PROJECT STATUS UPDATE for Pierce College - May 2015 Master Project/Planning Access analyst completed and provided to PMO design director a definition of scope of work document for completion of campus-wide ADA path-of-travel update so that College Project Team can procure architectural services to complete the update. Work on landscaping and access improvements is currently not moving forward. Limited programming work completed for campus-wide improvements. Design work to be coordinated with completion of other projects. This project includes funds reserved for campus-wide landscaping and accessibility compliance needs. PMO estimate is underway and considerations for High-Low Campus P.O.T is under study. Project Name: Sustainable Landscape and Campus Accessibility Compliance Project Manager: Contractor: Architect: Phase: Project No.: 05P-542 Andrew Ramsay PSOMAS / BERLINER AND ASSOCIATES ARC / TBD Master Project/Planning Current Highlights: Frequency Locaton Meeting Schedule As needed Pierce CPT Trailer Date Time Construction Budget Construction Start N/A Substantial Completion Percent Complete 90% Potentially Deferred Project is pending confirmation of project priorities and timelines under the revised updated master plan. Project is packaged with the SLE-South of Mall campus improvement project. Lanscaping scope to be deferred. Project Name: Landscaping - Park, Access Road, DeSoto and Mason Entrances Project Manager: Contractor: Architect: Phase: Project No.: 05P-542.02 Andrew Ramsay Potentially Deferred Current Highlights: Frequency Locaton Meeting Schedule As Needed Date Time Construction Budget $4,224,122 Construction Start 5/21/2018 Substantial Completion 9/27/2018 Percent Complete 50% Project is packaged with the Digital Arts and Media Building campus improvement project and follows the schedule activities and progress of that project. Project scope to be deferred. Project Name: Lot 5 & 6 East Project Manager: Contractor: Architect: Phase: Project No.: 05P-543.01 Andrew Ramsay PSOMAS / TBD Potentially Deferred Current Highlights: Frequency Locaton Meeting Schedule As Needed Date Time Construction Budget $3,319,843 Construction Start 4/19/2018 Substantial Completion 5/13/2020 Percent Complete 50% p. 1 of 23 Data Date: 06/04/2015

Transcript of PROJECT STATUS UPDATE for Pierce College - May...

Page 1: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Master Project/Planning

Access analyst completed and provided to PMO design director a definition of scope of work document for completion of campus-wide ADA path-of-travel update so that College Project Team can procure architectural services to complete the update. Work on landscaping and access improvements is currently not moving forward. Limited programming work completed for campus-wide improvements. Design work to be coordinated with completion of other projects. This project includes funds reserved for campus-wide landscaping and accessibility compliance needs. PMO estimate is underway and considerations for High-Low Campus P.O.T is under study.

Project Name: Sustainable Landscape and Campus Accessibility Compliance

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-542Andrew Ramsay

PSOMAS / BERLINER AND ASSOCIATES ARC / TBDMaster Project/Planning

Current Highlights:

Frequency

Locaton

Meeting Schedule As needed

Pierce CPT Trailer

Date

Time

Construction Budget

Construction Start N/A

Substantial Completion

Percent Complete 90%

Potentially Deferred

Project is pending confirmation of project priorities and timelines under the revised updated master plan.Project is packaged with the SLE-South of Mall campus improvement project. Lanscaping scope to be deferred.

Project Name: Landscaping - Park, Access Road, DeSoto and Mason Entrances

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-542.02Andrew Ramsay

Potentially Deferred

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $4,224,122

Construction Start 5/21/2018

Substantial Completion 9/27/2018

Percent Complete 50%

Project is packaged with the Digital Arts and Media Building campus improvement project and follows the schedule activities and progress of that project.Project scope to be deferred.

Project Name: Lot 5 & 6 East

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-543.01Andrew Ramsay

PSOMAS / TBD

Potentially Deferred

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $3,319,843

Construction Start 4/19/2018

Substantial Completion 5/13/2020

Percent Complete 50%

p. 1 of 23Data Date: 06/04/2015

Page 2: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

The master plan revision and update have not impacted this scope. Progress is on hold due to prioritization.Project scope to be deferred.

