Public Works Operations Center Project

29
Public Works Operations Center Project Works Operations Center Project July 16, 2018 Vancouver City Council Workshop Brian Carlson, Public Works Director

Transcript of Public Works Operations Center Project

Page 1: Public Works Operations Center Project

Public Works Operations Center Project Works

Operations Center Project

July 16, 2018 Vancouver City Council Workshop

Brian Carlson, Public Works Director

Page 2: Public Works Operations Center Project

Purpose: Update on Public Works Operations Center project

Topics: Site history, current site operations and challenges Review of master of planning efforts to date Consideration of alternatives Next steps

Key Points: Assessment of current site completed. Many buildings are beyond their useful life and are seismically vulnerable. Future needs and options evaluated. Alternatives being considered. Big decisions ahead. Follow up workshop: August 27

Presentation Overview

PW Ops Center Project - 2

Page 3: Public Works Operations Center Project

• Built in early 1950s by Clark Public Utilities • City purchased site in 1978, along with

adjacent Brookside property, for Public Works Operations Services (10.2 acres) – 90 employees and 150 vehicles – City population: 42,000

History of Operations Center

PW Ops Center Project - 3

Page 4: Public Works Operations Center Project

10.2 original acres • 1.5 acres added

2001-2002 • 3.5 acres added

2015-2018

Current Site Properties

PW Ops Center Project - 4

Page 5: Public Works Operations Center Project

15.2 Acres Total 10.1 acres east and 5.1 acres west of General Anderson Avenue

Current Operations Center Site

PW Ops Center Project- 5

Page 6: Public Works Operations Center Project

Current Site Operations

PW Ops Center Project - 6

• 245 regular employees, 25+ Seasonal • Work Groups Water Wastewater Stormwater Utilities Billing Grounds Facilities Maintenance Warehouse Equipment Services Streets, Traffic Operations & Engineering Pavement Management • 500+ vehicles and equipment

City population 185,000

Page 7: Public Works Operations Center Project

• Aged Infrastructure • Seismically vulnerable • ADA non-compliant • Maxed-out work

areas/spaces and inefficient layout

Key Concerns with Current Site

PW Ops Center Project- 7

Page 8: Public Works Operations Center Project

Aged Infrastructure

PW Ops Center Project - 8

• Original plumbing/electrical • No fire sprinkler system • Stormwater system non-compliant • 40 and 50 year old fuel tanks

Page 9: Public Works Operations Center Project

Seismically Vulnerable

PW Ops Center Project - 9

• Majority of structures seismically deficient • Liquefaction additional factor at site

Page 10: Public Works Operations Center Project

ADA Non-compliant

PW Ops Center Project - 10

• Elevated interior • Multiple levels • Accessibility issues throughout

Page 11: Public Works Operations Center Project

Space and Efficiency Issues

PW Ops Center Project - 11

• Maxed out work space • Disjointed and inefficient layout for workgroups • No room for expansion • Lack of adequate parking

Page 12: Public Works Operations Center Project

Problem Statement

PW Ops Center Project - 12

We have a significantly aged and inefficient facility housing essential first responder services that in a moderate seismic event is significantly compromised.

Page 13: Public Works Operations Center Project

2005-2008 Study • Redevelop current site and co-locate several City functions in

campus-style development; move half of Operations to new east Vancouver site

Master Planning Efforts

Presentation Title - 13

• Purchased 15.4 acres at 162nd Avenue/65th Street

• Great Recession: Hit pause • Other opportunities arose

Page 14: Public Works Operations Center Project

• Re-energized with purchase of Golden Skate in 2015

• Refresh and renew project planning goals

• Establish planning and study objectives

• Contract with Mackenzie Engineering in May 2017

Master Planning Efforts

PW Ops Center Project - 14

Current Planning Efforts

Page 15: Public Works Operations Center Project

Project Planning Goals • Modernize Operations Center campus • Relocate certain Public Works work groups to site

– Construction, Survey and Transportation Engineering (38 FTE) – Fire Equipment Shop (5 FTE) – Asset Management/GIS (9 FTE)

