Project Status Review Meeting - SUMMARY · page 2 of 4 are also bringing in exciting, related...

27
page 1 of 4 MEETING SUMMARY PURPOSE Project Status Review Meeting #44 DATE Wednesday, June 23, 2010 TIME 8:30AM – 10:00AM LOCATION 219 HB PARTICIPANTS Tom Krepel, Doreen Larson, Dave Tamm, Sharon Handelsman, Rich McCormick, Rick Porto, Maria Rose, Mary Jo Thomas, Andy Raisovich, Steve Shala, Evie Brantmayer, Dan Gockley, Erica Harvey, Shane Jordan, and Peter Wilkins. NOTE: A copy of the meeting agenda and handouts distributed to participants is appended to this summary report. This information is also posted on the institution’s website, under the Information Technology page at the following link: http://www.fairmontstate.edu/IT/PMO/ProjectStatusReviews.asp SUMMARY OF MAJOR PROJECTS Peter reviewed the items that were distributed to attendees with the meeting handout package. The Project Summary Report (Dashboard) shows two completed and seven active projects. The group also browsed the Major Project Summary Gantt Chart, and noted activity variations against the baseline schedules for the three projects highlighted in yellow. PROJECT STATUS REPORT UPDATES Online Application Redesign – The application was turned on in production on the morning of June 1, 2010. Preliminary data point to a higher application completion rate by roughly 10%. Andy reported the project complete. He also explained that there could be issues that were not found during testing, and we must rely on reports from applicants to identify these problems, but so far none have been reported and many applications have come in using this method. MAPWorks Implementation Erica reported that Sharon Handelsman has joined the MAPWorks implementation team for 201011 and is providing a helpful and positive “broad view” of the implementation. Dan Gockley, Pam Stephens and Andrea Pammer

Transcript of Project Status Review Meeting - SUMMARY · page 2 of 4 are also bringing in exciting, related...

page 1 of 4

MEETING SUMMARY  

PURPOSE  Project Status Review Meeting #44 

DATE  Wednesday, June 23, 2010 

TIME  8:30AM – 10:00AM 

LOCATION  219 HB 

PARTICIPANTS  Tom Krepel, Doreen  Larson, Dave  Tamm,  Sharon Handelsman, Rich McCormick, Rick Porto, Maria Rose, Mary Jo Thomas, Andy Raisovich, Steve  Shala,  Evie  Brantmayer,  Dan  Gockley,  Erica  Harvey,  Shane Jordan, and Peter Wilkins. 

NOTE:      A  copy  of  the meeting  agenda  and  handouts  distributed  to  participants  is appended to this summary report.   This  information  is also posted on the  institution’s website,  under  the  Information  Technology  page  at  the  following  link: http://www.fairmontstate.edu/IT/PMO/ProjectStatusReviews.asp

SUMMARY OF MAJOR PROJECTS 

Peter reviewed the items that were distributed to attendees with the meeting  handout  package.    The  Project  Summary  Report (Dashboard)  shows  two  completed  and  seven  active projects.    The group  also  browsed  the Major  Project  Summary Gantt  Chart,  and noted activity variations against the baseline schedules for the three projects highlighted in yellow. 

PROJECT STATUS REPORT UPDATES 

Online  Application  Redesign  –  The  application  was  turned  on  in production on the morning of June 1, 2010.  Preliminary data point to a higher application completion rate by roughly 10%.  Andy reported the project complete.   He also explained  that  there could be  issues that were not found during testing, and we must rely on reports from applicants  to  identify  these  problems,  but  so  far  none  have  been reported and many applications have come in using this method. 

MAP‐Works  Implementation  –  Erica  reported  that  Sharon Handelsman  has  joined  the  MAP‐Works  implementation  team  for 2010‐11 and  is providing a helpful and positive “broad view” of  the implementation.   Dan Gockley,  Pam  Stephens  and Andrea  Pammer 

page 2 of 4

are also bringing in exciting, related retention initiatives from Student Affairs.   She explained  that  their presentation was accepted  for  the fall IUPUI Assessment Conference entitled, “A Hierarchy of Freshman Assessment  and  Retention:  Spotlighting  Three  Levels.”    IT Collaboration with  EBI  staff  to  automate  data  loads  is  expected  to begin  in early  July.   Andy Raisovich agreed  that  this activity  can be continued by IT outside of the scope of this project, so the project can still be completed on schedule with the final report to HEPC at month end. 

Banner Workflow – Andy  informed  the group  that  this project was completed and put  in production as of  June 23rd.   He explained  the testing that occurred over the course of the spring on the mechanism that actually sends the emails out (the workflow engine), and thus far has proved reliable. 

Automated Decision Rules – Evie stated that work will resume on this project  and  IT  work  is  scheduled  to  be  complete  by  end  of  July.  Testing and training will be done  in September and October with go live  at  end  of  October,  in  sync  with  the  Admissions  Workflow Implementation project.  

Housing  Information System – Dan reported that oral presentations were held on May 18‐19th, and financial proposals were opened and reviewed  on May  25th.    Responses were  received  by  Procurement and the successful vendor finalized.  Procurement is notifying vendors regarding  the  outcome  of  the  process  and  the  contract  will  be finalized  as  soon  as  possible.    The  successful  vendor  indicates  the standard implementation requires five (5) months following the kick‐off of the project, and most  likely project completion will delay until the end of the fall semester.  The development phase will occur later in the summer at a time when housing staff are preparing for the fall opening.   The goal was to have development out of the way by that time.   Migrating  to  the new  system  in  the  fall  semester  should  still allow most new students to apply using the new system. 

