PROJECT SITE LOCATION MAP ON GOOGLE EATH

39
PROJECT SITE LOCATION MAP ON GOOGLE EATH PROJECT SITE SOH TOWARDS GURGAON PROJECT SITE HNA GURGAON R ROAD TOWRDS REWARI TOWRDS PALWAL

Transcript of PROJECT SITE LOCATION MAP ON GOOGLE EATH

Page 1: PROJECT SITE LOCATION MAP ON GOOGLE EATH

PROJECT SITE LOCATION MAP ON GOOGLE EATH 

PROJECT SITE

SOH

TOWARDSGURGAON

PROJECT SITE HNA G

URG

AON RRO

AD

TOWRDSREWARI

TOWRDSPALWAL

Page 2: PROJECT SITE LOCATION MAP ON GOOGLE EATH

500 M RADIUS MAP ON GOOGLE EARTH  AROUND THE PROJECT SITE 

A 28°16'46.94"N, 77° 3'21.23"E

B 28°16'46.57"N, 77° 3'28.59"E

C 28°16'41.96"N, 77° 3'28.51"E

D 28°16'42 06"N 77° 3'26 31"ED 28°16'42.06"N, 77° 3'26.31"E

E 28°16'43.66"N, 77° 3'26.21"E

F 28°16'43.64"N, 77° 3'22.21"E

G 28°16'45.33"N, 77° 3'22.35"E

H 28°16'45.42"N, 77° 3'21.03"E

Page 3: PROJECT SITE LOCATION MAP ON GOOGLE EATH
Page 4: PROJECT SITE LOCATION MAP ON GOOGLE EATH

WATER BALANCE DIAGRAM

T t l W t

Residential Fresh : 97 KLD

Residential  Flushing :  31 KLD

Waste Water : 78 KLD

Waste Water : 31 KLD 

Waste Water : 0 35 Total Waste water : 117 KLD

Non Residential Fresh : 0.44 KLD

Waste Water :  0.35  KLD 

Non Residential  Flushing:  0.44  KLD

Waste Water : 0.44 KLD 

Total WaterDemand ofproject : 161KLD

Proposed STP :170 KLD

Total FreshWater

Waste Water : 3 KLD 

Treated water

Visitor Fresh: 4 KLDKLD

Visitors Flushing: 4  KLD Waste Water : 4 KLD 

Treated Water : 94 KLD

WaterDemand:101 KLD

Recycled Treated Waste water : 60 KLD

water reuse : 60 KLD

Gardening:  24 KLD 

Surplus treated water : 34 KLD to discharge to sewer with 

prior permissionprior permission

Page 5: PROJECT SITE LOCATION MAP ON GOOGLE EATH
Page 6: PROJECT SITE LOCATION MAP ON GOOGLE EATH
Page 7: PROJECT SITE LOCATION MAP ON GOOGLE EATH
Page 8: PROJECT SITE LOCATION MAP ON GOOGLE EATH
Page 9: PROJECT SITE LOCATION MAP ON GOOGLE EATH
Page 10: PROJECT SITE LOCATION MAP ON GOOGLE EATH
Page 11: PROJECT SITE LOCATION MAP ON GOOGLE EATH
Page 12: PROJECT SITE LOCATION MAP ON GOOGLE EATH
Page 13: PROJECT SITE LOCATION MAP ON GOOGLE EATH
Page 14: PROJECT SITE LOCATION MAP ON GOOGLE EATH

12.0 MTR

WID

E SERVIC

E RO

AD30.0 M

TR W

IDE R

OAD

30.0 MTR

WID

E GR

EEN BELT

EXISTING

BUN

DH

Organized openspace 0.315 acre

22 23 24 25

3 4

9

8 7

14

2 5

6

15

STP / WTPBelow

OS - 30.015 acre

OS - 1

OS - 50.0896 acre

OS - 40.015 acre

24.0 MTR

WID

E INTER

NAL SEC

TOR

AL RO

AD

OS - 20.009 acre OS - 6

0.0095 acreOS - 70.0095 acre

OS

- 80.

004

acre

UGT/TRF

Page 15: PROJECT SITE LOCATION MAP ON GOOGLE EATH

Organized openspace 0.315 acre

STP / WTPBelow

OS - 1

OS - 50.0896 acre

UGT/TRF

L512.0 MTR WIDE SERVICE ROAD

24.0 MTR WIDE INTERNAL SECTORAL ROAD

L5 6.225ACRES

ARCHITECT`SSIGNATURE

OWNERSIGNATURE

OWNER :-

M/S FAITH BUILDTECH PVT. LTD.

PROJECT

SHEET TITLE

R0DDJAY

DEALT SCALE

DATE

20-06-2018

JOB NO.

DRG. NO.

NPROPOSED (L5)6.225 ACRESDDJAY SCHEME INSECTOR-35 SOHNA

KEY PLANSCALE:-1:3000

PLANTING PLAN L5SCALE:-1:750

Page 16: PROJECT SITE LOCATION MAP ON GOOGLE EATH

12.0 MTR WIDE SERVICE ROAD

12.0 MTR WIDE SERVICE ROAD

60.0 MTR WIDE SECTORAL ROAD

24.0 MTR WIDE INTERNAL SECTORAL ROAD

12.0 MTR WIDE SERVICE ROAD

12.0 MTR WIDE SERVICE ROAD

60.0 MTR WIDE SECTORAL ROAD

12.0 MTR

WID

E SERVIC

E RO

AD30.0 M

TR W

IDE R

OAD

30.0 MTR

WID

E GR

EEN BELT

EXISTING

BUN

DH

Organized openspace 0.315 acre

22 23 24 25

3 4

9

8 7

14

2 5

6

15

OS - 30.015 acre

OS - 1

OS - 50.0896 acre

OS - 40.015 acre

OS - 20.009 acre OS - 6

0.0095 acreOS - 70.0095 acre

OS

- 80.

