FIXED MARINE STRUCTURES. Piers Wharves Bulkheads Quays Dolphins Trestles Catwalks Moles.
Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC...
Transcript of Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC...
![Page 1: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/1.jpg)
Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop
Eric Martineau – February 3, 2016
![Page 2: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/2.jpg)
Content
• Current state of the wharf
• Stabilization recommendation
• Construction work
2
![Page 3: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/3.jpg)
Project Objective Ensure the stability of the wharves and enable the use of the wharf and its ground surface for port opera8ons over the medium term.
Q106 Q105
![Page 4: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/4.jpg)
Situation actuelle • Wooden wharf constructed around 1925 • Expected lifespan: 25 years • Max. deforma8ons of the wharf: 1,860 mm (Q105)
3,360 mm (Q106)
![Page 5: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/5.jpg)
Rehabilitation Options Reconstruc8on of the Wharf $26,700,000
![Page 6: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/6.jpg)
Rehabilitation Options Wharf Stabiliza8on – Scenario 1 $5,050,000
![Page 7: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/7.jpg)
Rehabilitation Options Wharf Stabiliza8on – Scenario 2 $3,250,000
![Page 8: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/8.jpg)
Tie-beam Installation Diagram
![Page 9: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/9.jpg)
Construction Work Worksite
![Page 10: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/10.jpg)
Construction Work Drilling Work
![Page 11: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/11.jpg)
Construction Work Soil Basin
![Page 12: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/12.jpg)
Construction Work Conflict with Exis8ng Wharf
![Page 13: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/13.jpg)
Construction Work Tie-‐beam Installa8on
![Page 14: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/14.jpg)
Construction Work Tie-‐beam Tensioning
![Page 15: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016](https://reader035.fdocuments.in/reader035/viewer/2022081600/605b863f3192b37a667b9e18/html5/thumbnails/15.jpg)