PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020...
Transcript of PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020...
![Page 1: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/1.jpg)
PS Planning
Fernando Pedrosa
![Page 2: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/2.jpg)
2
Table of Contents
• Progress report on the activities between 23th January to 6th February 2020
• Works foreseen for the next 2 weeks
06-Feb-2020
![Page 3: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/3.jpg)
3
23rd January 2020As performedAs presented the 23rd January 2020
06-Feb-2020
![Page 4: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/4.jpg)
4
24th January 2020As performedAs presented the 23rd January 2020
06-Feb-2020
![Page 5: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/5.jpg)
5
27th January 2020As performedAs presented the 23rd January 2020
06-Feb-2020
![Page 6: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/6.jpg)
6
28th January 2020As performedAs presented the 23rd January 2020
06-Feb-2020
![Page 7: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/7.jpg)
7
29th January 2020As performedAs presented the 23rd January 2020
06-Feb-2020
![Page 8: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/8.jpg)
8
30th January 2020As performedAs presented the 23rd January 2020
06-Feb-2020
![Page 9: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/9.jpg)
9
31st January 2020As performedAs presented the 23rd January 2020
06-Feb-2020
![Page 10: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/10.jpg)
10
3rd February 2020As performedAs presented the 23rd January 2020
06-Feb-2020
![Page 11: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/11.jpg)
11
4th February 2020As performedAs presented the 23rd January 2020
06-Feb-2020
![Page 12: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/12.jpg)
12
4th February 2020As performedAs presented the 23rd January 2020
06-Feb-2020
![Page 13: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/13.jpg)
13
6th and 7th February 2020 F61 line works
• Equipment installation
10 MHz water manifold installation (SS11, SS46, SS51, SS56)
Amplifiers cabling for the pickups systems
TE-MSC works to complete the connection of all MUs and Straight section
equipment
“Carotage” for the RF rigid line + RF rigid installation
PS SWY
activities in
the next slide
06-Feb-2020
![Page 14: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/14.jpg)
14
6th February 2020
• LV consolidation
• LT smoothing
• Overhead crane
modifications
• BTP Alignment
• Installation of the cooling
manifold for the PSC10
SS11
• PSC10 SS36 internal
cabling
• CV works – magnet
valves modification
• TE-MSC works to
complete the connection
of all MUs and Straight
section equipment
06-Feb-2020
![Page 15: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/15.jpg)
15
7th February 2020
• LV consolidation
• BTP vacuum closure, leak
detection and pump down
• LT Smoothing
• Overhead crane
modifications
• Installation of the cooling
manifold for the PSC10
SS11
• PSC10 SS36 internal cabling
• CV BTP water line pressure
test (access only to the ext.
gallery needed)
• CV works – magnet valves
modification
• TE-MSC works to complete
the connection of all MUs
and Straight section
equipment
We will re-install the SMH16 the 13/02/2020, so all works that
require the opening of the vacuum must be completed by the
11/02/2020
If your activity doesn’t appear in these slides or is not yet approved
in IMPACT please contact me as soon as possible
06-Feb-2020
![Page 16: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/16.jpg)
16
10th February 2020
F61 line works
• Equipment installation
10 MHz water manifold installation (SS66)
Amplifiers cabling for the pickups systems
TE-MSC works to complete the connection of all MUs and Straight section
equipment
MU93 repair
Asbestos pipe removedPS SWY
activities in
the next slide
06-Feb-2020
Material to be removed from
this area before Monday (RF,
VSC, MSC, …)
![Page 17: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/17.jpg)
17
10th February 2020
• LV consolidation
• BI line alignment
• VSC works to close the
F16 line in the PS SWY +
LT (including leak
detection and pump
down)
• Beam stoppers
connection to the services
• F16 + LT MSC equipment
connection to the services
• F16 BLMs installation
• F16.QDN163 re-
installation + alignment
• Re-install the stairs that
were removed to allow
the LT smoothing
• Finish the vacuum pump
down and start the BTP
smoothing
06-Feb-2020
![Page 18: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/18.jpg)
18
11th February 2020
F61 line works
• Equipment installation
10 MHz water manifold installation (SS66)
Amplifiers cabling for the pickups systems
TE-MSC works to complete the connection of all MUs and Straight section
equipment
MU93 repair
MU97 damper installation
Asbestos pipe removed
PS SWY
activities in
the next slide
06-Feb-2020
![Page 19: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/19.jpg)
19
11th February 2020
• LV consolidation
• BI line alignment
• VSC works to close the
F16 line in the PS SWY +
LT (including leak
detection and pump
down)
• Beam stoppers
connection to the services
• F16 + LT MSC equipment
connection to the services
• F16 BLMs installation
• BTP smoothing
06-Feb-2020
![Page 20: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/20.jpg)
20
12th February 2020
F61 line works
• Equipment installation
10 MHz water manifold installation (SS66)
Amplifiers cabling for the pickups systems
TE-MSC works to complete the connection of all MUs and Straight section
equipment
MU93 repair
SS93 BPM installation
Asbestos pipe removed
PS SWY
activities in
the next slide
06-Feb-2020
![Page 21: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/21.jpg)
21
12th February 2020
• LV consolidation
• BI line alignment
• VSC works to close the