004

acre

UGT/TRF

PUMPROOM

UTG & PUMP ROOM

CAP. = 170 KLDAREA = 170 M2

RAW WATER = 75 KLDOMESTIC WATER = 75 KL

STP

24.0 MTR

WID

E INTER

NAL SEC

TOR

AL RO

AD

COMMUNITY

ORGANIZED OPEN SPACE

UGT/TRF

COMMERCIAL

PLOT LINE

LEGEND:

Area for switching station(502 sqyard)

DEALT

VIKAS KUMAR

SCALE

1: 750

DATE

JOB NO.10042017

PROPOSED 6.20625 ACRES DDJAY SCHEME INSECTOR-35 SOHNA(L5)

SEWERAGE LAYOUT

Page 17: PROJECT SITE LOCATION MAP ON GOOGLE EATH

12.0 MTR WIDE SERVICE ROAD

12.0 MTR WIDE SERVICE ROAD

60.0 MTR WIDE SECTORAL ROAD

24.0 MTR WIDE INTERNAL SECTORAL ROAD

12.0 MTR WIDE SERVICE ROAD

12.0 MTR WIDE SERVICE ROAD

60.0 MTR WIDE SECTORAL ROAD

12.0 MTR

WID

E SERVIC

E RO

AD30.0 M

TR W

IDE R

OAD

30.0 MTR

WID

E GR

EEN BELT

EXISTING

BUN

DH

Organized openspace 0.315 acre

22 23 24 25

3 4

9

8 7

14

2 5

6

15

OS - 30.015 acre

OS - 1

OS - 50.0896 acre

OS - 40.015 acre

OS - 20.009 acre OS - 6

0.0095 acreOS - 70.0095 acre

OS

- 80.

004

acre

UGT/TRF

RWH RW

H

PUMPROOM

UTG & PUMP ROOM

CAP. = 170 KLDAREA = 170 M2

RAW WATER = 75 KLDOMESTIC WATER = 75 KL

RWH

STP

24.0 MTR

WID

E INTER

NAL SEC

TOR

AL RO

ADCOMMUNITY

ORGANIZED OPEN SPACE

UGT/TRF

COMMERCIAL

PLOT LINE

LEGEND:

Area for switching station(502 sqyard)

DEALT

VIKAS KUMAR

SCALE

1: 750

DATE

JOB NO.10042017

PROPOSED 6.20625 ACRES DDJAY SCHEME INSECTOR-35 SOHNA(L5)

STORM WATER LAYOUT

Page 18: PROJECT SITE LOCATION MAP ON GOOGLE EATH

24.0 MTR

WID

E INTER

NAL SEC

TOR

AL RO

AD

12.0 MTR

WID

E SERVIC

E RO

AD30.0 M

TR W

IDE R

OAD

30.0 MTR

WID

E GR

EEN BELT

EXISTING

BUN

DH

Organized openspace 0.315 acre

22 23 24 25

3 4

9

8 7

14

2 5

6

15

OS - 30.015 acre

OS - 1

OS - 50.0896 acre

OS - 40.015 acre

OS - 20.009 acre OS - 6

0.0095 acreOS - 70.0095 acre

OS

- 80.

004

acre

UGT/TRF

PUMPROOM

UTG & PUMP ROOM

CAP. = 170 KLDAREA = 170 M2

RAW WATER = 75 KLDOMESTIC WATER = 75 KL

STP

12.0 MTR WIDE SERVICE ROAD

12.0 MTR WIDE SERVICE ROAD

60.0 MTR WIDE SECTORAL ROAD

24.0 MTR WIDE INTERNAL SECTORAL ROAD

12.0 MTR WIDE SERVICE ROAD

12.0 MTR WIDE SERVICE ROAD

60.0 MTR WIDE SECTORAL ROAD

COMMUNITY

ORGANIZED OPEN SPACE

UGT/TRF

COMMERCIAL

PLOT LINE

LEGEND:

Area for switching station(502 sqyard)

DEALT

VIKAS KUMAR

SCALE

1: 750

DATE

JOB NO.10042017

PROPOSED 6.20625 ACRES DDJAY SCHEME INSECTOR-35 SOHNA(L5)

WATER SUPPLY LAYOUT(DUAL PLUMBING)

Page 19: PROJECT SITE LOCATION MAP ON GOOGLE EATH

Risk Assessment

� Background

An emergency is defined as a situation or an impending situation caused by the forces of nature,

an accident, an intentional act or otherwise that constitutes a danger of major proportions to

life or property.

Numerous events can be "emergencies," including:

• Fire/explosion

• Hazardous materials incident

• Flood or flash flood

• Severe weather (hurricane, tornado, winter storm)

• Earthquake

• Criminal activity

• Air plane crash

� Descriptions of the Emergency and Mitigation Measures

• Fire

Buildings are designed and constructed to confine and control a fire to allow building

occupants time to evacuate. Buildings are also designed to allow fire department

personnel time to access and gain control over the fire. Buildings are designed for the

expected fire loads they will encounter during their lifespan. Bombs, terrorist may

exceed these expectations and subject the building to fire loads for which they were not

designed. For example, a building designed to maintain its structural stability for three

hours, may fail in a much shorter period of time under these adverse conditions.

Equipment and procedures dealing with egress and exit facilities, fire alarm systems,

voice communication systems, fire suppression systems and other life safety devices

and features will play a major role in enhancing occupant safety in the event of a fire

and/or explosion. Property owners and managers must ensure that these life safety

features are maintained in operable condition and ready for use at all times. All the

buildings must have the approved fire safety plan which includes the following:

a) The emergency procedures to be used in case of fire including sounding the fire alarm,

notifying the fire department, provisions for access for fire fighting, instructing

occupants on procedures to be followed when the fire alarm sounds, evacuating

endangered occupants and confining, controlling and extinguishing the fire.

b) The appointment and organization of designated supervisory staff to carry out fire

safety duties.

c) The instruction of supervisory staff and other occupants so that they are aware of their

responsibilities for fire safety.

d) The holding of fire drills including the emergency procedures appropriate to the

building,

e) The control of fire hazards in the building,

f) The maintenance of building facilities provided for the safety of occupants,

Page 20: PROJECT SITE LOCATION MAP ON GOOGLE EATH

g) The provision of alternative measures for the safety of occupants during any shutdown

of fire protection equipment and systems or part thereof.

h) Instructions, including schematic diagrams, describing the type, location and operation

of building fire emergency systems.

Property management should, at a minimum, develop and introduce emergency fire

procedures for occupants and key property personnel to follow in the event of fire.

• Bomb Threats

Bomb threats are usually made by telephone. Few of these threats are real. Bombers

that go to the trouble of manufacturing and placing a device typically will not call in a

warning.

Bombers usually prefer to place devices in easily accessible locations (e.g., outside of

buildings, lobbies, near exits) to minimize risk of capture. Evacuating a building without

first checking these common areas may put occupants at increased risk. Bombers have

used telephone threats to herd people towards a device.

