Project Report, TXUT-001-PR-017, Rev. 1, 'The Evaluation ... · Perry's Chemical Engineers'...
Transcript of Project Report, TXUT-001-PR-017, Rev. 1, 'The Evaluation ... · Perry's Chemical Engineers'...
• No. TXUT-001-PR-017E N E R C O N PROJECT REPORTfcellence--ryptoject E'vy ddy, COVER SHEET REV. 1
PAGE NO. 1 of 13
PROJECT REPORT
For
the Evaluation of Lake Granbury Water Temperature Due to theOperation of CPNPP Units 3 and 4
Independent Review Required: No
Prepared by: Jar
Reviewed by: 9_?ýLd1C~I)4 ~ 'Reviewer
Reviewed by: Aikm (:' <'/Indepe6dent Rdvieh(er
Approved by:
Date: -5-11-519Date:
Date:,
Dat:_________
ProtpiManag&r or Designee
No. TXUT-001-PR-017PROJECTREPORTF~-ENE RCON_ for RE.
£ •-• • •, the Evaluation of Lake PAGE NO. 2 of 13Granbury Water:Temperature'
Due to the Operation of_ _ _ _ _ _ _ _ _CPNPP Units 3 and 4 .......
PROJECT, REPORT REVISION STATUS
REVISION DATE DESCRIPTION
0 5/7/09 Initial Issue1 511.5/09 Revised to provide
additional reference.;and'data
irfforrhation. Alsorevised control
boundary.
PAGE REVISIONSTATUS
PAGE NO. REVISION PAGE NO. REVISIONAll: 0-A ll '
APPENDIX REVISION STATUS
APPENDIXNO. PAGE NO. REVISION NO. APPENDIX NO. PAGE NO. REVISION NOadded F ALL 1 A,B,C,,D,E' ALL 1
No. TXUT-001-PR-017PROJECT REPORT REV.EN ERCO.. N for REV. I
the Evaluation of Lake PAGE NO. 3 of 13Granbury Water-Temperature
Due to the Operation of___CPNPP Units 3 and 4
TABLE OF CONTENTS
Section Page
Summary 4Purpose- 5Results. 5References 5Data 6Assumptidns 9Methodology 10Evaluation 13
Attachments Pages
Attachment A: 'Cooling Pond' Information 3Attachment B: Bin Information 1Attadhment.C. Wet Bulb Conditions 37Attachment D: DeCordova Readings, 1Attachment E: Other Intake ,Flows 1Attachment F:- Revised Elevation-AreaýVolume Estirinates for Lake GranbUry, Hood 5.
County, Texas
No. TXUT-001-PR-017PROJECT REPORT REV.ENERCON _for_"RV
E.cefena-Evrypro]j-m, dy the Evaluation of Lake PAGE NO. 4 of 13Granbury Water Temperature
Due to the Operation ofCPNPP Units 3 and 4
Summary
The evaluation uses a control volume/energy balance approach based on the first law ofthermodynamics or conservation of energy to determine the daily temperatures of the lowerLake Granbury volume (upstream of DeCordova Dam). The methodology uses the highestdifferential temperature between the discharge and the background temperatures, historicallyoccurring: during the winter months, and a period of low flows through the lower lake volume.Historical data with a reasonable number of recorded river temperatures (river temperatureswere not recorded on regular bases) and times where low flow rates through the, lower' lakevolume were searched. A 65-day period between December 11, 2001: and February 13, 2002was selected for evaluation along with assumed preliminary design information forthe proposedComanche Peak Nuclear Power Plant (CPNPP) Units 3 and 4. The nettemperature increase forthe 65-day period is conservatively evaluated to be <1.00°F, which would be mitigated by thelake's surface evaporation.
No. TXUT-001-PR-017PROJECT REPORT REV. I
ENERCON for REV.!the Evaluation of Lake PAGE NO. 5 of 13
Granbury Water TemperatureDue to the Operation of
CPNPP Units 3 and 4
Purpose
The purpose of this evaluation is to enhance the information supplied in the CORMIX runs forthe iowerLake Granbury area and to verify results would meet the predicted permitrequirements. CORMIX inputs a single flow regime for the river or lake that provides a plume forthe thermal or toxin input. Low lake or river flow conditions reliably provide the largestconservative thermal plumes that will meet permitted or proposed permitted conditions ascalculated by CORMIX; however, CORMIX provides no information on possible accumulationsof heat. This energy balance provides a conservative estimate of heat accumulation in the areabetween the cooling tower blowdown discharge and the lake intakes.
