Purple Line Extension Section 2 Construction Community Meeting February 20, 2020

Transcript of Purple Line Extension · The PLE project team is working to deliver the project consistent with...

Page 1: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Purple Line ExtensionSection 2 Construction Community Meeting February 20, 2020

Page 2: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Agency News

2

Metro is growing, and that's great news for LA because we have big plans for new rail and busway lines in the coming years

A temporary transitional naming system will help riders connect the letter to the color while we update customer information

Page 3: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Agenda

> Wilshire/Rodeo Station > Staging Yards> Utility Work> N Cañon Closure> Piling> Decking> Geotechnical

Instrumentation

3

> Century City/Constellation Station> Advance Utility Relocation (AUR)> Constellation Blvd. Full Closure

Extension> Tunnel Boring Machine Launch> Water Line Relocation> Piling> Decking

> Business Interruption Fund (BIF)> #EatShopPlay #BeverlyHills #Century

City

Page 4: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Purple Line ExtensionProject Alignment

4

Page 5: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Sections 1, 2 & 3 Status

5

Forecasted Schedule

Section Section 1 Section 2 Section 3

Length 3.92 Miles 2.59 Miles 2.56 Miles

New Stations Wilshire/La Brea

Wilshire/Fairfax

Wilshire/La Cienega

Wilshire/Rodeo

Century City/

Constellation

Westwood/UCLA

Westwood/VA

Hospital

Pre-Construction

Activities

2014 – 2015 2016 – 2018 2018 – 2019

Construction 2015 – 2023 2018 – 2025 2019 – 2026

Operations 2023 2025 2027

*Subject to change. The PLE project team is working to deliver the project consistent with Measure M

Page 6: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Purple Line ExtensionSection 2 Alignment

6

Page 7: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Section 2 Wilshire/Rodeo Station

Page 8: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Wilshire/Rodeo Station BoxStation Box

8

Rendering shows length of the underground station box on Wilshire Bl from Cañon Dr to Beverly Dr

Page 9: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Wilshire/Rodeo Station Schedule*As of February 2020, subject to change. Pending Council approval.

9

Page 10: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Driveway InstallationReeves Staging Yard

10

Where: Wilshire/Reeves Yard (on Reeves Dr)

Duration: 1 week

Start Date: Mid-February 2020*

Work Hours: Monday – Friday, 7am – 4pm

Traffic Control:

Sidewalk closures adjacent to yard from 7am – 4pm

Closure of southbound Reeves Dr from 9am – 4pm

For your safety, do not use streets as awalkway

*Dates subject to change

Page 11: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

11

Remaining Work: Installation of pedestrian push

buttons Sidewalk and street restoration Replacement of temporary traffic

poles with permanent poles

Duration: 4-6 weeks*

Work Hours: Monday – Friday,

9am – 4pm

> Parking meters were removed on Clifton Wy. Replacement parking available at 257 N Cañon Dr from 8am to 6pm

Traffic Signal Installation Clifton Wy/Crescent Dr

*Dates subject to change

Intersection of Clifton Wy/ Crescent Dr

Traffic Control:

Intermittent lane, crosswalk, and sidewalk closures will be required

Traffic Control Officers will be in place to mitigate traffic impacts

Pedestrian access will be maintained during construction

Page 12: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

N Cañon Drive Cul-de-SacThrough September 2021* *Dates subject to change

12

Page 13: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

N Cañon Drive Detour

Note: Wayfinding signage installed prior to closure

During work at Clifton Wy and N Crescent Dr, Clifton Wy between N Cañon Dr and N Crescent Dr becomes one way eastbound

Vehicles trying to access N Cañon Dr from Crescent Dr need to go to Brighton Wy

13

Page 14: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Pile Drilling InstallationThrough July 2020*

14

Pile installation includes: Drill 100-120 foot holes, place piles, and

back fill piles along the perimeter of the station box

All work occurs behind K-rail and/or traffic closures within station box area

Schedule Through July 2020* Piling to shift to south side of Wilshire Bl

in April 2020*

Work Hours 7 days a week 8am – 9pm, drilling 9pm – 11pm, non-drilling

*Dates subject to change

Need new pic

North side piling work on Wilshire Bl

Page 15: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Piling at Wilshire Bl/Beverly DrLane Reductions Outside K-rail

15

Duration: through April 2020*

Work hours in the Intersection Only (outside piling k-rail):

> Monday – Friday, 9am – 4pm

> Saturday – Sunday, 7am –10pm (non-drilling activities after 8pm)

Beverly Dr Lane Reduction:

One through lane open northbound and southbound during work hours

Pedestrian Control:

North crosswalk and west crosswalk will be closed at the intersection

Pedestrian detour will be provided

*Dates subject to change

Page 16: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

16

Pile Drilling InstallationPhotos of piling on north side of Wilshire Bl

Need new pic

Page 17: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Pile Drilling InstallationProtected sidewalk features wayfinding signage

17

Page 18: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Wilshire Bl Piling Set-upNorth Side Piling Set-up (October 2019 to April 2020*)