Data  Center‐  IBM  Chassis/Blade  Replacement  and  SAN  Storage  –Steve explained that BC6 was successfully brought on‐line by May 14, while  the  decommission  of  BC  2  will  be  delayed  until  the decommissioning  of  our  Exchange  2003  system  later  this  year.  Correction  of  issues  encountered  during  project  execution  requires changes to our fiber channel SAN fabric.  This should be completed by July 1st.   This was not  in  the  scope of  the project but necessary  to move  forward  with  other  projects.  Completion  remains  slated  for September 30th. 

Exchange 2010 Transition –   Steve stated that we have worked with Microsoft to find that we can run Exchange 2010 in our environment.  

page 3 of 4

This was  verified  this with Cisco,  and we  have  tested  the  install  of Exchange 2010 in a virtual environment to minimize any issues during the  real  install.    Hardware  is  fully  configured with  SAN  space  and prerequisites and  read  for  full  install  in  the next  few days.   We are behind on our build and  testing  scheduled however using Exchange 2010  simplifies  our  configuration  which  should  allow  us  to  regain some lost time.  At this point we are still planning on having all active mailboxes migrated before the fall semester. 

Content Management System – Upgrade to 6.x – Shane reported this project  chartered and approved on  June 3rd.   The project began on schedule and meetings have been held to solicit suggestions  for the upgrade and also to discuss the separation of the web site into micro sites.   An  initial group of business units have been  identified.   There was a meeting with  the deans where we  talked about  the web  site upgrade and informed them of the changes that are coming. 

Oracle Database Upgrade (Banner) – This project was chartered as of June 11th with  J.R.  Farley  the designated PM.   The official  ‘start’ of defined  project  tasks  is  almost  two weeks  away,  but we’ve made efforts to co‐ordinate with campus offices regarding the testing plans, and many have already been submitted for approval. 

PENDING PROJECTS 

Admissions Workflow Implementation – Sharon described the value associated  with  this  project  to  include  moving  away  from  paper processing  and  the  inclusion  of  training  for  various  stakeholder groups who will  be  impacted  by  the  change. A  project  charter  has been  created,  was  discussed  among  Enrollment  Services  and  IT management, and is ready for approval. 

Non‐Credit  Online  Education  Registration‐Stage  2  ‐  The  payment processor  integration  between  the  Lumens  software  and  the Treasurer’s office has been completed for WVU and they’re ready to start talking to the vendor (Augustsoft) about purchasing the product.  A project charter is expected to be drafted shortly. 

Virtualization of Phone System – This project awaits Cisco’s support decision and timeline. 

Online Application for Graduate Programs – A meeting  is slated for June 28th to refine requirements, and advance the project chartering process. 

Recruiter  Goals  and  Tracking  –  Expected  to  be  activated  and completed in the near‐term. 

VMS Platform Retirement – Phase 2 – Andy informed the group that he  is working  on ways  to  emulate  the  platform  and  bring  about  a 

page 4 of 4

migration to mitigate the risk, and cost, of continuing to operate this outdated technology. 

Rolling  Semesters  Investigation  –  Doreen  emphasized  the importance of this capability to PCTC, and asked that  it be escalated in priority.  She will serve as Sponsor with Rich’s retirement. 

Blackboard – Vista to Learn 9.1 Upgrade.   

Intranet Development – Dave stated that a charter is expected by the end of July. 

Address  Correction  Software  –  Sharon  reported  that  we  have  re‐opened our study in this area, and are looking to a vendor demo, and updated proposal. 

Enterprise  Data  Warehouse  and  Operational  Data  Store Implementation – Dave described this project as a strategic initiative for 2010‐11. 

IT Procurement Process Automation  ‐ Dave mentioned an effort  to streamline  the  process  under  the  wing  of  the  newly  formed  TLC (Teaching and Learning Commons). 

NEW BUSINESS 

 

Sharon  requested  the  addition  of  web‐based  scheduling  of classrooms  to  the  list  of  pending  projects,  and  explained  the predecessor  activity  underway  to  “inventory”  the  various  types  of classrooms and centrally record their attributes. 

Rick  noted  the  omission  of  the  Competitive  Program  Online Application  initiative  from the pending project  list, and asked that  it be reinstated. 

Rick  also explained  that  the  State Auditor’s office has  contacted us and  requested  our  participation  in  a  pilot  exercise  around  travel reporting. 

NEXT MEETING  Date:         Thursday, August 12, 2010 Time:         10:00AM – 11:30AM Location:   219 HB 

 

MEETING AGENDA Subject: Project Status Review #44 Date: Wednesday, June 23, 2010 Time: 8:30AM – 10:00AM Location: 219 HB Project Summary Information:

• Project Summary Report – Dashboard • Major Project Overview – Summary Gantt Chart

Project Status Report Updates: • Online Application Redesign • MAP-Works Implementation • Banner Workflow • Automated Decision Rules • Housing Information System • Data Center - IBM Chassis/Blade Replacement and SAN Storage

Expansion • Exchange 2010 Transition • Content Management System - Upgrade to 6.x • Oracle Database Upgrade (Banner)