Results
The cooling tower blowdown discharge into Lake Granbury will create a plume that is warmerthan the surrounding environment and will, therefore, be more buoyant. The plume will spreadacross the, surface of the control volumewith enough. energy to iniduce additional evaporation.This evaporation provides the largest heat transfer from the control volume and is modeled as a
cooling pond for this report. The heattransfer, along with normal mixing limits, will heat the arealess than 1IF and agrees with the CORMIX findings. In addition, the normal evaporation thatequates to more than 1.7 billion btu/day (Reference 12) removed from the lake surface will morethan mitigate the heat buildup determined by this evaluation. Therefore, the discharges from theplant into Lake Granbury should meet the predicted permit requirement of less than 3°F heatbuildup.
References
1. Banerjee, T., M. Cerha, K. Kallfisch, and R. Dalal. TXU - Comanche Peak Units 3 and 4,Optimization Study for Secondary-Side Cooling Water*System. August 15, 2007.
2. Boss, SK., Ph.D., P.G. Bathymetry and Volume Storage of a Portion of Lake Granbury,Hood County, Texas. Department of Geosciences, University of Arkansas, Fayetteville,AR. July 11, 2007.
3. Brunett, B. Brazos River Authority, Hydrologist. Personal Communication, E-mailRequests for Historical Darn Release Data. July 13 and October 1, 2007.
4. National Oceanic and Atmospheric Administration (NOAA), National Climatic DataCenter (NCDC). Thirty Years (.1977 - 2006).of Meteorological Data for Minera! Wells,
Texas, Station No. 93985. http://cdo.ncdc:noaa.gov/cgiibin/climatenormals.pl?directAccessed January 7, 2008.
5. Perry, R. H., and D.W. Green. Perry's Chemical Engineers' Handbook, 7 t" edition, 1997.McGraw-Hill, Inc., New York.
No. TXUT-001PR-017PROJECT REPORT REV. I
for REV._1Elenc•--Every ,ojecver,yd ty. the Evaluation of Lake PAGE NO.6 of 13
Granbury Water TemperatureDue to the Operation of
CPNPP Units 3 and 4
6. Sammon, J. Brazos River Authority, Environmental Planner. Personal Communication,E-mail request for Lake Granbury Historical Temperature Data. June 15, 2007.
7. Texas Commission on Environmental Quality (TCEQ). Water Use Data, TCEQ ExternalPublishing FTP Server. ftp:/Iftp.tceq.state.tx.us/pub/OPRR/waterrights/ Accessed April2009.
8. U.S. Geological Survey (USGS), National Water Information System. USGS SurfaceWater Data for the Nation, Water Data for Texas. http://waterdata.usgs.gov/tx/nwis/Accessed April 2009.
9. Ward, G.H. Potential Impacts of Comanche Peak Cooling Tower Operation on TotalDissolved Solids in the Lower Reach of Lake Granbury. Consultant in Water Resources.January 31, 2008.
10., Boss, S.K. White Paper: Revised Elevation-Area-Volume Estimates for Lake Granbury,Hood County, Texas. May 11, 2009.
11. Comanche Peak Nuclear Power Plant, Units 3 & 4, COL Application, Part. 3Environmental Report, Rev 0. Table 2.7-45.
12. Comanche Peak Nuclear Power Plant, Units 3 & 4,, COL Application,, Part 3Environmental Report, Rev 0. Table 2.3-2.
Data
mv is in Ibm and is obtained from the bathymetric volume in acre-feet (Reference 10) andconverted to Ibm using the following conversion:
* ~ ga 3581 IIbmAcre - feet ga325,851 g * 8.34 Ibmacre - feet gal
where:
8.34 Ibm/gal is the mass of water per gallon for the temperatures examined (Reference5).
Cp specific heat of water is -1 btu/Ibm OF (Reference 5).
mr is the daily mass flow rate through the bathymetric volume in Ibm/day. Volumetric flow ratewas provided by the Brazos River Authority'(Reference 3). The volumetric flow isconverted to mass flow (Ibm/day), as follows, to determine the mass flow rate used inthe evaluation:
Ibm = cfs * 448.83 *gpm 8.34*bm,60 min 24 hrday cfs gal .hr day
No. TXUT-001-PR-017~~ ~PROJECT REPORT RV
E N E R CO N for REV.__rr-Evy•project Eve,da the Evaluation of Lake PAGE.NO. 7 of 13
Granbury Water TemperatureDue to the Operation ofCPNPP Units 3 and 4
Where:
gpm is the volumetric flow rate in gallons per minute.
