CORPORATE PRESENTATION DECEMBER 2017

Transcript of Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35...

Page 1: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

CORPORATEPRESENTATIONDECEMBER2017

Page 2: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

Certainstatementscontainedinthispresentation,includingallstatementsthatarenothistoricalfacts,containforward-lookingstatementsandforward-lookinginformationwithinthemeaningofapplicablesecuritieslaws(“forward-lookinginformation”).Suchforward-lookinginformationincludes,butisnotlimitedto,statementsorinformationwiththerespecttotheoverallobjectivesandstrategicplans,workprograms,explorationbudgetsandtargetsandmineralresourceestimatesofPureEnergyMineralsLimited(“PureEnergy”orthe“Company”).ReadersshouldreviewalloftheCompany’spublicdisclosureincludingitsmostrecentAnnualInformationFormandtheriskfactorscontainedtherein,thetechnicalreportsonitsproperties,anditsauditedfinancialstatementsandManagement'sDiscussionandAnalysis (MD&A),allasfiledonwww.sedar.com fromtimetotime.

Forward-lookinginformationincludes,butisnotlimitedto,statementsrelatedtoactivities,eventsordevelopmentsthattheCompanyexpectsoranticipateswillormayoccurinthefuture,including,withoutlimitation;statementsrelatedtotheCompany'sreleaseofthePEATechnicalReport(“PEA”)fortheClaytonValleyLithiumProject(“Project”);theeconomicanalysisoftheProject;themineralresourceestimatefortheProject;theestimatedannualproductionofLiOH-H2OandLCE;theavailabilityanddevelopmentofmoresustainabletechnologiesforuseattheProject;theexpectedminelife;theestimatedNPVoftheProject;theestimatedIRRoftheProject;estimatedaverageoperatingcosts;estimatedcapitalcosts;estimatedEBITDA;theestimatedpaybackperiodfortheProject;theestimatedtimelineforconstructionoftheProject;theestimatedproductionscheduleattheProject;anticipatedchemistryofbrinesattheProject;expectedgrowthinthemarketforlithiumhydroxide;anticipatedchangesinbatteryformulationtechnologies;estimatedmarketpricesforlithiumhydroxide;anticipatedlithiumrecoverylevelsattheProject;expectedpilotplanttestingattheProject;designworkattheProject;andthedevelopmentofatimelineforcompletionofafeasibilitystudyfortheProject.Forward-lookinginformationisoftenidentifiedbytheuseofwordssuchas"plans","planning","planned","expects"or"lookingforward","doesnotexpect","continues","scheduled","estimates","forecasts","intends","potential","anticipates","doesnotanticipate",or"belief",ordescribesa"goal",orvariationofsuchwordsandphrasesorstatesthatcertainactions,eventsorresults"may","could","would","might"or"will"betaken,occurorbeachieved.Forward-lookinginformationisbasedonanumberoffactorsandassumptionsmadebymanagementandconsideredreasonableatthetimesuchinformationisprovided.Forward-lookinginformationinvolvesknownandunknownrisks,uncertaintiesandotherfactorsthatmaycausetheactualresults,performance,orachievementstobemateriallydifferentfromthoseexpressedorimpliedbytheforward-lookinginformation.

AnumberofotherfactorsmayadverselyimpactPureEnergyandtheProject,including:theCompany’sinabilitytocompletefurthermineralresourceandmineralreserveestimates;theinabilitytocompleteasubsequentfeasibilitystudy;theinabilitytoanticipatechangesinbrinevolumeorgradedueanumberoffactors;changestotheeconomic analysis;thefailuretoobtainnecessarypermitstoexploreanddeveloptheProject;environmentalissuesordelays;inabilitytosuccessfullycompleteadditionaldrillingattheProject;andinabilitytoobtainfinancingforfutureexplorationanddevelopmentworkandconstructionofaplantattheProject.AlthoughPureEnergyhasattemptedtoidentifyimportantfactorsthatcouldcauseactualactions,events,orresultstodiffermateriallyfromthosedescribedintheforward-lookinginformation,theremaybeotherfactorsthatcauseactions,events,orresultsnottobeasanticipated,estimated,orintended.Therecanbenoassurancethatforward-lookinginformationwillprovetobeaccurate.Theforward-lookinginformationcontainedhereinispresentedforthepurposeofassistinginvestorsinunderstandingtheCompany'splan,objectives,andgoalsandmaynotbeappropriateforotherpurposes. Accordingly,readersshouldnotplaceunduerelianceonforward-lookinginformation.PureEnergydoesnotundertaketoupdateanyforward-lookinginformation,exceptinaccordancewithapplicablesecuritieslaws.

