work Plan for EMPimplementation

The Contractor’s Project Manager shall be responsible for implementationof EMP provisions and will coordinate the over-all implementation of thesaid plan. Along with the Work Programme, the Contractor shall submit aplan including method statement and timeline about specific actions that willbe taken by him to implement the provisions laid out in the EMP

8 8

2RegulatoryPermissions andConsents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consentfor plants, water and extraction and borrow areas operations. This includes:

8

· Consent for establishment and operation of plant (for concrete work)from SPCB. 8 8

· PUC certification for all vehicles/equipment used for/duringconstruction. 8 8

· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.

8 8

· Permission for water extraction, if applicable in the local area context. 8 8

The Contractor shall abide by all conditions laid out in the said clearances. 8 8

3Consultation andCommunityConsent

The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of land forall construction related activities including:a) Setting-up and operation of construction camp including labour camps,stock yards etc. 8 8

b) borrow areas and 8 8c) Disposal of debris and other waste material. 8 8

4 Construction/Labour Camp

a) Location: The camp and plant site/s location and establishment shall bedone in a manner that does not interfere or disturb the activities of localinhabitants, particularly those of schools and health facilities. Writtenpermission (no objection certificate) shall be taken from the Gramsabha andthe land owner prior to location selection and a copy shall be submitted tothe Engineer approval.

8 8

b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds. 8 8

Page 72 of 198

Page 74: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks, Sanctuaries,Biosphere Reserves, Reserve Forests and Ramsar Sites) and CoastalRegulation Zone.

8 8

b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for women workers.If a common mess is not provided/operated additional space for cookingshall be provided. The contractor shall ensure that hygienic conditions aremaintained during the operation of such camps/facilities.

8 8

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is not usedas a cooking medium in the construction /labour camp. 8 8

d) Potable water supply: Drinking water supply of at least 40Ipcd with therequired supply points shall be provided. 8 8

e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall be providedby the contractor.

8 8

5 Site Clearance

a) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s(including those from Forest Dept., if required) are obtained prior to cuttingof such trees.

8 8

b) The non-timber grade trees are to be stacked and possession is to begiven to Employer/concerned Govt. Department. 8 8

c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. Thetop soil shall be reinstated in the cyclone shelter compound after theconstruction is over.

8 8

6Protection ofProperties andResources

The Contractor shall take due care to protect and prevent damages to thefollowing resources during preparatory and construction work:a) Water supply lines 8 8b) Irrigation canals 8 8c) Cart, cattle and/or foot trail/tracks 8 8d) Cultural properties and sites/structures of religious importance 8 8e) Houses, Farmlands, Orchids and/or Trees. 8 8f) School and other existing buildings adjacent to the site of construction. 8 8

Page 73 of 198

Page 75: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

In case of damage due to construction activity, the restoration/repairs shallbe carried out by the contractor at his own cost. 8 8

7 Quarry OperationsThe Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.

8 8

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractor followingthe stipulations given below: The finalisation of all such locations shall bedependent on the approval of the Engineer on technical and environmentalgrounds. This includes on-site verification to cross-check the accuracy ofdetails provided by the contractor. Only after receipt of the written approvalfrom the Engineer, the Contractor shall enter into a formal agreement withlandowner.

8 8

b) The Contractor shall not procure any kind of construction material (suchas aggregates, sand and earth) from ecologically protected areas. 8 8

c) Identification and Selection: 81. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to bedone on an agricultural land, top-soil stripping, stacking and preservation ismust.

8 8

2. Borrow pits shall not be located within a distance of 100mts. From anyNH, SH or other roads. 8 8

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 8 8

4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 8 8

5. No borrow area shall be opened with in 500mts. from a reserved orprotected forest area, protected sites, wildlife movement zone and culturalheritage site.

8 8

6. No tree cutting shall be undertaken. 8 87. Borrow area near any surface water body will be at least 100mts.away. 8 8

d) Operation 81. Area up to which material will be extracted shall be cleareddemarcated on ground. 8 8

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 8 8

Page 74 of 198

Page 76: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level. 8 8

4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 8 8

e) Rehabilitation of Borrow Areas: 8 81. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon 8 8

2. Preserved top soil has be spread uniformly over land (except in caseswhere borrow area is developed as a water body) used as a borrow area. 8 8

9 Water Extraction/Use

Water for construction and for use at construction camps (including labourcamps) is to be extracted with prior written permission of(a) the individualowner, in case the source is private well/tube well; (b) Gram Panchayat incase the source belongs to community: and (c) Irrigation Department incase the source is an irrigation canal or river.

8 8

10Safety of RoadUsers and LocalResidents

a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roads whichwill be used for transporting materials.

8 8

b) Material shall be covered during transportation to prevent spillage,accidents and pollution. 8 8

c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into theconstruction.

8 8

11 Worker’s Safety

a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aid facility;emergency response arrangement; proper storage of hazardous/toxic andpolluting materials and; measures for ensuring fire electrical andmechanical safety arrangements in camp and in work site.

8 8

b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.

8 8

Page 75 of 198

Page 77: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 8 8

12 Air pollution a) Wind barriers or screens shall be provided in the downwind directionat air pollution causing sources like plant sites and fine material storagestock yards

8 8

b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

8 8

c) All plants and equipment shall comply with pollution control norms. 8 8d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100m beforethe settlement)

8 8

13 Water Pollution

a) All measures (including provision of temporary silt fencing to controlsediment run-off) required for avoiding adverse impacts to water bodies(such as ponds, streams, canals and rivers), water sources (such as handpumps and wells) and adjacent farmland shall be undertaken by theContractor.

8 8

b) Storage of materials like fuel, chemicals, and cement shall be done ina manner (with impervious layer on bottom and a covered shed on top) thatdoes not contaminate land and ground/surface water.

8 8

14 Noise Pollution

a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal to ensureleast disturbance to school children and other adjacent residents.

8 8

b) Ear plugs shall be provided to the labour facing risk from high noisepollution such as plant site and those working near generators, heavyequipment /machinery.

8 8 8

c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operation ofcamp.

8 8

15 Disposal Debris/wastes

a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

8 8

b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and water bodies. Inno case, debris shall be disposed within 500mts. of ecologically sensitiveareas, including forests, wetlands and protected natural habitats.

8 8

Page 76 of 198

Page 78: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

16Restoration andRehabilitation ofSites

All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

8 8

Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps,plants, in and around the construction site; disposal of debris/constructionwastes at pre-approved locations and; restoration of borrow areas and othersites/ locations used for material sourcing.

8 8

17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram panchayat (including those related to temporary use of land,water extraction and disposal of debris) shall be settled by the Contractor.

8 8

Third Party Quality Audit for Construction of Cyclone Shelters, Roads to Cyclone Shelters &Habitations, Bridges and Culverts under NCRMP (Details of Guntur in March,2013)

Sl.No Activity Measures to be implemented by the contractor Compliced Not

complicedNot

applicable Total

1 Work Plan for EMPimplementation

The Contractor’s Project Manager shall be responsible for implementation ofEMP provisions and will coordinate the over-all implementation of the saidplan. Along with the Work Programme, the Contractor shall submit a planincluding method statement and timeline about specific actions that will betaken by him to implement the provisions laid out in the EMP

16 16

2RegulatoryPermissions andConsents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consentfor plants, water and extraction and borrow areas operations. This includes:

16

· Consent for establishment and operation of plant (for concrete work)from SPCB. 16 16

· PUC certification for all vehicles/equipment used for/duringconstruction. 16 16

· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations for 16 16

Page 77 of 198

Page 79: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

materials like sand and earth.

· Permission for water extraction, if applicable in the local areacontext. 16 16

The Contractor shall abide by all conditions laid out in the said clearances. 16 16

3Consultation andCommunityConsent

The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:a) Setting-up and operation of construction camp including labour camps,stock yards etc. 16 16

b) borrow areas and 16 16c) Disposal of debris and other waste material. 16 16

4 Construction/Labour Camp

a) Location: The camp and plant site/s location and establishment shall bedone in a manner that does not interfere or disturb the activities of localinhabitants, particularly those of schools and health facilities. Writtenpermission (no objection certificate) shall be taken from the Gramsabhaand the land owner prior to location selection and a copy shall be submittedto the Engineer approval.

16 16

b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds. 16 16

c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks, Sanctuaries,Biosphere Reserves, Reserve Forests and Ramsar Sites) and CoastalRegulation Zone.

16 16

b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for women workers.If a common mess is not provided/operated additional space for cookingshall be provided. The contractor shall ensure that hygienic conditions aremaintained during the operation of such camps/facilities.

16 16

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp. 16 16

d) Potable water supply: Drinking water supply of at least 40Ipcd with therequired supply points shall be provided. 16 16

Page 78 of 198

Page 80: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall be providedby the contractor.

16 16

5 Site Clearance

a) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s(including those from Forest Dept., if required) are obtained prior to cuttingof such trees.

16 16

b) The non-timber grade trees are to be stacked and possession is to begiven to Employer/concerned Govt. Department. 16 16

c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. Thetop soil shall be reinstated in the cyclone shelter compound after theconstruction is over.

16 16

6Protection ofProperties andResources

The Contractor shall take due care to protect and prevent damages to thefollowing resources during preparatory and construction work:a) Water supply lines 16 16b) Irrigation canals 16 16c) Cart, cattle and/or foot trail/tracks 16 16

d) Cultural properties and sites/structures of religious importance 16 16e) Houses, Farmlands, Orchids and/or Trees. 16 16f) School and other existing buildings adjacent to the site ofconstruction. 16 16

In case of damage due to construction activity, the restoration/repairs shallbe carried out by the contractor at his own cost. 16 16

7 Quarry OperationsThe Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.

16 16

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractor followingthe stipulations given below: The finalisation of all such locations shall bedependent on the approval of the Engineer on technical and environmentalgrounds. This includes on-site verification to cross-check the accuracy ofdetails provided by the contractor. Only after receipt of the written approvalfrom the Engineer, the Contractor shall enter into a formal agreement withlandowner.

16 16

Page 79 of 198

Page 81: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

b) The Contractor shall not procure any kind of construction material (suchas aggregates, sand and earth) from ecologically protected areas. 16 16

c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to bedone on an agricultural land, top-soil stripping, stacking and preservation ismust.

16 16

2. Borrow pits shall not be located within a distance of 100mts. From anyNH, SH or other roads. 16 16

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 16 16

4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 16 16

5. No borrow area shall be opened with in 500mts. from a reserved orprotected forest area, protected sites, wildlife movement zone and culturalheritage site.