md is the daily discharge flow in Ibm/day. Volumetric flow rate was provided by the URSoptimization study (Reference 1).. The volumetric flow is converted to mass flow(Ibm/day), as follows, to determine the mass flow rate used in the, evaluation:
ibm _ * ibm min hrIbm- gpm * 834- * 60- * 24-day gal hr day
Where:
gpm is the volumetric flow rate in gallons per minute.
mi is the daily intake flow in Ibm/day. Volumetric flow rate was provided by the URS optimizationstudy (Reference 1), plus Wolf Hollow and CPNPP Units 1 .and 2 historical data. Thevolumetric flow is converted to mass flow rate (Ibm/day), as. follows, to determine themass flow rate used in the evaluation:
Ibm Ibm 60min hr__--=gpm *8.34- * 6--' 24 -day gal hr day
Where:
, gpm is the volumetric flow rate in gallons per minute
mri is the additional daily upstream flow into the bathymetric volume due to the difference. in theflow between intake and discharge flows in Ibm/day.
tv begins as the initial average lake temperature and is the evaluated daily volumetrictemperature for each day thereafter. The initial average daily temperature of the lake isthe average of temperatures from 12/11/2001 (55.940F), 1/9/2002 (52.6820F), 1/15/2002(49. 1F), and 2/13/2002 (49.334°F) provided by the Brazos River Authority for the 65-day study (Reference 6), and calculated to be 51.7640 F.
ti is the initial average lake temperature. The initial average daily temperature of the lake is theaverage of temperatures from 12/11/2001 (55.94°F), 1/9/2002 (52.6829F), 1/15/2002
No. TXUT-O01-PR-017PROJECT REPORT REV.IEF.,I E N E R C 0 N for V.
E•rCeI~en---&j__,*C y,• the Evaluation of Lake PAGE NO. 8 of 13Granbury Water Temperature
Due to the Operation ofCPNPP Units 3 and 4
(49.1°F), and 2/13/2002 (49.334°F) provided by the Brazos River Authority for the 65-day study (Reference 6) or 51.7640F.
td is the discharge temperature based on bin data from the URS optimization study (Reference1). Average daily wet bulb temperatures as determined from Reference 4 are used 'inassociation with bin data from the URS optimization study (Reference 1) for the selectionof daily intake and discharge flows, along with the discharge temperature.
Additional evaporation .(md*Cp*Athl) used-to determine the evaporation losses from the volumeis found using cooling pond 'information from Perry's Chemical Engineers' Handbook(Reference 5). The area of the cooling pond used for cooling the maximum dischargetemperature down to an acceptable temperature is found using' the nomograph(Attachment A) from Reference 5 and is found to have an approximate size of 118.83acres. The cooling pond size in Ref. 5 is smaller than the area being evaluated (281.60acres in Reference 10) and is considered conservative for this study. The temperature(thl) used is the difference in the discharge temperature and the daily volumetrictemperature, minus the cooling pond approach of 3'F from Reference 5. The md value isnot the mass evaporated, but is used to determine the heat used for evaporation inaccordance with Reference' .5 guidance.
No. TXUT-001 -PRM01 7EN ER C PROJECT REPORT RE.
F- E NI E R C O -N for • REV. 1I__•__the Evaluation of Lake PAGENO. 9 of 13
Granbury Water TemperatureDue to the Operation of
__ CPNPP Units 3 and 4
Assumptions
1. Additional evaporation is estimated: in accordance with cooling pond information frpmPerry's Chemical Engineers' Handbook (Reference 5),and& included in Attachment'AA.
2. Surface or natural evaporation and solar loading were .neglected within the formalevaluation, but provide .basis forthe assumption that zero energy would be transferredacross the control surface.
3. Units 3 and 4' discharge temperatures and-flows are based on daily average wet bulbtemperatures in Ref. 4 and correlate with values from Reference 1.
4. Units 3 and 4'intake flows are based on daily average wet bulb temperatuhres, inReference 4. and correlate with values from Reference; 1..
5. Daily lake temperatures were not available; therefore, the baseline lake temperature isthe:average of the four lake temperatures for the 65-daylrun.
6. The highest differential lake temperatures as compared to thecooling'tower dischargeare assumed to occur during the winter months'.
7. Actual permit. conditions were not available;' therefore, information from the TexasA'dministrative..Code is used. The permit Condition for temperature change.is assumed-tobe less than 30F for the plant discharge (Reference 7).