Good housekeeping simplifies the task of identifying suspicious packages. Security

measures make it more difficult to plant a bomb. Locking cabinets, rooms, offices, etc.

also limits unauthorized access and reduces the areas that need to be searched.

Building owners and managers should consider the following in establishing procedures

for this type of threat:

Type of Evacuation:

There are three options available depending on the situation:

o Complete evacuation of the premises

o Partial evacuation to a safe outside area or another internal area

o No evacuation

Emergency Controller:

If sufficient warning has been provided, the building owner, building manager or other

senior designated individual should make the decision whether or not to evacuate. It is

important that the primary manager and alternates responsible for this decision are

recognized by the occupants as having the authority to make these important decisions.

Their decision may be made with advice from the police, fire department or other

knowledgeable persons. Public safety should always be the foremost consideration.

Blast-Resistant Precautions

The design and construction of high-risk buildings to provide life safety in the face of

explosions is receiving renewed attention. Steps for reducing the impact of an explosion

can include introducing enhancements in structural design coupled with a buffer zone

surrounding the building.

Page 21: PROJECT SITE LOCATION MAP ON GOOGLE EATH

• Criminal Activity

Emergencies arising from human activity can include situations instigated by an

intentional criminal, human error or situations resulting from large-scale industrial

accidents.

Criminal acts such as bomb threats have historically been one of the most common

types of threats. However, recent public concern has also focused on threats associated

with biological and chemical agents.

Accidents that occur in industrial facilities may place neighboring property and

lives at risk. Of particular concern are accidents that involve facilities that store

large quantities of toxic chemicals.

The building occupants’ roles and responsibilities should always be fixed. Regardless of

whether or not they have been delegated any formal responsibilities; occupants play an

integral part in effectively executing the Emergency Plan and ensuring their own

personal safety. Their role is particularly important in buildings where delegated

emergency personnel are not available 24 hours a day, 7 days a week.

Usually in these types of situations, local authorities will likely be involved in responding

to, and/or monitoring the emergency situation. Where applicable, building management

should consult with authorities to determine an appropriate course of action. However,

in some situations, a decision to evacuate may have to be made by building

management on their own without the opportunity for consultation.

When circumstances warrant an evacuation, the building occupants must be notified in

an appropriate manner, taking into consideration the serious nature and urgency of the

situation.

Well-planned and prearranged lockdown procedures may be appropriate for application

in occupancies such as schools to protect students and staff. The lockdown practices

and procedures should never interfere with the occupants’ abilities to evacuate

promptly should the circumstances warrant it.

Security personnel, receptionists, complaints department personnel or other employees

who are in a position where they may have to deal with violent or potentially violent

people should be given training on conflict resolution and work place violence.

Page 22: PROJECT SITE LOCATION MAP ON GOOGLE EATH

• Hazardous Material Accident

A hazardous materials accident can occur anywhere. Buildings located near chemical

manufacturing plants are particularly at risk. However, hazardous materials are

transported on our roadways, railways and waterways daily, so any area is considered

vulnerable to an accident.

Building management should maintain a current inventory of hazardous materials used

on-site including current Material Safety Data Sheets (MSDS). Appropriate spill control

and clean-up materials and equipment should be readily available.

Staff should be trained in spill clean-up procedures. Emergency phone numbers for

hazardous materials disposal companies should also be available. If possible, managers

should determine what hazardous materials might be present on neighboring

properties. A risk assessment of this exposure should also be carried out.

Action to be taken in this kind of Emergency:

• Call the local fire department to report the nature and location of the accident as soon

as possible.

• Keep building occupants away from the accident scene.

• Do not walk into, touch, smell or taste any of the spilled substance. Try not to inhale

gases, fumes and smoke. If possible, cover mouth with a cloth while leaving the area.

• Try to stay away from accident victims until the hazardous material has been identified.

• Try to stay upstream, uphill and upwind of the accident with clear access to an

evacuation route.

• Emergency Due to Natural Disaster

Emergencies due to sudden and powerful natural events are capable of inflicting

considerable damage to property and placing many lives at risk. These types of

emergencies generally result from severe weather conditions or earthquakes.

Subsequent flash floods that may follow can result in further property damage and risk

to lives.

Earthquake:

Building management should:

• Warn occupants to expect that the fire alarms and sprinklers will go off during an

earthquake.

• Instruct occupants that it is very dangerous to try to leave a building during an

earthquake because objects can fall on occupants. Many fatalities occur when people

run outside of buildings, only to be killed by falling debris from collapsing walls and

Page 23: PROJECT SITE LOCATION MAP ON GOOGLE EATH

broken glass. Occupants are generally safer to stay where they are until the earthquake

is over.

• Evacuate occupants once the shaking has stopped. Occupants should be evacuated

using the stairs and moved quickly away from the building to prevent injury from falling

debris.

• Call emergency services, as appropriate, and then give first aid as necessary. Do not try

to move seriously injured people unless they are in immediate danger of further injury.

• Put out small fires quickly if this can be done without endangering personnel. This will

prevent fires from spreading until firefighting resources become available. Fire is the

most common hazard following earthquakes.

• Clean up flammable liquid spills immediately.

• Expect aftershocks.

• Warn occupants of fallen power lines and other hazards.

• Arrange for qualified people to inspect the building for damage that may have occurred.

Severe Storms:

Thunderstorms, tornadoes, hail, blizzards, ice storms, high winds and heavy rain can develop

quickly and hit hard, posing a threat to life and property. Some problems cannot be

prevented. High winds will topple trees and heavy rains will cause rivers to flood. But some

damage can be avoided or at least reduced, if precautionary measures are taken, such as

knowing the type of storms common to your area and what time of year they are likely to

strike.

Storms often strike too quickly to allow management to provide instructions to occupants at

the time they occur. Occupants must be instructed as to correct procedures in advance. For

example, storms that are accompanied by high winds would require occupants to retreat to

interior spaces away from windows.

Management should be aware that electrical power might be unavailable for an extended

period of time. Therefore, backup generators and adequate fuel supplies may be very

helpful in maintaining essential building services (e.g., heating). After a severe storm, it may

be necessary to obtain the services of qualified personnel to inspect the building for damage

that may not be readily identified.

Floods:

Building management should assess the threat of flooding to their building. Usually this is

easily accomplished due to a history of similar earlier events. Alternatively, they can contact

the local municipal planning office for flood information. Many insurance companies also

have information on the potential for flooding in specified areas.