16 16

6. No tree cutting shall be undertaken. 16 167. Borrow area near any surface water body will be at least 100mts.away. 16 16

d) Operation 161. Area up to which material will be extracted shall be cleareddemarcated on ground. 16 16

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 16 163. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level. 16 16

4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 16 16

e) Rehabilitation of Borrow Areas: 16 161. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon 16 16

2. Preserved top soil has be spread uniformly over land (except in caseswhere borrow area is developed as a water body) used as a borrow area. 16 16

Page 80 of 198

Page 82: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

9 Water Extraction/Use

Water for construction and for use at construction camps (including labourcamps) is to be extracted with prior written permission of(a) the individualowner, in case the source is private well/tube well; (b) Gram Panchayat incase the source belongs to community: and (c) Irrigation Department incase the source is an irrigation canal or river.

16 16

10Safety of RoadUsers and LocalResidents

a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roads whichwill be used for transporting materials.

16 16

b) Material shall be covered during transportation to prevent spillage,accidents and pollution. 16 16

c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into theconstruction.

16 16

11 Worker’s Safety

a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aid facility;emergency response arrangement; proper storage of hazardous/toxic andpolluting materials and; measures for ensuring fire electrical andmechanical safety arrangements in camp and in work site.

16 16

b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.

16 16

c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 16 16

12 Air pollution a) Wind barriers or screens shall be provided in the downwind directionat air pollution causing sources like plant sites and fine material storagestock yards

16 16

b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

16 16

c) All plants and equipment shall comply with pollution control norms. 16 16

Page 81 of 198

Page 83: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100m beforethe settlement)

16 16

13 Water Pollution

a) All measures (including provision of temporary silt fencing to controlsediment run-off) required for avoiding adverse impacts to water bodies(such as ponds, streams, canals and rivers), water sources (such as handpumps and wells) and adjacent farmland shall be undertaken by theContractor.

16 16

b) Storage of materials like fuel, chemicals, and cement shall be done ina manner (with impervious layer on bottom and a covered shed on top)that does not contaminate land and ground/surface water.

16 16

14 Noise Pollution

a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal to ensureleast disturbance to school children and other adjacent residents.

16 16

b) Ear plugs shall be provided to the labour facing risk from high noisepollution such as plant site and those working near generators, heavyequipment /machinery.

16 16

c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operation ofcamp.

16 16

15 Disposal Debris/wastes

a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

16 16

b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In nocase, debris shall be disposed within 500mts. of ecologically sensitive areas,including forests, wetlands and protected natural habitats.

16 16

16Restoration andRehabilitation ofSites

All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

16 16

Page 82 of 198

Page 84: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps,plants, in and around the construction site; disposal of debris/constructionwastes at pre-approved locations and; restoration of borrow areas andother sites/ locations used for material sourcing.

16 16

17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram panchayat ( including those related to temporary use of land,water extraction and disposal of debris) shall be settled by the Contractor.

16 16

Third Party Quality Audit for Construction of Cyclone Shelters, Roads to Cyclone Shelters &Habitations, Bridges and Culverts under NCRMP (Details of Prakasam in March,2013)

Sl.No Activity Measures to be implemented by the contractor Compliced Not

complicedNot

applicable Total

1 Work Plan for EMPimplementation

The Contractor’s Project Manager shall be responsible for implementation ofEMP provisions and will coordinate the over-all implementation of the saidplan. Along with the Work Programme, the Contractor shall submit a planincluding method statement and timeline about specific actions that will betaken by him to implement the provisions laid out in the EMP

3 3

2RegulatoryPermissions andConsents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consentfor plants, water and extraction and borrow areas operations. This includes:

· Consent for establishment and operation of plant (for concrete work)from SPCB. 3 3

· PUC certification for all vehicles/equipment used for/duringconstruction. 3 3

· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.

3 3

· Permission for water extraction, if applicable in the local areacontext. 3 3

The Contractor shall abide by all conditions laid out in the said clearances. 3 3

Page 83 of 198

Page 85: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3Consultation andCommunityConsent

The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:a) Setting-up and operation of construction camp including labour camps,stock yards etc. 3 3

b) borrow areas and 3 3c) Disposal of debris and other waste material. 3 3

4 Construction/Labour Camp

a) Location: The camp and plant site/s location and establishment shall bedone in a manner that does not interfere or disturb the activities of localinhabitants, particularly those of schools and health facilities. Writtenpermission (no objection certificate) shall be taken from the Gramsabhaand the land owner prior to location selection and a copy shall be submittedto the Engineer approval.

3 3

b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds. 3 3

c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks, Sanctuaries,Biosphere Reserves, Reserve Forests and Ramsar Sites) and CoastalRegulation Zone.

3 3

b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for women workers.If a common mess is not provided/operated additional space for cookingshall be provided. The contractor shall ensure that hygienic conditions aremaintained during the operation of such camps/facilities.

3 3

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp. 3 3

d) Potable water supply: Drinking water supply of at least 40Ipcd with therequired supply points shall be provided. 3 3

e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall be providedby the contractor.

3 3

5 Site Clearancea) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s(including those from Forest Dept., if required) are obtained prior to cutting

3 3

Page 84 of 198

Page 86: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

of such trees.

b) The non-timber grade trees are to be stacked and possession is to begiven to Employer/concerned Govt. Department. 3 3

c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. Thetop soil shall be reinstated in the cyclone shelter compound after theconstruction is over.

3 3

6Protection ofProperties andResources

The Contractor shall take due care to protect and prevent damages to thefollowing resources during preparatory and construction work:a) Water supply lines 3 3b) Irrigation canals 3 3c) Cart, cattle and/or foot trail/tracks 3 3d) Cultural properties and sites/structures of religious importance 3 3e) Houses, Farmlands, Orchids and/or Trees. 3 3f) School and other existing buildings adjacent to the site ofconstruction. 3 3

In case of damage due to construction activity, the restoration/repairs shallbe carried out by the contractor at his own cost. 3 3

7 Quarry OperationsThe Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.

3 3

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractor followingthe stipulations given below: The finalisation of all such locations shall bedependent on the approval of the Engineer on technical and environmentalgrounds. This includes on-site verification to cross-check the accuracy ofdetails provided by the contractor. Only after receipt of the written approvalfrom the Engineer, the Contractor shall enter into a formal agreement withlandowner.

3 3

b) The Contractor shall not procure any kind of construction material (suchas aggregates, sand and earth) from ecologically protected areas. 3 3

c) Identification and Selection:

Page 85 of 198

Page 87: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to bedone on an agricultural land, top-soil stripping, stacking and preservation ismust.

3 3

2. Borrow pits shall not be located within a distance of 100mts. From anyNH, SH or other roads. 3 3

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 3 3

4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 3 3

5. No borrow area shall be opened with in 500mts. from a reserved orprotected forest area, protected sites, wildlife movement zone and culturalheritage site.

3 3

6. No tree cutting shall be undertaken. 3 37. Borrow area near any surface water body will be at least 100mts.away. 3 3

d) Operation 31. Area up to which material will be extracted shall be cleareddemarcated on ground. 3 3

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 3 33. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level. 3 3

4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 3 3

e) Rehabilitation of Borrow Areas: 3 31. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon 3 3

2. Preserved top soil has be spread uniformly over land (except in caseswhere borrow area is developed as a water body) used as a borrow area. 3 3

9 Water Extraction/Use

Water for construction and for use at construction camps (including labourcamps) is to be extracted with prior written permission of(a) the individualowner, in case the source is private well/tube well; (b) Gram Panchayat incase the source belongs to community: and (c) Irrigation Department incase the source is an irrigation canal or river.

3 3

Page 86 of 198

Page 88: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

10Safety of RoadUsers and LocalResidents

a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roads whichwill be used for transporting materials.

3 3

b) Material shall be covered during transportation to prevent spillage,accidents and pollution. 3 3

c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into theconstruction.

3 3

11 Worker’s Safety

a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aid facility;emergency response arrangement; proper storage of hazardous/toxic andpolluting materials and; measures for ensuring fire electrical andmechanical safety arrangements in camp and in work site.

3 3

b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.

3 3

c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 3 3

12 Air pollution a) Wind barriers or screens shall be provided in the downwind directionat air pollution causing sources like plant sites and fine material storagestock yards

3 3

b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

3 3

c) All plants and equipment shall comply with pollution control norms. 3 3d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100m beforethe settlement)

3 3

Page 87 of 198

Page 89: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

13 Water Pollution

a) All measures (including provision of temporary silt fencing to controlsediment run-off) required for avoiding adverse impacts to water bodies(such as ponds, streams, canals and rivers), water sources (such as handpumps and wells) and adjacent farmland shall be undertaken by theContractor.

3 3

b) Storage of materials like fuel, chemicals, and cement shall be done ina manner (with impervious layer on bottom and a covered shed on top)that does not contaminate land and ground/surface water.

3 3

14 Noise Pollution

a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal to ensureleast disturbance to school children and other adjacent residents.

3 3

b) Ear plugs shall be provided to the labour facing risk from high noisepollution such as plant site and those working near generators, heavyequipment /machinery.

3 3

c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operation ofcamp.

3 3

15 Disposal Debris/wastes

a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

3 3

b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In nocase, debris shall be disposed within 500mts. of ecologically sensitive areas,including forests, wetlands and protected natural habitats.

3 3

16Restoration andRehabilitation ofSites

All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

3 3

Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps,plants, in and around the construction site; disposal of debris/constructionwastes at pre-approved locations and; restoration of borrow areas andother sites/ locations used for material sourcing.

3 3

Page 88 of 198

Page 90: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram anchayat ( including those related to temporary use of land,water extraction and disposal of debris) shall be settled by the Contarctor.

3 3

Third Party Quality Audit for Construction of Cyclone Shelters, Roads to Cyclone Shelters &Habitations, Bridges and Culverts under NCRMP (Details of Nellore in March,2013)

Sl.No Activity Measures to be implemented by the contractor Compliced Not

complicedNot

applicable Total

1 Work Plan for EMPimplementation

The Contractor’s Project Manager shall be responsible for implementation ofEMP provisions and will coordinate the over-all implementation of the saidplan. Along with the Work Programme, the Contractor shall submit a planincluding method statement and timeline about specific actions that will betaken by him to implement the provisions laid out in the EMP

24 24

2RegulatoryPermissions andConsents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtaining permission/consentfor plants, water and extraction and borrow areas operations. This includes:

24

· Consent for establishment and operation of plant (for concrete work)from SPCB. 24 24

· PUC certification for all vehicles/equipment used for/duringconstruction. 24 24

· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations formaterials like sand and earth.

24 24

· Permission for water extraction, if applicable in the local areacontext. 24 24

The Contractor shall abide by all conditions laid out in the said clearances. 24 24

3Consultation andCommunityConsent

The Contractor shall consult and obtain written consents oflandowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:a) Setting-up and operation of construction camp including labour camps,stock yards etc. 24 24

Page 89 of 198

Page 91: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

b) borrow areas and 24 24c) Disposal of debris and other waste material. 24 24

4 Construction/Labour Camp

a) Location: The camp and plant site/s location and establishment shall bedone in a manner that does not interfere or disturb the activities of localinhabitants, particularly those of schools and health facilities. Writtenpermission (no objection certificate) shall be taken from the Gramsabhaand the land owner prior to location selection and a copy shall be submittedto the Engineer approval.