8. Conservatively assumed winds are 2 mph for the. Lake 'Granbury area. Using Table2.7"45 of Reference 11., wind speeds for the area near c PNPP are less than. 7.5 mph,verifying the conservatism of this assumption.
9. No rain or snow is assumed. for this, evaluation period-10.. All worksuch as. boating, actions-of wildlife, etc. are considered negligible.11. There is no mass gained or lost froni the control volume during'this evaluation. Actually
mass is lost due to evaporation in the-area, but is considered negligible due to thecooling that would' occur with this phenomenon.
12.. The cooling pond approach of 30F is Used because the discharge pond depth' isgreaterthan .5 feet.
13.. Heat transfer between earth and pond, changing temperature and hu midity .pf the air asit transverses the water, and rain have minor effects, on heat transfer for cooling ponds:(Reference'5), and therefore are assume'd negligible forthis evaluation.*
14. The variation temperature as defihed in Reference 5 of plus or minus 30F is assumed tobe.OOF for this report, and considered to be Conservative because of the large -surfacearea being evaluated.
No. TXUT-O01-PR-017~ , PROJECT REPORT REV. 1IN , ENERCON for-- Ey•d the Evaluation of Lake PAGE'NO. 10 of 13
Granbury Water Temperature,Due to the Operation of
CPNPP Units 3 and 4
Methodology
The first law of thermodynamics for a control volume is the approach ýused to evaluatethe laketemperature conditions around the discharge and intake structures. No mass is gained or lostduring this evaluation; however, the mass flow rates used provide weighted energy Yvaluescrossing the control surface.
Heat added dueto throuah'river
Heat added dueto differeritial'ininlet andioutlet.flows
Evaporationdueto'additional
discharge heat
Heat loss due toflow over dam
Heat eemoved due toplant (i.e.. Units 1, 2.
3 & 4 and Wolf,Hollow) intake
The, basic equation for steady state conditions ,is as follows:.
E,,,, 2 j 4 2 [ 2
Where:
'Plant (Unit 3& 4)discharge heating
Q is rate of energy transfer by heat across abouhdary in btu/day
No, TXUT-00O-R-017r PROJECT REPORT REV. 1
A ENERCON, t. for- t Evaluation of Lake PAGE NO. 11 of 13
Granbury Water TemperatureDue to the. Operation ofCPNPP Units 3 and 4
W is the rate of energy transfer by work across a boundary in watts. Work is, negligible andconsidered zero for this evaluation.
The velocity (V) across the control surface does not changeand is therefore neglected.
z is elevation in feet. There is no elevation (z). change across the control surface and is z.therefore zero.
h is: specific enthalpy in btu/lb.
gis gravitational acceleration..
r is mass flow rate in lb/day.,
Therefore the equation is as follows:
i7;h - nh hin ex
h Cp T
in ex
ex represents theenergy values exiting the control surface;
in representsý the energy values entering the control surface.
The following equation providest the internal energy in the control volume6
T2 represents the final temperature in OF.
T1 represents the. initial temperature in *F.
S=rn Cp-(T2 - "1 )
Q =m Cp T2 -m Cp T1
Combining these equations results in the governing equation:
T= {(mCpT +Y± hCpT-XrhCpT 'J÷ptmin ex
No. TXUT-001-PR-017PROJECT REPORT REV.I
FAENE N forcec-LEtyprojea Ee.ryd the Evaluation of Lake PAGE NO. 12 of 13
Granbury Water TemperatureDue to the Operation ofCPNPP Units 3 and 4
The inlet energy equation is broken down as follows:
rh Cp T = rmr Cp T, + rhri Cp Tj + md Cp Tdin
Where:
mr is the inlet mass flow due to dam operation, which brings about flow through the control,volume 'in Ibm/day.
mri is the mass flow across the control surface due to additional intake flow in-Ibm/day.
md is the mass flow from Units 3 and 4 in Ibm/day.
Tj is the initial temperature in 'F.
Td is the discharge temperature in 'F.
Cp is specific heat of water,, which is equal to approximately 1 btu/Ibm°F.
The exit energy equation is broken down as follows:
mrh Cp T = ihi Cp T, + mr Cp T, + md Cp AT 0ex
Where:
mi is the mass intake flow in Ibm/day.
mr is the through control volume flowt(same as in the inlet energy equation above).
md is the mass discharge flow as used per Reference 5 to determine evaporation in Ibm/day.
T, is the temperature of the control volume that is changing on a daily basis in -°F.
ATe is the difference between the discharge temperature and Tv, minus the approachtemperature of 3F.
