Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

14
Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status Proton Plan Status June Report June Report Eric Prebys

Transcript of Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Page 1: Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Proton Plan PMG 7/7/05 E Prebys 1

Proton Plan StatusProton Plan Status June Report June Report

Eric Prebys

Page 2: Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Proton Plan PMG 7/7/05 E Prebys 2

AgendaAgenda

• Operations Report – E. Prebys• Technical Progress – E. Prebys• Booster Corrector AIP Status – C. Drennan• Project Status and Cost Report – J. Sims• Plan for Baselining – B. Baller

Page 3: Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Proton Plan PMG 7/7/05 E Prebys 3

Operations Report

Page 4: Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Proton Plan PMG 7/7/05 E Prebys 4

Total Hourly Proton RateTotal Hourly Proton Rate

Total Peak Hourly Rate (BNB+NuMI+pbar)

0

2

4

6

8

10

12

12/1/04 1/30/05 4/1/05 6/1/05 8/1/05 10/1/05 12/1/05

Date

p/h

r (E

16)

Design

Fallback

Actual

Average Hourly Rate (BNB+NuMI+pbar, while up)

0

2

4

6

8

10

12

12/1/04 1/30/05 4/1/05 6/1/05 8/1/05 10/1/05 12/1/05

Date

p/h

r (E

16)

Design

Fallback

Actual

Emphasis on slip stacking problems

Page 5: Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Proton Plan PMG 7/7/05 E Prebys 5

NuMI Proton DeliveryNuMI Proton Delivery

NuMI PoT per Hour (E14)

0

50

100

150

200

250

300

350

400

450

500

3/14

/05

3/28

/05

4/11

/05

4/25

/05

5/9/

05

5/23

/05

6/6/

05

6/20

/05

7/4/

05

7/18

/05

8/1/

05

8/15

/05

8/29

/05

9/12

/05

9/26

/05

Design

Base

Actual

Target Failure

NuMI PoT per Week (E16)

0

50

100

150

200

250

300

350

400

450

500

3/14

/05

3/28

/05

4/11

/05

4/25

/05

5/9/

05

5/23

/05

6/6/

05

6/20

/05

7/4/

05

7/18

/05

8/1/

05

8/15

/05

8/29

/05

9/12

/05

9/26

/05

Design

Base

Actual

Page 6: Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Proton Plan PMG 7/7/05 E Prebys 6

NuMI Integrated (almost caught up)NuMI Integrated (almost caught up)NuMI PoT Cummulative (E18)

0

2

4

6

8

10

12

14

16

18

20

3/14

/05

3/21

/05

3/28

/05

4/4/

05

4/11

/05

4/18

/05

4/25

/05

5/2/

05

5/9/

05

5/16

/05

5/23

/05

5/30

/05

6/6/

05

6/13

/05

6/20

/05

6/27

/05

7/4/

05

Design

Base

Actual

Page 7: Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Proton Plan PMG 7/7/05 E Prebys 7

MiniBooNE (BNB) DeliveryMiniBooNE (BNB) Delivery

Weekly Proton Totals (BNB)

0

2

4

6

8

10

12

12/1/04 1/30/05 4/1/05 6/1/05 8/1/05 10/1/05 12/1/05

Date

To

tal

Pro

ton

s (

E1

8)

Design

Fallback

Actual

Cumulative Proton Totals (BNB)

0

50

100

150

200

250

300

12/1/04 1/30/05 4/1/05 6/1/05 8/1/05 10/1/05 12/1/05

Date

To

tal

Pro

ton

s (

E1

8)

Design

Fallback

Actual

Page 8: Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Proton Plan PMG 7/7/05 E Prebys 8

Technical Progress

Page 9: Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Proton Plan PMG 7/7/05 E Prebys 9

Scope Changes Since Last PMGScope Changes Since Last PMG

• Modified: 1.1.2 (Quad power supplies)

• Significantly reduced in scope• Keep original supplies and upgrade controls electronics• $1M+ -> ~$200K

1.2.1 (Determine rep rate limits)• Modified to include RF reliability concerns

1.3.4 (MI RF Upgrade)• Significantly reduced in scope• (more in a bit)

• Added: 1.2.12 (Booster RF Improvements)

• Systematic plan (based on 1.2.1) to refurbish Booster RF modulators

• Descoped: 1.2.6 (Booster alignment)

• Decided to treat as part of normal operations 1.2.8 (Cavity 20)

• Manpower limitations. Limited success of cavity 19

Page 10: Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Proton Plan PMG 7/7/05 E Prebys 10

ProgressProgress

• Baseline plan Aim for a director’s baseline review 7/21 B. Baller will give more details

• Technical ProgressLinac 1.01.01 PA Vulnerability –

• Committee report completeBooster 1.02.01 Determine rep. rate limit

• Good understanding of what limits repetition rate and reliability

• Generating report• Suggesting a plan of action (1.02.12)

1.02.02 Orbump (+ 400 MeV line) – • New injection scheme passed review!• Three magnets built• Beamline and girder design more or less complete• Power supply passed review• Will be ready for shutdown

Page 11: Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Proton Plan PMG 7/7/05 E Prebys 11

ProgressProgress

Booster 1.02.03 Correctors –

• Design nearly complete• See C. Drennan’s talk

1.02.05 Gamma-t system• Ongoing studies look encouraging• Made decision to scrap existing magnets when we install

the new correctors• If system is useful, will build (12) new magnets between

now and then) 1.02.11 Booster Dump Relocation

• Review going on in WH12NW as we speak, HOWEVER• Considering rather significant change to kicker location• Will be ready for shutdown

1.02.12 Booster RF Improvements• NEW SCOPE• Significant refurbishment plan for Booster modulators• Waiting for recommendations of 1.02.01

Page 12: Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Proton Plan PMG 7/7/05 E Prebys 12

ProgressProgress

Main Injector 1.03.01 Large Aperture Quads –

• On track for shutdown 1.03.02 Collimation –

• MI-8 Collimator design complete and reviewed• Will go in in shutdown• Working on conceptual MI ring collimation

1.03.03 NuMI MultiBatch Operations – • Regularly deliver 5 batches at (Total 2.1E13 protons)

to NuMI target• Aim to start slipstacking earlier than anticipated

1.03.04 RF Upgrade – • Discussed shortly

Studies 1.05 Proton Study Group–

• Preliminary report delivered to PAC on recycler retasking

• Overall report delayed by some more grandiose proposals than we anticipated.

• Hope to have a final report by 8/1

Page 13: Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Proton Plan PMG 7/7/05 E Prebys 13

Main Injector RF (1.03.04)Main Injector RF (1.03.04)

• Great progress has been made in understanding the limitations of the existing feed forward system. Calculations Beam studies

• News is good The preliminary result is that the capacity of the RF system

is >5.5E13 protons with no significant RF upgrade

• Working on specifications for going to 6E13 in the most conservative scenario (i.e. upgrade some fraction of cavities to 2 PA’s)

• This will free up a significant amount of money for other activities (e.g. Booster RF modulator refurbishment)

• Prototype tests proceed, but have been delayed due to badly overcommitted RF group

Page 14: Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.

Proton Plan PMG 7/7/05 E Prebys 14

Near Term PrioritiesNear Term Priorities

• Prepare for shutdown!!! 400 MeV Line+ORBUMP Booster dump relocation MI large aperture quads

• Prepare for baseline review Working on Design Handbook Settling on scope of baseline (B. Baller’s talk)