F16 line in the PS SWY +
LT (including leak
detection and pump
down)
• Beam stoppers
connection to the services
• F16 + LT MSC equipment
connection to the services
• F16 BLMs installation
• BTP smoothing
06-Feb-2020
![Page 22: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/22.jpg)
22
13th and 14th February 2020
F61 line works
• Equipment installation
10 MHz water manifold installation (SS66)
Amplifiers cabling for the pickups systems
TE-MSC works to complete the connection of all MUs and Straight section
equipment
MU93 repair
Asbestos pipe removedPS SWY
activities in
the next slide
06-Feb-2020
![Page 23: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/23.jpg)
23
13th February 2020
• LV consolidation
• BI line vacuum
connection, leak detection
and pump down
• VSC works to close the
F16 line in the PS SWY +
LT (including leak
detection and pump
down)
• Beam stoppers
connection to the services
• F16 + LT MSC equipment
connection to the services
• F16 BLMs installation
• SMH16 installation
• PR20 vacuum closure,
leak detection and pump
down
• Scaffolding installation
• BTP smoothing
• Start the MU27 re-
installation
All material that cannot be removed with the MU27
installed must be removed from the PS SWY outer
side before this date
06-Feb-2020
![Page 24: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/24.jpg)
24
14th February 2020
• LV consolidation
• BI line vacuum
connection, leak detection
and pump down
• VSC works to close the
F16 line in the PS SWY +
LT (including leak
detection and pump
down)
• Beam stoppers
connection to the services
• F16 + LT MSC equipment
connection to the services
• F16 BLMs installation
• BTP smoothing
• PR20 vacuum closure,
leak detection and pump
down
• Finish the MU27 re-
installation
06-Feb-2020
![Page 25: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/25.jpg)
25
17th to 21st February 2020
F61 line works
• Equipment installation
Amplifiers cabling for the pickups systems
TE-MSC works to complete the connection of all MUs and Straight section
equipment
Asbestos pipe removed
PS SWY
activities in
the next slide
06-Feb-2020
![Page 26: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/26.jpg)
26
17th February 2020
• LV consolidation
• SEH23 installation +
alignment
• Vacuum leak detection
and pump down of PR20
• MU27 alignment
• PSC10 SS36 cooling
manifold installation
06-Feb-2020
![Page 27: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/27.jpg)
27
18th February 2020
• LV consolidation
• Vacuum leak detection
and pump down of PR20
• Install the stairs on top of
MU27 that allow crossing
between inner and outer
side of the ring
• TE-MSC works to
connect the MU27 and
the straight sections that
are missing
• TE-VSC works to close
the PR30 sector
• PSC10 SS36 cooling
manifold installation
06-Feb-2020
![Page 28: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/28.jpg)
28
19th February 2020
• LV consolidation
• TE-MSC works to
connect the MU27 and
the straight sections that
are missing
• TE-VSC works to close
the PR30 sector
• Vacuum leak detection
and pump down of PR20
• PSC10 SS36 cooling
manifold installation
06-Feb-2020
![Page 29: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/29.jpg)
29
20th February 2020
• LV consolidation
• PR20 Vacuum sector
bake-out
• PR30 leak detection and
pump down
• PSC10 SS36 cooling
manifold installation
06-Feb-2020
![Page 30: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/30.jpg)
30
21st February 2020
• LV consolidation
• PR20 Vacuum sector
bake-out
• PR30 leak detection and
pump down
• PSC10 SS36 cooling
manifold installation
06-Feb-2020
![Page 31: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/31.jpg)
31
TT2
All renovated magnets are aligned with the
exception of:
• BHZ377 and BHZ378
• FTA line magnets (9020, 30 and 40)
• FTN.QFO415
• TT10 line magnets
06-Feb-2020
![Page 32: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/32.jpg)
32
TT2
• Cabling campaigns
• WIC installation
• Minor maintenance activities
• Alignment of the remaining magnets if time allows
06-Feb-2020
![Page 33: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/33.jpg)
B.151• EN-EL works to
power the 40, 80
and 200 MHz
systems from the
new power source
• EN-EL works to
power the TE-MSC
workshop from a
new power source
06-Feb-2020
![Page 34: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/34.jpg)
B.269 - Report• BLM system installation in the racks
• AC cabling
• Smoke detection installed
06-Feb-2020
![Page 35: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/35.jpg)
B.269 – Next 2 weeksIn the coming 2 weeks we will have some co-activity in the building and a
dedicated VIC is needed for all the works starting on week 7 (EN-EL cabling,
IT-CS and EN-EL power)
Note:
Planning and conditions agreed in the VIC must be respected – any change
needed must be re-discussed and documented
C17 +
additional
cabling
campaign
EN-EL works
to power the
racks
CV pipes inspection and repairs
06-Feb-2020
![Page 36: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/36.jpg)
B.355 – Next 2 weeks
EN-EL general
services renovation
EN-CV works in the new PS
CV cooling station
06-Feb-2020
![Page 37: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/37.jpg)
37
B.359 – next 2 weeks
TE-ABT control works
06-Feb-2020
![Page 38: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/38.jpg)
AOB – 5 weeks without access to the PS SWY
06-Feb-2020
![Page 39: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/39.jpg)
AOB
Sector under vacuum
• SS70 to SS80
• SS01 to SS10
06-Feb-2020
![Page 40: PS Planning - Indico€¦ · PS SWY activities in the next slide 06-Feb-2020. 14 6th February 2020 • LV consolidation • LT smoothing • Overhead crane modifications • BTP Alignment](https://reader034.fdocuments.in/reader034/viewer/2022050314/5f762f75e722b15644125ba1/html5/thumbnails/40.jpg)