Evaluation
The evaluation for determining the net temperature increase of Lake Granbury due to operationof CPNPP Units 3 and 4 for the 65-day period is detailed in the following table.
No. TXUT-001-PR-017_• PROJECT REPORT
for
REV.
the Evaluation of Lake Granbury Water Temperature PAGE NO. 13 of 13Due to the Operation of CPNPP Units 3 and 4
EVALUATION FOR DETERMINING THENET TEMPERATURE INCREASE OFLAKEGRANBURY DUE TO THE OPERATIONS OF CPNPP UNITS 3 AND 4
12/I/1 2u0s0 4.761~t~l.I. 7.0040T47* 4l.00.*r.lO i.06*r1t 4.441440- .60*0 4.0*0.09 -l+G~ UnW4"It 0I.7lIJfl4T4790097G0 0.040716430409*4 7.4444140 73 .61++419 1421404474 *,*.39l0t14 4944404 070 44.4•1• tn 440 244.44ll4/l4
1*/n•41 04 4.7044r.1* 7.00*1.044 1.0.09. 1.40 I.310[.4 4.974.4* 7.71r*.04 1071.0, 4.0*0.47 02.776 *377 09044.BI o0, 48 2s9* 3,1* 7.477 0471• 8 1I1Q 9 1 6 2<t~ l 449444073 *|04 •94449 9,471~,07l 5•ro441. 4 0, 1140440
8*414l00 044.41244.477 40.6 *9-O 2,5074.O 4.34[1-0 .4.0 •140 4?.72f+O 4.400.0 I.40t.12 •0 •4.441 8440 466 0.40444 04 09,03 fl S~ S 0741, 9 f*1. 0 14.4e44077 ,,ssoo41 o .aocoo 04.1 00 00417(4449
4*44/274 420*414* 704.0 104.4 4440.0 9.40.4 100.I.-*10 I.014 3.1i9047*944 - -S14* 92*07 ~ ~ 9*0 0044 47404 44416 44,44 410 4 0.0l0070 ,09747 9040 .714* 40140 0*O44 ,9.9 *4.9 2014 ,94e,934 .9i79994 494* .14.*49040 .914' 4070 4.44 9 49440
42141.404 4..404.42.0*4.474 rn.91.40.42r~lO $06.10 ,09047* ,94.09 ,10017 0.949*0424447 417*41040 004 747*292 7.01 .4*3f.10 94 24*07*74 9.31,40 4.. 94.4 4 9.1-0114947l/70,.,47r4 ,r09.91.t71r.01-..1,1V-09>*.4.9 79049 4394.5.V~0~7h 444440I4 71*11".1. 10.040 4044777944719 ~4*4 *.0 4 44 0 14404
11 V 1244 I134.3lWr.47I..-*,* 1474.04l4.049.4*0.4 -.- t-437,79499?404001 4~ 104940 -- 09,49 2.61.14 9409*40 *4944079 -M" 70.4l I00 004i* 474147707*4 .944004*.*70,940,7,*,Or40.,I.~t94,.9 *.0r01 440.*0..lO49
440l1o.4*04:049 0'44494444940471944*4173041 .011414 44 40 46449 1*
I*4t/O*4 1,004.4 7090.0 7.*9.40 ISI.0 04010-7,41.9 .91.0 44*110 *2.44409*349 *.09*0*1*S* ,*08a, 0004404441444 -9094949 44.0 947~.4.0 9,940*044/4.'** l.040t.* -4.?Ot09 ,*4r.o .~0.00 001.1 794109 94.49 4.3142 0.000470029 0.0940240490 4444944* 3.014* 044*9? *002*4 9.4041*479.4 44 9.44944
w0f104 44714 .9r. 0 t ,74.4 -- 4-10 .11. 10~.~00 ,01~ 09 s144 9*004004 Vol-4*94 04094 044 4406470*41 9090 9.94 0 014044*/*49*0*4 ~ ~ ~ ~ ~ ~ :ý ;.00e.3703.930*.04314 .744 ,7.9 4810 27.20.090901 0s.*999994*0914 -701143 'Alf4.1 4209 *4044494 t4.9.0 .0. 041,04~ 41*30001.4701.400'4 3.4*.0 4911 401.-- 9.1*4.09 .I r.94.9l4 10 .19441*449 O.444S040191243.1 xel.0* 141,290)0* 2411*1044 1.90400C o.0474 0 .04400