24 24

b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds. 24 24

c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks, Sanctuaries,Biosphere Reserves, Reserve Forests and Ramsar Sites) and CoastalRegulation Zone.

24 24

b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions ofLabour Laws. Separate toilet facilities shall be provided for women workers.If a common mess is not provided/operated additional space for cookingshall be provided. The contractor shall ensure that hygienic conditions aremaintained during the operation of such camps/facilities.

24 24

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp. 24 24

d) Potable water supply: Drinking water supply of at least 40Ipcd with therequired supply points shall be provided. 24 24

e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall be providedby the contractor.

24 24

5 Site Clearance

a) NO tree cutting is to carried out without the written instruction from theEmployer, who in turn will ensure that relevant regulatory permission/s(including those from Forest Dept., if required) are obtained prior to cuttingof such trees.

24 24

b) The non-timber grade trees are to be stacked and possession is to begiven to Employer/concerned Govt. Department. 24 24

Page 90 of 198

Page 92: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

c) The Contractor shall strip, store and preserve top soil from the site ofconstruction work and in the stock yards prior to stacking of materials. Thetop soil shall be reinstated in the cyclone shelter compound after theconstruction is over.

24 24

6Protection ofProperties andResources

The Contractor shall take due care to protect and prevent damages to thefollowing resources during preparatory and construction work:a) Water supply lines 24 24b) Irrigation canals 24 24c) Cart, cattle and/or foot trail/tracks 24 24d) Cultural properties and sites/structures of religious importance 24 24

e) Houses, Farmlands, Orchids and/or Trees. 24 24f) School and other existing buildings adjacent to the site ofconstruction. 24 24

In case of damage due to construction activity, the restoration/repairs shallbe carried out by the contractor at his own cost. 24 24

7 Quarry OperationsThe Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shall besubmitted to the Engineer prior to procuring material.

24 24

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractor followingthe stipulations given below: The finalisation of all such locations shall bedependent on the approval of the Engineer on technical and environmentalgrounds. This includes on-site verification to cross-check the accuracy ofdetails provided by the contractor. Only after receipt of the written approvalfrom the Engineer, the Contractor shall enter into a formal agreement withlandowner.

24 24

b) The Contractor shall not procure any kind of construction material (suchas aggregates, sand and earth) from ecologically protected areas. 24 24

c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs to bedone on an agricultural land, top-soil stripping, stacking and preservation ismust.

24 24

2. Borrow pits shall not be located within a distance of 100mts. From anyNH, SH or other roads. 24 24

Page 91 of 198

Page 93: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations. 24 24

4. No borrow pits shall be located within 500mts. from schools, colleges,playgrounds, religious structures and health centres. 24 24

5. No borrow area shall be opened with in 500mts. from a reserved orprotected forest area, protected sites, wildlife movement zone and culturalheritage site.

24 24

6. No tree cutting shall be undertaken. 24 247. Borrow area near any surface water body will be at least 100mts.away. 24 24

d) Operation1. Area up to which material will be extracted shall be cleareddemarcated on ground. 24 24

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 24 243. Borrowing of earth should be preferably limited to a depth of 1.5mtrfrom the existing ground level. 24 24

4. Slope at the edges will be maintained not steeper than 2:3 (Vertical :Horizontal) 24 24

e) Rehabilitation of Borrow Areas: 24 241. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon 24 24

2. Preserved top soil has be spread uniformly over land (except in caseswhere borrow area is developed as a water body) used as a borrow area. 24 24

9 Water Extraction/Use

Water for construction and for use at construction camps (including labourcamps) is to be extracted with prior written permission of(a) the individualowner, in case the source is private well/tube well; (b) Gram Panchayat incase the source belongs to community: and (c) Irrigation Department incase the source is an irrigation canal or river.

24 24

10Safety of RoadUsers and LocalResidents

a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety ofroad users and local people, particularly in the internal village roads whichwill be used for transporting materials.

24 24

b) Material shall be covered during transportation to prevent spillage,accidents and pollution. 24 24

Page 92 of 198

Page 94: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorised entry into theconstruction.

24 24

11 Worker’s Safety

a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aid facility;emergency response arrangement; proper storage of hazardous/toxic andpolluting materials and; measures for ensuring fire electrical andmechanical safety arrangements in camp and in work site.

24 24

b) All methods steps and measures are required for ensuring safety ofworkers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.

24 24

c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 24 24

12 Air pollution a) Wind barriers or screens shall be provided in the downwind directionat air pollution causing sources like plant sites and fine material storagestock yards

24 24

b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

24 24

c) All plants and equipment shall comply with pollution control norms. 24 24

d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100m beforethe settlement)

24 24

13 Water Pollution

a) All measures (including provision of temporary silt fencing to controlsediment run-off) required for avoiding adverse impacts to water bodies(such as ponds, streams, canals and rivers), water sources (such as handpumps and wells) and adjacent farmland shall be undertaken by theContractor.

24 24

b) Storage of materials like fuel, chemicals, and cement shall be done ina manner (with impervious layer on bottom and a covered shed on top)that does not contaminate land and ground/surface water.

24 24

Page 93 of 198

Page 95: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

14 Noise Pollution

a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal to ensureleast disturbance to school children and other adjacent residents.

24 24

b) Ear plugs shall be provided to the labour facing risk from high noisepollution such as plant site and those working near generators, heavyequipment /machinery.

24 24 24

c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimise noise during construction work and operation ofcamp.

24 24

15 Disposal Debris/wastes

a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

24 24

b) Location of Debris Disposal Sites: Debris disposal sites shall be locatedpreferably away from farmlands, water sources and water bodies. In nocase, debris shall be disposed within 500mts. of ecologically sensitive areas,including forests, wetlands and protected natural habitats.

24 24

16Restoration andRehabilitation ofSites

All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

24 24

Completion of work(as covered under clause 55.1 of GCC) will also includecompletion of rehabilitation and clean-up of the work sites including camps,plants, in and around the construction site; disposal of debris/constructionwastes at pre-approved locations and; restoration of borrow areas andother sites/ locations used for material sourcing.

24 24

17 LiabilitiesAny liability arising out of Contractor’s agreement with landowners/ localpeople/gram panchayat ( including those related to temporary use of land,water extraction and disposal of debris) shall be settled by the Contractor.

24 24

Page 94 of 198

Page 96: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

9.0 Statement Showing the Inspections and Site Visits of Districts during this 3 Months:

9.1 Statement Showing the Inspections and Site Visits of Districts during the Month of January -2013

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM DISTRICT DURING THE MONTH OF JANUARY 2013

Sl.No. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISIT NO. OFVISITS

1 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of Cyclone shelter at Runku inSanthabommali Mandal. 19.01.13,26.01.13 2

2 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002

Road from Deppuru, bhadapalli road to Onkuluru &cyclone shelter. 8.01.13 1

3 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram 8.01.13 1

4 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Pollada to Komrlathada&Cyclonic shelter 8.01.13 1

5 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B ROAD TO Devunalthada 8.01.13 1

6 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of Cyclone shelter at Kollipadu inSanthabommali Mandal. 3.01.13, 19.01.13, 24.01.13 3

7 NCRMP/B_W/AP/Br/R&B/ 01/Bendigedda/004 Construction of High level Bridge across Bendigedda atkm 4/10 of Pundi-Parlkimidi road in Srikakulam Dist. 12.01.13 1

8 NCRMP/B-W/AP/MPCS/PRED/ 01/Polaki/006 Road from Talasamudram to Dola regulator 24.01.13 1

9 NCRMP/B-W/AP/MPCS/PRED/ 01/Polaki/006 Road from Mabagam R&B road to Dubbakavanipeta viagajapathinagaram. 24.01.13 1

10 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/005 Road from R&B road Edullavalasa-Killam to jonnam viatalasamudram 24.01.13 1

11 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Kotcherla road to Pathasundarapalem 11.01.13 1

Page 95 of 198

Page 97: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

12 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Kotcherla road to Kollibhemavaram & tocyclone shelter 11.01.13 1

13 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from mentada to Dovupeta 11.01.13 1

14 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Koyyam R&B road to Moosavanipeta 11.01.13 1

15 NCRMP/B_W/BR/R&B/01/uppigedda/002 Construction of HLB across uppugedda at Km 7/6 ofSrikakulam municipal limits to Pukkalapeta 3.01.13, 5.01.13, 10.01.13, 24.01.13 4

16 NCRMP/BW/AP/Br/AR&B/01/Patnavanipeta/001

Construction of Bridge at km 11/6-8 of NH-5 toPatnavanipeta connecting Sundarapalem.

4.01.13, 10.01.13, 18.01.13, 21.01.13,22.01.13, 26.01.13, 27.01.13 7

17 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003 Road from DPN road Uddandapalem 9.01.13 1

18 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003 Road from K.Umilada to Koduru (Link road) 9.01.13 1

19 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003

Road from Borubadra, Malagam road to Kollipadu viaSeepuram, Ghantapeta 9.01.13 1

TOTAL 31

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIZIANAGARAM DISTRICT DURING THE MONTH OF JANUARY 2013

SNO. PACKAGE NO NAME OF WORK

TPQA INSPECTIONSDURING THIS MONTH

DATES OFVISIT

NO. OFVISITS

1 NCRMP/B-W/ AP/ Br/ R&B/ 02/Chakaligadda /008

Construction of Minor Bridge at Km 15/2 near Chakaligadda of Konada Ramatheertham R&Broad to Konatalapalem (via) Yerukonda, Pasupam, Kollayavalasa (ZP Road). 29.01.2013 1

Total 1

Page 96 of 198

Page 98: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISAKHAPATNAM DURING THIS MONTH OF JANUARY - 2013

SNO. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THISMONTH

DATES OF VISIT NO. OFVISITS

1 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004 Construction of cyclone shelter at Venkayyapalem in RambilliMandal

03.01.13, 05.01.13,08.01.13, 19.01.1322.01.13, 30.01.13

6

2 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Patimeeda in NakkapalliMandal

03.01.13, 09.01.13,10.01.13, 17.01.1323.01.13, 30.01.13

6

3 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Mullaparra in NakkapalliMandal

03.01.13, 17.01.13,23.01.13, 30.01.13 4

4 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Bangarrampeta in NakkapalliMandal 03.01.13, 30.01.13 2

5 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Ratnayampeta inPayakaraopeta Mandal 04.01.13, 12.01.13 2

6 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Gajapathinagaram inPayakaraopeta Mandal

04.01.13, 09.01.13,12.01.13 3

7 NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003 Road from R&B road to B.P Kallalu to Matchavanipalem 18.01.13 1

8 NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001 Road from NH-5 to Ramarayyadupalem 19.01.13 1

9 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B to road to Rajakoduru 19.01.13, 22.01.13 2

10 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B to road to Krishnampalem 19.01.13 1