Project Name: Village Road

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-543.04Andrew Ramsay

Potentially Deferred

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $1,916,931

Construction Start 3/16/2018

Substantial Completion 1/20/2019

Percent Complete 50%

Programming RFP

Project was re-evaluated for scope adjustment as part of the revised updated master plan that was approved by BOT. Project is packaged as part of the Digital Arts and Media Building campus improvement project. Negotiation for AOR services have concluded and agreement issuance is underway.

Project Name: Horticulture Building

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-521Andrew Ramsay

TBD

PHILLIPS METSCH SWEENEY M / TBD

Programming RFP

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget

Construction Start See 05P-521.03

Substantial Completion

Percent Complete

Project was re-evaluated for scope adjustment as part of the revised updated master plan that was approved by BOT. Project is packaged as part of the Digital Arts and Media Building campus improvement project. Negotiation for AOR services for demolition of existing facilities have concluded and agreement issuance is underway. Demolition will be procured as a separate construction contract.

Project Name: Horticulture Facility

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-521.03Andrew Ramsay / Nicolas Haddad

J.D. DIFFENBAUGH, INC. / TBD

HILL Partnership / TBD

Programming RFP

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $3,654,484

Construction Start 2/15/2017

Substantial Completion 12/11/2017

Percent Complete 50%

p. 2 of 23Data Date: 06/04/2015

Page 3: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Based on revised updated master plan approved by BOT, preparation for presentation of project to workshop for validation of scope and delivery method is pending.

Project Name: Digital Arts and Media Building

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-533Andrew Ramsay

TBD

DLR GROUP WWCOT / TBD

Programming RFP

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $20,393,866

Construction Start 4/19/2018

Substantial Completion 2/9/2020

Percent Complete 50%

Project is part of the revised updated master plan approved by the BOT. Project scope is being evaluated by campus.

Project Name: Agricultural Education Center

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-534Andrew Ramsay

Programming RFP

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $3,063,041

Construction Start 3/23/2018

Substantial Completion 3/22/2019

Percent Complete 50%

Based on revised updated master plan approved by BOT, preparation for presentation of project to workshop for validation of scope and delivery method is pending.

Project Name: SLE - South of Mall - Classroom Modernization/Technology/Low Voltage

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-535.03Andrew Ramsay

TBD

BERLINER AND ASSOCIATES ARC / TBD

Programming RFP

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $6,120,458

Construction Start 11/13/2017

Substantial Completion 3/11/2019

Percent Complete 50%

Procurement package for AOR services has been advertised. Procurement package for LLB contractor has been developed by CPT.

Project Name: Expanded Automotive and New Technical Education Facilities

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-536Andrew Ramsay

TBD

CARDE TEN ARCHITECTS / TBD

Programming RFP

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $16,997,181

Construction Start 8/29/2017

Substantial Completion 3/13/2019

Percent Complete 60%

p. 3 of 23Data Date: 06/04/2015

Page 4: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Procurement package for AOR services has been advertised. Procurement package for LLB contractor has been developed by CPT.

Project Name: Campus Fire Access Road Improvements

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-542.01Andrew Ramsay

PSOMAS / TBD

Programming RFP

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $228,010

Construction Start 8/29/2017

Substantial Completion 3/14/2019

Percent Complete 60%

Based on revised updated master plan approved by BOT, preparation for presentation of project to workshop for validation of scope and delivery method is pending.

Project Name: SLE - South of Mall - ADA/Landscaping

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-542.07Andrew Ramsay

Programming RFP

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $1,553,635

Construction Start 11/13/2017

Substantial Completion 3/11/2019

Percent Complete 50%

Procurement package for AOR services has been advertised. Procurement package for LLB contractor has been developed by CPT.

Project Name: Parking Lots and Roadways - Anthropology/Geography

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-543.02Andrew Ramsay

TBD

PSOMAS / TBD

Programming RFP

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $1,529,509

Construction Start 2/9/2016

Substantial Completion 11/22/2017

Percent Complete 60%

Procurement package for AOR services has been advertised. Procurement package for LLB contractor has been developed by CPT.

Project Name: Central Plant Expansion - West Central Plant

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-544.05Andrew Ramsay

CARDE TEN ARCHITECTS / TBD

Programming RFP

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $4,232,749

Construction Start 8/10/2017

Substantial Completion 11/19/2018

Percent Complete 60%

p. 4 of 23Data Date: 06/04/2015

Page 5: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Remaining restrooms will be grouped with other projects in the SLE-South of Mall campus improvement package.

