Purpose - NZ Transport Agency · POPULATION GROWTH (2011-2031) 30,000 500,000 1,500,000-12 to -2...

8
NZ Transport Agency Page 1 Purpose This paper provides an update to the 2009 Wellington Northern Corridor Summary Statement. The update relates specifically to the context, outcomes, strategic benefits and the implementation plan required to complete the Wellington Northern Corridor. Information that has not changed from the 2009 summary statement has not been restated, allowing the update to concentrate on how the Wellington Northern Corridor has evolved since it was established, bringing individual network improvements together as a programme of work. Key updates The outcomes first identified in 2009 remain the same. This shows that the improvements selected in 2009 for the Wellington Northern Corridor were robust, standing up to the detailed work of the past four years. Investigations completed since 2009 have highlighted some outcomes that were not previously recognised, such as resilience and reliability improvements. These strengthen the overall regional benefits of the Wellington Northern Corridor, and demonstrate how it will reduce the personal, business, and regional economic impact problems that exist on the current SH1. In particular, due to the confirmation of route alignments, there is more confidence about the resilience of the Wellington Northern Corridor. Some sections provide alternative routes and structures will be designed to withstand stronger earthquakes. Recent investigations show that, with the Wellington Northern Corridor, morning peak period trips from Levin to Wellington will be 40 minutes shorter, compared to earlier forecasts of 35 minutes. In 2009 there was not enough detailed information to forecast travel time reliability or crash savings. Travel time reliability is expected to improve significantly due to increased capacity, eg Transmission Gully is expected to eliminate virtually all travel time variability between Linden and MacKays Crossing. The number of fatal and serious crashes is expected to reduce from 140 to 100 in the first five-year period after the Wellington Northern Corridor’s construction has been completed. The expected construction cost for the Wellington Northern Corridor is largely unchanged. In 2009, the forecasted costs were $2.6b and current costs are now $2.5b (both expressed in 2012 dollar terms). The Benefit Cost Ratio (BCR) for the Wellington Northern Corridor has been updated to 1.6 (it was 1.1 in 2009). The increase in the BCR is a result of additional transport and wider economic benefits (eg travel time reductions, an increase in agglomeration benefits) being identified. Various sensitivity tests on the updated BCR have been undertaken. These tests show that the BCR for the Wellington Northern Corridor has a range between 1.1 and 2.8. The BCR has also been calculated in accordance with the recent changes to the Economic Evaluation Manual (eg 6% discount rate and 40 year evaluation period), which apply to all transport projects. Wider economic benefits suggest the Wellington Northern Corridor will deliver 865 additional permanent jobs in the region, whereas previously 650 were estimated. To construct the Wellington Northern Corridor it is expected that up to 8,000 new construction jobs will be created, peaking in 2018 with 1,000 active jobs. The number of construction jobs was previously not estimated. Project Summary Statement

Transcript of Purpose - NZ Transport Agency · POPULATION GROWTH (2011-2031) 30,000 500,000 1,500,000-12 to -2...

Page 1: Purpose - NZ Transport Agency · POPULATION GROWTH (2011-2031) 30,000 500,000 1,500,000-12 to -2 growth-3 to 4% growth 5 to 12% growth 13 to 30% growth *Whangarei, Auckland & Tauranga

NZ Transport Agency Page 1

PurposeThis paper provides an update to the 2009 Wellington Northern Corridor Summary Statement. The update relates specifically to the context, outcomes, strategic benefits and the implementation plan required to complete the Wellington Northern Corridor.

Information that has not changed from the 2009 summary statement has not been restated, allowing the update to concentrate on how the Wellington Northern Corridor has evolved since it was established, bringing individual network improvements together as a programme of work.

Key updates• Theoutcomesfirstidentifiedin2009

remainthesame.Thisshowsthattheimprovementsselectedin2009fortheWellingtonNorthernCorridorwererobust,standinguptothedetailedworkofthepastfouryears.