Pending Projects: • Admissions Workflow Implementation • Non-Credit Online Education Registration-Stage 2 • Virtualization of Phone System • Online Application for Graduate Programs • Recruiter Goals and Tracking • VMS Platform Retirement-Phase 2 • “Rolling Semesters” Investigation • Blackboard - Vista to Learn 9.1 Upgrade • Intranet Development • Address Correction Software • Enterprise Data Warehouse and Operational Data Store Implementation • IT Procurement Process Automation

New Business Schedule Next Meeting Adjourn

page 1

Estimate Actual

Online Application Redesign 090717‐01 Sharon Handelsman Andy Raisovich COMPLETE Jul‐09 Jul‐09 Jun‐10

MAP‐Works Implementation 090727‐01 Maria Rose Erica Harvey ACTIVE Jul‐09 Jul‐09 Jun‐10

Banner Workflow 090910‐01 Sharon Handelsman Andy Raisovich COMPLETE Sep‐09 Sep‐09 Jun‐10

Automated Decision Rules 091103‐01 Sharon Handelsman Evie Brantmayer ACTIVE Nov‐09 Nov‐09 Oct‐10

Housing Information System 100115‐01 Sharon Handelsman Dan Gockley ACTIVE Feb‐10 Feb‐10 Oct‐10

Data Center‐IBM Chassis/Blade Replacement & SAN Storage 100129‐01 Dave Tamm Steve Shala ACTIVE Nov‐09 Jan‐10 Sep‐10

Exchange 2010 Transition 100409‐01 Dave Tamm Steve Shala ACTIVE Apr‐10 Apr‐10 Sep‐10

Content Management System ‐ Upgrade to 6.x 100603‐01Dave Tamm                    M J Th

Shane Jordan ACTIVE Jun‐10 Jun‐10 Dec‐10

PROJECT SUMMARY REPORTApproval Date

Project Name StatusProject Identifier

Project StatusProject Sponsor Project ManagerCompletion Date

Start Date

Content Management System   Upgrade to 6.x 100603 01Mary Jo Thomas

Shane Jordan ACTIVE Jun 10 Jun 10 Dec 10

Oracle Database Upgrade (Banner) 100611‐01 Dave Tamm J.R. Farley ACTIVE Jun‐10 Jun‐10 Sep‐10

Admissions Workflow Implementation TBD Sharon Handelsman Andy Raisovich PENDING

Non‐Credit Online Education Registration‐Stage 2 TBD Sharon Handelsman Andy Raisovich PENDING

Virtualization of Phone System TBD Dave Tamm Steve Shala PENDING

Online Application for Graduate Programs TBD Sharon Handelsman Andy Raisovich PENDING

Recruiter Goals and Tracking TBD Sharon Handelsman TBD PENDING

VMS Platform Retirement‐Phase 2 TBD Dave Tamm Andy Raisovich PENDING

"Rolling Semesters" Investigation TBD Rich McCormick Andy Raisovich PENDING

Blackboard ‐ Vista to Learn 9.1 Upgrade TBD Dave Tamm Andy Raisovich PENDING

Intranet Development TBD Dave Tamm Andy Raisovich PENDING

Address Correction Software TBD Dave Tamm Andy Raisovich PENDING

Enterprise Data Warehouse and Operational Data Store Implementation

TBD Dave Tamm Andy Raisovich PENDING

IT Procurement Process Automation TBD Dave Tamm Joanie Raisovich PENDING

page 2

ID Task Name Start Finish

1 Online Application Redesign Mon 7/6/09 Tue 6/1/10

2 Develop list of needed application types Mon 7/6/09 Thu 7/9/09

3 Create blocks and questions for each application type Wed 7/15/09 Tue 7/28/09

4 Finalize decision tree Mon 7/6/09 Tue 7/21/09

5 Prepare and Review Presentation for Online Applications Wed 7/22/09 Sun 9/27/09

6 Present Prototype of Online Applications Mon 9/28/09 Mon 9/28/09

7 UNDERGRADUATE PROGRAMS Tue 9/29/09 Tue 6/1/10

8 Develop Decision Tree programs Tue 9/29/09 Mon 12/14/09

9 Application Development Mon 12/14/09 Fri 3/5/10

10 Tailor application questions in Banner Mon 10/26/09 Fri 3/5/10

11 Demonstration to CCB Mon 3/8/10 Mon 3/8/10

12 Testing by Enrollment Services Tue 3/9/10 Mon 5/31/10

13 Production Go-Live Tue 6/1/10 Tue 6/1/10

1415 MAP-Works Implementation Wed 7/1/09 Wed 6/30/10

16 License software Wed 7/1/09 Thu 8/13/09

17 IT Collaboration with EBI staff to automate data loads Wed 7/29/09 Tue 6/29/10

18 Initial load of faculty/staff users Wed 7/29/09 Mon 8/17/09

19 Initial load of freshman students and demographic informatio Thu 7/2/09 Thu 9/3/09

20 IRB and Registrar approvals Wed 8/19/09 Wed 8/19/09

21 Complete initial system configuration and customization Tue 7/28/09 Tue 9/8/09

22 Define additional configuration requirements Tue 9/15/09 Thu 10/15/09

23 Complete final system configuration and customization Fri 10/16/09 Tue 12/15/09

24 Define and communicate expectations for intervention effort Wed 7/1/09 Fri 10/30/09

25 Design survey Mon 7/13/09 Fri 9/4/09

26 Marketing plan implementation Tue 7/21/09 Wed 9/30/09

27 Train faculty/staff Mon 8/17/09 Fri 10/30/09

28 Deploy student survey Tue 9/8/09 Fri 9/18/09

29 Decision about follow-up survey and marketing Thu 10/1/09 Mon 10/19/09

Jun Jul u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan00 Qtr 3, 200 Qtr 4, 200 Qtr 1, 201 Qtr 2, 201 Qtr 3, 201 Qtr 4, 201 Qtr