18Example of construction area with piling set-up on the north side of Wilshire Bl

Page 19: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Wilshire Bl Piling Set-upSouth Side Piling Set-up (April 2020 to July 2020*)

19Example of construction area with piling set-up on the south side of Wilshire Bl

Page 20: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Piling Plan

20

NORTH SIDE PILING:

> Start Date: October 21, 2019

> Anticipated End Date: April 2020*

> Traffic Lane Closures Required:

> Wilshire/Beverly Dr

> Alleys between N Crescent and N Beverly Dr

*Dates subject to change

SOUTH SIDE PILING:

> Anticipated Start Date: April 2020*

> Anticipated End Date: July 2020*

> Traffic Lane Closures Required:

> Wilshire/Beverly Dr

> Wilshire/Reeves Dr

> Wilshire/S Cañon Dr

North Side Piling(October 2019 to

April 2020)

South Side Piling

(April 2020 to July 2020)

Decking (Beginning

August 2020)

Page 21: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Santa Monica Bl Haul Route

21

Haul Routes on Wilshire Bland Santa Monica Bl

Page 22: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

DeckingBeginning August 2020*

22

Construction of a concrete deck, curb-to-curb on Wilshire Bl

Decking will serve as the temporary street surface

Metro will work closely with first responders on emergency access and safety

Duration: Anticipated 13 weekends

Work Hours: Full closure 8pm Friday through 7am Monday

Additional activities during decking closures:

Ground improvements, piling, temporary civil improvements, dewatering system installation and geotechnical instrumentation

Excavation for decking on Wilshire Bl near Hamilton Dr

Installing deck panels

*Dates subject to change

Page 23: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

23

Geotechnical InstrumentationInstallation

Instruments will be installed within the tunnel alignment and station box area to monitor ground movement, settlement and other geological conditions. These installations will be within the public right of way and within privately owned properties.

Duration: Ongoing

Work Hours:

> Weekdays: 7am – 4pm

> Weekends: 8am – 7pm (as needed)Example of geotechnical instrument installation in Century City

Page 24: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

24

Geotechnical InstrumentationInstallation

Locations: Wilshire Bl, Young Dr, Lasky Dr, S Moreno Dr, Charleville Bl, Spalding Dr

Traffic Control> Intermittent lane, sidewalk, and crosswalk, parking meter closures will be required

for this work within the area of Moreno Dr on the west, Wilshire Bl on the north, La Cienega on the east, and as far south as Charleville Bl

> Flaggers will be available at alleys> Two lanes in each direction will be maintained for day work on Wilshire Bl > One lane in each direction will be maintained on Young Dr, Lasky Dr , Charleville

Bl, Spalding Dr

Page 25: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Century City/Constellation Station

25

Page 26: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Century City/ConstellationStation Box

Rendering shows length of the underground station box on Constellation Bl from Century Park East to Avenue of the Stars

26

Page 27: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Century City/Constellation Station Schedule

27

*As of February 2020, subject to change.

Page 28: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Century City/ConstellationAdvanced Utility Relocation Schedule

28

*As of February 2020, subject to change

Page 29: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Construction Staging Yards1940, 1950, 2010, 2040 Century Park East

29

> Utility installation

> Horizontal drillings to check for underground obstructions

Work Hours:

> Monday – Friday

> 6am – 5pm and 7pm – 5am

Tunnel shaft excavation

Tunnel shaft excavation progressInstallation of tower crane foundation

Page 30: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

30

Constellation Bl Full Closure Through July 2020

> No Public Access for Tenants through Driveway> Limited Access for: Large Trucks, Deliveries, Construction, Trash, FedEx/UPS

> Flaggers will be present for access

Page 31: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Constellation Bl Launch BoxTunnel boring machine assembly

31

Launch box invert beneath Constellation Bl full closure

Page 32: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Launch of Tunnel Boring Machines

• Excavation Duration: Approx. 2 years

• Anticipated Launch: Beginning March 2020

• Extraction Location: Wilshire Bl/ La Cienega Bl

*Dates subject to change

Page 33: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Constellation Bl Water Line Relocation Between full closure and Solar Way

Work will be done during night hours in stages to minimize impact and maintain traffic accessibility. Relocation will begin east of AOS and move west toward Solar Way.

Anticipated Start Date: March 2020*

Duration: 2-3 months

Work Hours: Monday – Friday, 8pm – 6am

Traffic Control:

> Partial and full lane closures will be required on Constellation Bl and AOS

> Access to Craft valet will be maintained through work

33

*Dates subject to change

Page 34: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Pile Drilling Installation

Process of reinforcing the station box by drilling 70-100 ft holes, placing piles, and backfilling with concrete around perimeter of station box. All work occurs behind k-rail and/or lane closures.