• Investigationscompletedsince2009havehighlightedsomeoutcomesthatwerenotpreviouslyrecognised,suchasresilienceandreliabilityimprovements.ThesestrengthentheoverallregionalbenefitsoftheWellingtonNorthernCorridor,anddemonstratehowitwillreducethepersonal,business,andregionaleconomicimpactproblemsthatexistonthecurrentSH1.

• Inparticular,duetotheconfirmationofroutealignments,thereismoreconfidenceabouttheresilienceoftheWellingtonNorthernCorridor.Somesectionsprovidealternativeroutesandstructureswillbedesignedtowithstandstrongerearthquakes.

• Recentinvestigationsshowthat,withtheWellingtonNorthernCorridor,morningpeakperiodtripsfromLevintoWellingtonwillbe40minutesshorter,comparedtoearlierforecastsof35minutes.

• In2009therewasnotenoughdetailedinformationtoforecasttraveltimereliabilityorcrashsavings.

• Traveltimereliabilityisexpectedtoimprovesignificantlyduetoincreased

capacity,egTransmissionGullyisexpectedtoeliminatevirtuallyalltraveltimevariabilitybetweenLindenandMacKaysCrossing.

• Thenumberoffatalandseriouscrashesisexpectedtoreducefrom140to100inthefirstfive-yearperiodaftertheWellingtonNorthernCorridor’sconstructionhasbeencompleted.

• TheexpectedconstructioncostfortheWellingtonNorthernCorridorislargelyunchanged.In2009,theforecastedcostswere$2.6bandcurrentcostsarenow$2.5b(bothexpressedin2012dollarterms).

• TheBenefitCostRatio(BCR)fortheWellingtonNorthernCorridorhasbeenupdatedto1.6(itwas1.1in2009).TheincreaseintheBCRisaresultofadditionaltransportandwidereconomicbenefits(egtraveltimereductions,anincreaseinagglomerationbenefits)beingidentified.

• VarioussensitivitytestsontheupdatedBCRhavebeenundertaken.ThesetestsshowthattheBCRfortheWellingtonNorthernCorridorhasarangebetween1.1and2.8.

• TheBCRhasalsobeencalculatedinaccordancewiththerecentchangestotheEconomicEvaluationManual(eg6%discountrateand40yearevaluationperiod),whichapplytoalltransportprojects.

• WidereconomicbenefitssuggesttheWellingtonNorthernCorridorwilldeliver865additionalpermanentjobsintheregion,whereaspreviously650wereestimated.ToconstructtheWellingtonNorthernCorridoritisexpectedthatupto8,000newconstructionjobswillbecreated,peakingin2018with1,000activejobs.Thenumberofconstructionjobswaspreviouslynotestimated.

Project Summary Statement

Page 2: Purpose - NZ Transport Agency · POPULATION GROWTH (2011-2031) 30,000 500,000 1,500,000-12 to -2 growth-3 to 4% growth 5 to 12% growth 13 to 30% growth *Whangarei, Auckland & Tauranga

NZ Transport Agency Page 2 For more information, visit our website www.nzta.govt.nz

Ōtaki

Te Horo

LevinLake Horowhenua

O–taki River

Waikanae

Paraparaumu

Paekakariki

Raumati South

TASMAN SEA

Ka-piti Island

Pukerua Bay

Otaihanga

Waikanae River

Pauatahanui

Lake Wairarapa

Upper HuttRimutaka Hill

Featherston

Plimmerton

Paremata

Porirua

Linden

Cannons Creek

Waitangirua

Mana

Peka Peka

To Palmerston North

Grenada North

Petone

Lower Hutt

WELLINGTON Eastbourne

Kilbirnie

Hataitai

Kaiwharawhara

To Masterton

MacKays

Airport to Mt Victoria Tunnel section

Tunnel to Tunnel section

Terrace Tunnel improvements

Aotea Quay to Ngauranga section

Linden to MacKays section (Transmission Gully)

MacKays to Peka Peka section

Peka Peka to Ōtaki section

Ōtaki to Levin section

Existing State Highway

LEGEND

Wellington Northern Corridor (Wellington Airport to Levin)Roads of National Significance

Airport to Mt Victoria Tunnel section

Tunnel to Tunnel section– Basin Bridge– Buckle Street underpass– Inner City bypass improvements