Building management may wish to consider the following:

• Providing pumps, generators, sandbags, etc., for temporary flood relief.

• Providing permanent breakwaters and dikes where the flood potential is high.

Page 24: PROJECT SITE LOCATION MAP ON GOOGLE EATH

• Evaluate the potential impact on ground level and underground tanks.

• Hazardous materials stored at or below grade moved to a safe location.

• Protection of drinking water sources.

• Impact of floodwater on high value and process equipment.

• Electrical hazards that may be created due to the presence of water (to both permanent

and temporary wiring).

• Affect of flooding on the structural integrity of the building.

• Retain a list of qualified personnel and contractors who can be contacted to assess and

repair flood damage.

• Arrange to have drinking water tested after a flood. This is particularly important in areas

where drinking water is obtained from wells.

� Airplane Crash

Buildings may experience roof collapse resulting from airplane crash. Building owners and

property managers should be aware of the potential for roof failure resulting from this effect.

The property management should consult with a professional engineer and /or architect to

assist in analyzing the integrity of the existing structure.

Based upon information of this nature, tolerable and un-tolerable conditions can be identified.

Procedures can be adopted that would identify conditions when unsafe loads may be

experienced and incorporate safe practices.

When intolerable conditions are expected or imminent, evacuation may be appropriate.

� Training, Drill and Exercise Considerations

In addition to the training, individuals have key roles to play during an emergency. Everyone

working in the facility will require some form of training to become familiar with the established

Emergency Plans. This could include distribution of the specific procedures to each employee

and occupant/tenant, periodic discussion sessions with occupants and tenants to review the

procedures, technical training in the use of special equipment if necessary and participation in

evacuation drills intended to improve awareness of the egress features provided in the building.

In addition to conducting fire drills at the frequency required, it is also necessary to periodically

assess the other types emergency procedures similarly through exercises or drills.

The purpose of conducting drills and exercises is to:

• Assess the ongoing effectiveness of the facility’s emergency procedures given different

scenarios and make corrections where necessary;

• Determine that sufficient adequately trained people are available to respond and carry out the

activities outlined in the emergency procedures;

• Ensure that the building occupants understand how to react in accordance with the building's

emergency response and evacuation procedures; and

• Provide an opportunity for emergency response training and practice.

Page 25: PROJECT SITE LOCATION MAP ON GOOGLE EATH

Annexure-

Noise and Vibration Reduction Plan

The proposed project is for construction of group housing. During construction phase, sources

of noise emissions are expected from various construction equipments. General noise levels

generated from the operation of equipment and machinery used during construction period are

provided below –

Name of Source Noise Level at 16 m (50 ft) from source in dB (A)*

Noise Level at 1 m from source (calculated) in dB (A)

Air Compressor 87 111

Back Hoe/Loader 81 105

Concrete Pumper 70 94

Concrete Vibrators 77 101

Cranes - mobile 81 105

Dump Truck 83 107

Generator Not considered 75 (as prescribed by CPCB)

Hammering 86 110

Jackhammer 88 112 *Source: www.gvrd.bc.ca/education/pdf04/ColumbiaWorkshop1-ConstructionNoise.pdf

Following mitigation measures shall be adopted during construction period-

• Workers employed in high noise areas will be rotated. Earplugs/muffs, or other hearing

protective wear will be provided to those working very close to the noise generating

machinery.

• Servicing of all construction vehicles and machinery shall be done regularly and during

routine servicing operations, the effectiveness of exhaust silencers shall be checked and if

found defective will be replaced. Vehicles hired for bringing construction materials at sight

shall conform to the noise emission standards and shall be operated during non peak hours.

• Smooth flow of traffic should be ensured on the internal road to avoid idling and honking of

vehicles.

• Regular sprinkling of water for dust suppression.

• Use of PUC certified vehicles / machinery.

• Ambient Noise level monitoring shall be conducted at suitable locations at periodic intervals

during construction phase to conform to the stipulated standards both during day and night

time. Data shall be reviewed and analyzed by the project manager for adhering to any strict

measure.

• Noise levels will also be monitored at point sources for occupational noise exposure and

ensuring health risk.

Page 26: PROJECT SITE LOCATION MAP ON GOOGLE EATH

1

Annexure -

ELECTRICAL HAZARDS AND SAFETY PLAN WITH CODES & STANDARDS

Reduction the Risk:

� Install electrical systems to a suitable standard, e.g. BS 7671 requirements for electrical

installations and then maintain them in a safe condition.

� Effectively earth the non-current carrying metallic parts of the equipment

� Provide enough socket-outlets to avoid overloading due to use of adaptors.

� Choose equipment that is suitable for its working environment.

� Ensure that equipment is safe when supplied and then maintain it in a safe condition.

� Provide an accessible and clearly identified switch near each fixed machine to cut off

power in an emergency.

� For portable equipment, use socket-outlets which are close by so that equipment will be

easily disconnected in and emergency.

� Replace damaged dictions of cable completely.

� Protect light bulbs and other equipment which could easily be damaged in use.

� Use, an RCD (Residual Current Device) for additional safety

Work Safely:

� Make sure that people who are working with electricity are competent to do the job.

� Work permit system to be followed

� Suspect or faulty equipment is taken out of use, labeled ‘DO NOT USE’ and kept secure

until examined by a competent person.

� Not to allow work on or near exposed live parts of equipment unless it is absolutely

unavoidable.

� Minimize the potential for water or chemical spills on or near electrical equipment.

� Use equipment with three-prong plugs.

� Use circuit protection devices designed to automatically limit or shut off the flow of

electricity in the event of a ground-fault, overload, or short circuit in the wiring system.

Overhead power lines- When working near overhead lines, if possible, have them

switched off.

� Repairs of high voltage or high current equipment will be performed by trained

electricians.

� Electrical line diagram, showing flow of energy, indicating the location of transformers,

earth pits electrical panel boards and distribution of power from power house or

generator house switch room, cable network to be displayed.

Page 27: PROJECT SITE LOCATION MAP ON GOOGLE EATH

2

� Use of be proper protective equipment’s e.g. rubber gloves, safety shoes and clothing’s

for the electrician.

� Plan to be made in such a way to provide ease of maintenance.