Project Name: Restrooms Renovations Campus

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-575Andrew Ramsay

TBD (See 05P-535.03)

Berliner & Associates Arc

Programming RFP

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $233,630

Construction Start 11/13/2017

Substantial Completion 2/19/2018

Percent Complete 27%

In Design

Completion of construction documents is in progress and submission to DSA Awaits close-out of PE General project.

Project Name: P.E. Facilities - Improvements

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-527.04Andrew Ramsay

Carde Ten Architects

In Design

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $600,785

Construction Start 10/6/2017

Substantial Completion 6/11/2018

Percent Complete 90%

AOR activities are needed beyond the 5 year current contract limit for professional services.

Project Name: SLE - Center for the Sciences Technology Upgrades

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-535.10Keykhosrow (Kay) Khadem

TBD

James Heimler, Architect,

In Design

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $542,576

Construction Start 11/29/2017

Substantial Completion 3/28/2018

Percent Complete 90%

Bid Award

BOT approved award of contractor services.

Project Name: Campus-wide Security Upgrade

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-535.11Nicolas Haddad

Diebold, Inc.

Bid Award

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $2,133,540

Construction Start 8/17/2015

Substantial Completion 2/16/2016

Percent Complete 95%

p. 5 of 23Data Date: 06/04/2015

Page 6: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

In Construction

Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.

Project Name: Life Science, Chemistry, Physics Building

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-502Kurt Supinger

FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects, LLPIn Construction

Current Highlights:

Frequency

Locaton

Meeting Schedule Weekly

Pierce CPT Trailer

Date

Time

Thursday

10:00 AM

Construction Budget $15,622,748

Construction Start 10/7/2010

Substantial Completion 5/12/2016

Percent Complete 88%

Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.

Project Name: Phase II Renovations - Administration Building - Interior and Exterior

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-505.02Kurt Supinger

FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects, LLPIn Construction

Current Highlights:

Frequency

Locaton

Meeting Schedule Weekly

Pierce CPT Trailer

Date

Time

Thursday

10:00 AM

Construction Budget $8,552,658

Construction Start 10/7/2010

Substantial Completion 5/12/2016

Percent Complete 93%

General Contractor preconstruction services are underway. Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.

Project Name: Phase II Renovations - Computer Science and Computer Learning

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-507Kurt Supinger

FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects, LLPIn Construction

Current Highlights:

Frequency

Locaton

Meeting Schedule Weekly

Pierce CPT Trailer

Date

Time

Thursday

10:00 AM

Construction Budget $6,568,511

Construction Start 10/7/2010

Substantial Completion 5/29/2017

Percent Complete 36%

p. 6 of 23Data Date: 06/04/2015

Page 7: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

General Contractor preconstruction services are underway. Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.

Project Name: Phase II Renovations - Behavioral Science, Social science, Mathematics, and English Buildings

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-510Kurt Supinger

FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects

In Construction

Current Highlights:

Frequency

Locaton

Meeting Schedule Weekly

Pierce CPT Trailer

Date

Time

Thursday

10:00 AM

Construction Budget $12,766,418

Construction Start 10/7/2010

Substantial Completion 5/29/2017

Percent Complete 16%

Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.

Project Name: Campus Center (Existing) - General

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-530.01Kurt Supinger

FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects, LLPIn Construction

Current Highlights:

Frequency

Locaton

Meeting Schedule Weekly

Pierce CPT Trailer

Date

Time

Thursday

10:00 AM

Construction Budget $1,966,972

Construction Start 10/7/2010

Substantial Completion 5/12/2016

Percent Complete 85%

General Contractor preconstruction services are underway. Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.

Project Name: SLE - North of Mall - Classroom Modernization/Technology/Low Voltage

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-535.02Kurt Supinger

FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects, LLPIn Construction

Current Highlights:

Frequency

Locaton

Meeting Schedule Weekly

Pierce CPT Trailer

Date

Time

Thursday

10:00 AM

Construction Budget $3,868,939

Construction Start 10/7/2010

Substantial Completion 5/29/2017

Percent Complete 0%

p. 7 of 23Data Date: 06/04/2015

Page 8: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

General Contractor preconstruction services are underway and field investigation has been initiated. AOR has received BUG info for reprogramming.