Terrace Tunnel improvements

Aotea Quay to Ngauranga section

Linden to MacKays section (Transmission Gully)

MacKays to Peka Peka section

Peka Peka to Ōtaki section

Ōtaki to Levin section

N

Page 3: Purpose - NZ Transport Agency · POPULATION GROWTH (2011-2031) 30,000 500,000 1,500,000-12 to -2 growth-3 to 4% growth 5 to 12% growth 13 to 30% growth *Whangarei, Auckland & Tauranga

NZ Transport Agency Page 3

National context updates

The Roads of National Significance Programme was announced in 2009 and represents one of New Zealand’s biggest ever infrastructure investments. Since 2009 the Government has released the National Infrastructure Plan, Connecting New Zealand, Safer Journeys and its updated Government Policy Statement on Land Transport Funding, both of which support the programme.Fromnorthtosouth,theRoadsofNationalSignificanceare:

PuhoitoWellsford-SH1

CompletingtheWesternRingRoute,Auckland-SH16,SH18andSH20

VictoriaParkTunnel,Auckland-SH1(completed)

WaikatoExpressway-SH1

TaurangaEasternLink-SH2

WellingtonNorthernCorridor-SH1

ChristchurchMotorways–SH1,SH74andSH76

TheTransportAgencystartedworkonallsevenRoadsofNationalSignificance,andhasalreadycompletedone–theVictoriaParkTunnelinAuckland.

In2011,researchonthewidereconomicimpactsclarifiedthebenefitsassociatedwithimprovedbusinessoutputandproductivity(oftenasaconsequenceofbusinesseslocatedcloselytoeachother–otherwiseknownasagglomeration),imperfectcompetition(betterrelationshipsbetweencostsandrevenues),jobcreationandchanges(asaresultofimprovedaccesstolabourandmarkets),andthemethodsfortheirassessment.Thisprovidedgreaterclarityofthevalueofthesebenefits.

ThecompletedVictoriaParkTunnelproject

Page 4: Purpose - NZ Transport Agency · POPULATION GROWTH (2011-2031) 30,000 500,000 1,500,000-12 to -2 growth-3 to 4% growth 5 to 12% growth 13 to 30% growth *Whangarei, Auckland & Tauranga

NZ Transport Agency Page 4 For more information, visit our website www.nzta.govt.nz

Regional context updates

Population forecasts show that Wellington will remain the third largest metropolitan area in New Zealand. In 2013 the regional population was 471,300, increasing at 0.7% per year. By 2031, the population is forecast to increase to about 550,000.

WELLINGTON NELSON

BLENHEIM

PICTON

Tasman

Marlborough

75

% travels to Napier

25%

trav

els to

Well

ington

NEW PLYMOUTH

WANGANUI

NELSON

BLENHEIM

PICTON

NAPIER

HASTINGS

TAUPO GISBORNE

PALMERSTON NTH

Manawatu

Taranaki

Hawke’s Bay

Tasman

Marlborough

Buller

Wellington Northern Corridor

WELLINGTON

AIRPORT RAILWAYPORT

less than 2m tonnes

PORT

2-5m tonnes

SAFETY

Increased safety risk

VULNERABLE INFRASTRUCTUREFORESTRY FREIGHT

1-2m tonnes

6-7m tonnes

LEGEND

POPULATIONREGION POPULATION (2011)

POPULATION GROWTH (2011-2031)

30,000

500,000

1,500,000

-12 to -2 growth

-3 to 4% growth

5 to 12% growth

13 to 30% growth

*Whangarei, Auckland & Tauranga

import and export >5m tonnes p.a

>5m passengers

15% of timber exports

Wellingtoncontinuestodeveloparangeoftertiaryeducationandresearchinstitutions,includingthenewCallaghanInnovationandthreeexistingCrownResearchInstitutes.Asaconsequence,Wellingtonstillhasthehighestproportionofpeopleemployedinknowledge-intensiveservicesamongallofNewZealand’sregions.