4n0t~o 4S041>t .007044.0~.1 240.0 .00.0 .010, 1.,109 4.2.454*0,2119909,003*1.-M7 71091991-0 -%t-.4 442401 *44040 9910 410 44 4*44./9lo14 0r..1 0 -c-.0 4.101l -e0.4 0 .7.0 ...9*r.0 -It-,0 1$7F-1. 51* d $ .4*00914 .. 0.00 9 .0-01791 *.04.9144747 7-7094 s,0,4 P97. $4 1. I4Old*I I
44/0406 14014.t001.1 .l09.0.0.0.904o940 "7910 1..*14. SI. 391.0704"11 0.049901144990 "497,451444141 *44 1 -741000429499 94*1,444 041r" I 0.994*l9t7019011.4 7401014095 1 .0*0. 10 ,01 . .. 00 4.0F~0 4.,-01 3 14910*00 0.7100900 *449 ol0.1.4040* 0 11,21491 7,9.0 0494 * $49900
-l-*704.09 1.4901.9.9 1 .01.0 -It.71.0 ,91.0 It.-.0 o.*14 9..0089190 -le,,904904 040197400 2.047101001440. 2410*4 "'.I40 e4ll. 04I.0*4917.1004 ,400143640.9494.4 L4.0 . 41 .*. 0 4.- -. 0 4.2.1 1 31 449499 .. 94203 3 00449149 .*U-.044100400494404000. * *.4014
I./120*2 I47...f.-12 ?00l4.0 1.434410 l.001.40 4.0*1-10 ?7.044.3 4,fll,09 4.00.124 04.30t610
II ~ ~ 7- 1~~.71• I . l{ .+.z .J*I IAC 0 I~ ~ I~ ~ -.4+ . [• It. • I• +3.7 7 - 1.
1/4l/200* 4.41?;*4000.42.0001. 4.22*4.40+ 4240m140 0400.10 9*41.0 1.3004<09 4,071.12 S4.44009190890
494/74444 4.4*4*.4+*7,0 .044441 14,44*04.4 + *0 4.4044 00440 7.740409 4.+i444109 4.7*1420*.*7009499*7
4/7lira 0*4.J49400044* roO 1 ,.000 I040 0 4,44040.04404 140" .740400 4.404.0 124*-21 " *0.494440170+
4141*•0901.490000l44 7.0641.0 4.S]il.10 *04.l04. a.4 07.10 .44.4 4.044406 U~L.I.43 $4*2fil04o *40f
11110.40"44*1.4*4•11.1* 9.040.09 9.330140 4,941.40 0804.10 9.74440 i.4.014 1,0414 94.4700604004044
4I~/17/94 4.47,QG**r2 74440144,44 [tO J4*I 4.4*1.0444.4400 40 .444.4.7 4.801.494 4.9704434?4414270 930 * -
194.11200 4.1.4*40.4*I 7.09.00.09+ 4.01144101.9044 00040 .7009 2.10 4.4*14 440*+h2[o• m[I£ S.4000412.40*70*
4/09004.904.4 901,--0 1-0410 C 1.S13.10- 341. .140 411,0 "n-114 - 71.049040"4
4/113'Ii0* 1.474 0..1 1 I0 7. 7-1 1 .1 0 1 -1•01 4 1.01.00 l4.10 04.4400044
4/14/100* 1£062000014 ?+7.0071. 4.040.10 4.441410 4.,04410 7.114.*0 4.0*044 L£001.2 94,040*0*1010300
412•*4/04*I .4704*4.l4 /+7,89 -44 3.4401*t0I|.744•.I01 44A4 *7.l019,7720 4.8*0409 4.248 12J9141 0,074484804/14*4110 1,40071.l* 7.07.1.09 4.0044O 42001 0 .4.40 .. 4T01.0 7,90140 401,4* 51. 1 41040074/706* 1.4740*l41l 7.0144 4.901-|0 4.7S1410 4*734I0 ,260.0 400c09- 4.401 4.2e.r -1. 4011.0901
./-/10 4.47001.4* 7.0r10 0.i0*140 4.14144 4,411.10 1.11140 4.1 .41.w -. 40.42 I0.490449444m434*