Project Name: SLE Community Services/Agriculture Science Building Renovation

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-535.05Nicolas Haddad

H. A. NICHOLS CO., INC. / Balfour Beatty Construction LLCBERLINER & ASSOCIATES ARC / PBWS Architects, LLPIn Construction

Current Highlights:

Frequency

Locaton

Meeting Schedule As needed

Pierce CPT Trailer

Date

Time

Construction Budget $3,504,745

Construction Start 11/14/2011

Substantial Completion 5/17/2016

Percent Complete 31%

Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.

Project Name: SLE Faculty Center/Campus Center

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-535.07Kurt Supinger

FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects, LLPIn Construction

Current Highlights:

Frequency

Locaton

Meeting Schedule Weekly

Pierce CPT Trailer

Date

Time

Thursday

10:00 AM

Construction Budget $2,748,103

Construction Start 10/7/2010

Substantial Completion 5/12/2016

Percent Complete 85%

LLB Contractor has mobilized. Visitor side recorrective work is underway.

Project Name: Stadium ADA Improvements

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-537Nicolas Haddad

FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCFTR INTERNATIONAL, INC. / PBWS Architects, LLPIn Construction

Current Highlights:

Frequency

Locaton

Meeting Schedule Weekly

Pierce CPT Trailer

Date

Time

Every Thursday

8:00 AM

Construction Budget $10,687,653

Construction Start 7/26/2011

Substantial Completion 8/18/2015

Percent Complete 86%

p. 8 of 23Data Date: 06/04/2015

Page 9: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

General Contractor preconstruction services are underway. Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.

Project Name: SLE - North of Mall - ADA/Landscaping

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-542.06Kurt Supinger

FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects, LLPIn Construction

Current Highlights:

Frequency

Locaton

Meeting Schedule Weekly

Pierce CPT Trailer

Date

Time

Thursday

10:00 AM

Construction Budget $5,710,748

Construction Start 10/7/2010

Substantial Completion 5/29/2017

Percent Complete 47%

Procurement package for AOR services has been advertised. Procurement package for LLB contractor has been developed by CPT.

Project Name: Mason Reroute

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-543.03Andrew Ramsay

Kanaan Construction, Inc. / TBD (See 05P-536)PSOMAS / TBD

In Construction

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $2,095,319

Construction Start 5/25/2011

Substantial Completion 3/4/2018

Percent Complete 22%

CPT has received GMP from contractor. Contract executed. Notice to proceed with construction issued to start on June 10, 2015.

Project Name: Campus-wide Telecommunications Upgrade (VoIP)

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-544.04Kurt Supinger

Balfour Beatty Construction LLC

PSOMAS / PBWS Architects, LLP

In Construction

Current Highlights:

Frequency

Locaton

Meeting Schedule Weekly

Pierce CPT Trailer

Date

Time

Thursday

10:00 AM

Construction Budget $2,211,299

Construction Start 2/21/2013

Substantial Completion 9/9/2015

Percent Complete 0%

p. 9 of 23Data Date: 06/04/2015

Page 10: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

In Close Out

Project merged with the Digital Arts and Media Building project. Based on revised updated master plan approved by BOT, project scope development and project initiation is pending.

Project Name: Convert Existing Library

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-508.01Andrew Ramsay

In Close Out

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget

Construction Start See 05P-533

Substantial Completion

Percent Complete 100%

Close-out is incomplete construction contract to complete corrections to the ADA parking has been awarded. This completion contract has been packaged with the NOM CIP. AOR revising drwgs to reflect existing conditions.

Project Name: Photovoltaic Arrays for Parking Lots 1 & 8

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-544.03Kurt Supinger

Chevron Energy Solutions Co. / Balfour Beatty Construction LLCChevron Energy Solutions Co. / PBWS Architects, LLPIn Close Out

Current Highlights:

Frequency

Locaton

Meeting Schedule As needed

Pierce CPT Trailer

Date

Time

Construction Budget $10,135,944

Construction Start 12/28/2010

Substantial Completion 1/10/2012

Percent Complete 90%

In DSA Closeout

Fire sprinkller CCD submission to DSA has ocurred. AOR preparing Smart board Bid package. PL7 accessible parking CD's have been reviewed by CPT - AOR to provide revisions.