EmploymentgrowthinWellingtonaveraged1.6%pabetween2000and2010comparedwith1.7%paoverthesameperiodforthenationaleconomy.WhilethisgrowthrateislowerthantheupperNorthIsland,WellingtonhasahighGDPpercapita-28%higherthanthenationalaverage.ThisreflectsWellington’s“nationaloffice”functionandthetypeofemploymentavailable.

Tourismisgrowing,withWellingtonrecordingthefourthhighestinternationalvisitorspend(andthirdhighestdomesticspend)ofanyregionin2012.ThisisexpectedtogrowwithWellingtonInternationalAirportforecastingthatpassengernumberswillincreasetoabout10.5millionby2030.

Wellingtonremainsanetimporteranddoesnotgeneratesignificantexportfreightduetothepresenceofmainlyserviceandknowledgebasedsectors.Throughfreight,however,isimportantasWellington’sgeographiclocationprovidesthehubforpeopleandfreightmovementsbetweentheNorthandSouthIslands.

CentrePort(PortsofWellington)isoneofthebusiestportsinNewZealandbecauseoftheCapital’sroleinfreight.Itsinfrastructure

enablesthemovementofapproximately11milliontonnesoffreightperannum.ThisvolumeissignificantlygreaterthanthemajorityofotherNewZealandports,withtheexceptionofPortsofAucklandandthePortofTauranga.

Centreport’sforecastincreaseinoperations,alongwiththegrowthfromothersectorsdescribedabove,willincreasepressureonthetransportnetwork,includingtheexistingSH1.

Since2009therehavebeensomenotablechangestothestrategicregional/localtransportpolicy/planningcontextthathaverecognisedthedevelopmentoftheWellingtonNorthernCorridor.Keychangesincludenewregionallandtransportstrategiesforboththe

Page 5: Purpose - NZ Transport Agency · POPULATION GROWTH (2011-2031) 30,000 500,000 1,500,000-12 to -2 growth-3 to 4% growth 5 to 12% growth 13 to 30% growth *Whangarei, Auckland & Tauranga

NZ Transport Agency Page 5

Regional context updates

Population forecasts show that Wellington will remain the third largest metropolitan area in New Zealand. In 2013 the regional population was 471,300, increasing at 0.7% per year. By 2031, the population is forecast to increase to about 550,000.

WellingtonandManawatu-Wanganuiregions,anewWellingtonRegionalPolicyStatementandanupdatetotheWellingtonRegionalStrategy.

Alsosince2009,aNetworkPlanfortheWellingtonNorthernCorridorhasbeendeveloped.ThisPlanconsidershoweachsectionconnectswiththewidertransportnetworkandwhatimprovementsareneededtomaketheWellingtonNorthernCorridoreffective.ThekeypurposeofthePlanistoensurethattheimprovementsconnectoptimallyandcomplementlocalroads,publictransportandotherlocalinfrastructure.

Existing SH1 issuesTheexistingSH1routeremainsvulnerabletoclosureeitherafterasignificantearthquake,tsunamiorstormevent,orduetootherunplannedeventssuchastrafficcrashesandbadweather.DetailedinvestigationscompletedforTransmissionGullyindicatethatfollowingalargeearthquakeononeofthemajorfaultlines,thecoastalroutecouldbeclosedforbetweenthreeandsixmonths-whereastheTransmissionGullyroutecouldbeclosedforlessthanamonth.

TrafficisoftencongestedalongtheexistingSH1routecausingdelaysandresultinginunreliabletraveltimes.Forexample,investigationsforTransmissionGullyshowthattheLindentoMacKayssectionsuffersfromtraveltimes50%longerinpeakperiodsthaninnon-peakperiods.

Furthermore(asdemonstratedbytherecentKiwiRAP1initiative)SH1hasapoorsafetyrecordwithoneofthehighestnumbersoffatalandseriouscrashesperkilometreinNewZealand,especiallythesectionbetweenParaparaumuandLevinwhichaverages0.23fatalandseriousinjurycrashesperkilometreperyear.Thisissimilartothe0.21resultforthesectionofSH2fromPokeno(SH1)toMangatarata(SH25)intheWaikatoandBayofPlentyregion.

