Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane

Transcript of Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World...

Page 1: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Quality Tools for Construction Projects

By

Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS

World Quality CongressMumbai

June 27-28, 2014,

© 2014 by Rumane

Page 2: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Topics to be Discussed

Introduction Principles of Construction Quality Quality Tools Applicable Tools

Study Stage Design Stage Construction Stage

Page 3: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Introduction

Quality is a universal phenomenon, which has been a matter of great concern throughout the recorded history of human kind.

It was always the determination of builders and makers of the products to ensure that their products meet the customer’s desire.

With advent of globalization and competitive market, the emphasis on quality management has increased.

Quality has become the most important single factor for the survival and success of the companies.

Page 4: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Introduction

Customer demands for better products and services at the lowest possible costs have put tremendous pressure on organizations to improve the quality of products, services and processes to compete in the market and improve business results.

It became important that construction projects be more qualitative, competitive, and economical to meet owner’s expectations.

Page 5: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Construction Projects

What is Construction Project? Construction is translating Owner’s goals and objectives,

by the contractor, to build the facility as stipulated in the contract documents, plans, specifications within budget and on schedule.

Construction projects are custom oriented and custom design having specific requirements set by the customer/owner to be completed within finite duration and assigned budget.

Page 6: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Quality Definition (Construction Projects)

What is Construction Quality? The definition of quality for construction projects is

different to that of manufacturing or services industries as the product is not repetitive, but unique piece of work with specific requirements.

Quality in construction project is not only the quality of product and equipment used in the construction of facility, it is the total management approach to complete the facility.

TABLE 1 illustrates Principles of Construction Quality.

Page 7: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Principles of Construction Quality (TABLE 1)

Principle Construction Project’s Principle

Principle 1 Owner, Consultant, Contractor are fully responsible for application of quality management system to meet defined scope of work in the contract documents

Principle 2 Consultant is responsible to provide Owner's requirements explicitly and clearly defining in the contract documents

Principle 3 Method of payments (Work progress, material, equipment..etc.) to be clearly defined in the contract documents. Rate analysis of BOQ or BOM item to be agreed before signing of contract

Principle 4 Contract documents should include a clause to settle the dispute arising during construction stage

Principle 5 tendering/bidding stage and submit his proposal taking into consideration all the requirements specified in the contract documents

Page 8: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Principles of Construction Quality (TABLE 1)-Contd

Principle Construction Project’s Principle

Principle 6 Contractor shall follow an agreed upon quality assurance and quality control plan Consultant shall be responsible to oversee the compliance with contract documents and specified standards

Principle 7 Contractor is responsible to provide all the resources, manpower, material, equipment.etc. to build the facility as per specifications

Principle 8 Contractor shall follow the submittal procedure specified in the contract documents

Principle 9 Each member of project team should participate in all the functional areas to continuously improve quality of project

Page 9: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Principles of Construction Quality (TABLE 1)-Contd

Principle Construction Project’s Principle

Principle 10 Contractor is responsible to construct the facility as specified and use the material, products, equipment, and methods which satisfy the specified requirements.

Principle 11 Contractor to build the facility as stipulated in the contract documents, plan, specifications within budget and on schedule to meet owner's objectives

Principle 12 Contractor should perform the works as per agreed upon construction program and handover the project as per contracted schedule.

Page 10: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Quality in Construction Project

Quality management in construction projects is different to that of manufacturing. Quality of construction projects can be defined as follows:

• Construction Project quality is fulfillment of owner’s needs as per defined scope of works within a budget and specified schedule to satisfy owner’s/user’s requirements.

• The phenomenon of these three components can be called as “Construction Project Trilogy” and is illustrated in Figure QCP.1

Page 11: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Quality in Construction Project (Figure QCP.1)

DEFINEDSCOPE

BUDGETSCHEDULE

Figure QCP.1Construction Project Triology

QUALITY

Page 12: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Quality Tools

• What is Quality Tools?• Quality tools are the charts, check sheets, diagrams,

graphs, techniques, and methods which are used to create an idea, engender planning, analyze the cause, analyze the process, foster evaluation and create a wide variety of situations for continuous quality improvement.

• What is the befit of applying Quality Tools?• Applications of tools enhance chances of success and help

maintain consistency, accuracy, increase efficiency and process improvement.

Page 13: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Quality Tools

• There are several types of tools, techniques, methods, in practice, which are used as quality improvement tools and have variety of applications in manufacturing and process industry.

• However all of these tools are not used in construction projects due to the nature of construction projects which are customized and non repetitive.

Page 14: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Quality Tools

• How many categories of Quality Tools are used in Construction Projects?

• There are ten most common broader categories of Quality Management Tools used in Construction Projects.

• Each of these categories have various types of tools.• Some of these quality management tools that are most

commonly used in construction industry are listed under following broader categories (TABLE 2);

Page 15: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Categories of Quality Tools (TABLE 2)

Categories Serial Number

Classic Quality Tools 1

Management and Planning Tools 2

Process Analysis Tool 3

Process Improvement Tools 4

Innovation and Creative Tools 5

Lean Tools 6

Cost of Quality 7

Quality Function Deployment 8

Six Sigma 9

Triz 10

Page 16: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Development of Construction Projects

Construction project development has three major elements. These are;

Study Design Construction

As the project develops, more information and specifications are developed.