Project Name: Center for the Sciences

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-501Ed Cadena

Sinanian Development, Inc

Hellmuth, Obata & Kassaba / CWA AIA, Inc.

In DSA Closeout

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $47,842,460

Construction Start 8/27/2007

Substantial Completion 8/6/2010

Percent Complete 87%

p. 10 of 23Data Date: 06/04/2015

Page 11: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Close-out ongoing. Acoustical treatment in corridor for noise attenuation will be added to the SLE-South of Mall campus improvements package.

Project Name: Phase I Renovations - Business Education

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-513.01Doug Cottone

Delmac Construction

Fsy Architects, Inc.

In DSA Closeout

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $1,431,008

Construction Start 1/9/2009

Substantial Completion 8/9/2010

Percent Complete 66%

Close-out ongoing.

Project Name: Phase I Renovations - Faculty Office

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-515Doug Cottone

FEI Enterprises, Inc / A.G. Araja EngineeringJohnson Fain Inc. / FSY Architects, Inc.

In DSA Closeout

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $2,203,305

Construction Start 1/9/2009

Substantial Completion 6/22/2009

Percent Complete 86%

Close-out ongoing.

Project Name: Phase I Renovations - Fine Arts and Music

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-516Doug Cottone

FEI Enterprises, Inc / Delmac Construction / A.G. Araja EngineeringJohnson Fain Inc. / FSY Architects, Inc.

In DSA Closeout

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $3,037,300

Construction Start 1/9/2009

Substantial Completion 12/30/2009

Percent Complete 86%

p. 11 of 23Data Date: 06/04/2015

Page 12: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Building occupied effective 1/31/2015. Rented swing space has been demobilized. Intercom for Arena Theater is being sourced by the completing contractor.

Project Name: Early Renovations - Theater Building - Performing Arts

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-518.03Doug Cottone

TAISEI CONSTRUCTION / GMZ Engineering, Inc. / TBDFSY ARCHITECTS, INC. / TAISEI CONSTRUCTIONIn DSA Closeout

Current Highlights:

Frequency

Locaton

Meeting Schedule As needed

Pierce CPT Trailer

Date

Time

Construction Budget $798,384

Construction Start 4/17/2012

Substantial Completion 1/26/2015

Percent Complete 99%

Building occupied effective 1/31/2015. Rented swing space has been demobilized. Intercom for Arena Theater is being sourced by the completing contractor.

Project Name: Performing Arts Building Improvements

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-518.04Doug Cottone

TAISEI CONSTRUCTION / GMZ Engineering, Inc. / TBDTAISEI CONSTRUCTION

In DSA Closeout

Current Highlights:

Frequency

Locaton

Meeting Schedule As needed

Pierce CPT Trailer

Date

Time

Construction Budget $12,323,577

Construction Start 4/17/2012

Substantial Completion 9/10/2014

Percent Complete 99%

Original contract scope completed with the exception of some isolated outstanding items remaining to be completed under a separate close-out construction contract. AOR is reengaged in developing CCD and construction documents.

Project Name: P.E. Facilities - General

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-527.01Doug Cottone

FTR INTERNATIONAL, INC. / TBD

Steinberg Architects

In DSA Closeout

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $17,423,876

Construction Start 8/25/2008

Substantial Completion 2/1/2010

Percent Complete 56%

p. 12 of 23Data Date: 06/04/2015

Page 13: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Close-out ongoing.

Project Name: P.E. Facilities - Pool Piping and Deck

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-527.03Doug Cottone

Ftr International, Inc.

Steinberg Architects

In DSA Closeout

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $825,000

Construction Start 8/25/2008

Substantial Completion 2/1/2010

Percent Complete 56%

Project has been submitted for DSA close-out. Punchlist has been satisfied.

Project Name: New Maintenance and Operations Facility

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-540Doug Cottone

Gkkworks

Gkkworks

In DSA Closeout

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $13,120,963

Construction Start 7/13/2010

Substantial Completion 12/1/2011

Percent Complete 77%

Close-out and follow-on punch list closeout ongoing.

Project Name: Library/Learning Crossroads Building

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-541Doug Cottone

Bernards Bros. Inc.