11 NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006 B.T to the road from R & B road to Venkayyapalem 19.01.13, 22.01.13 2

12 NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 Road from R & B road to Pothurajanapalem 11.01.13 1

13 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 Road from R&B road to Pedateenarla to Chinateenarla 23.01.13 1

14 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 Road from Upamaka Rajayyapeta R&B road to Janakayyapeta 23.01.13 1

Page 97 of 198

Page 99: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

15 NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001 Providing B.T to the road from Vempudi to Patimeeda 23.01.13 1

16 NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/002 B.T to the road from R&B to Mullaparra up to beach end 23.01.13 1

17 NCRMP/B-W/AP/RCS/PRED/03/S.Rayavaram/006 Road from R&B Road to Revupolavaram Cyclone shelter . 31.01.13 1

18 NCRMP/B-W/AP/MPCS/PRED/03/S.Rayavaram/009 Construction of Cyclone shelter at Bangarampalem I&II H/OVakadu. 31.01.13 1

19 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from R&B road to Gajareddypalem 08.01.13, 19.01.13,22.01.13 3

20 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 Construction of cyclone shelter at Rajayyapeta 09.01.13, 17.01.13 2

21 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/008 Road from ZP Road Palamanpeta to Korlayyapeta 09.01.13, 17.01.13 2

22 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 Construction of cyclone shelter at Palmanpeta 09.01.13, 17.01.13 2

23 NCRMP/B-W/AP/MPCS/PRED/03/Atchutapuram/006 Construction of cyclone shelter at Kadapalem 08.01.13 1

24 NCRMP/B-W/AP/MPCS/PRED/03/Atchutapuram/006 Construction of cyclone shelter at Vadapalem 08.01.13 1

25 NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/009 Road from R&B road to Vadapalem 08.01.13 1

26 NCRMP/B-W/AP/RCS/PRED/03/Atchutapuram/007 Road from R&B road to Kothapatnam 08.01.13 1

27 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from Rajala R&B road to Rajarayyudupalem 08.01.13 1

28 NCRMP/B-W/AP/MPCS/PRED/03/Paravada/005 Construction of cyclone shelter at Jalaripeta 11.01.13 1

29 NCRMP/B-W/AP/MPCS/PRED/03/Paravada/005 Construction of cyclone shelter at Mutyalammpalem 11.01.13 1

TOTAL 53

Page 98 of 198

Page 100: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN EAST GODAVARI DURING THIS MONTH OF JANUARY 2013

SNO. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISIT NO. OFVISITS

1 NCRMP/B-W/AP/RHB/ PRED/04/Katrenikona/003

Road from PR road to Dasarivanipeta and to CycloneShelter 16.012.2013 1

2NCRMP/B-W/ AP/MPCS/PRED/04/Thondangi/001

Cyclone Shelter at Avulamanda and of Thondangi Mandal, E.G.Dt.

03.01.2013, 11.01.2013, 15.01.2013and 31.01.2013 4

3 Cyclone Shelter at Lakshmanudipeta of ThondangiMandal, E.G.Dt.

03.01.2013, 11.01.2013, 15.01.2013and 31.01.2013 4

4 NCRMP/B-W/ AP/MPCS/PRED/04/Uppalaguptam/002

Cyclone Shelter at Pedaraghavulapeta of UppalaguptamMandal, E.G.Dt.

04.01.2013, 10.01.2013, 12.01.2013,18.01.2013, 22.01.2013, 24.01.2013

and 30.01.2013.7

TOTAL 16

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS OF WEST GODAVARI DISTRICT (YEAR-II WORKS) DURING THIS MONTH JANUARY2013

SNO. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THISMONTH

DATES OF VISITS NO. OF VISITS

1. NCRMP/B-W/AP/RCS/PRED/05/Achanta/002 Road from R&B road to Ayodya lanka Marrimula cyclone shelter. 19.01.2013 1

2.NCRMP/B-W/AP/RCS/PRED/05/Kalla/003

Road from R&B road to Modi Cyclone Shelter 10.01.2013 1

3. Road from R&B road to S.C Bose Colony Cyclone Shleter 10.01.2013 1

4. NCRMP/B-W/AP/RCS/PRED/05/Bhimavaram/004

Construction of approach road to cyclone shelter in Losari of BhimavaramMandal. 02.01.2013 1

Page 99 of 198

Page 101: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

12. NCRMP/B-W/AP/RHB/PRED/05/Kalla/004 K.G. R&B Road to Mamidipudi of Kalawapudi. 10.01.2013 1

13.NCRMP/B-

W/AP/RHB/PRED/05/Bhimavaram/005

Road from Dongapindi R & B Road to Revu (Pallipalem) in Dongapindi ofBhimavaram Mandal. 02.01.2013 1

14. Road from R & B Road to Sarvodhyanagar (Garivelladibba) H/o Losari ofBhimavaram Mandal. 02.01.2013 1

41. NCRMP/B-W/AP/MPCS/PRED/05/Narsapur/001

Sardupalli Palem of Vemuladeevi 23.01.2013 1

42. Pedamynavani lanka 23.01.2013 1

43. NCRMP/B-W/AP/MPCS/PRED/05/Narsapur/003

Chinamynavani lanka 23.01.2013 1

44. Vemuladeevi East 23.01.2013 1

45. NCRMP/B-W/AP/MPCS/PRED/05/Mogalturu/002

Yetimondi of Perupalem 24.01.2013 1

46. Bellamkondavarimeraka 24.01.2013 1

Total 13

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN KRISHNA DISTRICT DURING THE MONTH JANUARY 2013

SNO. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THISMONTH

DATES OF VISITS NO. OFVISITS

1 NCRMP/B-W/AP/RCS/PRED/06/Nagayalanka/006

Road from China Zinkapalem to Gollamanda via peda Zinkapalem 09.01.13 1

Road from R&B road to Cyclone Shelter at Gollamanda 09.01.13 1

Road from ZP Road to Cyclone shelter at Natchugunta 09.01.13 1

Road from Krishna river to Elechetla Dibba Cyclone shelter 09.01.13 1

2 NCRMP/B-W/AP/RHB/PRED/06/Nagayalanka/009 Road from R&B Road Dananjaya Colony to Krishnapuram 09.01.13 1

TOTAL 5

Page 100 of 198

Page 102: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN GUNTUR DISTRICT DURING THIS MONTH OF JANUARY- 2013

SNO. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISIT NO. OFVISITS

1

NCRMP/B-W/AP/RCS/PRED/07/Karalapalem/002

Road from Ganapavaram R&B Road to Pedamarpuvaripalem.7.1.2013, 8.1.203, 17.1.2013,

26.1.2013, 27.1.2013, 30.1.2013,31.1.2013.

7

2 Road from R&B road to chinapuluguvaripalem 5.1.2013, 30.1.2013, 31.1.2013. 3

3 Road from Ganapavaram PR Road to Bonthagorlapalem. 5.1.2013 1

4 NCRMP/B-W/AP/Br/R&B/07/Bapatla/010

Reconstruction of HLB @ km 5/2 of Bapatla - Suryalanka roadacross perali drain in Guntur District. 8.1.2013, 10.1.2013. 2

5 NCRMP/B-W/AP/RCS/PRED/07/Pvpalem/001

Road from R & B Road to Hanumanth Nagar. 31.1.2013. 1

6 Road from R & B Road to Adarshnagar. 31.1.2013. 1

7 NCRMP/B-W/AP/RCS/PRED/07/Pvpalem/001 Road from R & B Road Allur to Yadavapalem 4.1.2013, 5.1.2013, 7.1.2013, 8.1.2013. 4

TOTAL 19

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN PRAKASAM DISTRICT DURING THE MONTH OF JANUARY-13

Sl.No. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISIT NO. OFVISITS

1 NCRMP/B-W/APMPCS/PRED/08/NG Padu/003 Kanaparthy cyclone shelter in Nagulappapadu mandal. 04.01.2013 1

2 NCRMP/B-W/AP/Br/R&B/08/Kanaparthi/012

Construction of High level Bridge at Km 16/10 ofNaguluppalapadu – Kanaparthi road in Prakasam District 03.01.2013 1

Page 101 of 198

Page 103: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from NH5 to Mulaguntapadu 05.01.2013, 10.01.2013, 15.01.2013

29.01.2013, 30.01.2013, 31.01.2013 6

4 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from Pakala R&B road to Mosanaladinne

05.01.2013, 10.01.2013, 15.01.201326.01.2013, 28.01.2013, 29.01.2013

31.01.20137

5 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

Road from R&B road to Binginapalli Harijanawada CycloneShelter 10.01.2013 1

6 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from R&B road to Chalivendradibba 10.01.2013, 15.01.2013, 23.01.2013

25.01.2013, 28.01.2013 5

7 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001

Road from Pakala ZP Road to Aulavaripalem Cycloneshelter 10.01.2013 1

8 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001 Road from R&B Road to Somarajupalli 10.01.2013 1

9 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001 Road from R&B road to Narravaripalem 10.01.2013 1

10 NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07 Road from MC Road to Subbarayudu Satram 11.01.2013 1

11 NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09 Road from R&B road Pellur to Vasepallipadu 10.01.2013, 23.01.2013

24.01.2013, 28.01.2013 4

12 NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10 Road from R&B road to Kesupalem 10.01.2013 1

13 NCRMP/B-W/APMPCS/PRED/08/Ulavapadu/001

Chakicherla cyclone shelter in Ulavapadu mandalprakasam district 11.01.2013 1

TOTAL 31

Page 102 of 198

Page 104: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN NELLORE DISTRICT DURING THE MONTH OF JANUARY 2013

SLNO Package Number Name of work

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISITS NO. OFVISITS

1 NCRMP/B-W/AP/RHB/PRED/09/V.CHALEM/RHB/007

Providing BT Surface to the road from R&B road toEdagali kandriga 01.01.2013, 02.01.2013 2

2 NCRMP/B-W/AP/RHB/PRED/09/V.CHALEM/RHB/007

Road from Suvepalli-Pudiparthi road to SrikanthColony 01.01.2013, 02.01.2013 2

3 NCRMP/B-W/AP/PRED/09/MUTHUKUR/RHB/006 Road from R&B road to Patuvarikandriga 01.01.2013 1

4 NCRMP/B-W/AP/PRED/09/MUTHUKUR/RCS/002

Road from R&B Road kappaladoruvu to bandla palemH.wada 01.01.2013 1

5 NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005 Road from KT R&B road to Allaganipadu to vavilla 11.01.2013 1

6 NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005

Road from R&B road Kancharlapalam HW toAlaganipadu.