� Automatic protection of all electrical equipment through selective reliving system

Safety measures:

� Shock treatment training of personnel

� Fire fighting equipment’s and training of personnel for effective use

� Fire detection and alarm system

� Fire alarm systems at appropriate places

� Access for fireman

� Adequate fire fighting arrangement

� Adequate safety measures complying to the occupational safety manuals to prevent

accidents/hazards to the maintenance workers.

Page 28: PROJECT SITE LOCATION MAP ON GOOGLE EATH

3

LIST OF STANDARDS (IS CODES) FOR FIRE PROTECTION SYSTEM

S. NO. IS NO. TITLE

1. 1668 : 1990 List of practice for provision and maintenance of water supplies

and fire fighting

2. 3844 : 1989 Code of practice for installation and maintenance of internal

fire hydrants and hose reels on premises (first revision)

3. 11360 :

1985

Specification for smoke detectors for use in automatic electrical

fire alarm system

4. 2175 : 1988 Specification for heat sensitive fire detectors for use in

automatic fire alarm system (second revision)

5. 11360 :

1985

Specification for smoke detectors for in automatic electrical fire

alarm system

6. 2189 : 1999 Code of practice for selection, installation and maintenance of

automatic fire detection and alarm system (second revision)

7. 636 : 1988 Non –percolating flexible fire fighting delivery hose (third

revision)

8. 884 : 1985 Specification for first aid hose reel for fire fighting (first revision)

9. 901 : 1988 Specification for couplings, double male and double female

instantaneous pattern for fire fighting (third revision)

10. 902 : 1992 Specification for suction hose couplings for fire fighting (first

revision)

11. 903 : 1993 Specification for fire hose delivery couplings, branch pipe,

nozzles and nozzle spanner (fourth revision)

12. 904 : 1983 Specification for two way and three way suction collecting

heads for fire fighting purposes (second revision)

13. 905 : 1980 Specification for delivery breechings, dividing and collecting,

instantaneous pattern for fire fighting purposes (second

revision)

14. 906 : 1988 Specification for revolving branch pipe for fire fighting (third

revision)

15. 907 : 1984 Specification for suction strainers, cylindrical type for fire

fighting purpose (second revision)

16. 908 : 1975 Specification for fire hydrant, stand post type (second revision)

17. 909 : 1992 Specification for underground fire hydrant: Sluice valve type

(third revision)

18. 910 : 1980 Specification for combined key for hydrant, hydrant cover and

lower valve (second revision)

19. 926 : 1985 Specification for fireman’s axe (second revision)

20. 927 : 1981 Specification for fire hooks (second revision)

21. 928 : 1984 Specification for fire bells (second revision)

22. 937 : 1981 Specification for washers for water fittings for fire fighting

purposes (second revision)

Page 29: PROJECT SITE LOCATION MAP ON GOOGLE EATH

4

23. 940 : 1989 Specification for portable fire extinguisher, water type (gas

cartridge) (third revision)

24. 2171 : 1999 Specification for portable fire extinguishers, dry powder

(cartridge type) (third revision)

25. 2175 : 1988 Specification for heat sensitive fire detectors for use in

automatic detectors for use in automatic fire alarm system

(second revision)

26. 2546 : 1974 Specification for galvanized mild steel fire bucket (first revision)

27. 2871 : 1983 Specification for branch pipe, universal for fire fighting purposes

(first revision)

28. 2878 : 2004 Specification for fire extinguisher, carbon-dioxide type (portable

and trolley mounted) (third revision)

29. 3582 : 1984 Specification for basket strainers for fire fighting purposes

(cylindrical type) (first revision)

30. 4308 : 1982 Specification for dry powder for fire fighting (first revision)

31. 5290 : 1993 Specification for landing valve (third revision)

32. 5714 : 1981 Specification for hydrant, stand pipe for fire fighting (first

revision)

33. 6234 : 1986 Specification for Portable fire extinguishers, water type (storage

pressure) (first revision)

34. 8090 : 1992 Specification for couplings, branch pipe nozzle, used in hose

reel tubing for fire fighting (first revision)

35. 8423 : 1994 Specification for controlled percolating hose for fire fighting

(first revision)

36. 9972 : 1981 Specification for portable automatic sprinkler heads

37. 10204 :

1982

Specification for portable fire extinguishers mechanical type.

38. 13039 :

1991

Code of practice for provision and maintenance of external

hydrant system

39. 13385 :

1992

Specification for fire extinguishers 50 capacity wheel mounted

water type (gas cartridge)

40. 13386 :

1992

Specification for 50 litre capacity fire extinguisher, mechanical

foam type

41. 13849 :

1993

Specification for portable fire extinguisher dry powder type

(constant pressure)

42. 14609 :

1999

Specification for ABC dry powder for fire fighting

43. 15051 :

2002

Specification for High pressure fire hose delivery couplings

44. 15105 :

2002

Design and installation of fixed automatic sprinkler fire

extinguishing system.

Page 30: PROJECT SITE LOCATION MAP ON GOOGLE EATH

5

APPLICABLE STANDARDS AND CODES FOR ELECTRICAL EQUIPMENT,

FITTINGS AND SAFETY MEASURES

S. NO. IS CODE NO. TITLE OF THE CODE

A. HT PANEL AND CABLES

1. IS: 2516 Circuit Breakers

2. IS: 2705 Current transformer

3. IS: 3156 Potential transformer

4. IS: 9385 High voltage fuses

5. IS: 6875 Control switches

6. IS: 1248 Electrical direct acting indicating instruments

7. IS: 722 AC electricity meter of induction type

8. IS: 3231 Electrical relays

9. IS: 2147 Degree of protection provided by enclosures for low voltage

switchgear and control gears

10. IS: 375 Marking and arrangement for switch gear, busbars, main

connection and auxiliary wiring

B. MV SWITCHGEARS AND DISTRIBUTION BOARDS

1. IS: 13947 Specification for low voltage switchgear and control gear

2. IS: 5578 Guide for marking of insulated conductors

3. IS: 11353-85 Guide for uniform system of marking and identification of

conductors and apparatus terminals

4. IS: 12063 Classification of degree of protection provided by enclosures of

electrical equipment

5. IS: 2675-83 Enclosed distribution fuse boards and cut-outs for voltages not

exceeding 1000V

6. IS: 2551-52 Danger notice plates

7. IS: 8623-93 Factory built assembles of switchgear and control gear for

voltages up to and including 1000 V AC and 1200V DC

8. IS: 8828 Miniature air break circuit breakers for voltages not exceeding

1000V

9. IS: 9926 Fuse wires used in rewritable type electric fuse up to 650 Volts

10. IS: 13703 HRC fuse links for voltage above 650V

11. IS: 2705

(Part-I,II &III)

