Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry...

22
Public Procurement and Sport Events Eliane Viegas Mota Director, Auditing of Social Policies Ministry of Transparency and Comptroller General

Transcript of Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry...

Page 1: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Public Procurement and Sport Events

Eliane Viegas MotaDirector, Auditing of Social Policies

Ministry of Transparency and Comptroller General

Page 2: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

The Challenges of Hosting Major Sports Events

The Brazilian Experience

Page 3: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Panamerican/Parapanamerican Games Rio 2007

Federations Cup FIFA 2013

World Cup FIFA 2014

Olympic/Paraolympic Games Rio 2016

Page 4: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Collegiate Bodies To Coordinate and Plan the World Cup 2014 (Olympic Games 2016)

GOVERNANCE STRUCTURE (Strategic Coordination / Planning Cycles)

World Cup’s Management

Committee (CGCOPA)

World Cup’s Executive Group (GECOPA)

Responsibility Committee (Host Cities)

Page 5: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

CGCOPA(STRATEGIC)

GECOPA(TACTICAL)

Chambers(OPERATIONAL)

Steering Committee for the World CupDevelops directives for the strategic plan for the World Cup

Executive Committee for the World CupEstablishes the strategic plan and goals

Earmarks related actions in the budget

Coordinates actions carried out with federal resources

Thematic Chambers (Ministries)

Proposes policies and technical recommendations

Health, sustainability, touristic development & culture, education & labor, and

transparency

Page 6: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Private events, with requirements definition by theorganizers (FIFA and IOC)

Public investments (investments made by governmentagencies)

Page 7: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Public investments and public procurement

World Cup - 12 host cities (unnecessary)

Olympic Games - one host city and football cities

Page 8: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Ministry of Sport with a central role in coordinating theorganization of major events

Lack and difficulty of adequate coordination of initiatives(central government and local governments)

Page 9: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Situations that stand out

- Severe planning failures

- Problems regarding the disclosure of information related to the investments made (resources applied)

- Rigid timeline for completion of interventions

- Excessive requirements imposed by organizers

- Selection process of host countries/cities

Page 10: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Some (good) practices – the "brazilian case”- Development of specific sections of the Transparency

Portal (“Copa 2014” and "Jogos Rio 2016”)- Creation of a Task Force under the MPF (Federal

Prosecutor Office) for monitoring the works for the WCup

- Audit actions conducted by CGU (WCup and Olympics)- Creation of a Task Force for monitoring the works for

the WCup and Olympics – federal level (initiatives/deadlines/schedules)

- Monitoring conducted by Federal Court of Accounts

Page 11: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Transparency Portal - Section “Copa 2014”

Information were available (but no longer available)

Page 12: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack
Page 13: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Transparency Portal - Section “Jogos Rio 2016”

“Incomplete, unclear and disorganized”

Very difficult to obtain the informations required

Page 14: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

http://www.portaltransparencia.gov.br/rio2016/

Infrastructure

Summary Table

Highlights

Security Actions

Development of High Performance Athletes

Page 15: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

MPF Task Force (World Cup 2014)

Recommendations to Public Managers- Arena Amazônia- Maracanã- Arena Pantanal

Schedule was an important concern

Olympic/Paraolympic Games: no task force

Page 16: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Improve the detailing of designs

Revision of the composition of services

Implementation of control mechanisms Adjustments in procurements

Analysis performed by CGU – World Cup

Stadium/Arenas

Analysedaprox. USD 1 billion (3 Stadiums)

In engineering Designsand their Execution

(Manaus, Rio de Janeiro, Cuiabá)

Overestimated Budget (Unit Price and/or Quantities);

Designs of poor quality;

Effective Reduction of Aprox. USD 100 million

Page 17: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Analysis performed by CGU – World Cup

Maracanã Stadium – Rio de Janeiro/RJ – March/2012

• The initial analysis by CGU in August

2011 found USD 87 Million overprice

and other irregularities

• Decision by the Federal Court of

Accounts in September 2011 – USD

48.4 Million overprice after consultations

between CGU and the state government

Page 18: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Analysis performed by CGU – World Cup

Amazon Stadium – Manaus/AM – March/2012

• The initial analysis by CGU in November

2011 found USD 34 Million overprice and

other irregularities

• Decision by the Federal Court of Accounts

in August 2012 – expanded the scope of

audits. USD 43 Million overprice after

consultations between CGU and the state

government

Page 19: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Analysis performed by CGU – World Cup

Pantanal Arena – Cuiabá/MT – February 2013

• The analysis by CGU in July 2011

found an amount of USD 34 Million in

irregularities in the execution of the

contract, like unjustly anticipated

payments and additions to the

contract.

Page 20: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Analysis performed by CGU – World Cup

Technical visits (once a month) to monitor the development of Stadiums/Arenas (schedule, stage of works, procurement informations)

Publication of the information at Transparency Portal

Page 21: Public Procurement and Sport Events · Olympic Games - one host city and football cities. Ministry of Sport with a central role in coordinating the organization of major events Lack

Analysis performed by CGU – Olympic/Paraolympic Games

The analysis performed by CGU in December 2015 foundan amount of USD 34 Million in irregularities in theexecution of a contract (25% of the contract value)for the contruction of venues in the cluster of Deodoro.