• Improve efficiency of operations • Ensure “Operational Status” after seismic event • Build for the long-term in mind • Integrate sustainable design practices • Contribute to the positive development of the Fourth Plain corridor

Master Planning Efforts

PW Ops Center Project - 15

Page 16: Public Works Operations Center Project

Master Planning Objectives • Gather and apply operational information • Evaluate and analyze existing conditions

– Facilities condition – Seismic – Soils/Drainage – Hazmat – Zoning and development code

• Evaluate if existing structures can be incorporated into new layout • Constructability while maintaining operations • Prepare concept design alternates and costs

Master Planning Efforts

PW Ops Center Project - 16

Page 17: Public Works Operations Center Project

Operational Information • Staffing – current and future

– Current staffing at site: 245 FTE + 25 seasonal = 270 – Relocated staff: 46 FTE + 6 seasonal = 52 – Total current staffing: 291 FTE + 31 seasonal = 322 – 15-20 Year projection: 362 FTE + 35 seasonal = 397

• Leads to an overall acreage need of 26 acres

Master Planning Efforts

PW Ops Center Project - 17

Page 18: Public Works Operations Center Project

6 Concept Alternates Studied • Alternates 1 – 3 (full consolidation of all services)

– Alternate 1: Existing property (15.2 acres) – Alternate 2: Plus two NE properties (16.0 acres) – Alternate 3: Two NE properties plus Market (16.9 acres)

• Alternate 4 (partial consolidation) – Plus two NE properties and – Relocate Equipment Services to new site

• Alternate 5 (full consolidation at new site)

• Alternate 6 (seismic upgrade only)

Master Planning Efforts

PW Ops Center Project - 18

Page 19: Public Works Operations Center Project

Alternate 1 – Full Consolidation

PW Ops Center Project - 19

Existing properties

Page 20: Public Works Operations Center Project

Existing properties plus two NE properties

Alternate 2 – Full Consolidation

PW Ops Center Project - 20

Page 21: Public Works Operations Center Project

Existing properties plus two NE and Market properties

Alternate 3 – Full Consolidation

PW Ops Center Project - 21

Page 22: Public Works Operations Center Project

Alternate 4 – Relocate Equipment Services

PW Ops Center Project - 22

Existing properties plus two NE properties

Page 23: Public Works Operations Center Project

Alternate 5 – New Site

- 23

Full consolidation of services at new site on 25-30 acres

Page 24: Public Works Operations Center Project

Alternates 1 – 6 Costs

PW Ops Center Project -24

• Alternate 1: $157M (full consolidation, existing property)

• Alternate 2: $151M (full consolidation + NE properties)

• Alternate 3: $141M (full consolidation + NE and Market properties)

• Alternate 4: $123M (relocate Equipment Services + NE properties)

• Alternate 5: $126M (full consolidation at new site)

• Alternate 6: $ 53M (seismic upgrade only – not to Operational Level, addresses life safety risk and collapse, also includes ADA required upgrades and fire sprinkler system)

Note: Cost estimates in 2021 $

Page 25: Public Works Operations Center Project

Other Issues and Challenges at Existing Site

PW Ops Center Project - 25

Non-costed Issues • Some parcels split zoning, require rezoning • Fourth Plain Overlay District Challenges – will require variances • Nonconforming setbacks for some current structures • Stormwater management challenges

Other Challenges • Construction phasing • Limited future expansion

Page 26: Public Works Operations Center Project

Other Considerations for Discussion

PW Ops Center Project - 26

• Does this project still fit goals/vision of Fourth Plain Subarea Plan?

• Does the current site best fit long-term City needs? And is it in the best long-term location?

• Is it better to free up property for other redevelopment purposes?

• Few available 25-30 acre properly zoned sites: Is it acceptable to consider alternate site outside current City limits but within current service area?

Page 27: Public Works Operations Center Project

Location, Location

PW Ops Center Project - 27

Page 28: Public Works Operations Center Project

Follow up Council Workshop scheduled August 27 • Project financing strategies • Policy direction in relocation versus redevelopment

Next Steps

PW Ops Center Project - 28

Page 29: Public Works Operations Center Project

Questions and Discussion

• Brian Carlson, Public Works Director [email protected]

PW Ops Center Project - 29