09.01.2013, 11.01.2013,21.01.2013, 24.01.2013 4

7 NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006

Road Connecting R&B Road through Voturu Villagein SPSR Nellore District 21.01.2013 1

8 NCRMP/B-W/AP/RCS/PRED/09/TADA/009 Providing BT road to Peda Pannam Gadu in TadaMandal of Nellore Dt. 09.01.2013, 31.01.2013 2

9 NCRMP/B-W/AP/RCS/PRED/09/TADA/009 Road from @ km 56/8 to CK Road to PeriyavettuKuppam Cyclone Shelter 09.01.2013, 31.01.2013 2

10 NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012

Ring Road to TP Gudur- Salipeta R & B Road via CSPuram and Mandapam Village 16.01.2013 1

11 NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/012 Road from R & B Road C S Puram to Sivaramapuram 16.01.2013 1

Total 18

Page 103 of 198

Page 105: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

9.2 Statement Showing the Inspections and Site Visits of Districts during the Month of February -2013

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM DISTRICT DURING THE MONTH OF FEBRUARY 2013

Sl.No. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISIT NO. OF VISITS

1 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of Cyclone shelter at Runku inSanthabommali Mandal.

09.02.2013, 11.02.2013,12.02.2013, 13.02.2013,18.02.2013, 25.02.2013

6

2 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of Cyclone shelter at Kollipadu inSanthabommali Mandal.

11.02.2013, 12.02.2013,25.02.2013 3

3 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Kotcherla road to Pathasundarapalem 7.02.13 1

4 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005

Road from Kotcherla road to Kollibhemavaram & tocyclone shelter 7.02.13 1

5 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Mentada to Dovupeta 7.02.2013, 11.02.2013 2

6 NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005 Road from Koyyam R&B road to Moosavanipeta 7.02.13 1

7 NCRMP/B_W/BR/R&B/01/uppigedda/002

Construction of HLB across Uppugedda at Km 7/6 ofSrikakulam municipal limits to Pukkalapeta 8.02.2013, 11.02.2013 2

8 NCRMP/BW/AP/Br/AR&B/01/Patnavanipeta/001

Construction of Bridge at km 11/6-8 of NH-5 toPatnavanipeta connecting Sundarapalem.

7.02.2013, 8.02.2013,11.02.2013, 16.02.2013 4

TOTAL 20

Page 104 of 198

Page 106: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIZIANAGARAM DISTRICT DURING THE MONTH OF FEBRUARY- 2013

Sl.No. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISIT NO. OF VISITS

1 NCRMP/B-W/AP/Br/R&B/02/Chakaligadda/008

Construction of Minor Bridge at Km 15/2 near Chakaligadda ofKonada Ramatheertham R&B road to Konatalapalem (via)Yerukonda, Pasupam, Kollayavalasa (ZP Road) inVizianagaram District.

05.02.201315.02.201319.02.201328.02.2013

4

Total 4

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISAKHAPATNAM DISTRICT DURING THE MONTH OF FEBRUARY - 2013

Sl.No. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THIS MONTHDATES OF VISIT NO. OF VISITS

1 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004

Construction of cyclone shelter at Venkayyapalem in RambilliMandal 04.02.2013 14.02.2013 2

2 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Patimeeda in Nakkapalli Mandal 06.02.2013 12.02.2013

21.02.2013 26.02.2013 4

3 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Mullaparra in Nakkapalli Mandal 06.02.2013 12.02.2013

21.02.2013 26.02.2013 4

4 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

Construction of cyclone shelter at Bangarrampeta in NakkapalliMandal 21.02.2013 26.02.2013 2

5 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

Construction of cyclone shelter at Ratnayampeta in PayakaraopetaMandal

09.02.2013 12.02.201325.02.2013 26.02.2013 4

Page 105 of 198

Page 107: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

6 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

Construction of cyclone shelter at Gajapathinagaram inPayakaraopeta Mandal

09.02.2013 12.02.201325.02.2013 26.02.2013 4

7 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B to road to Kattubolu to Marriaplem 16.02.2013 1

8 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B to road to Krishnampalem 16.02.2013 1

9 NCRMP/B-W/AP/RHB/PRED/03/Achutapuram/007 Road from R & B road to Avarajam 16.02.2013 1

10 NCRMP/B-W/AP/RHB/PRED/03/Achutapuram/007 Road from R & B road to Avasomavaram 16.02.2013 1

11 NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 Road from R & B road to Jalaripeta 16.02.2013 1

12 NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 Road from R & B road to Pothurajanapalem 16.02.2013 20.02.2013 2

13 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 Road from R&B road to Pedateenarla to Chinateenarla 09.02.2013 1

14 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 Road from Upamaka Rajayyapeta R&B road to Janakayyapeta 09.02.2013 1

15 NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001 Providing B.T to the road from Vempudi to Patimeeda 09.02.2013 1

16 NCRMP/B-W/AP/RCS/PRED/03/S.Rayavaram/006 Road from R&B Road to Revupolavaram Cyclone shelter 12.02.2013 1

17 NCRMP/B-W/AP/MPCS/PRED/03/S.Rayavaram/009

Construction of Cyclone shelter at Bangarampalem I&II H/OVakadu. 12.02.2013 1

18 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from R&B road to Rajvaram 12.02.2013 1

19 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 Construction of cyclone shelter at Rajayyapeta 12.02.2013 1

Page 106 of 198

Page 108: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

20 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/008 Road from ZP Road Palamanpeta to Korlayyapeta 12.02.2013 1

21 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 Construction of cyclone shelter at Kumarapuram 12.02.2013 1

22 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 Construction of cyclone shelter at Palmanpeta 12.02.2013 1

23 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from Rajala R&B road to Rajarayyudupalem 16.02.2013 1

24 NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005 Road from R&B road to Annavaram cyclone shelter 08.02.2013 1

25 NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005 Road from R&B road to Chinanagamayyapalem cyclone shelter 08.02.2013 1

26 NCRMP/B-W/AP/MPCS/PRED/03/Bheemili/008 Construction of cyclone shelter at Chepala Dibbadapalem. 08.02.2013 1

27 NCRMP/B-W/AP/MPCS/PRED/03/Bheemili/008

Construction of cyclone shelter at Boyaveedhi (Bheemili Municipalityarea ) 08.02.2013 1

28 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 Road from R&B Road to Rajakoduru in Rambilli Mandal 23.02.2013 1

TOTAL 43

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN EAST GODAVARI DISTRICT DURING THIS MONTH OF FEBRUARY 2013

Sl.No PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISIT NO. OF VISITS

1 NCRMP/B-W/ AP/RHB/ PRED/04/ KARAPA/001 Road from Gurajanapalli to Bandulavaripalem 18.02.2013 1

2 NCRMP/B-W/ AP/MPCS/PRED/04/Thondangi/001 Cyclone Shelter at Avulamanda and of Thondangi Mandal, E.G.Dt. 13.02.2013 17.02.2013 2

Page 107 of 198

Page 109: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3 Cyclone Shelter at Lakshmanudipeta of Thondangi Mandal, E.G.Dt. 13.02.2013 17.02.2013 2

4 NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002

Cyclone Shelter at Pedaraghavulapeta of Uppalaguptam Mandal,E.G.Dt.

07.02.2013, 14.02.2013,18.02.2013, 20.02.2013,23.02.2013, 25.02.2013

26.02.2013

7

MPCS

5 NCRMP/B-W/AP/MPCS/PRED/04/I.Polavaram/003 Construction of Cyclone Shelter at Byravapalem (Type-D) 08.02.2013 18.02.2013 2

6 NCRMP/B-W/MPCS/PRED/04/Katrenikona/005 Construction of Cyclone Shelter at Mogasanitippa (Type-B) 12.02.2013 1

7 NCRMP/B-W/ AP/MPCS/PRED/04/Katrenikona/006

Construction of Cyclone Shelter at Balusutippa of KatrenikonaMandal in E.G.Dt. Type-D 18.02.2013 1

8

NCRMP/B-W/AP/MPCS/PRED/04/Katrenikona/007

Construction of Cyclone Shelter at Kothapalem 07.02.2013 18.02.2013 2

9 Construction of Cyclone Shelter at Molletimogga 07.02.2013 18.02.2013 2

10 Construction of Cyclone Shelter at Neelarevu-1 07.02.2013 1

11 Construction of Cyclone Shelter at Chirrayanam 07.02.2013 1

12 NCRMP/B-W/AP/MPCS/PRED/04/Katrenikona/008

Construction of Cyclone Shelter at Pallamkurru. 07.02.2013 18.02.2013 2

13 Construction of Cyclone Shelter at Pandi. 07.02.2013 1

14NCRMP/B-W/MPCS/PRED/04/Allavaram/009

Construction of Cyclone Shelter at Rameswaram (Type-A) 12.02.2013 1

15 Construction of Cyclone Shelter at samanthakuru (Type-B) 12.02.2013 1

16NCRMP/B-W/MPCS/PRED/04/Sakhinetipalli/010

Construction of Cyclone Shelter at Pallipalem (Type-D) 09.02.2013 1

17 Construction of Cyclone Shelter at Kesavadasupalem (Type-D) 09.02.2013 1

18 NCRMP/B-W/MPCS/PRED/04/Malikipuram/011 Construction of Cyclone Shelter at Kesanapalli (Type-D) 09.02.2013 1

Page 108 of 198

Page 110: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

19 Construction of Cyclone Shelter at Padamatipalem (Type-D) 09.02.2013 1

20 NCRMP/B-W/MPCS/PRED/04/Mamidikudurua/012 Construction of Cyclone Shelter at Karavaka (Type-B) 09.02.2013 1

RHB

21 NCRMP/B-W/AP/RHB/PRED/04/Sakhinetipalli/008

Road from R&B road to Korukondavari group 09.02.2013 1

22 Road from R&B road to Gondi Kodapa 09.02.2013 1

23NCRMP/B-W/AP/RHB/PRED/04/Allavaram/012

BT Road from Komaragiripatnam to Kadadari and to Cyclone shelter 12.02.2013 1

24 Road from R&B road to Samanthakuru to ChakkavaripetaRamaswaram 12.02.2013 1

25NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/014

Road from R&B road to Guthanadeevi Gogulanka 08.02.201318.02.2013 2

26 Road from R&B Road to Ramalayampeta Pallamkurru (V) 18.02.2013 1

27 NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/016 Road from N.Kothapalli to G.Pora in Katrenikona 07.02.2013

18.02.2013 2

28NCRMP/B-W/AP/RHB/PRED/04/I.Polavaram&Tallarevu/009

Road from Gogullanka to Byravalanka. 08.02.2013 1

29 Road from G.Vemavaram to Gandivaripalem of G.Vemavaram. 09.02.2013 1

30 NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/016 Road from R&B road to Aravapalem 09.02.2013 1

RCS

31

NCRMP/B-W/AP/RCS/PRED/04/Malikipuram/009

Approach road from R&B road to Turupupalem Cyclone Shelter 09.02.2013 1

32 Road from R&B road to Kesanapalli (New) Cyclone Shelter 09.02.2013 1

33 Road from R&B road to Padamatipalem Cyclone Shelter 09.02.2013 1

34NCRMP/B-W/AP/RCS/PRED/04/Razole&Sakhinetipalli/010

Road from R&B road to Katrenipadu Lanka Cyclone Shelter 09.02.2013 1

35 Road from R&B road to Kesavadasupalem (New) Cyclone Shelter 09.02.2013 1

Page 109 of 198

Page 111: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

36 NCRMP/B-W/AP/RCS/PRED/04/Mamidikuduru/013 Road from R&B road to Karavaka Cyclone Shelter 09.02.2013 1

37 NCRMP/B-W/AP/RCS/PRED/04/Katrenikona/015

CC Road from main proposed road to Neelarevu II Cyclone shelterin Neellarevu 07.02.2013 1

38 NCRMP/B-W/AP/RCS/PRED/04/Allavaram/016 Road from R&B road to Samanthakurru Cyclone Shelter 12.02.2013 1

Total 52

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN WEST GODAVARI DISTRICT DURING THE MONTH FEBRUARY 2013

S NO. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THISMONTH

DATES OF VISITS NO. OF VISITS

9.