Current transformers

12. IS: 3156

(Part-I,II &III)

Voltage transformers

13. IS: 1248 Indicating instruments

14. IS: 3231 Relays

15. IS: 375 Marking and arrangement of busbars Indian Electricity Act and

Rules

Page 31: PROJECT SITE LOCATION MAP ON GOOGLE EATH

6

C. CABLES AND CABLE TRAYS

1. IS: 7098

(Part-I)

XLPE insulated LT

2. IS: 1554

(Part-I)

PVC insulated (heavy duty) electric cables: For working

voltages upto and including 1100V

3. IS: 8130 Conductors for insulated electric cables and flexible coards

4. IS:

3961(Part-II)

Recommended current ratings for cables: PVC insulted and

PVC sheathed heavy duty cables

5. IS: 5831 PVC insulated and sheath of electric cables

6. IS: 10810 Methods of tests for cables

D. WIRING SYSTEM

1. IS: 732 Code of practice for electrical wiring installation (system

voltage not exceeding 1100V)

2. IS: 1646 Code of practice for fire safety of buildings: general electrical

installation

3. IS: 9537 Conduits for electrical installation

4. IS: 2667 Fitting for rigid steel conduits for electrical wiring

5. IS: 3480 Flexible steel conduits for electrical wiring

6. IS: 3837 Accessories for rigid steel conduits for electrical wiring

7. IS: 694 PVC insulated cables upto and including 1100V

8. IS: 1293 Plugs and sockets outlets of rated voltage upto and including

250V

9. IS: 8130 Conduits for insulated electric cable and flexible cord

10. IS: 3854 Switches for domestic and similar purposes

11. IS: 3419 Fittings for rigid non-metallic conduits

12. IS: 4648 Guide for electrical layout in residential building

13. IS: 4649 Adopters for flexible steel conduits

14. IS: 14772 Boxes for enclosures of the electrical accessories

15. IS: 4615 Switch socket outlets (non-interlocking type)

16. IS: 8884 Code of practice for installation of electric bells and call system

17. IS: 2551 Electric danger notice plates

18. IS: 3646 Code of practice for interior illumination

19. IS: 371 Ceiling roses

20. IS: 302 General and safety requirements for household and similar

electrical appliances

21. IS: 3043 Code of practice for earthing

E. LIGHT FIXTURES

1. IS: 1913 Electric light fittings: General and safety requirements

2. IS: 1777 Industrial lighting fittings with metal reflectors

3. IS: 5077 Decorative lighting out fits

4. IS: 10322

(Part-I to IV)

Specification for luminaries: Flood lights

Page 32: PROJECT SITE LOCATION MAP ON GOOGLE EATH

7

5. IS: 10322

(Part-V)

Luminaries for street lighting

6. IS: 1258 Bayonet lamp holders

7. IS: 3323 Bi-pin lamp holders for tubular: fluorescent lamps

8. IS: 1534 Ballasts for use in fluorescent light fittings

9. IS: 2215 Starters for fluorescent lamp

10. IS: 6616 Ballast for HP MV lamps

11. IS:1569 Capacitors for use in fluorescent, HPMV and LPSV lamps

circuits

12. IS: 2418

(Part-I)

Tubular fluorescent lamps

13. IS: 9900

(Part-I)

High pressure mercury vapour lamps

F.BATTERY AND BATTERY CHARGER

1. IS: 9128 Heavy duty batteries- specifications

2. IS: 6303 General requirement and tests for dry cells and batteries

G. TRANSFORMERS

1. IS: 10561 Application guide for power transformers

2. IS: 6209 Methods for partial discharge measurement

3. IS: 2071

(Part-II)

Method for high voltage testing

4. IS: 10028 Code of practice for selection, installation and maintenance of

transformers

5. IS: 9128

(Part-I)

Specification for power transformers: General

6. IS: 11171 Dry type power transformers ANSI C57, 96 IEEE guide for

loading dry type distribution and power transformers

7. IS: 2026

(Part-IV)

Specifications for power transformers: Terminal marking

tapping and connections

8. IS: 3639 Specifications for fitting and accessories for power transformer

H. BUS TRUNKING/DUST (FOR DG SETS AND TRANSFORMERS)

1. IS: 5486

(Part-II)

Particular requirement of bus bar trunking system

2. IS: 439/2 Particular requirement of bus bar trunking system

3. IS: 529 Degree of protection

4. IS: 60331 Applicable for cast resin bus bar fire rating

Page 33: PROJECT SITE LOCATION MAP ON GOOGLE EATH
Page 34: PROJECT SITE LOCATION MAP ON GOOGLE EATH

I||lD RE$EARCH & DEIJELOPI|EIIT HOU$E PtlI LTD,N ABL ACCREDITED IABARATO RY

(lSO 9001 :201 S/tSOl &01 :201 5/OHSAS/18M1 :2007)

C-10, 2nd Floor, Sector-6, Noida-201301 (U.P.)Tel. : +91 120 4215489, E-mail : [email protected]

TEST REPORT{Water)

Page l/2

ReDort No. : rRDH-0518-COM-WQ-831Date of Renortins aTloqza18Issued to M/s f nd Tech House Consult, G-8/6, Ground Floor, Sector-l1, Rohini,

Delhi-110085

Project Name Development of Residential Colony under DDJAY {6.206 Acres}, Village-Mohammadpur Gujar and Sohna Sector-35, Sohna, Gurugram by M/SFaith Buildtech Pvt. Ltd

Nafure of Sample Ground WaterIdentification of Samnle Water collected from nearbv oroiect site in 2 litre can

Date of SamDlins 29lOsl2018Method of sampling lS 3025- Part 1{1987)

Date of testing: 29 | os / 2018 To 0al6120 1 8

Sampled by IRDH - Team

RESULTS

S

No. Parameter Test Protocol Results Unit

Requirements as per

rs 10500- 2012

Acceptable Limit( Max)

Permissiblelimits(*tax)

