Purple Line Extension Section 2 Community Meeting

20
Purple Line Extension Section 2 Community Meeting 1 February 9, 2017

Transcript of Purple Line Extension Section 2 Community Meeting

Purple Line Extension

Section 2

Community Meeting

1

February 9, 2017

Agenda

• Project Overview and Schedule

• Memorandum of Agreement (MOA)

• Advanced Utility Relocation

• Contact Information

• Q&A

2

Purple Line Extension Project Alignment

3

Purple Line Extension Project Status

Section 1 Alignment

5

Section 2 Alignment

6

Wilshire/Rodeo Station

Century City/

Constellation

Station

Section 2 –Wilshire/Rodeo Station Area

7

Plan View Including Laydown Yards

Section 2 – Construction Process

• Relocation of Third Party Utilities

• Southern California Edison

• Southern California Gas

• AT&T

• Design-Build of Station and Tunnels

• Includes relocation of City Utilities

8

Section 2 - Metro’s Proposed Schedule

Purple Line Extension – Section 2

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026

Draft SEIS to be complete for public review

3rd Party Utility Relocation

Final SEIS to be complete

Demo Station Entrance*

Design-Builder Utility Relocation*

Piling and Decking*

Station Construction / Tunneling*

Open for Revenue Services

9

North Santa Monica Blvd Reconstruction

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026

Construction Schedule

*Dates and durations based on Metro’s Assumptions. Design Build Contractor may have different means and methods and may forecast different dates

Purpose of Memorandum of Agreement (MOA)

Ensure that the project complies with the standards and requirements of the City

and minimize the impact to the City residents and businesses.

10

MOA Focus Areas

• Allowable Work Hours and Workdays

• Construction Staging

• Traffic

• Parking

• Noise, Light and Dust Mitigation and Monitoring

• Independent Compliance Monitor for enforcement of permit conditions

• Business Mitigation Assistance

•Eat, Shop and Play Program (Metro)

•Business Interruption Fund (Metro)

•Business Mitigation Program (Metro)

•My Beverly Hills (BH Chamber)

• Tree removal and replacement

• Advance notification system

Section 2 MOA Development & Approval

• Input from community and key stakeholders

• Negotiations between the City and Metro

• City Council approval

• Metro Board of Directors approval

12

North Santa Monica Blvd Reconstruction

2017 2018

Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4

Construction

Third Party Utilities - Anticipated Schedule

Westside Purple Line Extension – Section 2

2017 2018

Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4

Southern California Edison (SCE) Q1 2017

Southern California Gas (SCG) Q2 2017

AT&T – Q4 2017

13

Section 2 Items coming to Council:

• Encroachment Permit to install temporary Sound Monitoring Equipment

• Permit application for Southern California Edison for the use of the public right-of-

way

Third Party Utilities - Relocation

14

15

• 28 construction work days

• Monday-Friday

• 9 am - 4 pm

• All business access

maintained

Reeves access

maintained with

1 lane

Alley access maintained

Maintain 2 lanes in each direction

Phase 1 – SoCal Edison Civil Work

16

Maintain 2 lanes in

each direction

Alley access maintained

• 22 construction work days

• Monday-Friday

• 9 am – 4 pm

• All business access

maintained

Reeves access

maintained

Phase 2 – SoCal Edison Civil Work

17

Maintain 2 lanes

in each direction

Single-lane Alley access

maintained

• 10 construction work days

• Monday-Friday

• 4 pm – 11 pm

• All business access

maintained

Phase 3 – SoCal Edison Civil Work

Section 2 – SoCal Edison Civil Work

NEXT STEPS

• Request City Council approval for permits associated with third party utilities

• First permit is for the Southern California Edison Civil work

• Planned power outages do not occur until SCE is ready to pull the new electrical cables into the newly installed underground infrastructure.

• Work with community to develop MOA

• Additional community meetings prior to future permits

• Individual outreach meetings with community stakeholders

18

Stay in Touch

City Webpage: www.beverlyhills.org/purpleline

Email: [email protected]

19

Phone:Metro 24-Hour Hotline: (213) 922-6934

Beverly Hills Info Line : (310) 285-2467

Beverly Hills Chamber of Commerce: (310) 248-1000

Nixle: Text BEVHILLS to 888777

@CityofBevHills /CityofBeverlyHills

Workshop

Station 2

Section 2 overallMetro Representatives are available to also answer questions about:

• Supplemental Environmental Impact Statement (SEIS) Status

• Property Acquisition

20

Station 1

Focus on details of SoCal Edison civil work