CAUTIONARYSTATEMENT

2Mineralresourceswhicharenotmineralreservesdonothavedemonstratedeconomicviability.Thecategoryofinferredresourceistheleastreliableresourcecategoryandissubjecttothemostvariability.Untilmineralreservesandresourcesareactuallyminedandprocessed,thequantityofmineralreserveandresourcegradesmustbeconsideredasestimatesonly.PatrickHighsmithMSc.,CPG.,isaqualifiedpersonasdefinedbyNI43-101,andhassupervisedthepreparationofthescientificandtechnicalinformationthatformsthebasisforthispresentation.Mr.HighsmithisnotindependentoftheCompanyasheisadirector.

Page 3: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

ThePEAisbaseduponaprocessflowsheetthatmaychange,whichwouldimpactallcostsandestimates.OperatingcostsfortheProjectwerebaseduponassumptionsincludingfutureenergycosts,watercosts,labor,regulatorycostsandothervariablesthatarelikelytochange.Capitalcostswerebaseduponplantequipmentandotheritemsthoughttobenecessaryforproduction.Lithiumhydroxidemonohydratepriceforecastswerebaseduponthird-partyestimatesandmanagementassumptionsthatmaychangeduetomarketdynamics.Changesinestimatedcoststoacquire,construct,install,oroperatetheequipment,orchangesinprojectedpricing,mayadverselyimpactProjecteconomics.

TheeconomicanalysisincludedinthePEAisbaseduponinferredmineralresourcesonly.Mineralresourcesthatarenotmineralreservesdonothavedemonstratedeconomicviability.ThePEAispreliminaryinnatureandincludesinferredmineralresourcesthatareconsideredtoospeculativegeologicallytohave theeconomicconsiderationsappliedtothemthatwouldenablethemtobecategorizedasmineralreserves.ThereisnocertaintythattheProjectenvisionedbythisPEAwillberealized.Themineralresourceestimates,uponwhichthePEAisbased,relyuponassumptionsoutlinedinthe“ResourceEstimate”sectionofthetechnicalreportrelatingtothePEA.Somefiguresintheresourceestimatemayhavebeencalculatedusingafactortoconvertshorttonstometrictonnes.

CAUTIONARYSTATEMENT(cont.)

3Mineralresourceswhicharenotmineralreservesdonothavedemonstratedeconomicviability.Thecategoryofinferredresourceistheleastreliableresourcecategoryandissubjecttothemostvariability.Untilmineralreservesandresourcesareactuallyminedandprocessed,thequantityofmineralreserveandresourcegradesmustbeconsideredasestimatesonly.PatrickHighsmithMSc.,CPG.,isaqualifiedpersonasdefinedbyNI43-101,andhassupervisedthepreparationofthescientificandtechnicalinformationthatformsthebasisforthispresentation.Mr.HighsmithisnotindependentoftheCompanyasheisadirector.

Page 4: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

4

Page 5: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

ANEWMANAGEMENTTEAMWITHTHERIGHTEXPERIENCETODELIVER

PAULZINKChiefFinancialOfficerPaulhasmorethan35yearsexperienceinprojectfinance,financialanalysis,strategicplanning,royalties,mergersandacquisitions,andbusinessdevelopment.BeginninghiscareerininvestmentbankingwithJ.P.Morgan&Company,hehasheldseniormanagementpositionsatInternationalRoyaltyCorporation,RareElementResourcesLtd.,EurasianMineralsInc.,PegasusGoldInc.,andKochIndustriesInc.

PaulholdsaB.A.inEconomicsandInternationalRelationsfromLehighUniversity.