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Project: Major Project OverviewDate: Tue 6/22/10Page 1

page 3

ID Task Name Start Finish

30 Deploy communications for intervention Wed 9/9/09 Tue 12/15/09

31 Identify additional spring activities Tue 12/15/09 Wed 1/13/10

32 Load updated demographic information (Fall) Tue 8/18/09 Fri 1/22/10

33 Load updated demographic information (Spring) Wed 1/13/10 Wed 5/19/10

34 Preparation of reports on pilot for HEPC Sun 9/20/09 Wed 6/30/10

35 Initial report on structure and game plan Sun 9/20/09 Sun 9/20/09

36 Mid-project progress report Thu 2/18/10 Thu 2/18/10

37 Final report on outcomes and next steps Wed 6/30/10 Wed 6/30/10

3839 Banner Workflow Thu 9/10/09 Wed 6/23/10

40 Project start Thu 9/10/09 Thu 9/10/09

41 iAS upgrade/install on new hardware Fri 9/11/09 Fri 9/25/09

42 Gathering/documentation of feedback criteria/sliding scale Fri 9/11/09 Fri 10/2/09

43 Workflow server software install Sat 9/26/09 Fri 10/16/09

44 Verification of baseline delivered test workflows Sat 10/17/09 Tue 11/24/09

45 Initial feedback workflow developed Wed 11/4/09 Tue 1/5/10

46 Project review checkpoint with stakeholders Wed 12/16/09 Wed 12/16/09

47 Familiarize new project sponsor with project and determine Mon 3/15/10 Wed 3/24/10

48 Development/delivery of final draft of email content Wed 1/13/10 Wed 3/24/10

49 Definition of Banner letter code to record email Tue 3/9/10 Tue 3/16/10

50 Rewrite workflow generation job (online and paper applicatio Tue 3/9/10 Tue 3/16/10

51 Testing of workflow generation job and email Mon 3/15/10 Mon 3/22/10

52 Last-minute testing after online application deployment Tue 5/11/10 Tue 6/22/10

53 Production deployment Wed 6/23/10 Wed 6/23/10

5455 Automated Decision Rules Tue 11/3/09 Mon 10/25/10

56 Project Start Tue 11/3/09 Tue 11/3/09

57 Create design specs for the process that will load decision c Tue 11/3/09 Fri 11/20/09

58 Determine reporting needs for the process that will load dec Tue 11/3/09 Fri 11/20/09

Jun Jul u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan00 Qtr 3, 200 Qtr 4, 200 Qtr 1, 201 Qtr 2, 201 Qtr 3, 201 Qtr 4, 201 Qtr

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Project: Major Project OverviewDate: Tue 6/22/10Page 2

page 4

ID Task Name Start Finish

59 Communicate design specs and reporting needs to IT Fri 11/20/09 Fri 11/20/09

60 IT Development (Initial Scope) Mon 11/23/09 Tue 12/22/09

61 IT Development (Expanded Scope) Tue 2/16/10 Fri 7/30/10

62 Testing Tue 9/7/10 Fri 10/8/10

63 Conduct Training Mon 10/11/10 Fri 10/22/10

64 Implement Mon 10/25/10 Mon 10/25/10

6566 Housing Information System Tue 2/23/10 Fri 10/15/10

67 Develop RFP for Housing software Tue 2/23/10 Mon 3/8/10

68 Mail RFP to potential vendors Mon 3/22/10 Mon 3/22/10

69 Review RFP documents Wed 4/28/10 Wed 5/19/10

70 Oral Presentations by Candidate Vendors Tue 5/18/10 Wed 5/19/10

71 Issue purchase order for software Mon 5/31/10 Wed 6/30/10

72 Development phase Thu 7/1/10 Wed 9/1/10

73 Testing phase Thu 9/2/10 Fri 10/1/10

74 Training phase Mon 10/4/10 Fri 10/15/10

75 Go live Fri 10/15/10 Fri 10/15/10

7677 Data Center - IBM Chassis/Blade Replacement and SAN Sto Sat 11/14/09 Thu 9/30/10

78 Create and post RFB for required IBM Hardware Sat 11/14/09 Sat 11/14/09

79 Award RFB and process for purchasing Fri 12/11/09 Fri 12/11/09

80 Equipment/Software Acquisition Tue 1/5/10 Fri 3/26/10

81 Decommission and migration plan completed Mon 1/4/10 Mon 2/15/10

82 Installation of physical hardware Tue 2/2/10 Tue 2/2/10

83 System builds completed Tue 2/23/10 Sat 5/15/10

84 Migration of systems Wed 3/31/10 Thu 9/30/10

85 Migration of all systems from BC1 Wed 3/31/10 Thu 4/15/1086 Migration of all systems from BC2 Wed 3/31/10 Thu 9/30/1087 Decommission and removal of old hardware Fri 4/16/10 Thu 9/30/10

Jun Jul u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan00 Qtr 3, 200 Qtr 4, 200 Qtr 1, 201 Qtr 2, 201 Qtr 3, 201 Qtr 4, 201 Qtr

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Project: Major Project OverviewDate: Tue 6/22/10Page 3

page 5

ID Task Name Start Finish

88 BC1 decommission and removal Fri 4/16/10 Fri 6/25/1089 BC2 decommission and removal Wed 9/1/10 Thu 9/30/109091 Exchange 2010 Transition Thu 4/1/10 Thu 9/30/10