TABLE 3 Illustrates various activities during Study Stage

Page 17: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Study Stage (TABLE 3)

Element Description

Problem Statement/Need Identification

Define project needs, goals, objectives

Need Assessment Identification of needs

Prioritization of needs

Leveling of needs

Deciding what needs to be addressed

Need analysis Perform project need analysis/study to outline the scope of issues to be considered in the planning phase.

Feasibility Study Technical studies, economics assessment, financial assessment, market demand, environmental and social assessment.

Establish Project objectives/Goals

Scope, time, cost, quality.

Page 18: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Study Stage (TABLE 3)-Contd

Element Description

Identify project delivery system

Establish how the participants, owner, designer (A/E), and contractor will be involved to construct the project/facility.(Design/Build/Bid, Design/Build, Guaranteed Maximum Price, CM type, PM type, BOT, Turnkey..etc)

Identify project team Select Designer (A/E) firm if Design/Bid/Build type of contract system is selected. Select other team members based on project delivery system requirements.

Identify alternatives (Conceptual alternatives)

Identify alternatives based on a predetermined set of performance measures.

Preliminary resources

Estimate resources

Preliminary schedule Estimate the duration for completion of project/facility

Page 19: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Study Stage (TABLE 3)-Contd

Element Description

Preliminary financial implications

Preliminary budget estimates of total project cost (life cycle cost) on the basis of any known research and development requirements. This will help arrange the finances. (funding agency).

Authorities clearance Identify issues, sustainability, impacts, project constraints and potential approvals (environmental authorities, permits) required so that subsequent design and authority approval processes.

Select alternatives Select preferred alternative.

Project initiation Project charter

Page 20: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Development of Construction Projects

TABLE 4 Illustrates various activities during Design Stage

Page 21: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Design Stage (TABLE 4)

Element Description

Develop concept design

Report, drawings, models, presentation

Project planning Prepare project plan

Schematic design Preliminary design, value engineering

Design development Detailed design

Construction documents

Construction contract documents

Page 22: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Development of Construction Projects

TABLE 5 Illustrates various activities during Construction Stage

Page 23: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Construction Stage (TABLE 5)

Element Description

Bidding/Tendering Bidding package and request for proposal.

Contractor selection Most competitive bidder

Construction Contractor to execute contracted works.

Monitoring & Control Monitor and control scope, schedule, cost, quality, risk, procurement of the project.

Commissioning and Handover

Testing, commissioning and handover.

Project close out Close the project.

Page 24: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Applicable Tools (Study Stage)

Study Stage

Some of the Tools which are useful for application during Study Stage are as follows; 5W2H (FIGURE 1) Need Analysis (TABLE 6) Brainstorming (FIGURE 2) Delphi Techniques (FIGURE 3)

Page 25: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

5W2H (FIGURE 1)

Serial Number

5W2H Related Analyzing Questions

1 Why New project

2 What What advantage it will have over other similar projects

3 Who Who will be the customer for this project

4 Where Where can we find market for the project

5 When When the project will be ready for use

6 How many How many such projects are in the market

7 How much How much market share we will have by this project

Page 26: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Need Analysis (TABLE 6)

Serial Number

Points to be considered for Need Analysis

1 Is the project in line with organization’s strategy/strategic plan and mandated by management in support of a specific objective?

2 Is the project a part of mission statement of the organization?

3 Is the project a part of vision statement of the organization?

4 Is the need mandated by regulatory body?

5 Is the need for meeting government regulations?

6 Is the need to fulfill the deficiency/gap of such type of project(s) in the market?

7 Is the need created to meet market demand

Page 27: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Need Analysis (TABLE 6)-Contd

Serial Number

Points to be considered for Need Analysis

8 Is the need to meet the research and development requirements?

9 Is the need for technical advances?

10 Is the need generated to construct a facility/project which is innovative in nature?

11 Is the need aims to improve the existing facility?

12 Is the need a part of mandatory investment?

13 Is the need to develop infrastructure?

14 Is the need will serve the community and fulfill social responsibilities?

Page 28: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Need Analysis (TABLE 6)-Contd

Serial Number

Points to be considered for Need Analysis

15 Is the need created to resolve specific problem?

16 Is the need will have effect on environment?

17 Is the need has any time frame to implement?

18 Is the need has financial constraints?

19 Is the need has major risk?

20 Is the need within capability of the owner/client, either alone or in cooperation with other organizations?

21 Is the need can be managed and implemented?

Page 29: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Need Analysis (TABLE 6)-Contd

Serial Number

Points to be considered for Need Analysis

22 Is the need realistic and genuine?

23 Is the need measurable?

24 Is the need shall be beneficial?

25 Is the need comply with environmental protection agency requirements?

26 Is the need comply with government’s health and safety regulations?

Page 30: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Brainstorming (FIGURE 2)