Bernards Bros. Inc. (HMC)

In DSA Closeout

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $36,861,971

Construction Start 4/12/2011

Substantial Completion 3/22/2013

Percent Complete 10%

Corrective work partially completed. CPT to prepare Scope of Work for AOR RFP.

Project Name: FTA Bus Rapid Transit Extension & Winnetka / Mason DeSoto Entrances

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-588.03Ed Cadena

PIMA CORPORATION / GMZ Engineering

BERLINER AND ASSOCATIONS ARC / TBDIn DSA Closeout

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $1,281,226

Construction Start 4/20/2009

Substantial Completion 4/6/2010

Percent Complete 77%

p. 13 of 23Data Date: 06/04/2015

Page 14: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Completed

Close-out ongoing.

Project Name: Child Development Center

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-509Doug Cottone

L.A. Builders, Inc.

Carde Ten Architects

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $8,794,230

Construction Start 6/11/2008

Substantial Completion 8/2/2010

Percent Complete 100%

Close-out ongoing.

Project Name: Measure J Animal Science Facilities

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-521.04Ed Cadena

Gmz Engineering, Inc.

Ktgy Group, Inc.

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $245,057

Construction Start 6/7/2012

Substantial Completion 9/4/2012

Percent Complete 100%

Completed.

Project Name: Animal Science Facilities

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-522Ed Cadena

Tobo Construction, Inc.

PMSM / Berliner & Associates Architects

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $1,179,607

Construction Start 7/28/2008

Substantial Completion 7/31/2009

Percent Complete 100%

Completed.

Project Name: Campus Sheriff Station

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-525Ed Cadena

Profile Structures, Inc.

Amador Whittle Architects

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $530,263

Construction Start 10/7/2006

Substantial Completion 4/10/2007

Percent Complete 100%

p. 14 of 23Data Date: 06/04/2015

Page 15: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Close-out ongoing. DSA Certification obtained.

Project Name: Exhibition & Events Center - Phase 1B

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-526.03Doug Cottone

Tobo Construction, Inc.

Froehlich, Kow & Gong

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $2,022,152

Construction Start 9/18/2007

Substantial Completion 6/11/2009

Percent Complete 100%

Close-out ongoing. DSA Certification obtained.

Project Name: Exhibition & Events Center - Phase 1B - Fence Relocation

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-526.06Doug Cottone

ENVIRONMENTAL CONSTRUCTION / GMZ Engineering, Inc. / TBDFROEHLICH, KOW & GONG

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $1,525,904

Construction Start 4/18/2011

Substantial Completion 3/28/2014

Percent Complete 98%

Completed.

Project Name: Student Services Building

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-528Ed Cadena

Akg Construction, Inc.

Wwcot

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $17,835,704

Construction Start 9/28/2007

Substantial Completion 10/12/2009

Percent Complete 100%

Close-out ongoing.

Project Name: Old Book Store Renovation

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-529Ed Cadena

Kahromic Contracting, Inc

Johnson Fain Inc.

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $2,436,714

Construction Start 3/2/2007

Substantial Completion 4/4/2008

Percent Complete 100%

p. 15 of 23Data Date: 06/04/2015

Page 16: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Close-out ongoing.

Project Name: SLE - College Services (CSB) Building Mailroom Relocation

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-535.01Ed Cadena

G. Coast Construction,Inc

Berliner & Associates Arc

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $631,448

Construction Start 1/26/2010

Substantial Completion 9/24/2010

Percent Complete 100%

Close-out ongoing.

Project Name: SLE Temporary CDC Reuse

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-535.06Ed Cadena

Gmx Construction, Inc.

Steinberg Arch Inactive

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $772,094

Construction Start 9/1/2010

Substantial Completion 3/15/2011

Percent Complete 100%

Close-out ongoing.

Project Name: SLE - Faculty Office Replastering

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-535.08Ed Cadena

Ranbay Construction Corp. / GMZ Engineering, Inc.Fsy Architects, Inc.

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $470,922

Construction Start 6/23/2011

Substantial Completion 8/17/2012

Percent Complete 100%

Close-out ongoing.

Project Name: SLE- Campus Wide Improvements

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-535.09Doug Cottone

Simple Design

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $96,115

Construction Start 7/25/2011

Substantial Completion 11/30/2012

Percent Complete 100%

p. 16 of 23Data Date: 06/04/2015

Page 17: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Close-out ongoing.