NCRMP/B-W/AP/RCS/PRED/05/Narsapur/006

R&B road to Chinamynavanilanka 19.02.2013 1

10. P.R road to Ramanujapuram 19.02.2013 1

11. Road from P.R road to Prakasapuram 19.02.2013 1

15. NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/006 Khalipatnam R&B Road to Khalipatnam ferry 19.02.2013 1

26.

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/010

Road from SP R&B road to Pasaladeevi 14.02.2013 1

27. LT R&B road to Modi 14.02.2013 1

28. SP R&B road to Gannabathulavari palem of Chamakuripalem 14.02.2013 1

29.

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/012

Road from R&B road to SC Colony of Pedalanka 19.02.2013 1

30. R&B road to Rajeev Nagar of Darbharevu 19.02.2013 1

31. SP R&B road to Pedathota of Turputallu 19.02.2013 1

Page 110 of 198

Page 112: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

32. R&B road to Peta of Turputallu 19.02.2013 1

33. R&B road to Pedathota of Turputallu 19.02.2013 1

34.

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/013

R&B road to Guttulavarimeraka 12.02.2013 1

35. Road from R & B Road to Pulaparthivaripalem 12.02.2013 1

36. R&B road to Pedaedigapalem 12.02.2013 1

37. R&B road to Evanivarimeraka 12.02.2013 1

Total 16

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN GUNTUR DURING THE MONTH OF FEBRUARY 2013

Sl.No. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THEMONTH

DATES OF VISIT NO. OF VISITS

1 NCRMP/B-W/AP/BR/R&B/07/Bapatla/010

Re construction Of HLB@ km 5/2 of Bapatla - Suryalanka Road acrossperali drain in Guntur DT. 4.2.2013 1

2

NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002

Road from Ganapavaram R&B raod to Pedamarpuvaripalem. 27.02.2013 1

3 Road from R&B raod to Chinapuluguvaripalem. 27.02.2013 1

4 Road from Ganapavaram PR Road to Bonthagorlapalem. 4.02.2013 1

5NCRMP/B-W/AP/RCS/PRED/

07/karlapalem/002

Road from R&B Road to HanumanthNagar. 4.02.2013 1

6 Road from R&B Road to AdarshNagar. 4.02.2013 1

7 NCRMP/B-W/AP/RCS/PRED/07/karlapalem/002 Road from R&B Road to Pedagollapalem Cyclone sheltor. 4.02.2013 1

Page 111 of 198

Page 113: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

8 Road from R&B Road to Yaramvaripalem. 4.02.201227.02.2013 2

9 NCRMP/B-W/AP/RCS/PRED/07/PV palem/001 Road from R&B Road to Mandevaripalem. 4.02.2013 1

10 Year II Chandolu bridge to Nizampatnam road in km 14/6 in Guntur dt 18.02.2013 1

11 Year II Molugunta to Kothapalem road in Km ¼ in Nizampatnam mandal of GunturDistrict. 18.02.2013 1

12 NCRMP/B-W/AP/RCS/PRED/07/PV palem/001 Road from R&B Road Alluru to Yadavapalem. 18.02.2013,

27.02.2013 2

13 NCRMP/B-W/AP/Br/R&B/07/bapatla/011

Re construction of HLB @ km 2/4 Of Bapatla- pandurangapuram roadacross Perali drain 27.02.2013 1

14 Phase -1Alternate works

Road from NH 214 to Dandubata (via) M.V.Rajupalem in KarlapalemMandal 4.02.2013 1

TOTAL 16

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN PRAKASAM DISTRICT DURING THE MONTH OF FEBRUARY-2013

S NO. PACKAGE NO NAME OF WORKTPQA INSPECTIONS DURING THIS MONTH

DATES OF VISIT NO. OF VISITS

1 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from NH5 to Mulaguntapadu

01.02.2013, 02.02.201315.02.2013, 18.02.2013

26.02.20135

2 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from Pakala R&B road to Mosanaladinne

01.02.2013, 02.02.201315.02.2013, 21.02.2013

26.02.20135

3 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from R&B road to Binginapalli Harijanawada Cyclone Shelter 12.02.2013 1

4 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from R&B road to Chalivendradibba

01.02.2013, 02.02.201315.02.2013, 21.02.2013

26.02.20135

TOTAL 16

Page 112 of 198

Page 114: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SPSR NELLORE DISTRICT DURING THE MONTH OF FEBRUARY 2013

SLNO Package Number Name of work

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISITS NO. OFVISITS

1 NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005 Road from KT R&B road to Allaganipadu to vavilla 06.02.13 1

2 NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005 Road from R&B road Kancharlapalam HW to Alaganipadu. 06.02.13, 25.02.13 2

3 NCRMP/B-W/AP/RCS/PRED/09/TADA/009

Providing BT road to Peda Pannam Gadu in Tada Mandal of NelloreDt.

01.02.13, 06.02.13, 12.02.13,20.02.13 4

4 NCRMP/B-W/AP/RCS/PRED/09/TADA/009

Road from @ km 56/8 to CK Road to Periyavettu KuppamCyclone Shelter 12.02.13, 20.02.13 2

5 NCRMP/B-W/AP/RHB/PRED/09/CHITTAMURU/003 Road from R&B Chittamur to Soma Samudram 01.02.13 1

6 NCRMP/B-W/AP/RHB/PRED/09/RHB/KAVALI/004 Road from pedattapupalem R&B road to chennyapalam H.wada 11.02.13 1

Year-II

7 NCRMP/B-W/AP/RHB/PRED/09/Kota/023 Road from At km 22/5 of Yamadinne palem road to Gunnampadia 22.02.13, 28.02.13 2

8 NCRMP/B-W/AP/RHB/PRED/09/V.Chalam/021

Road from Thirumalammapalem R&B Road to Gajulapalli Koneru inV.Chalam mandal 15.02.13, 28.02.13 2

Total 15

Page 113 of 198

Page 115: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

9.3 Statement Showing the Inspections and Site Visits of Districts during the Month of March -2013

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM DISTRICT DURING THIS MONTH OF MARCH 2013

Sl.No. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THISMONTH

DATES OF VISIT NO. OFVISITS

1 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005 Construction of Cyclone shelter at Runku in Santhabommali Mandal. 4.03.13,8.03.13,11.3.13,1

9.3.13,25.3.13 5

2 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Deppuru, bhadapalli road to Onkuluru & cyclone shelter. 15.03.13 1

3 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram 15.03.13 1

4 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Pollada to Komrlathada&Cyclonic shelter 15.03.13 1

5 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B ROAD TO Devunalthada 15.03.13 1

6 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of Cyclone shelter at Kollipadu in SanthabommaliMandal.

4.3.13,7.3.13,8.3.13,11.3.13,19.3.13,26.3.13 6

8 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006 Road from Talasamudram to Dola regulator 31.03.13 1

9 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006

Road from Mabagam R&B road to Dubbakavanipeta viagajapathinagaram. 31.03.13 1

10 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/005

Road from R&B road Edullavalasa-Killam to jonnam viatalasamudram 31.03.13 1

11 NCRMP/B_W/BR/R&B/01/uppigedda/002

Construction of HLB across uppugedda at Km 7/6 of Srikakulammunicipal limits to Pukkalapeta 14.03.13,22.03.13 2

12 NCRMP/BW/AP/Br/AR&B/01/Patnavanipeta/001

Construction of Bridge at km 11/6-8 of NH-5 to Patnavanipetaconnecting Sundarapalem. 13.03.13 1

TOTAL 21

Page 114 of 198

Page 116: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIZIANAGARAM DISTRICT DURING THIS MONTH OF March - 2013

SlNo. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THISMONTH

DATES OF VISIT NO. OFVISITS

1 NCRMP/B-W/AP/RD/R&B/ 02/Konada/009

Improvements to Road from Konada Ramatheertham (R&B) Roadto Konathalapalem (Via) Pasupam, Yerukonda, Kollayavalasa fromKm 12/0 to 16/5 (Km 0/0 to 4/0 i.e. upto NH-5 crossing) inVizianagaram District, Andhra Pradesh

07.03.13 1

2 NCRMP/B-W/ AP/ Br/ R&B/ 02/Pulligadda/ 007

Construction of Minor Bridge at Km. 7/2 near Puligadda of Konada –Ramatheertham R&B Road to Konathalapalem via Yerukonda,Pasupam, Kollayavalasa (Z.P. Road)

07.03.13 1

3 NCRMP/B-W/ AP/ Br/ R&B/ 02/Chakaligadda /008

Construction of Minor Bridge at Km 15/2 near Chakaligadda ofKonada Ramatheertham R&B road to Konatalapalem (via)Yerukonda, Pasupam, Kollayavalasa (ZP Road) in VizianagaramDistrict.