WALTERWEINIGMSc,CPG,PPMVPProjects&PermittingWalterhasnearly30yearsofexperienceinmininghydrogeology,permitting,andprojectmanagementatsitesaroundtheglobe.Hehasmanagedmulti-disciplinaryengineeringandscientificteamstoaccomplishcomplexdesignandpermittingprojectsinsurfaceandundergroundminingandenvironmentalarenas.

WalterhasaBScingeologyfromtheUniversityofWisconsinandanMScinhydrologyandwaterresourcesfromtheUniversityofArizona.

PATRICKHIGHSMITHMSc,CPG;CEO,Director

Seniorminingprofessionalwithover25yearsmulti-commodityexperience,includingexploration,operations,andbusinessdevelopmentwithBHPBilliton,RioTinto,andNewmont.FoundingCEOofLithiumOneInc.andco-engineeroffriendly2012mergerwithGalaxyResources.

55

Page 6: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

LITHIUMDEMANDISDRIVINGEXPLORATION…ANDANEXPLOSIONOFCOMPANIES!

66

Page 7: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

CONSENSUSISGATHERINGAROUND500KTPABY2025…BATTERIESAREDRIVINGDEMAND

77BenchmarkMineralIntelligence,LithiumHydroxideMarketForecast,April,2017

Page 8: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

GLOBALEVBUSINESSISJUSTSTARTINGTOMAKEWAVES

GlobalAutoSalesin2016at88MVehicles:~$2Trillion

AreWeReadyfora$300BEV

Industry?

88

Page 9: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

$0

$200

$400

$600

$800

$1,000

$1,200

2010

2011

2012

2013

2014

2015

Source:BloombergNewEnergyFinance 99

AverageBatteryPackPrice(BEV&PHEVBatteryPacks)

$/kW

h

$0

$200

$400

$600

$800

$1,000

$1,200

2010

2011

H12012

H22012

H12013

H12014

H22014

H22015

AverageEVBatteryPricePercentageChangeBetweenPeriods(2010– H22015)

$/kW

h

-20% -14% -7% -7% -5% -5% -35%

WHYISTHISFORREALTHISTIME?BATTERYCOSTSAREPLUMMETING

Page 10: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

1010

Page 11: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

World-ClassInfrastructurePowerLines,Roads,andNorthAmerica’sOnlyLithiumProducer…

CLAYTONVALLEYNEVADA– APRODUCTIVEDISTRICTCLAYTONVALLEY,NEVADA– HOMETOANOLDPRODUCERANDNEWPOTENTIAL

11

Page 12: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

THECLAYTONVALLEYPROJECTCONTINUESTOGROW

EXPANDEDPUREENERGYCLAIMS:

ExistingClaims: 24,600ACRES

ClaytonNE: 1,060ACRES

Triton: 390ACRES

TOTAL:26,050ACRES

ExistingClaims

AlbemarleSilverPeakMine

AdvantageClaimAreas

Wells

TRITONCLAIMBLOCK CLAYTONNECLAIMBLOCK

NewAcquisitionsfromAdvantageLithium:- AdjoinsAlbemarle’sSilverPeakMine- Includes6ExplorationWellsonEastSide- AverageLithiumGrade:204mg/L- MaximumLithiumValues:322mg/L- AllShareTransactionfor100%Interest

AREASOFEXPLORATIONFOCUSIN2018

12

Page 13: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

CLAYTONVALLEYPROJECT– SUMMARYOFPRELIMINARYECONOMICASSESSMENT(PEA)

KeyEconomic Indicators(CurrencyinUS$)

AfterTax - Net PresentValue(8%Discount) $264million

AfterTax- InternalRateofReturn(IRR) 21%

Average AnnualProduction(LithiumHydroxide) 10,300 tonnes

AverageAnnualProduction(Lithium CarbonateEquivalent) 9,100 tonnes

MineLife 20 year

Production Royalties 3%

Steady-State AnnualEBITDA*(nameplateproduction) $100million

PaybackPeriod(fromcommencementofproduction) 4.4 years

*- EBITDAisanon-IFRSearningsmeasurewhichdoesnothaveanystandardizedmeaningprescribedbyIFRSandthereforemaynotbecomparabletoEBITDApresentedbyothercompanies.EBITDArepresentsearningsbeforeinterestexpense,incometaxes,depreciationandamortization.Investorsarecautionedthatthisnon-IFRSfinancialmeasureshouldnotbe construedasanalternativetoothermeasuresoffinancialperformancecalculatedinaccordancewithIFRS. 1313