CommuterstoWellingtonarewellcateredforwithrail,busandferryservices,togetherwiththeroadnetwork.Theseservicesandnetworksgenerallyoperateatcapacityduringthepeakcommutingperiods.Thedisruptionstothetransportnetworkfromtheweathereventsinmid2013showedthedisruptiontopeopleandbusinessproductivitythatcanbecausedbyonlyhavingafewalternativeroutestoandfromWellingtonCity.

WellingtonInternationalAirport–TheAirport’sMasterPlan(2010)forecastsdomesticandinternationalpassengerswillgrowtoabout9million

and1.5millionrespectivelyby2030.

1NZRoadAssessmentProgramme.ItisapartnershipbetweentheNZAutomobileAssociation,NZTransportAgency,MinistryofTransport,ACCandNZPolicewithapurposeofanalysingtheroadsafetyofthestatehighwaynetwork.

Page 6: Purpose - NZ Transport Agency · POPULATION GROWTH (2011-2031) 30,000 500,000 1,500,000-12 to -2 growth-3 to 4% growth 5 to 12% growth 13 to 30% growth *Whangarei, Auckland & Tauranga

NZ Transport Agency Page 6 For more information, visit our website www.nzta.govt.nz

Outcomes

Increased productivity and output indicators are shown below for the Transport Agency’s standard 40 year economic evaluation period. The Wellington Northern Corridor includes infrastructure that will endure far longer than this evaluation period and we can expect these impacts to last equally as long.

More efficient and reliable journeys

Traveltimesareexpectedtoreduceby40minutesfromLevintoWellingtonAirportin2031inbothdirectionsduringthepeakperiods.2

Significantreliabilityimprovementsareexpected.Forexample,TransmissionGullyisexpectedtoeliminatevirtuallyalltraveltimevariabilitybetweenLindenandMacKaysCrossing.

Safer journeys Thecombinednumberoffatalandseriouscrashesisexpectedtoreducefrom140to100inanyfiveyearperiodaftertheWellingtonNorthernCorridorhasbeencompleted.Inthefiveyearperiodbetween2008to2012therewere135fatalandseriouscrashes.

Increase in all traffic movements ThehighcapacityoftheWellingtonNorthernCorridorwillprovideforanadditional12,000vehiclesperdayatPoriruaand20,000vehiclesperdaysouthoftheWellingtonCBDby2031.

Effectiveness of Heavy Commercial Vehicle (HCV) movements

Traveltimesavingsofupto40minutesinpeakperiods.AlsotheWellingtonNorthernCorridorisaHighProductivityMotorVehicleroute–designedforlongerandheaviervehicles.

New and permanent jobs Increasedaccessibilityfromoutsideandwithintheregionisexpectedtoleadtonewemploymentfor865to3,700peopleasorganisationssetupnewplacesofemployment,andplanneddevelopmentsoccur.

Construction jobs About8,000constructionjobsareexpectedtobecreatedtodelivertheWellingtonNorthernCorridor.

Journey time reductionsEarlyworkontheAoteatoNgaurangasectionhasimprovedtraveltimereliabilityandprovidedtraveltimesavingsoftwominutes3inthepeakperiodbetweenthePetoneOverbridgeandtheTerraceTunnel.

Facilitating public transport, walking and cyclingTheWellingtonNorthernCorridorispartofamulti-modalapproachtomeetingtheWellingtonregion’sfuturetransportdemands.

Inadditiontoimprovingtheregion’sstatehighwaynetwork,theWellingtonNorthernCorridorwilldeliversignificantenhancementstotheregion’spublictransport,walkingandcyclingnetworks,forexample:

• TheBasinBridgeandMtVictoriaTunnelDuplicationimprovementswillfacilitateamoreefficientandreliablepublictransportspinethroughtheCBDtothesouthernandeasternsuburbs,and

• Upto31kmofnewwalkingandcyclingfacilitieswillbecreatedoncetheWellingtonNorthernCorridoriscompleted.MorefacilitiesmaybeidentifiedoncetheinvestigationsfortheŌtakitoLevinsectionhavebeenfullycompletedin2014.