07.03.1312.03.1326.03.13

3

Total 5

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISAKHAPATNAM DISTRICT DURING THIS MONTH OF MARCH - 2013

SlNo. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISIT NO. OFVISITS

1 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004

Construction of cyclone shelter at Venkayyapalem inRambilli Mandal

05.03.13, 08.03.13, 09.03.13,20.03.13, 22.03.13, 25.03.13,

28.03.137

2 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

Construction of cyclone shelter at Patimeeda in NakkapalliMandal

04.03.13, 08.03.13, 14.03.13,18.03.13, 19.03.13, 25.03.13,

28.03.137

Page 115 of 198

Page 117: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

Construction of cyclone shelter at Mullaparra in NakkapalliMandal

04.03.13, 08.03.13, 14.03.13,18.03.13, 19.03.13, 25.03.13,

28.03.137

4 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

Construction of cyclone shelter at Bangarrampeta inNakkapalli Mandal

04.03.13, 08.03.13, 14.03.13,18.03.13, 19.03.13, 25.03.13,

28.03.137

5 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

Construction of cyclone shelter at Ratnayampeta inPayakaraopeta Mandal 08.03.13, 18.03.13, 28.03.13 3

6 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

Construction of cyclone shelter at Gajapathinagaram inPayakaraopeta Mandal 08.03.13, 18.03.13, 28.03.13 3

7 NCRMP/B-W/AP/RCS/PRED/03/S.Rayavaram/006 Road from R&B Road to Revupolavaram Cyclone shelter . 21.03.13, 25.03.13, 27.03.13,

28.03.13 4

8 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from R&B road to Rajvaram 15.03.13, 18.03.13, 21.03.13,

25.03.13, 28.03.13 5

9 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 Road from R&B road to Gajareddypalem 13.03.13, 20.03.13, 21.03.13,

25.03.13 3

10 NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/009 Road from R&B road to Vadapalem 13.03.13, 20.03.13 2

TOTAL 48

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN EAST GODAVARI DISTRICT DURING THIS MONTH OF MARCH 2013

Sl.No. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISIT NO. OFVISITS

1 NCRMP/B-W/ AP/RCS/ PRED/04/KARAPA/001

ROAD FROM APPROACH ROAD TO CYCLONESHELTER AT ADAVIPUDI IN E.G.Dt. 20.03.2013 1

2 NCRMP/B-W/ AP/RHB/ PRED/04/KARAPA/001

ROAD FROM GURAJANAPALLI TOBANDULAVARIPALEM 20.03.2013 1

Page 116 of 198

Page 118: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3NCRMP/B-W/ AP/MPCS/PRED/04/Thondangi/001

Cyclone Shelter at Avulamanda and of Thondangi Mandal ,E.G.Dt.

05.03.2013, 14.03.2013, 18.03.2013,25.03.2013 & 29.03.2013 5

4 Cyclone Shelter at Lakshmanudipeta of Thondangi Mandal,E.G.Dt.

05.03.2013, 14.03.2013, 18.03.2013,25.03.2013 & 29.03.2013 5

5 NCRMP/B-W/ AP/MPCS/PRED/04/Uppalaguptam/002

Cyclone Shelter at Pedaraghavulapeta of UppalaguptamMandal, E.G.Dt.

07.03.2013, 11.03.2013 &22.03.2013. 3

Total 15

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN GUNTUR DISTRICT DURING THIS MONTH OF MARCH 2013

SlNo. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THISMONTH

DATES OF VISIT NO. OFVISITS

1 NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/003 Road from R&B Road to Alavaripalem. 1.03.2013 1

2 NCRMP/B-W/AP/RCS/PRED/07/karlapalem/002

Road from R&B Road to Chinapuluguvaripalem. 5.03.13,23.03.2013 2

3 Road from Ganapavaram R&B Road to Pedamarpuvaripalem. 23.03.2013 1

4NCRMP/B-W/AP/RCS/PRED/07/Pvpalem/002

Road from R&B Road Alluru to Yadavapalem. 7.03.2013, 23.03.2013. 2

5 Road from R&B Road mandevaripalem. 1.03.2013 1

6 NCRMP/B-W/AP/Br/R&B/07/Bapatla/011

Re construction of HLB @km 2/4 of Bapatla -Pandurangapuramroad across peralidrain in Guntur Dt. 7.03.2013 1

Year-2

7 NCRMP/B-W/AP/MPCS/PRED/07/NZM/004

Construction of Multi Purpose Cyclone Shelter at Fisherman Colonyof Nizampatnam Village of Nizampatnam Mandal 15.03.2013 1

Page 117 of 198

Page 119: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

8 NCRMP/B-W/AP/MPCS/PRED/07/NZM/004

Construction of Multi-Purpose Cyclone Shelter at Padamata veedhiof Nizampatnam Village of Nizampatnam Mandal. 15.03.2013 1

9 NCRMP/B-W/AP/MPCS/PRED/07/NZM/004

Construction of Multi-Purpose Cyclone Shelter Near MRO Office inNizampatnam, Nizampatnam Mandal. 15.03.2013 2

10 NCRMP/B-W/AP/MPCS/PRED/07/Repalle/005 Lankevanidibba 15.03.2013, 20.03.2013 2

11 NCRMP/B-W/AP/MPCS/PRED/07/Nizampatham/003 Sanjeevanagar of Kothaptnam 15.03.2013 1

12 MPCSRCS/PRED/07/Repalle/001 Mollagunta of Kattava 15.03.2013 1

13MPCSRCS/PRED/07/Nizampatnam/001

At Harbour of Nizampatnam village 15.03.2013 1

14 At Nakshatranagar of Kothapalem 15.03.2013 1

TOTAL 18

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN PRAKASAM DISTRICT DURING THIS MONTH OF MARCH-2013

Sl.No. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THISMONTH

DATES OF VISIT NO. OFVISITS

1 NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001 Road from R&B road to vijayanagar colony cyclone shelter 02.03.2013 1

2 NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001 Road from R&B road to cyclone shelter at Mankenavaripalem 02.03.2013 1

3 NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001 Road from R&B road to Ramnagar colony cyclone shelter 02.03.2013 1

4 NCRMP/B-W/APMPCS/PRED/08/NGPadu/003 Kanaparthy cyclone shelter in Nagulappapadu mandal. 12.03.2013

14.03.2013 2

Page 118 of 198

Page 120: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

5 NCRMP/B-W/AP/Br/R&B/08/Kanaparthi/012

Construction of High level Bridge at Km 16/10 of Naguluppalapadu– Kanaparthi road in Prakasam District 12.03.2013 1

6 Year-2 Road from ZP road to Sriramapattapupalem in Ulavapadu Mandal 14.03.201321.03.2013 2

7 Year-2 Road from MC Road to Veerapalli in Ulavapadu mandal. 14.03.201321.03.2013 2

8 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from NH5 to Mulaguntapadu 23.03.2013

28.03.2013 2

9 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from Pakala R&B road to Mosanaladinne 23.03.2013

28.03.2013 2

10 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from R&B road to Chalivendradibba 23.03.2013

28.03.2013 2

total 16

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN NELLORE DISTRICT DURING THIS MONTH OF MARCH2013

Sl.No. Package Number Name of work

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISITS NO. OFVISITS

1 NCRMP/B-W/AP/RCS/PRED/09/TADA/009

Providing BT road to Peda Pannam Gadu in TadaMandal of Nellore Dt.

02.03.2013, 13.03.2013,20.03.2013, 25.03.2013 4

2 NCRMP/B-W/AP/RCS/PRED/09/TADA/009

Road from @ km 56/8 to CK Road to PeriyavettuKuppam Cyclone Shelter

02.03.2013, 20.03.2013,25.03.2013 3

Year-II

3 NCRMP/B-W/AP/RHB/PRED/09/Kota/023

Road from At km 22/5 of Yamadinne palem road toGunnampadia

06.03.2013, 23.03.2013,28.03.2013 3

4 NCRMP/B-W/AP/RHB/PRED/09/V.Chalam/021

Road from Thirumalammapalem R&B Road toGajulapalli Koneru in V.Chalam mandal

14.03.2013, 22.03.2013,30.03.2013 3

Total 13

Page 119 of 198

Page 121: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

10. Grama Sabhas for Community based Cyclone Shelter Management Maintenance WelfareCommittees (CSMMWC):

As per the instruction from the Client, The field staff (Social) of TPQA Consultant are involved in organizing the Grama

Sabhas to form committees for the cyclone shelters from 12-03-2013 to 25-03-2013 in Guntur, Machalipatnam, West

Godavari and East Godavari districts. The Grama Sabhas were conducted smoothly and in some of the villages, the

Secretary was unanimously elected by the local people. However, some suggestions were made by the people during the

Grama Sabhas which are as follows.

Suggestions made by the people in Grama Sabhas

It will be better if some honorarium or incentive is provided to the Secretary.

The Secretary alone cannot manage the shelter. He shall be associated with the VRO or the local Panchayat

Secretary. Then only the management will be strong.

As the government is planning to keep equipment for cyclone warning and some utensils in kitchen to cook during

cyclone period, there is a need for a watchman who shall reside in the Cyclone shelter so that there will be safety

for the material and building.

During the cyclone, no electricity or solar system will work in the shelter. Some alternative arrangement shall be

made for lighting in the shelter. There shall be provision for Generator.

Precautions for health and nutrition shall be made much before the rainy season.

In this regard, the field staff (Social) would like to make the following suggestions:

Suggestions by the Field Staff (Social)

The utilization of local knowledge and resources will be more useful and the people shall be educated through

Participatory Rural Appraisal (PRA) exercises.

Already in the Grama Sabhas, the field staff (Social) suggested the health officials to chalk out a program in their

time sheet for health education

The education on health and nutrition shall be regular as the ANM visits the villages regularly

There is need to think about the cooking arrangements and food during the cyclone period

The field staff (Social) also requested the Mandal level officials to organize some of their training programs through

cyclone shelters. In this regard, request was made to MPDO, Fisheries Development Officer, PHC Doctor etc. and

they agreed for the proposal. But formal suggestion shall be made from the government for more effective

implementation of the program.

The Grama Sabhas for Community based Cyclone Shelter Management Maintenance Welfare Committees (CSMMWC) in

March month are started from 12-3-2013 in Guntur district. The MROs and the MPDOs of the respective mandals along with

other mandal level officials who are members in the committee also attended the Grama Sabhas. The field staff (Social) of

TPQA Consultant, Mr. V. Srinivars, Communication Expert, NCRMP, A.P. Secretariat and N. Shyam Sagar. Field

Coordinator, PME, organized the Grama Sabhas. The public and local leaders of the respective villages also attended the

Page 120 of 198

Page 122: Quarterly Progress Report - Jan-March 2013

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Grama Sabhas. The details of the district wise Grama Sabhas coordinated by the field staff (Social) were as follows:

GRAMA SABHAS FOR CSMMWC IN GUNTUR Dist.,Date Mandal Gramasabhas Remarks

14-03-2013 Nizampatnam

1) Harbour of Nizampatnam2) Nakshatra Nagar3) Sanjeevanagar4) Fishermen colony5) Near MRO office6) Padamativeedhi

14-03-2013 Repelle 7) Mollagunta of Katta8) Lankavanidibba

GRAMA SABHAS FOR CSMMWC IN WEST GODAVARI Dist.,Date Mandal Gramasabhas Remarks

20-03-2013 Narsapur

1) Sardupallipalem

Secretary elected unanimously

2) Chinmyavani Lanka3) Pedamaghavani Lanka4) Veemuladeevi (East)

20-03-2013 Mogalturu 5) Intheru6) Pedathadika

GRAMA SABHAS FOR CSMMWC IN KRISHNA Dist.,Date Mandal Gramasabhas Remarks

16-03-2013&

21-03-2013Bandar

1) Poletitippa

Secretary elected unanimously

2) Gilakaladindi3) Pedapatnam-I4) Tallapalem5) V. Kanuru6) Kammavari Cheruvu7) Pallitammalapalem