Page 14: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

DescriptionofCapitalCosts US$

BasinActivities $29M

PlantFacilities&Equipment $100M

Infrastructure&Utilities $30M

DirectCosts $159M

IndirectCosts* $34M

Contingency $56M

Owner’sandOtherCosts** $48M

TotalInitialCapitalCosts $297M

SustainingCapitalCosts(LoM) $62M

*- IndirectCostsarethosecoststhatcannotbedirectlyattributedtotheconstructionofthephysicalfacilitiesbutarerequiredtosupporttheconstructioneffort.Itemsincludedinthiscategoryinclude,butarenotlimitedto:spareparts,freight,EPCMservicesandstart-upservices.

**Owner'sCostsencompassallthosecostsspecificallyattributabletotheOwnerthatarenotincludedelsewhereintheestimate.Typicalitemsincludedinthiscategoryinclude,butarenotlimitedto:landownershipcosts,feasibilitystudycosts,legalfees,permittingcostsandfees,Ownerprojectsupportstaff,specialistconsultants,andoperationsorganizationestablishment(includingtraining,etc).OtherCostsincludeinitialpurchaseandchargingoftheplantwiththeproprietarysolvent.

14

AFIRSTPASSESTIMATEOFCONSTRUCTIONCOSTS

14

Page 15: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

DescriptionofSteadyStateOperatingCosts(US$)UnitCostLiOH·H2O

UnitCostLCE

%ofTotal

Labor $427/t $485/t 14

Power $394/t $447/t 12

OperatingSupplies&Services $2,227/t $2,528/t 69

MaintenanceSupplies $169/t $192/t 5

Total $3,217/t $3,652/t 100%

15

FIRSTPASSESTIMATEOFDIRECTOPERATINGCOSTS– VERYENCOURAGING

15

Page 16: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

16

KEYASSUMPTIONS:

100%EquityFinancing

ProductionRamp-upover~15months:

4,100tonnesLiOH�H2Oin2021

10,800tonnesLiOH�H2Oin2022

11,400tonnesLiOH�H2Oin2023

ConstructionCommencingin2019

EffectiveTaxRateof20%

Theeconomicanalysisisbaseduponinferredmineralresourcesonly.Mineralresourcesthatarenotmineralreservesdonothavedemonstratedeconomicviability.ThisPEA is preliminaryinnatureandincludesinferredmineralresourcesthatareconsideredtoospeculativegeologicallytohavetheeconomicconsiderationsappliedtothemthatwouldenablethemtobecategorizedasmineralreserves.ThereisnocertaintythattheProjectenvisionedbythisPEAwillberealized

NEWTECH=HIGHMARGINS

16

0

20

40

60

80

100

120

140

160

180

200

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40

MILLIONS(USD

)