Project Name: SMP - Irrigation Systems Replacement/Lot 5

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-542.05Keykhosrow (Kay) Khadem

Pierre Sprinkler & Landscape

Cwa Aia, Inc.

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $438,836

Construction Start 3/19/2012

Substantial Completion 5/22/2012

Percent Complete 100%

Master project. Programming study on campus wide improvements to parking lots and roadways was previously completed.

Project Name: Parking Lots and Roadways

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-543Ed Cadena

BERLINER AND ASSOCIATES ARC

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget

Construction Start N/A

Substantial Completion

Percent Complete 100%

Completed.

Project Name: RWGPL - Horticulture Intersection at Brahma Drive

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-543.06Ed Cadena

Ranbay Construction Corpo

Psomas

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $397,870

Construction Start 6/1/2010

Substantial Completion 8/15/2010

Percent Complete 100%

Completed.

Project Name: PLRW - Lot 6 West

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-543.07Ed Cadena

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $3,079,724

Construction Start

Substantial Completion 9/15/2010

Percent Complete 100%

p. 17 of 23Data Date: 06/04/2015

Page 18: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Master project. Programming study on campus-wide infrastructure upgrades completed. Scope has been distributed to appropriate new construction projects. May need to be revisited for adjustments based on revised and updated master plan.

Project Name: Infrastructure Expansion Master

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-544Ed Cadena

PSOMAS

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget

Construction Start N/A

Substantial Completion

Percent Complete 100%

Completed.

Project Name: Waterless urinals

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-554.01Ed Cadena

Brej Corporation

Winzler & Kelly

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $65,513

Construction Start 8/21/2008

Substantial Completion 11/21/2008

Percent Complete 100%

Completed.

Project Name: RWGPL - Brahma Drive

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-573.01Doug Cottone

Djm Construction Company

Psomas

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $1,957,333

Construction Start 4/23/2007

Substantial Completion 8/25/2008

Percent Complete 100%

Completed.

Project Name: Campus-Wide Improvements - Parking Lot 7

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-573.02Ed Cadena

Griffith Company

Psomas

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $2,909,200

Construction Start 6/20/2002

Substantial Completion 10/9/2002

Percent Complete 100%

p. 18 of 23Data Date: 06/04/2015

Page 19: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Completed as a part of 05P-526.03 Exhibition & Events Center - Phase 1B. Close-out underway.

Project Name: RWGPL - West Parking Lot

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-573.04Ed Cadena

Psomas

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget

Construction Start

Substantial Completion

Percent Complete 100%

Close-out underway.

Project Name: RWGPL - East Parking Lot @ Exhibition / Ag Science

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-573.05Ed Cadena

Griffith Company

Psomas

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $2,358,846

Construction Start 6/2/2008

Substantial Completion 9/2/2008

Percent Complete 100%

Completed.

Project Name: RWGPL - Parking Lot 1

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-573.06Doug Cottone

Griffith Company

Psomas

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $2,238,763

Construction Start 10/1/2008

Substantial Completion 2/9/2009

Percent Complete 100%

Program close-out ongoing.

Project Name: Landscape and Site Master Plan

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-573.09Ed Cadena

United Contractors Co.,

Berliner & Associates Arc

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $6,521,113

Construction Start 4/24/2009

Substantial Completion 5/31/2011

Percent Complete 100%

p. 19 of 23Data Date: 06/04/2015

Page 20: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Completed.

Project Name: Early Release Package - El Rancho Road

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-573.12Ed Cadena

Djm Construction Company

Psomas

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $1,417,899

Construction Start 4/23/2007

Substantial Completion 8/25/2008

Percent Complete 100%

Close-out is ongoing.

Project Name: RWGPL - Botanical Garden

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-573.13Ed Cadena

Grounds Control, Inc.

Division Of The State Arc

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $232,204

Construction Start 1/9/2007

Substantial Completion 2/15/2008

Percent Complete 100%

Completed.

Project Name: Temporary Facilities - Relocation, Acquisition (Village)

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-577.01Ed Cadena

Profile Structures, Inc.

Amador Whittle Architects

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $7,674,188

Construction Start 4/3/2006

Substantial Completion 4/9/2007

Percent Complete 100%

Completed.

Project Name: Temporary Facilities - SMCI Trailers & Swing Space Utilities

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-577.02Ed Cadena

Tek Up Construction, Inc.