2Thesourcesforthetraveltimesarethetransportmodelsforthesectionsofthecorridor.Therefore,thetotalisnotthetruetraveltimebutindicatesthescaleofthereductionacrossthecorridor.

3AnaverageasmeasuredbyfixedBluetoothreceivers.

Amenity outcomesAsaconsequenceofsignificantvolumesoftrafficrelocatingtothenewSH1,theWellingtonNorthernCorridorwillprovideimprovedamenityforthecentresandsettlementsonthewestcoastofthelowerNorthIsland.TherewillalsobereducedtrafficwithinWellingtonCity,includingalongthewaterfrontroads(egOrientalParade)andontheroadsaroundtheBasinReserve,providinganopportunityforbetteraccessandurbanamenity.

Page 7: Purpose - NZ Transport Agency · POPULATION GROWTH (2011-2031) 30,000 500,000 1,500,000-12 to -2 growth-3 to 4% growth 5 to 12% growth 13 to 30% growth *Whangarei, Auckland & Tauranga

NZ Transport Agency Page 7

Updated economics

The Wellington Northern Corridor has a funding assessment profile4 of “HHL”, which has not changed since 2009. It has retained a High strategic fit profile due to its alignment with government objectives and existing road operating conditions continue to demonstrate the need for the improvements. It has retained a High effectiveness profile due to its demonstrated ability to meet the needs of the regional network. It has a Low efficiency rating because the updated BCR of 1.6 remains between 1 and 2. This efficiency rating is typical for a major infrastructure project, and it is noted that over a 40 year period a $3b return is expected from the Wellington Northern Corridor.

CostsTheexpectedcosttocompletetheWellingtonNorthernCorridorisnow$2.5b(expressedin2012dollars).Thishasn’tchangedsignificantlyfromthe2009estimateof$2.4b(whichisequivalentto$2.6bin2012dollars).Thereishigherconfidenceinthesecostsastheyarebasedondetailedinvestigationsandconfirmedalignmentsforthenewsectionsofroad.Nevertheless,asensitivitytestoncostshowsthatusinga95thpercentilecost6theBCRwouldbe1.3.OthersensitivitytestsshowthattheBCRrangesbetween1.1and2.8.

In2009,anestimateofagglomerationbenefitswasprovided,however,itonlyconsideredtheWellingtonurbanarea.ThecurrentappraisalnowconsiderstheareaasfarnorthasŌtaki.AgglomerationbenefitsarenotevaluatedbeyondŌtakibecauseemploymentintheareasneartheWellingtonNorthernCorridorbeyondthispointdoesnotmeettherequiredcriteriasetoutintheresearch.FortheWellingtonNorthernCorridortheagglomerationbenefitsareestimatedat$410mpresentvalue.

In2009WiderEconomicBenefits(WEBs)estimatesweremadeforthetwobenefittypeswhereevaluationmethodshadbeenfirmlyestablished:agglomerationandlabourdemand.Noallowancewasmadeforimperfectcompetitionorlaboursupplyimpacts.TheestimatemadefortheamountofnewemploymentresultingfromtheimprovedaccessibilityprovidedbytheWellingtonNorthernCorridorwasbasedontwo

factors:theamountofexistingemploymentandresultsfromagglomerationmodelling.Forthecurrentanalysisthebenefitshavebeenestimatedonthebasisoftheproportionsoftheexistinglabourforceonly.Thisprovidesamoretransparentapproachtotheirassessment.Inlinewithcurrentadvice,thelabourdemandbenefitsarebasedonthetaxwedgegeneratedbynewemploymentratherthanthefullincreaseinGDP.In2009thefullGDPofnewlabourwasassumed.

Usingcurrentadvice,865additionaljobsareestimatedtobegeneratedoncompletionoftheWellingtonNorthernCorridor,resultinginbenefitsof$800mpresentvalue.Thisissimilartothe$715mpresentvalueestimatedin2009,thereforeitdoesnothaveamaterialimpactontheBCR,butassistswithbetterunderstandingofthebenefitsandprovidesusefulinformationformonitoringpurposes.