I pH IS3025P-I1 r983 7.80 6.5-8.5 No Relaration

) Turbiditv IS 3025 P-I0 11984) 4.5 NTU I 5

3. Total Hardness rs 3025 P-21 (2009) 428.0 mgn 200 600

4.Total Ilissoh.edSolids [DS) IS 3025 P-r6(1984) I128.0 mg4 500 2000

3. Calcium as Ca IS 30?5 P-40 ir99l) 86.{ mg/l 200

6. Magnesium as Mg IS 3025 P-16 f1994) 5l .51 mg/lJU 100

7.Total Alkalinity as

CaCO-rIS 3025 P-23 (1986) 128.0 mgA

200 600

8. Chloride as Cl rs 302s P-32 (1988) 310.0 mg/l 250 1000

9. Barium as Ba Anner F ofIS:13428 <0.05 mg/l o.7 No Relaxation

10. Ammonia as N IS 3025 P-34 (1988) <0. I mg/l 0.5 No Relaxation

l1 Sulphate as SOr IS 3025 P-2a 11986) 70.0 mg/l 200 400

12. Nitrate as NO3 IS 3025 P-34 (r988) 32.0 mg/l 45 No Relaxatron

Head Office: G-8/6, Ground Floor,Sector-11, Rohini, Delhi-110085Tel.: +91 - 11-2757 1410, 64607252E-mail : [email protected]

,A5.ANZ

Page 35: PROJECT SITE LOCATION MAP ON GOOGLE EATH

IIID RESEARCH & DEIIELOPIdE}IT HOtJSE P\lI LTD,

N ABL AC C RED'TED LABO RAT O RY(lSO 9001 :201 5/lSOl $01 :201 S/OHSAS/I 80Ai :2007)

C-10, 2nd Floor, Sector-6, Noida-201301 (U.P.)Tel. : +91 120 4215489, E-mail : [email protected]

Report Nc. - IRD[I-O5f8-COI{-I\'Q{31 Prge: 2/2

S

No. Parameter Test Protocul Results IInit

Requirements as per

IS 10sfi)- 2012

Acceptable Limit( Max)

Permissiblelimits(Max)

13. Fluoride as F APIIA,22"dEdition o.26 mdr 1.5

1jl. lron as Fe is 3025 P-53 i20O3) 0.10 mC/lcl.3 No Relaxation

15. Aluminiumas Al rs 302s P-55i 2003) <o.01 mC/t0.03 0.2

16. Anicnic Detergent Anner K oflS:l 3428 {.05 mgA0.2 I

17.PhenolicComoounds

IS 3025 P-43 (1992) <0.001 mdl 0.001 0.002

18. Boron as B rs 3025 P-57 i2005). <0.1 mg/10.5

19. Chromium as Cr rs 3o2s P-52 (2003) <0.01 me/l 0.05 No Relaration

20. Lead as Pb is 3025 P47 il 994) 4.01 mg/l 0.01 No Relaxation

2t. Copper as Cu rs 3025 P42 (1e92) <0.01 tndl 0.05 1.5

,,} Merctrry as Hg IS 3025 P-48 (l994) <0.001 ng/l 0.001No Relaxation

23. Manganese as Mn rs 3025 P-59 (2006) <0.01 mg/l 0.10.3

24. Zinc as Zn IS 30?5 P49 f 1994) 4.01 mgA 5l5

tq Arsenic as As IS 3025 P-37 (1988) 4.01 mC/l 0.01No Relaxation

26. Nickel as Ni IS 3025 P-54 (2003) €.ol mg/l 0.0?No Relaxation

71 Cadmium as Cd rs 3025 P-11 (1992) <0.001 ml 0.003No Relaxation

'Frd ofReport'

1- Tes Rqort is limited to the invoi.ce mised2-Tut Reltort camot be rqtroluced in a ptrt or as *hole in cowt *irtout laboraory permission3- Samples shall be rdainedfor 1 weeks afo tat rqtort submilled.

Head Office: G-8/6, Ground Floor,Sector-ll, Rohini, Delhi-1100851s1.; +91 - 11 - 27571410, 54607252E-mail : [email protected]

,AS-At{Z

Page 36: PROJECT SITE LOCATION MAP ON GOOGLE EATH

I}ID RESEARCH & DEIIELOPi'EI{T l|OUSE PtlI LTD.NABL ACCRED'TED LABARATORY

(S O 9AM : 201 dns O I /nO1 : 201 5/O HS AS/1 8 001 : 2007)C-l0, 2nd Floor, Sector-6, Noida-201301 (U.p.)

Tel. : +91 120 4215489, E-mail : [email protected]

TEST REPORT(Soil)

Renoft No. : rRDH-0518-COM-SL-831

Date of Reuortins 07/06/2018Issued to M/s Ind Tech House Consult, G-8/6, Ground Floor, Sector-11, Rohini, Delhi-

110085Project Name Development of Residential Colony under DDJAY

Mohammadpur Gujar and Sohna Sector-35, Sohna,Buildtech Pvt. Ltd

{6.206 Acres}, Village-Gurugram by M/S Faith

Nature of Sample SoilIdentification of Samole Soil samole collected from Proiect siteDate of Samnlins 29/As/2A!8Method of samDlins USDA methodDate of testing: 29/0s12018 To 0al06/2018Sampled bv IRDH - Teanr

RESULTS

S. No. Parameter Tesf Method Results Unit

I pH IS 2720 P-26 i1987) 7.98

2. Conductivity IS 14767 (RA 2016) 556.0 pS/cm

3. Moisture IS 2720 P-25 iI972) 5.8 o/o b.v mass

4. Water Holding Capacity IRD}VSOP-SL/07 40.0 Yo

5. Specific Grali4' IS 2720 P-3 ir980) 2,20

6. Bulk densiw IRD}YSOP-SLIO6 I .{l gm./cc

7. Chlcride IRDIVSOP-SUI4 2l1.0 mgkc

8. Caicium IRD}VSOP-SL/I7 1904.0 mdkg

9. Sodium IRDWSOP-SIJII 178.0 mgAig

10. Potassium IRDWSOP-SL/I2 96.0 mg/kC

11. Magnesium IRDiVSOP.SUI6 216.0 mg/kg

12. Organic matter ls 2720P-22 (1972\ 0.6t %o by mass

13.CationExch4ngeCapacit-v(CEC)

IRDII/SOP.SLIOg r4.0 meq/l00gm

14. Alailable nitrogen IS 14684 112.0 mgkc

15. Available Phosphorous IRD}#SOP-SL/10 7.O ng/kg

Head Office: G-816, Ground Floor,Sector-11 , Rohini, Delhi-110085Tef .: +91 - 11 - 2757 1419, 646A7252E-mail : [email protected]

JAS-Alrlz

Page 37: PROJECT SITE LOCATION MAP ON GOOGLE EATH

IIID RESEARCl| & DEI,ELOPIIEilT l|OU$E PIII LTD.N ABL AC C RED'TE D LABO RATO RY

(lS O 9001 : 201 S/r S O I qni : 2Ot SlO H SAS/1 AN)t : 2007 )C-10, 2nd Floor, Sector-6, Noida_201301 (U.p.)

