Project situation analysis and technical reporting
UNEP/GEF FNR_Rio project – 3rd Project Steering Committee, March 13th, 2012, Tehran, IranPeter Herkenrath, International Consultant
Contents
1. The outputs of the project2. Status of delivery of outputs3. Some conclusions4. Next steps for outputs
13 March, 2012
2Project situation analysis and technical reporting
The project outputs
International Consultant: Global situation analysis – reporting
requirements (output 1.1)Pilot countries: National analysis study (output 1.2) National manual (output 1.3) Recommendations for improved information
management and national reporting (outputs 2.1 and 2.2)
Needs analysis: training and technology (output 2.3)
Report on the quality of reporting (output 2.4)
13 March, 2012
3Project situation analysis and technical reporting
Testing the joint reporting format: additional outputs (added to output 1.3/ national manual)
International Consultant: Assessment of options for joint reporting Draft joint reporting format for the three
Rio ConventionsPilot countries: Completed report using the draft joint
reporting format Questionnaire on experience with testing
the draft joint reporting format
13 March, 2012
4Project situation analysis and technical reporting
Status of output delivery
• National situation analysis: done by all countries (one country: draft only)• National manual for integrated reporting: 5 countries: 1st/2nd draft (final: end of project)• Recommendations for improved information management and national reporting and the needs analysis for training and technology: 3 countries• Testing the joint reporting format: all countries have expressed their willingness to do so
13 March, 2012
5Project situation analysis and technical reporting
Preliminary conclusions from outputs• Approaches to reporting vary between countries• Key priorities: collaboration between focal points/ agencies in charge of different conventions• management of national environmental data & information required for reporting• Workshops & consultations have brought stakeholders together• Improved communication between stakeholders• Key personnel has been trained
13 March, 2012
6Project situation analysis and technical reporting
Next steps for outputs: pilot countries
• Completed joint reporting format (output 1.3): 30th April• Completed questionnaire on experiences with joint reporting format (output 1.3): 30th April•Outstanding outputs : 30th June (relevant pilot countries)• Final version of national manual (output 1.3): 30th September• Report on quality of national reports (output 2.4): 30th September
13 March, 2012
7Project situation analysis and technical reporting
Next steps for outputs: International consultant
• Report on pilot country experiences with joint reporting format (output 1.3): 31st May• Report on pilot country project experience (output 2.4): 31st October
13 March, 2012
8Project situation analysis and technical reporting
Key outcome: Improved systems of reporting to the Rio Conventions• Improved collaboration of focal points, agencies and stakeholders across the three conventions• Improved management of national environmental data & information• Improved reporting rate for Rio Conventions• National manual capturing the project experience, recommendations and improvements
13 March, 2012
9Project situation analysis and technical reporting