92 Physical hardware installed and configured Thu 4/1/10 Tue 6/15/10

93 Exchange 2010 Installed and configured Tue 5/11/10 Fri 7/2/10

94 Testing and issue resolution completed Tue 7/6/10 Fri 7/23/10

95 Migration of user mailboxes and public folders Sat 7/24/10 Wed 8/18/10

96 Removal of old Exchange system from domain and hardwar Mon 8/30/10 Thu 9/30/10

9798 Content Management System - Upgrade to 6.x Tue 6/1/10 Fri 12/31/10

99 Project Start Tue 6/1/10 Tue 6/1/10

100 Solicit Web Tester suggestions for upgrade Tue 6/1/10 Tue 6/1/10

101 Identify Business Units and responsible parties Tue 6/1/10 Wed 6/16/10

102 Separate the web site into micro sites Mon 6/7/10 Sun 8/15/10

103 Upgrade micro-sites from Drupal 5.x to Drupal 6.x Mon 6/7/10 Wed 9/15/10

104 Train users on Drupal 6.x Thu 7/15/10 Fri 10/1/10

105 Enhance micro-sites with new features Wed 9/15/10 Wed 12/1/10

106 Program Completion Tue 6/1/10 Fri 12/31/10

107108 Oracle Database Upgrade (Banner) Tue 6/29/10 Sun 9/26/10

109 Upgraded 11g test database and environment Tue 6/29/10 Wed 7/7/10

110 Test plan submission to Applications Services Wed 6/30/10 Wed 6/30/10

111 Testing Feedback Checkpoint #1 Mon 7/12/10 Mon 7/12/10

112 Testing Feedback Checkpoint #2 Mon 7/26/10 Mon 7/26/10

113 Testing Feedback Checkpoint #3 Mon 8/9/10 Mon 8/9/10

114 Testing Feedback Checkpoint #4 Mon 8/30/10 Mon 8/30/10

115 Executed and approved test plans Thu 7/1/10 Mon 9/13/10

116 Upgraded 11g Production Database Tue 9/14/10 Sun 9/26/10

Jun Jul u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan00 Qtr 3, 200 Qtr 4, 200 Qtr 1, 201 Qtr 2, 201 Qtr 3, 201 Qtr 4, 201 Qtr

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Project: Major Project OverviewDate: Tue 6/22/10Page 4

page 6

PROJECT STATUS REPORT   

Project ID  090717‐01  Date  6/21/10 

Project Name  Online Application Redesign 

Project Description 

Redesign the application process to direct students to the appropriate application,  which will  allow  us  to  customize  applications  based  on student type.  This will include all student and admit types for both the University  and  Pierpont  applications  for  undergraduates,  with  the exception of competitive applications. 

We will also analyze the application questions to determine if any can be eliminated  and  if  any  can be worded  to  avoid  free‐form  answers and reduce possible data entry errors and processing time. 

Project Sponsor  Sharon Handelsman 

Project Manager  Andy Raisovich 

Progress and Accomplishments 

 The application was turned on in production on the morning of June 1, 2010.  Some statistics on application completion:  

Between  Between  Between 

6/1/10  6/21/10  6/1/09  6/21/09  9/1/09  5/31/10  Apps started  332  375  7261  Apps completed  301  300  5595  Yield  90.66%  80.00%  77.06%   Though the sample timeframe for the new application is very short, at least preliminarily this points to a higher application completion rate by roughly 10%. 

Schedule Variances 

 Testing had been scheduled to be complete by May 7, but that was stretched throughout May and reconstituted as working sessions between ES and Application Services to hammer out bugs as they were found. 

page 7

Issues or Risks 

 There could be issues that were not found during testing, and we must rely on reports from applicants to identify these problems, but so far none have been reported and many applications have come in using this method. 

Project Outlook (Estimate To Complete) 

Complete. 

 

page 8

PROJECT STATUS REPORT   

Project ID  090727‐01  Date  6/21/10 

Project Name  MAP‐Works Implementation 

Project Description 

Fairmont  State University  and Pierpont Community & Technical College will participate in an HEPC‐sponsored pilot of MAP‐Works retention  software  from  Educational  Benchmarking,  Inc.    The software  will  be  configured,  student  data  will  be  loaded  from Banner and other sources, surveys will be deployed to students, and  survey  results will  be  combined with  demographic  data  to identify students at most risk and to support cross‐campus efforts to provide support for at‐risk students.   

Project Sponsor  Maria Rose 

Project Manager  Erica Harvey 

Progress and Accomplishments 

 Sharon Handelsman has joined the MAP‐Works implementation team for 2010‐11 and is providing a helpful and positive “broad view” of the implementation.  Dan Gockley, Pam Stephens and Andrea Pammer are also bringing in exciting, related retention initiatives from Student Affairs.  Five faculty/staff members have active MAP‐Works data analysis projects underway.  Reports from them are due on Jun 24 so that they can be included in the June 30 final report to HEPC.   Our presentation was accepted for the fall IUPUI Assessment Conference entitled, “A Hierarchy of Freshman Assessment and Retention: Spotlighting Three Levels.”    J.R. Farley was able to provide the Banner data needed to update the MAP‐Works database after the completion of the spring semester, and this was successfully loaded into the system. 