417/707*o 4.1770041.1* 7.07401.09 40 0 4014 0,7-0l~l~l .40*i 9.99.0 *,109 14.o 4 *0.17 02.494O44t4040 10
4f/70/404 4,47N0441,47 ?Pi • 7090040 l4404 .494.941.4*094444 7.79,494 304040 4.40+1.4 0*.049090414009
/70/74401 I.417144*I 79.4444.0 1.421I0 .. 4*90 .4.4.4.0 o.4"""09 9701.09 4.97971. 0*.4931440 491/9749 I.697104744* 73.09*1I9. 14 .. 4*9I.S1 7.77=4 . C= 4 * %44s;d*470004S404/00 4141 1:4l. ,71+t-. 1,4451i0. 190.1 O 4.41.4- 77,101.09 L,4141 7 4 1400444
17i7100* 1.417941F 7I90L4 F- 1.3444-10 .,7C-.10 ..40 ;.'I 4.44 4._044 07.31044844
z/147404 4,429474l2 1.742140 4,04*14 4._40440 7.747-10 7*709 ?,7r4. 4.0144* 97.947440.47
*14/740*+ 4,19i4t40l4 7,001.444 1.9444.*l., 0,440 2.977-444 7.014[09 0,090.09 4.101.0* 9*.009040104
*/14*004,49*140 190*4014,101.21.4r4442.44.01.07.0 4.41., 170010, 7.04*0*074Is7/31*0 444* 1,fl7.0.9 -.04141-414 2,444 0.It0 940. 4914 0.7*4004
wc- v14.*4042,74414449 -.70740 :,;::.1o 2,4.4 .94-V,040 .4-.45.49474
4.007743410
-322-3-4099
0'.40,4004
9.7444--714
0- ....4 .4 I94
0*49744I 004.4*4-409.4494 710494 00144H +*+ 94199 00 77,0401970
10444449 *.044404447,1440? 2*944t'944* 4.3*0444 94.79 94 4*4047049
44404444 0.,644.40 4*m044+ 479444444 0900,00 *4.7 40 441970407
049404044l 4.644440• 444*009 34400148+ 9.04940 0410 74 f 3040++1*,4008*0404 4.0444.40 4040402* 004I041*4 9,44 m tM 1.01914.9 7 14.91002
9444*78 .2.4+*4410 4444*448 244i944448 0.07040 949.4+ 4 I.4 437404
000.441044* 4.04444 4o 1044916 121444440 0.404,49 9419•4 04 47.4345941.
8044l9m 2.614.40 1406*0004 20010140• 8.77240 4.17• 94 t4,4049041
00404407 4.044.4*10*00040*0044+4*44 8,77040* 948. 48 1.91*+40044* .0=.4* 14040 71*44o09! 8 -144 .01 04 71 4,0*4704
1410*1904 4,041*40. 130220044J 44044•9719 0320400 591* *0 7 14.,080004
+ • ? ~ ~ ~ ,l.1 11?• •1i+ +++ 1 Is 11 411 IA?
070*4049% 7.044*410 04*74 *4400*40 44,41400 011 11 00?+•.460040400
)101440*004 .041[40i40*0•4* 2*910449t 8991.00l 04 744 70 00.0014870
370*4423 olt 4.0144 144094,54* *791 4940 +9 5000 914• 44404.44470*4
440]2904* 14,094.10 14fl0409 200104971 0,4049 94 14 0* 44,4174977
440o9044 2.049400 4443044900 ** 4 0700404 91174 04 91.1300421
44070*4 .60,010 -1-* 44401 440441 94:0 04 44979*7
No. TXUT-001-PR-017W71 ON PROJECT REPORT REV. I
for _ _ _ _ _ _
&U•wre-F-Irmle,•t Ero -y •• the Evaluation of Lake Attachment AGranbury Water Temperature Page I of 3
Due to the Operation of CPNPPI Units 3 and 4
COOLING POND INFORMATION(Reference 5)
EVAPORATIVE COOLING 12-23
10 Coong CafoG I.o SoeaC Ondin$sig
-- Sevice
aI -i 0
90:
fill
70
To 80 0 O
Ternap WoIe Leoving NotZles, Dte.F.