> Anticipated Start Date: Spring/Summer 2020*

> Duration: 3-4 months

> Work Hours: 7 days a week, 7am – 4pm and 8pm – 6am

> Coordinating directly with Westfield Mall, Century Plaza Hotel, Century Park, Watt Plaza and JMB

34

*Dates subject to change

Page 35: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

35

Pile Drilling InstallationPhotos of launch box piling on Constellation Bl

Page 36: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Piling StagesAnticipated Start Date: Spring/Summer 2020* *Dates subject to change

Page 37: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

DeckingBeginning June 2020*

37

> Construction of a concrete deck, curb-to-curb on Constellation Bl

> Decking will serve as the temporary street surface

> Metro will work closely with first responders on emergency access and safety

> Work will be done in stages, beginning east of AOS, through the Constellation/AOS intersection, then west of AOS.

Duration: Anticipated 8 weekends

Work Hours: Full closures Friday, 8pm through Monday, 6am

Asphalt removal on Wilshire Bl

Concrete deck panel installation at Launch Box

*Dates subject to change

Page 38: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Decking StagesAnticipated Start Date: June 2020* *Dates subject to change

Page 39: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

39

Page 40: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

40

Greenleaf Gourmet Chopshop1888 Century Park East Century City, CA 90067

(424) 239-8706

Page 41: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Helping local businesses as we build.Purple Line Extension Update

Page 42: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

BIF Information and Eligibility

> Financial assistance to small “mom & pop” businesses with 25 or fewer full-time employees directly impacted by Metro Rail construction along three project areas

> Crenshaw/LAX Transit Project

> Purple Line Extension, Sections 1, 2 & 3

> Regional Connector Project, Little Tokyo area & 2nd/Broadway Segment

> Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements

> Grant amount determined by business revenue loss directly related to period of Metro construction disruption

Page 43: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

BIF Information and Eligibility

> To date, 1,060 grants have been have been awarded totaling more than $26 million to 387 small “mom & pop” businesses along all three project areas:

> Crenshaw/LAX Transit Project

> Regional Connector, Little Tokyo area and 2nd/Broadway segment*

> Purple Line Extension Section 1 and Section 2

*Segment eligibility based on full street closure with duration greater than six continuous months.

Page 44: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Business Interruption Fund

100% 97% 99% 94%84%

76%

Businessesreferred to

supportservices

Applicationsprocessedwithin 9business

days

Clientssatisfaction

rating

Businessesremaining

open after 6months of

grant award

Businessesremaining

open after 1year of grant

award

Businessesremaining

open after 2years of grant

award

Measures of Effectiveness(as of CY 2019 Q4)

Page 45: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Business Interruption Fund

Value of BIF Grants Awarded:$26,167,690.69*

$15,440,564.52

$5,571,526.50

$2,209,271.48 $1,996,164.16 $950,164.03

Crenshaw/LAX Purple LineExtension Section 1

Purple LineExtension Section 2

RegionalConnector, Little

Tokyo Area

RegionalConnector,

2nd/BroadwaySegment

(*As of 2/14/2020)

Page 46: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

BIF Grant Award Update

> Purple Line Extension Section 1 (as of 2/14/20)

> BIF Grants Awarded: 215

> BIF Grant Amount Awarded: $5,571,526.50

> Number of small businesses awarded: 79

> City of Beverly Hills only

> BIF Grants Awarded: 41

> BIF Grant Amount Awarded: $1,066,676.76

> Number of small businesses awarded: 17

> BIF Business Advisor: Brian Lazo, PCR, 213.739.2999

Page 47: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

BIF Grant Award Update

> Purple Line Extension Section 2 (as of 2/14/20)

> BIF Grants Awarded: 71

> BIF Grant Amount Awarded: $2,209,271.48

> Number of small businesses awarded: 38

> City of Beverly Hills only

> BIF Grants Awarded: 59

> BIF Grant Amount Awarded: $1,860,844.80

> Number of small businesses awarded: 32

> BIF Business Advisor: Darrell Smith, PCR, 213.739.2999

Page 48: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

BIF and Eat Shop Play Workshop

When: Tuesday, February 25, 2020

Time: 10am – 2pm – Stop by any time for one-on-one assistance

Where: 2029 Century Park East

Conference Room B

Los Angeles, CA 90067

Page 49: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Updates on La Cienega and Rodeo Stations

Wednesday, March 46:30pm – 8pm

Beverly Hills City Hall2nd Floor Municipal Gallery

445 N Rexford DrBeverly Hills, CA 90210

*On-site parking free after 5pm

49

Next Community MeetingBeverly Hills

Page 50: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

La Cienega and Rodeo Stations

Wednesday, March 412pm – 1pm

Link to the online meeting: WebexAccess Code: 806 634 776 | Password: Purple

Join by phone: 1-650-479-3207 (toll-free)

50

Lunch with Us: Public WebinarBeverly Hills

Page 51: Purple Line Extension · The PLE project team is working to deliver the project consistent with Measure M. Purple Line Extension Section 2 Alignment 6. Section 2 Wilshire/Rodeo Station.

Section 2: Construction Community Meeting

Thursday, May 216:30pm – 8pm

Century Plaza Towers2029 Century Park EastLos Angeles, CA 90067

Concourse Level D, Room A

*Parking will be validated51

Next Community MeetingSection 2