Schedule Variances 

 IT Collaboration with EBI staff to automate data loads is expected to begin in early July.  Andy Raisovich agreed that this activity can be continued by IT outside of the scope of this project, so the project can still be completed on schedule with the final report to HEPC. 

page 9

Issues or Risks   

Project Outlook (Estimate To Complete) 

This project is on schedule overall.   

 

page 10

PROJECT STATUS REPORT   

Project ID  090910‐01  Date  6/21/10 

Project Name  Banner Workflow 

Project Description 

 To install and configure Banner Workflow. Develop a single workflow to provide faster feedback to applicants  Set  the  stage  for  determining  whether  outside  workflow consulting  services  should  be  engaged  for  future  process reengineering advice in Enrollment Services. 

Project Sponsor  Sharon Handelsman 

Project Manager  Andy Raisovich 

Progress and Accomplishments 

Completed and in production as of 6/23/2010. 

Schedule Variances 

The project has been tied to the completion date of the online application redesign, scheduled to trail the application deployment date by three days.  Because the application deployment slid, so did this.  Along the way, other potential problems were identified, edits to the text of the email were made, and employee vacations intervened.  Solutions were identified and implemented, and the application was deployed in production. 

Issues or Risks 

Testing has been occurring with IT and ES over the course of the spring on the mechanism that actually sends the emails out (the workflow engine), and thus far has proved reliable.  However, as with all other systems, unexpected problems can arise.  ES and IT will be on the lookout for these as work begins on other aspects of Workflow implementation. 

Project Outlook (Estimate To Complete) 

Complete. 

 

page 11

PROJECT STATUS REPORT   

Project ID  091103‐01  Date  6/22/10 

Project Name  Automated Decision Rules 

Project Description 

To design a process that will assign the appropriate decision code to applicants in Banner and produce specified reports. 

Project Sponsor  Sharon Handelsman 

Project Manager  Evie Brantmayer 

Progress and Accomplishments 

Project  scope has been  redefined and we are creating our own process. 

A shell has been created by  IT but not  finished.   Work will resume  on  this  project  and  IT  work  is  scheduled  to  be complete by end of July.   

Testing and training will be done in September and October with go live at end of October. 

August is skipped due to start of school activities. 

Schedule Variances 

The  target  for  completion  has  been  rescheduled  due  to delays in the beginning of workflow project.   

Issues or Risks The  project  completion  date  will  be  tied  to  Workflow implementation and may be changed because of it. 

Project Outlook (Estimate To Complete) 

Estimated completion is now 10/25/10. 

 

page 12

PROJECT STATUS REPORT   

Project ID  100115‐01  Date  6/14/10 

Project Name  Housing Information System 

Project Description 

Complete  an RFP  for  a  supplemental housing  software  solution that  interfaces  with  our  campus  Student  Information  System.  Implement  the software  solution  for complete utilization during the 2011‐2012 recruiting cycle that begins in September 2010. 

Project Sponsor  Sharon Handelsman 

Project Manager  Dan Gockley 

Progress and Accomplishments 

Three vendors submitted proposals and were asked to complete oral presentations.  Oral presentations were held on May 18‐19th.  Oral presentations were reviewed on May 25th resulting in clarifying questions for each vendor’s proposal.  Financial proposals were opened and reviewed on May 25th.  Responses were received by Procurement and the successful vendor finalized.  Procurement is notifying vendors regarding the outcome of the process and the contract will be finalized as soon as possible. 

Schedule Variances 

Issuing the purchase order was delayed due to the questions identified as a result of the oral presentations and the review of the financial documents.  Development, testing and training will be delayed and adjusted due to the delays.  The successful vendor indicates the standard implementation requires five (5) months following the kick‐off of the project.   

Issues or Risks 

The delay regarding the issuing of the purchase order will most likely delay project completion until the end of the fall semester.  The development phase will occur later in the summer at a time when housing staff are preparing for the fall opening.  The goal was to have development out of the way by that time. 

page 13

Project Outlook (Estimate To Complete) 

Projected completion is the end of the fall semester.  Due to delays, we will need to begin the application cycle for the 2011‐2012 academic year with the current system and migrate the information.  The most likely solution is to implement the housing application in the new software and replace the current application as soon as possible.  On average, fewer than 70 applications are submitted from new students through December each year.  Migrating to the new system in the fall semester should still allow most new students to apply using the new system. 

 

page 14

PROJECT STATUS REPORT   

Project ID  100129‐01  Date  6/21/10 

Project Name  Data Center ‐ IBM Chassis/Blade Replacement and SAN Storage Expansion 

Project Description 

1. Replace aging IBM hardware with new equipment and add a redundant blade center for our web services network. 

2. Add storage capacity to our existing IBM SAN to maximize its useful lifespan until its replacement in the next two years. 

Project Sponsor  Dave Tamm 

Project Manager  Steve Shala 

Progress and Accomplishments 

 BC6 was successfully brought on‐line by May 14 

Schedule Variances 

 ecommission of BC 2 will be delayed until the decommissioning D

of our Exchange 2003 system later this year.   

Issues or Risks 

 dditional issues were discovered when trying to map SAN space 

 

Ato the new hardware.  After several weeks of troubleshooting with IBM support the case was escalated to a Critical Situation case within IBM and we also received support from our local IBMreseller’s IBM engineer.    This issue also caused our VMware issues that caused the initial VMware SAN issues.   Now that thissue is known we are in the process of correcting them.  

 orrection of the issue above requires changes to our fiber 

is Cchannel SAN fabric.  This should be completed by July 1st.  Thwas not in the scope of the project but necessary to move forward with other projects.  