4Thefundingassessmentprofileisthebasisforcomparisonandprioritisationwithotheractivitiesnationally.Ingeneral,activitieswithhigherassessmentprofileswillbeconsideredaheadofthosewithlowerprofilesforinclusionintheNLTPandforNZTAinvestment.

5TheBCRshavebeencalculatedinaccordancewiththeNZTA’sEconomicEvaluationManual.ItisnotedthatthebenefitsoftheWellingtonNorthernCorridorarenowevaluatedovera40-yearperiodratherthana30-yearperiodasundertakenin2009.

6Thatis,ifaprojectwascompleted20times,onewouldexpecttheout-turncosttocomewithinthisvalueon19ofthe20occasions.

TheBCRs5fortheWellingtonNorthernCorridor,measuringthedirecttransportbenefitsarisingfromimprovementsrelativetocosts,areasfollows:

Discount Rate BCR without WEBs BCR including WEBS

6% 1.6 1.7

SensitivityTestsonDiscountRate

8% 1.2 1.4

4% 2.2 2.3

Page 8: Purpose - NZ Transport Agency · POPULATION GROWTH (2011-2031) 30,000 500,000 1,500,000-12 to -2 growth-3 to 4% growth 5 to 12% growth 13 to 30% growth *Whangarei, Auckland & Tauranga

Website: www.nzta.govt.nz/projects/wellington-northern-corridor/index.html

Contact us

Delivery programmeThedeliveryprogrammeforeachsectionoftheWellingtonNorthernCorridorisshownbelow.

Section Description Completion Date

Airport to Mt Victoria Tunnel (2 km) DuplicationoftheMtVictoriaTunnel,andwideningofRuahineStreetandWellingtonRoad

2022

“Tunnel to Tunnel” (3 km) AbridgeonthenorthernsideoftheBasinReserve,anunderpassforBuckleStreet(aspartoftheNationalWarMemorialPark)andimprovementstotheexistingInnerCityBypass

2017

Terrace Tunnel improvements (3 km) Includestunnelduplication 2024

Aotea Quay to Ngauranga (4 km) Useofexistingmotorwayshouldersasa“fourthlane”,andtheimplementationofanewtrafficmanagementsystem

2022

Ngauranga to Linden AlinkroadbetweenPetone(SH2)andGrenada(SH1)maybedevelopedbyeithertheNZTAorlocalcouncilsifitisdeterminedthatitwilldeliverbenefitstothesectionofSH1betweenNgaurangaandLindenand/ortoSH2betweenNgaurangaandPetone

2023

Linden to MacKays (Transmission Gully) (27 km) Four-laneexpresswaystandard7fromnorthWellingtontoMacKaysCrossing

2020

MacKays to Peka Peka (16 km) Four-laneexpresswaystandardfromMacKaysCrossingtoPekaPeka

2018

Peka Peka to Ōtaki (15 km) Four-laneexpresswaystandardfromPekaPekatoŌtaki 2020

Ōtaki to Levin (approx 30 km) AphasedupgradeoftheexistingSH1tofour-lanesovertime.Firstphase(tobecompleted2019-2024)includeswidening,improvedpassingopportunitiesandupgradestonarrowbridgesandkeyintersections.Priortothisphase,minorsafetyimprovementsarealsobeingconsidered

2024

7Expresswaysaredualcarriagewaysthatallowmotoriststodriveatspeedsofupto100km/h.Theyaredesignedtobestraighterandflatterthanotherroads.Forsafetyreasons,trafficineachdirectionisseparatedbyacentralbarrierorstripofland.Afour-laneexpresswayallowsforhighervolumesofthroughtrafficthancanbeaccommodatedbyatwo-laneroad.Providingtwolanesineachdirectionalsoallowsfast-movingtraffictoovertakeslower-movingvehicles.Accessfromlocalroadstotheexpresswayisrestrictedtoreducetheriskofcrashesandallowmoreconsistenttraveltimes.Whereaccessisprovided,thisusuallytakestheformofaninterchange.