Tet. : +91 120 4215489, E_mait : [email protected]

Repoft N& - IRffI-OS1$C{}M-SLS1 Pege 2ll

S. No. Parameter Test Method Results Unit

16.

Textue

IRD}VSOP-SL/08 %o by massSand 66,8Clay 24.O

silt 09.2

17.Sodium AbsorptiutRatidSAR) IRDTVSOP-SL/I3 1.03 By calculation

rErd ofReport'

I- Txt Rqort is limitd to the invoice rcised2-Test Rqtort cannot be tqnoilted ia a part or as w*ole ia cost tithost labrntity permission3- Senqles shall be rdainedfor 1 wec*s afer tx rqott submitted.

Head Office: G-816, Ground Floor,sector-11, Rohini, Delhi-110095Tel.: +91 - 11 - 2757141A, 64607252E+nail : [email protected]

.ilts-Ar{z

C?

Page 38: PROJECT SITE LOCATION MAP ON GOOGLE EATH

IIID RE$EARCH & DEIIELOP||{EIIT l|OUSE Ptll LTD,N ABL AC C RED'TED LABO R,ATO RY

(SA 94il :201 5/,5o1 4001 :201 5/OHSAS/I 8001 :2007)C-l0, 2nd Floor, Sector-6, Noida-201301 (U.P.)

Tel. : +91 120 4215489, E-mail : [email protected]

TEST REPORT(AmbientAir)

'Eld ofReport"

1- Tes Repafi is limited ta the invoi.ce mised2-Test Report camot be rqtruduced in a part ot as *'hole in cost firhout laboraory permissian3- Sanples sho& be raaiaedfor 1 *eeks efa tat rqort ssbmiaed-

Repofi No tRDH-0518-COM-MQ-831

Date of Reporting 07/6/2A,3

fssued to M/s f nd Tech House Consult, G-815, Ground Floor, Sector-ll, Rohini,Delhi-110085

Project Name Development of Residential Colony under DDIAY t6.206 Acres),Village-Mohammadpur Gujar and Sohna Sector-35, Sohna, Gurugramby M/S Faith Buildtech Pvt. Ltd

Twe of Monitorins Ambient Air MonitoringDate of Sampling 29las/2a18 to 30/0s/2018 ts* 1) &

02 | a6 / 2AL8 rc A3 / O6 / 2Ot8) {Sf; 2}Incation Project sitePararneters to be samnled PM25, PM16, SO2, NOr, CO

Weather condition Clear sky

M€thod of samoline As per standard MethodDuration of Monitoring 24 hourly

RE,SIJLTS

S.No

Parameter Method ResultsUnit

Requirrcment(CPCBlimits)*s#1 s#2

I Particr:late Matter as Pld2.5 TRDWSOP/AAQMIOI 82.0 87.0 pg/m' 60

2. Particulate Matter as PMyo IS 5182 P- 23 (2006) 180.0 190.0 pg/m' 100

3. Sulphur dioxide as SO2 rs 5182 P-02 i2001) 08.0 10.0 Fg/m= 80

4. Nitrogen dioxide as NO? rs 5182 P-06 (2006) 24.0 26.0 pdm' 80

5. Carbon monoxide as CO IRDIYSOP/AAQIvI/O8 0.80 0.82 mgm' 4.0

*Ga&tte notifieation puhlishetl by MaEF&CC, New Delhi on 18 Nov. 2009

Head Office: G-8/6, Ground Floor,Sector-11, Rohini, Delhi-110085Tel.: +91- 11-27571410, 64607252E-mail : [email protected]

Page 39: PROJECT SITE LOCATION MAP ON GOOGLE EATH

IUUSEARCH & DEIIELOPF'EiIT ltOUSE PtlI LTD,NABL ACCREDITED LABARATORY

(lSO 9001 :201 5/lSOl 4001 :201 S/OHSAS/I BlOt :2007)C-10, 2nd Floor, Sector-6, Noida-201301 (U.p.)

Tel. : +91 120 4215489, E-mail : [email protected]

TEST REPORT(AmbientNoise)

RESULTS

'End ofRepcrt"

1- Tes Rqott is limited to the invoiu ruised2:T:o R?"n,.1ryot be rqroilaced in a1mrt or as t*ole in cout *ithoar lzboraory prmbsion3- Sampla shall be raainedfor 1 weeks aSo test rqnrt sabmiaed.

Report No I RDH-0518-COM-ANQ-831Date of Reporting a7lffilz0LgIssued to M/s Ind Tech House Consult, G-816, Ground Floor, Sector-ll^, Rohini,

Delhi-110085Prcject Name Developrnent of Residential Colony under DDJAY (6.206 Acres),

Village-Mohammadpur Gujar and Sohna Sector-35, Sohna, Gurugramby M/S Faith Buildtech Pvt. Ltd

Type of Monitoring Ambient Noise MonitoringDate of Sampling 2elo5/2o78 to 30/0s1201s {s# t} &

02 / 06 / 20L8 b A3 / A6 / 2A1,8) (Sf 2)Location Project siteMethod of samplins As per standard MethodSampling Protocol lS:9876-2004; lS 9989-2003Duration of Monitorins 24 hourlySample drann by IRDH Laboratory

Sr. Ho. locations Dry Time (Lday)ffisoAM - 1&00PM

Night Time {tnight}losoPM-06{nAM

ANQ Project site s#1 s#2 s#r s#253.9 s3.6 40.4 4L.2

CPCB LimitsSr. No DayTime Nightfime

t Industrial area 70

7 Commercial area 65 5,t

J. Residmtial area 45

4. Silence Zrne 50 40

6-)ry{Q)

Head Office: G-8/6, Ground Floor,sector-'ll, Rohini, Delhi-110095Tel.: +91 - 11 - 2757141A, 64607 252E+nail : [email protected]

,A5.ANZ