Project Outlook (Estimate To Complete) 

 

page 15

PROJECT STATUS REPORT   

Project ID  100409‐01  Date  6/21/10 

Project Name  Exchange 2010 Transition (Version Change) 

Project Description 

Build a new Exchange 2010 email system and migrate all faculty and staff mailboxes.  This will allow for both Fairmont State’s and Pierpont’s continued growth and stability of its email system, as well as ensure compatibility with future Unity voicemail system upgrades and enhancements.   

Project Sponsor  Dave Tamm 

Project Manager  Steve Shala 

Progress and Accomplishments 

Worked with Microsoft to find that we can run Exchange 2010 in our environment.  Verified this with Cisco.  Have tested the install of Exchange 2010 in a virtual environment to minimize any issues during the real install.  Hardware fully configured with SAN space and prerequisites and read for full install in the next few days.  

Schedule Variances 

Changed project from installing Exchange 2007 to Exchange 2010.  This is after Microsoft said 2010 was compatible with our voicemail system.  We then verified this with Cisco.  Microsoft also recommended some hardware changes that simplify our environment.   

Issues or Risks 

Issues discovered when trying to create data volumes for the new Exchange servers.  This lead to several weeks of troubleshooting with IBM support.  Issues was finally discovered and we are in the process of correcting it.  

Project Outlook (Estimate To Complete) 

We are behind on our build and testing scheduled however using Exchange 2010 simplifies our configuration which should allow us to regain some lost time.     At this point we are still planning on having all active mailboxes migrated before the fall semester.  

 

page 16

PROJECT STATUS REPORT   

Project ID  100603‐01  Date  6/16/10 

Project Name Content Management System – Upgrade to 6.x 

 

Project Description 

This project represents the first major upgrade to the content management system.  This upgrade is needed to ensure that the content management system stays up‐to‐date with any security issues and the newest technology available.   

Project Sponsor  Dave Tamm and Mary Jo Thomas 

Project Manager  Shane Jordan 

Progress and Accomplishments 

The project began on schedule.  Meetings have been held to solicit suggestions for the upgrade and also to discuss the separation of the web site into micro sites.  An initial group of business units have been identified.  There was a meeting with the deans where we talked about the web site upgrade and informed them of the changes that are coming. 

Schedule Variances 

No variances to report at this time. 

Issues or Risks  None to report 

Project Outlook (Estimate To Complete) 

The project is still on track to be completed on time. 

 

page 17

PROJECT CHARTER  

 Project Name 

Content Management System – Upgrade to 6.x 

 Project ID  100603‐01  Start Date 

06/01/2010 

Project Summary Description 

This project represents the first major upgrade to the content management system.  This upgrade is needed to ensure that the content management system stays up‐to‐date with any security issues and the newest technology available.  The upgrade will consist of the following major components:  • Separation of web site into micro sites • Upgrade from Drupal 5.x to Drupal 6.x • Change from the TinyMCE editor to the FCKEditor to provide a better 

editing experience for the users. • Change the Revisioning module to a more robust revisioning system that 

should provide additional functionality to users. • Implement automatic creation of URLs based on the content. • New server setup  Separating the web site into micro sites will provide multiple benefits.  Having micro sites will increase web site performance and decrease the risk of web site failure.  Each micro site would be able to take on its own look and feel making it targeted to the users of that site.  Micro sites would allow editors additional functionality when updating their site and allow then to manage their site in a more efficient manner.  The most logical way to separate the web site would be based on business unit.  Areas of the web site are currently maintained by editors throughout the institution.  Each area has an editor that maintains their set of pages.  Examples of business units would be: Each academic school, Admissions, Financial Aid, Foundation/Alumni, Business Office, Information Technology, etc.  The current web site running on a virtual server.  There are limitations on the amount of CPUs and memory that Red Hat will utilize.  By changing the web sites to run on a physical server, we will be able to increase the resources provided to the server, therefore allowing increased performance of the web site.  Key areas of the web site will be identified for initial enhancements.  The areas identified will be determined based on web analytics of the web site and editor participation.  Editor participation is determined based on the number of edits and consistency of keeping their area of the web site up to date.  Areas that are not identified for initial enhancements will be eligible for enhancements to their area of the web site after project completion.  

Page | 1  

page 18

Page | 2  

Project Need and Justification 

 The content displayed on  the website  is a valuable communications  tool  for the institutional communities of Fairmont State University and Pierpont C&TC and  a  critical  component  of  their  Recruiting  and  Admissions  strategy  and processes.   As  the web  site continues  to grow and new  features are added, the  need  to  continue  maintenance  and  moving  forward  with  upgrades becomes more vital.  Editors want to provide their users with the best possible experience on their area  of  the web  site.    By  separating  the web  site  into micro  sites,  editors would be able to enhance their area of the web without affecting other areas.  This  is considered a major upgrade to the web site.   Because of this being a major upgrade, the time to perform the upgrade  is  longer.   Future upgrades would not be as time extensive.   