Division Of The State Arc

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $675,433

Construction Start 2/2/2004

Substantial Completion 4/15/2005

Percent Complete 100%

p. 20 of 23Data Date: 06/04/2015

Page 21: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Completed.

Project Name: Temporary Village Expansion

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-577.05Ed Cadena

Singpoli Construction

Gonzalez Goodale Architec

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $2,689,437

Construction Start 5/28/2008

Substantial Completion 9/2/2008

Percent Complete 100%

Close-out underway.

Project Name: Temporary Village Expansion - Electrical / Low Voltage

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-577.06Ed Cadena

Unique Home Remodeling

Steinberg Arch Inactive

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $70,131

Construction Start 6/9/2009

Substantial Completion 8/20/2009

Percent Complete 100%

Close-out underway.

Project Name: Temporary Village Expansion - Partitions

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-577.07Ed Cadena

Barrett Robinson Inc.

Steinberg Arch Inactive

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $20,800

Construction Start 7/1/2009

Substantial Completion 7/27/2009

Percent Complete 100%

Close-out underway.

Project Name: Campus Improvements - Utilities

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-579.01Ed Cadena

Chevron Energy Solutions

Psomas

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $20,870,331

Construction Start 1/24/2008

Substantial Completion 3/16/2010

Percent Complete 100%

p. 21 of 23Data Date: 06/04/2015

Page 22: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Program close-out ongoing.

Project Name: Campus-Wide Improvements - Central Plant

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-579.05Ed Cadena

Chevron Energy Solutions

Tetra Design, Inc.

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $7,341,577

Construction Start 7/28/2009

Substantial Completion 1/7/2011

Percent Complete 100%

Completed.

Project Name: Campus Improvements - Utilities Early Release Package

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-579.06Ed Cadena

Djm Construction Company

Pc Associates

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $8,644,052

Construction Start 4/23/2007

Substantial Completion 8/25/2008

Percent Complete 100%

Program close-out ongoing.

Project Name: SMP - Remove & Replace Transit Pipes

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-588.08Ed Cadena

FTR INTERNATIONAL, INC.

Completed

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $398,424

Construction Start 7/21/2009

Substantial Completion 11/24/2009

Percent Complete 100%

Cancelled

Project cancelled.

Project Name: Green Technologies Building

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-532Ed Cadena

Cancelled

ZIMMER GUNSUL FRASCA ARCHITECT

Cancelled

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $196,970

Construction Start N/A

Substantial Completion N/A

Percent Complete 0%

p. 22 of 23Data Date: 06/04/2015

Page 23: PROJECT STATUS UPDATE for Pierce College - May 2015pshare.piercecollege.edu/committees/pcc/Shared... · 6/25/2015  · Project Name: Life Science, Chemistry, Physics Building Project

PROJECT STATUS UPDATE for Pierce College - May 2015

Project has been fully defunded. Project has been cancelled.

Project Name: Agoura Satellite Center - Land Acquisition

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-538.01Ed Cadena

Cancelled

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget

Construction Start

Substantial Completion

Percent Complete 0%

Project has been cancelled as an outcome of the revision and updating of the master plan.

Project Name: Parking Lots and Roadways - Off-site Traffic Mitigation

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-543.05Ed Cadena

Cancelled

PSOMAS

Cancelled

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget

Construction Start

Substantial Completion

Percent Complete 0%

Scope has been distributed to related new construction projects. Electrical feeders remained under this project. Project to be deferred.

Project Name: Infrastructure - Campus-Wide Utilities Extensions

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-544.01Andrew Ramsay

Berliner & Associates Arc

Deferred

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget $1,347,473

Construction Start 7/13/2018

Substantial Completion 7/13/2018

Percent Complete 90%

Project has been cancelled as an outcome of the revision and updating of the master plan.

Project Name: Campus Improvements - Traffic Mitigation

Project Manager:

Contractor:

Architect:

Phase:

Project No.: 05P-579.02Ed Cadena

Cancelled

PSOMAS

Cancelled

Current Highlights:

Frequency

Locaton

Meeting Schedule As Needed Date

Time

Construction Budget

Construction Start

Substantial Completion

Percent Complete 0%

p. 23 of 23Data Date: 06/04/2015