Identify Team

Members

Select Team

Members

Define the Problem or

Issue to Team

Members

Circulate Problem

Statement (Facilitator)

Explain Brainstorming

Rules )Facilitator (

General Ideas)Team

Members(

Record IdeasModify Ideas

Evaluate Ideas

Select Idea(s)

Implement Idea(s)

Point Scale Criteria

Highest Score

On White Board or Flip Chart

Checklist or Any other technique

No criticis

m

Free Flow of Ideas

Freewheel Thinking

Large Quantity of Ideas

Variety of

Ideas

Page 31: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Delphi Technique (FIGURE 3)

Identify/Select Subject Matter

Identify Team Members

having Expertise/Knowledge of the

Subject

Select Team Members/Panel of Experts

Circulate Questions to Team

Members

Response from Team Members

Summarize ResponseAccept

Idea(s)

Proceed with the

Idea(s)/Solution

Check for

Consensus

YESRe-circulate Feedback/

Answers to Team

Check for

Consensus

Iteration

Accept Idea(s)

Proceed with the Idea(s)/

Solution

NO

YES

NO

Page 32: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Applicable Tools (Design Stage)

Design Stage

Some of the Tools which are useful for application dusting Design Stage are as follows; PDCA DMADV Mistake Proofing Cost of Quality

Page 33: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

PDCA during Design(FIGURE 4)

Page 34: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Fundamental Objectives of DMADV (FIGURE 5)

1 Define—What is important?

Define the project goals and customer deliverables

2 Measure—What is needed?

Measure and determine customer needs and specifications

3 Analyze—How we fulfill?

Analyze process options and prioritize based on capabilities to satisfy customer requirements

4 Design—How we build it?

Design detailed process (es) capable of satisfying customer requirements

5 Verify—How do we know it will work?

Verify design performance capability

Page 35: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Mistake Proofing (FIGURE 6)

Serial Number

Items Points to be Considered to Avoid Mistakes

1 Information 1. Terms of Reference (TOR)

2. Client’s preferred requirements matrix

3. Data collection

4. Regulatory requirements

5. Codes and Standards

6. Historical Data

7. Organizational requirements

Page 36: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Mistake Proofing (FIGURE 6)-Contd

Serial Number

Items Points to be Considered to Avoid Mistakes

2 Mismanagement 1. Compare production with actual requirements

2. Interdisciplinary coordination

3. Application of different codes and Standards

4. Drawing size of different trades/specialist consultant (s)

3 Omission 1. Review and check design with TOR

2. Review and check design with client requirements

3. Review and check design with Regulatory requirements

Page 37: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Mistake Proofing (FIGURE 6)-Contd

Serial Number

Items Points to be Considered to Avoid Mistakes

3 Omission 4. Review and check design with Codes and Standards

5. Check for all required documents

4 Selection 1. Qualified team members

2. Available material

3. Installation method

Page 38: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Cost of Quality during Design Phase

Categories of Quality costs related to design phase of construction projects can be summarized as follows;

1.Internal Failure Costs

2.External Failure Costs

3.Appraisal Costs

4.Prevention Costs

Page 39: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Applicable Tools (Construction Stage)

Construction Stage

Some of the Tools which are useful for application dusting Construction Stage are as follows; DMAIC Networking Arrow Diagram Cost of Quality

Page 40: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Fundamental Objectives of DMAIC (FIGURE 7)

1 Define—What is important?

Define the project goals and customer deliverables

2 Measure—How are we doing?

Measure and determine current performance

3 Analyze—How we fulfill?

Analyze and determine root cause of the defects

4 Improve—What needs to be done?

Improve the process by permanently removing the defects

5 Control—How do we guarantee performance?

Control the improved process’s performance to ensure sustainable results

Page 41: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Networking Arrow Diagram (FIGURE 8)

A B C D

F

GH

E

Excavation Compaction Waterproofing Formwork

ReinforcementInstallation of Utilities

Concrete Casting

Page 42: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

PDCA during Execution(FIGURE 9)

Page 43: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Flow Diagram (FIGURE 10)

Approved shop drawing/

Approved composite drawing

Preparation of Related

Works

Site Co-

ordination

Quality Check by Contractor

Submit Checklist

Inspection by

Consultant

Approved Material

Proceed Next Activity

Functional Relationship

Approved

Not Approved

Page 44: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

Conclusion

Thus it can be summarized that with implementation of quality tools, qualitative, compitative and economical construction can be achieved.

Page 45: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.

THANKS to Publisher

This material is derived from the book titled;

“Quality Tools for Managing Construction Projects”

Author: Abdul Razzak Rumane

Publisher: CRC Press (A Taylor & Francis Group Company) Florida, USA

ISBN: 9781466552142

http://www.crcpress.com/product/isbn/9781466552142

Page 46: Quality Tools for Construction Projects By Dr. Abdul Razzak Rumane, PhD, FIE, FCQI, AVS World Quality Congress Mumbai June 27-28, 2014, © 2014 by Rumane.