Key Stakeholders 

Organization/Individual  Impact Level  Known Requirements Communications  High   Information Technology  High   Admissions  High   Pierpont C&TC  High   Public Relations  High        

 

Human Resource Requirements 

Role  Individual Assigned  Activity (Level of Effort) 

IT Lead  Shane Jordan  100% IT – Server Setup  Jonathon Lynch  25% Communications Lead  Bob Heffner  100% Communication Support  Kevin Funk  100% Pierpont Advisor  Sarah Hensley  30% Public Relations  Amy Pellegrin  20% Foundation/Alumni Advisor 

TBD  20% 

Drupal Trainer  TLC Members  10% General Web Advisors  Ron Weist 

Deb Woods Kevin Philyaw Tina Mascaro Michelle Poland Bradley Omanson Ed Reger 

10% from each individual 

      

Procurement Requirements 

Type of Material/Equipment  Estimated Cost  When Needed 2 – Servers  $16,000  10/1/2010           

 

page 19

Page | 3  

Major Project Deliverables 

Key Deliverables  Milestone Dates  Critical Dependencies Project Start  6/1/2010   Solicit Web Tester suggestions for upgrade 

6/3/2010   

Identify Business Units and responsible parties 

6/15/2010   

Separate the web site into micro sites 

8/15/2010  Business Units identified 

Upgrade micro‐sites from Drupal 5.x to Drupal 6.x 

9/15/2010  Successful separation of web sites into micro‐sites 

Train users on Drupal 6.x  10/1/2010  Successful upgrade of micro‐sites to 6.x 

Enhance micro‐sites with new features 

12/1/2010  Successful upgrade of micro‐sites to 6.x 

Program Completion  12/31/2010  All Key Deliverables are completed successfully 

      

Constraints and Assumptions 

 Deliverable dates are based on the ability to dedicate resources to this project.  Project completion is based on the availability of modules to successfully upgrade the web sites.  Not all micro‐sites need to be enhanced with new features during the initial project. Enhancements can be added to sites after project completion.  

 Project Manager Assigned  

Shane Jordan 

APPROVALS:  

Project Sponsor:  

David Tamm  

Signature: /s/ David Tamm 

Date:  6/3/2010 

 

Mary Jo Thomas  /s/ Mary Jo Thomas  3 June 2010 

IT Management:  

Andy Raisovich  

Signature: /s/ Andy Raisovich 

Date:  03‐ JUN‐ 2010 

  

page 20

PROJECT STATUS REPORT   

Project ID  100603‐01  Date  6/18/10 

Project Name  Oracle Database Upgrade (Banner) 

Project Description 

Effort to upgrade Banner’s Oracle database from 10g to 11g. 

Project Sponsor  Dave Tamm 

Project Manager  J.R. Farley 

Progress and Accomplishments 

 The official ‘start’ of the project is almost two weeks away, but we’ve made efforts to co‐ordinate with campus offices with regards to the testing plans, and many have already submitted those for our approval.  

Schedule Variances 

None. 

Issues or Risks  None. 

Project Outlook (Estimate To Complete) 

Project is on‐schedule. 

 

page 21

PROJECT CHARTER   

 Project Name 

 Oracle Database Upgrade (Banner) 

 Project ID 

 100611‐01  Start Date  06/11/2010 

Project Summary Description 

 This project represents the effort to upgrade our Banner Oracle database, currently at version 10g, to the current 11g standard.  

Project Need and Justification 

 The 10g database software will be unsupported by Oracle as of July 2011.  Thus the upgrade is required for continued support by Oracle and Sungard.  

Key Stakeholders 

Organization/Individual  Impact Level  Known Requirements Applications Services  High  N/A Banner administrative users  Medium  Test plan development and 

execution           

 

Human Resource Requirements 

Role  Individual Assigned  Activity (Level of Effort) Database Administrator 

J.R. Farley  Medium 

Banner Student Testing 

Evie Brantmayer  Medium 

Banner Recruiting Testing 

Steve Leadman  Medium 

Banner General Testing 

Neil Tennant/JR Farley  Medium 

Banner FinAid Testing  Cindy Hudok  Medium Banner AR Testing  Cheri Gallo  Medium Banner Housing Testing 

Dan Gockley  Medium 

Banner Budgeting Testing 

Debbie Stiles  Medium 

Banner Purchasing Testing 

Holly Fluharty  Medium 

Banner Accounting Testing 

Carolyn Fletcher  Medium 

Banner Fixed Assets Testing 

Patty Murray‐Fidura  Medium 

Banner Payroll Testing  Cinda Ewing  Medium Banner HR Testing  Maria Marshall  Medium      

 

Procurement Requirements 

Type of Material/Equipment  Estimated Cost  When Needed n/a               

 

Page | 1  

page 22

Page | 2  

Major Project Deliverables 

Key Deliverables  Milestone Dates  Critical Dependencies Upgraded 11g test database and environment (1) 

June 30, 2010   

Test plan submission to Applications Services (2) 

June 30, 2010   

Testing feedback checkpoints (3) 

July 12, 2010 July 26, 2010 August 9, 2010 August 30, 2010 

(2) 

Executed and approved test plans (4) 

September 13, 2010  (1), (2) 

Upgraded 11g Production Database 

September 26, 2010  (4) 

      

Constraints and Assumptions 

 Sungard has stated that they will officially support for Oracle 11g release 2 (traditionally the more stable release for each major Oracle version) by the end of Q2, once testing has been completed.  Building our test environment, we will be going on the assumption that such certification of Banner on 11gR2 will occur.  

 Project Manager Assigned  

J.R. Farley 

 APPROVALS:  

Project Sponsor:  David Tamm  

Signature: /s/ David Tamm 

Date:  6/11/10 

IT Management:  Andy Raisovich  

Signature: /s/ Andy Raisovich III 

Date:  6/21/10 

 

page 23