18-03-2013 Kruthivennu 8) Intheru Secretary elected unanimously9) Pedathadika

GRAMA SABHAS FOR CSMMWC IN EAST GODAVARI Dist.,Date Mandal Gramasabhas Remarks

25-03-2013 Thondangi 1) Avulamanda Secretary elected unanimously2) Laxmanudipeta

Page 121 of 198

Page 123: Quarterly Progress Report - Jan-March 2013

Page 122 of 198

Page 124: Quarterly Progress Report - Jan-March 2013

Page 123 of 198

Page 125: Quarterly Progress Report - Jan-March 2013

Page 124 of 198

Page 126: Quarterly Progress Report - Jan-March 2013

Page 125 of 198

Page 127: Quarterly Progress Report - Jan-March 2013

Page 126 of 198

Page 128: Quarterly Progress Report - Jan-March 2013

Page 127 of 198

Page 129: Quarterly Progress Report - Jan-March 2013

Page 128 of 198

Page 130: Quarterly Progress Report - Jan-March 2013

Page 129 of 198

Page 131: Quarterly Progress Report - Jan-March 2013

Page 130 of 198

Page 132: Quarterly Progress Report - Jan-March 2013

Page 131 of 198

Page 133: Quarterly Progress Report - Jan-March 2013

Page 132 of 198

Page 134: Quarterly Progress Report - Jan-March 2013

Page 133 of 198

Page 135: Quarterly Progress Report - Jan-March 2013

Page 134 of 198

Page 136: Quarterly Progress Report - Jan-March 2013

Page 135 of 198

Page 137: Quarterly Progress Report - Jan-March 2013

Page 136 of 198

Page 138: Quarterly Progress Report - Jan-March 2013

Page 137 of 198

Page 139: Quarterly Progress Report - Jan-March 2013

Page 138 of 198

Page 140: Quarterly Progress Report - Jan-March 2013

Page 139 of 198

Page 141: Quarterly Progress Report - Jan-March 2013

Page 140 of 198

Page 142: Quarterly Progress Report - Jan-March 2013

Page 141 of 198

Page 143: Quarterly Progress Report - Jan-March 2013

Page 142 of 198

Page 144: Quarterly Progress Report - Jan-March 2013

Page 143 of 198

Page 145: Quarterly Progress Report - Jan-March 2013

Page 144 of 198

Page 146: Quarterly Progress Report - Jan-March 2013

PM-TPQA-NCRMP Inspection of Runku Cyclone shelterin Srikakulam District. Stilt floor Slab Centering andreinforcement work is in progress.

PM-TPQA-NCRMP Inspection of Runku Shelter inSrikakulam District. Slab centering verification.

PM-TPQA-NCRMP Inspection of Runku shelter inSrikakulam District. Verification slab Reinforcement .

PM-TPQA-NCRMP Inspection of Runku Shelter inSrikakulam District. Slab centering verification.

Page 145 of 198

Page 147: Quarterly Progress Report - Jan-March 2013

DPM-TPQA-NCRMP Inspection of Runku cyclone shelterin Srikakulam District. Verification of Steps.

PM-TPQA-NCRMP Inspection of Runku Shelter inSrikakulam District. Slab centering verification at Beamand column junction.

PM-TPQA-NCRMP Inspection of Runku shelter inSrikakulam District. Verification slab Reinforcement .

PM-TPQA-NCRMP Inspection of Runku shelter inSrikakulam District. Verification slab Reinforcement .

Page 146 of 198

Page 148: Quarterly Progress Report - Jan-March 2013

Patimeeda Cyclone shelter in VisakhapatnamDistrict. TPQA inspection on 09-01-2013.

Reinforcement spacing checking.

Reinforcement spacing checking.

Reinforcement spacing checking.

Reinforcement spacing checking.

Page 147 of 198

Page 149: Quarterly Progress Report - Jan-March 2013

Patimeeda Cyclone shelter in VisakhapatnamDistrict. TPQA inspection on 09-01-2013.

Concrete temperature checking

Slump checking

Slump checking

Cube casting

Page 148 of 198

Page 150: Quarterly Progress Report - Jan-March 2013

Patimeeda Cyclone shelter in VisakhapatnamDistrict. TPQA inspection on 30-01-2013.

Site view

First floor de shuttering work is in progress

Site view

Page 149 of 198

Page 151: Quarterly Progress Report - Jan-March 2013

NCRMP,TPQA inspection of Road Connecting R&BRoad through Voturu Village in SPSR Nellore District

on 20.12.2012-View of BT layer

View of BT layer

View of BT layerView of BT layer at curve location

Page 150 of 198

Page 152: Quarterly Progress Report - Jan-March 2013

NCRM-TPQA inspection of Providing BT road to Peda PannamGadu in Tada Mandal of Nellore width checking

View of WBM Gr-III layer

Volumetric analysis for WBM Gr-III layer Thickness checking for WBM Gr-III layer

Page 151 of 198

Page 153: Quarterly Progress Report - Jan-March 2013

Gradation for WBM Gr-III layerGradation for WBM Gr-III layer

Gradation for WBM Gr-III layer Thickness checking for WBM Gr-III layer

Page 152 of 198

Page 154: Quarterly Progress Report - Jan-March 2013

Page 153 of 198

Page 155: Quarterly Progress Report - Jan-March 2013

Page 154 of 198

Page 156: Quarterly Progress Report - Jan-March 2013

Page 155 of 198

Page 157: Quarterly Progress Report - Jan-March 2013

Page 156 of 198

Page 158: Quarterly Progress Report - Jan-March 2013

Page 157 of 198

Page 159: Quarterly Progress Report - Jan-March 2013

Page 158 of 198

Page 160: Quarterly Progress Report - Jan-March 2013

Page 159 of 198

Page 161: Quarterly Progress Report - Jan-March 2013

Page 160 of 198

Page 162: Quarterly Progress Report - Jan-March 2013

Page 161 of 198

Page 163: Quarterly Progress Report - Jan-March 2013

Page 162 of 198

Page 164: Quarterly Progress Report - Jan-March 2013

Page 163 of 198

Page 165: Quarterly Progress Report - Jan-March 2013

Page 164 of 198

Page 166: Quarterly Progress Report - Jan-March 2013

Page 165 of 198

Page 167: Quarterly Progress Report - Jan-March 2013

Page 166 of 198

Page 168: Quarterly Progress Report - Jan-March 2013

Page 167 of 198

Page 169: Quarterly Progress Report - Jan-March 2013
Page 170: Quarterly Progress Report - Jan-March 2013
Page 171: Quarterly Progress Report - Jan-March 2013
Page 172: Quarterly Progress Report - Jan-March 2013
Page 173: Quarterly Progress Report - Jan-March 2013
Page 174: Quarterly Progress Report - Jan-March 2013

DPM-TPQA-NCRMP Inspection of Runku Cyclone shelterin Srikakulam District on 11-03-2013. Stilt floor Slab

Completed.

DPM-TPQA-NCRMP Inspection of Runku Shelter inSrikakulam District. Columns reinforcement verification.

PM-TPQA-NCRMP Inspection of Runku Shelter inSrikakulam District. Verifying the alignment of First floor

columns.

PM-TPQA-NCRMP Inspection of Runku Shelter inSrikakulam District. Verifying the alignment of First floor

columns.

Page 175: Quarterly Progress Report - Jan-March 2013

DPM-TPQA-NCRMP Inspection of Kollipadu Cycloneshelter in Srikakulam District. First floor Slab Completed.

DPM-TPQA-NCRMP Inspection of Kollipadu Shelter inSrikakulam District. First floor curing work is in progress.

DPM-TPQA-NCRMP Inspection of Kollipadu Shelter inSrikakulam District. Verifying the dimensions of First floor

steps.

DPM-TPQA-NCRMP Inspection of Kollipadu Shelter inSrikakulam District on 11-03-2013. Curing for first floor

slab is in progress.

Page 176: Quarterly Progress Report - Jan-March 2013
Page 177: Quarterly Progress Report - Jan-March 2013
Page 178: Quarterly Progress Report - Jan-March 2013

DPM, TPQA inspection on 14-03-2013

FDD testing of GSB

DPM, TPQA inspection on 14-03-2013

FDD testing of GSB

Page 179: Quarterly Progress Report - Jan-March 2013
Page 180: Quarterly Progress Report - Jan-March 2013
Page 181: Quarterly Progress Report - Jan-March 2013
Page 182: Quarterly Progress Report - Jan-March 2013
Page 183: Quarterly Progress Report - Jan-March 2013
Page 184: Quarterly Progress Report - Jan-March 2013
Page 185: Quarterly Progress Report - Jan-March 2013
Page 186: Quarterly Progress Report - Jan-March 2013
Page 187: Quarterly Progress Report - Jan-March 2013
Page 188: Quarterly Progress Report - Jan-March 2013
Page 189: Quarterly Progress Report - Jan-March 2013
Page 190: Quarterly Progress Report - Jan-March 2013
Page 191: Quarterly Progress Report - Jan-March 2013
Page 192: Quarterly Progress Report - Jan-March 2013
Page 193: Quarterly Progress Report - Jan-March 2013
Page 194: Quarterly Progress Report - Jan-March 2013
Page 195: Quarterly Progress Report - Jan-March 2013

Text Box

Page 196: Quarterly Progress Report - Jan-March 2013

Electrical PVC Pipe laying in slab at Cyclone ShelterPadaraghavulapeta in Uppalagutham Mandal, EG Dt

Electrical PVC Pipe laying in slab at Cyclone ShelterPadaraghavulapeta in Uppalagutham Mandal, EG Dt

Electrical PVC Pipe laying in slab at Cyclone Shelter Kollipaduin Santhabommali Mandal in Srikakulam District

Electrical PVC Pipe laying in slab at Cyclone Shelter Kollipaduin Santhabommali Mandal in Srikakulam District.

Page 197: Quarterly Progress Report - Jan-March 2013

Wall chipping for Electrical Pipe laying at Cyclone ShelterPatimeeda in Nakkapalli Mandal of Visakhapatnam District

3 phase Distribution board at Cyclone Shelter Avulamanda inThondangi Mandal, EG Dist.

6 Amps Lighting Switch board at Cyclone ShelterGajapathinagaram in Payakaraopeta Mandal of VSKP District

Distribution Board at Cyclone Shelter Ratnayampeta inPayakaraopeta Mandal of Visakhapatnam District.

Page 198: Quarterly Progress Report - Jan-March 2013

Electrical wiring in progress at Cyclone Shelter Ratnayampetain Payakaraopeta Mandal of Visakhapatnam District

Colour code for 3 phase wiring at Cyclone ShelterRatnayampeta in Payakaraopeta Mandal of Visakhapatnam Dt

Earth Continuity Testing at Cyclone Shelter ThopupalemKanuparthy in N G Padu Mandal, Ongole District

Earth Electrode Resistance Testing at Cyclone ShelterThopupalem Kanuparthy in N G Padu Mandal, Ongole District