YEAR

REVENUE

DIRECTCOSTS

NON-OPERATINGCOSTS

Page 17: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

LITHIUMHYDROXIDEBASECASEPRICINGMODELFORCLAYTONVALLEYPROJECT

ADynamicPricingModelBasedonRealMarketAnalysis

17

BaseCasePricingusedinPEAFinancialModel

Page 18: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

VERYCOMPETITIVEDIRECTPRODUCTIONCOSTS

PUREENERGYEstimatedDirectCosts$3,217/tonne

18SlideborrowedfromNemaska Lithium

Page 19: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

19

Page 20: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

PHASE3DRILLPROGRAM– IMPORTANTINPUTSTONEWRESOURCE

20

Li=209mg/L

StrongPumpTest

HigherGradeat

Depth

Li=70mg/L

Li=175mg/L

Li=134mg/L

Page 21: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

Variabledrainableporositywithgeologyanddepth;assignedaconservative6%tothemodel

21

CLAYTONVALLEYPROJECT:HOSTAQUIFERS

Porosity10– 20%

Porosity4– 10%

PorosityHighlyVariable

Page 22: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

22

Magnesium*toLithiumRatio:2.9

Avg CalciumContent(mg/L)*:1,536

Sulfate*toLithiumRatio:18.2

WORLD-CLASSCHEMISTRY

RESOURCES&KEYTECHNICALPARAMETERS

NOTE:Mineralresourcesthatarenotmineralreservesdonothaveanydemonstratedeconomicviability.Inferredresourcesaretheleastreliableresourcecategoryandaresubjecttothemostvariability.PleaseseetheCompany’sfulltechnicalreportatwww.sedar.comorwww.pureenergyminerals.com fordetailsonhowtheresourcewasderivedandforthereportingdetailsintermsoflithiummetal(Li)andlithiumhydroxidemonohydrate(LiOH�H2O).

HIGHERCONFIDENCE,BETTERUNDERSTOODIN3D,POISEDFORGROWTHINFY2018

Lithium Resource LCE

(metric tonnes)Average Lithium Grade

(mg/L)

816,000

TOTAL INFERRED SOURCES

102

TOTALINFERREDRESOURCES

218,000 123

*Chemistryderivedfromglobalaveragecalculationsfromdatabase,June2017

Page 23: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

LiP™ LiSX™ LiEL™

NoEvaporation

Ponds

RealTimeRecovery

23

THEREISABETTERWAY:PRELIMINARYFLOWSHEETFORNEWLITHIUMPROCESS

Page 24: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

24

THEREISABETTERWAY:MAKINGITAREALITYWITHAPILOTPLANT

Preliminary3DPerspectiveDrawingofClaytonValleyPilotPlant

Page 25: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

CLAYTONVALLEYEXECUTIONSCHEDULE

ClaytonValleySouthExecutionSchedule 2017 2018 2019 2020 2021 2022

ProjectActivity Duration Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4EnvironmentalBaselineStudies 12monthsPermittingforPilotPlant 12monthsDesignofPilotPlant 9monthsProcurementofPilotPlant 9monthsConstructionofPilotPlant 6monthsOperationofPilotPlant 6monthsEnvironmentalImpactAssessmentorStudy 12monthsPermittingforProjectExecution 12monthsFeasibilityStudy- BasinActivities 15monthsFeasibilityStudy- PlantActivities&FeasibilityReport 9monthsProjectFinancing 3monthsDesign&Engineering- ProjectExecution 9monthsProcurement&Delivery- ProjectExecution 12monthsConstruction 15monthsCommissioning 6monthsRamp-Up 9months

RealisticandAggressive - It’sallaboutthePilotPlant

25

Page 26: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

FÉNIXMINE

SALARDEATACAMA

LITHIUMTRIANGLE

TERRACOTTAPROJECT,ARGENTINA

LITHIUMTRIANGLE

TERRACOTTAPROJECT,ARGENTINA– WORLDCLASSDISCOVERYPOTENTIAL

26

Page 27: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

Pocitos Salar

Largeanddeepclosedstructuralbasinwithmultipleaquifers

Majorstructures– faultsandfolds

Recentvolcanismandactivehydrothermalsystems

Complexmetasedimentary andvolcanicrocksinbasin

Lithiumindicatedinnear-surfacebrinesanddeepergeophysicaltargets

27

TERRACOTTAPROJECT– FAVORABLEGEOLOGYANDNEWGEOPHYSICALTARGETS

Page 28: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

TERRACOTTAPROJECT– VESRESULTS:“THERE’SSALTWATERDOWNTHERE”

28

Interpretedconductivematerial(red)istheprimedrilltarget

Page 29: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,

NEXTSTEPS

SurfaceSamplingUnderway:Lithiumanomalies

ZonationofbrinechemistryGeologicalmapping

EnvironmentalImpactReportUnderway

Planningfor5to10drillholes:Mixtureofcoreandrotary

SchedulingwithDrillingCompanies

DrillingExpectedtoCommenceinQ12018

TERRACOTTAPROJECT– THEANOMALYHASHUGESCALE

29

Page 30: Pure Energy - Corp Presentation 120117 Compressed · Chief Financial Officer Paul has more than 35 years experience in project finance, financial analysis, strategic planning, royalties,