FlO. 12.24 So oal cl~i~oaaaca~eI. (,lacaiaara u laj a-{;Im it ".. la h -1 410
at , 1laiacall,
COOLING PONDSWhe.n oiapCeoC-1111-1 lars a1fre -lble. l-451in! f
5i heal fli tn aarer..A pand slot I, N! ustn
TABLE 12-4 Dag-e Adjusitmntrit 11611 Applied to Laervirig-AirWetaBulb Temperature to Find ¢ooled-Wrair TemparacurasaofSpray Ponds"
FSla, ar. nat i na•Aa~ .aa'a a F.WeFBl Tm .tot-toFn heoI Wet 0 Tept-tso
Cco la} -3 +2alIliaatloa Lo f
70 - I, I3 ÷5
25 -15 +3, Z
sal)
a 0 -4tc ) +a "2,
20 b -u Ul R
at ca'rc:hisa:hsolaall ic~t~tat~La hy p hiattaa.' op ala aonlla tltla .w01. IIca {t6
ia 1l fi a hiah Fio a :.msatan |ofaI [O taaaallaciai.n thal,,l aaa~as I,.:
rea-. aia h~ly iml~rUr , a a ld lao ia a It ,aLa a as dlairalala. FoaaIlrittataaal ad-la ir prMt Islam ill adlt ta llhl
.dw-lahstu is lL himL Ialr i lat m "1100 n1•!uiatli 1oaatd
Lltrt hcaal It fnaaa ita ik ta f0oal al" v a oLlald 5afia-ta[ctnahlr : /r l laaca EnLZa I l S L 1)1, I 11:), aJ e, % hlal iiia; r 6-n'
*att atuaaplie r taria ltia.ltta sa IOti f wars taler s, tlhl csaavataa-lli. taiata1 .IL iseal js -AL s-trt a t a laiIt i l Iaa las svaaalld Min la ] i ju Ll la tan aull a Ti e ttltpdtl.itLtO 5e ni. tretll t o cas Ilar L•'aJLLIiLIILLLL trtatpIraattra ;lOda 5 clrsjaioala~l asIt
i it t l, 12 ta I .a ltt Ph 6aatcaraa la ttwl ctola jo iad i-r-fialaaata o n hli u.iia -Ilibr-iis s l,-uF nftr ff-t'/l ~i ,; I .- flat a,,, ;,,I of •,;n,,li.-tioniw-i~ i$ Usullkt Ismli ht11.ý wry%1% ýýunlyh~el Id M&•It, ,urwi~s
a a lc t laa alba1 lira Ld km at lW iraa alu-la I- iakicp tla aIiaas,t.ac- cai lac r1 r-- i.~a aasr h&,! a lo -tsaaid v aa aootaa ll j .iic-1osa ti
Liz- ula Ia la rqliarsa- ltI wIns f '/-a a iT..ta appm-at-la of 1.7 Ito 2.2*'(3 taa I Fla ila laeh t araaaticale itsa 0• ltdtil ntt aa lelCiih• .l . Fa,"r
dlaaaa I aa ilal~%Ai Itlaaa t s 24• , a -la htaalhap, tla)lasoaraa .aoaato ttttiltataiisll i m Iua 6 lsi- c•araaai,- hs pbiy sat at ma Lai 1.C (01l 1 R 'i a 0.4-a15-fL) LIolht mtd 1-73% ~naL~ fot- 019)n ta341~) datIs'aala.- -a f paaaail h raialed'u daao c kLOii ta i oaaa -ding i-ltat I tll ide-
J rstalot sal pt.aad acpthllA 'alopthl ofaa la-ott 0.9 Iti (3, 0) lpsasn:asIai,-ablel to prLotOatOL055a adacttitet"olLaaha'aallrf" flaow Sailla ;laldaI lacaviiaa,trr.ltllt- IataL alsl attall tia aIaaaaa la'a l aaSl .taI ta- 'ltt• { talaltatIS i Iattals
Iaatais roaaasl..id ra'a ta aflift 1aaaaad jatrla, rtala-a cc0. -ra- sac teoaariai a'!i.i i
ra;n tisas l iih l satat spat ll w aal b alr iailatta L da ,tth op iiath aa;
tIiaC paaalrla.' a~liagiaa ta-taaporalaaira- icaa hlaaiaalahli aal t laaaaar Ias it Iraas-croaetlhea rmaaler. etail rni
ha i '. 1:R-'2 ; a au i to, a toaptal tttuatlata l m oa l loie aI.ls -do,+#' I., ild. llh;tlgml ['I woui -d [iI •ll i•ditv f be, I ,, ln t "D vve i-ý,
iipraaalaahls ito ra'aalalalritalh I lao tlaaitt,n1 i a attafh l ;ii]Iti\tilaa alsalc 017. Vr I.is
atl aol¢' sal•ao.Siyil iaada hit"oaa- P• t rie ra il at o a1 l ta. - tars- a a iill'tla.' jsaoaliVarfuiaa a i-1-5 ) l c a1 lldaaa aa l laas .toi. tlat-paaaad tha st-tO a rl csdtaaaaai u r
jtl a .hr~a fla a i l.a Is giahtla r maa s l t sa aa e ar a
is•I •I , il~l s V. is17RVh~ '00r~ltui =1P. 0. 111P0 (II iil tsf 111
la a.- sir.s
.TAlEtt 1 t-r I mS flumaEla sfd csaldoar l R I[t- ft.artoa l
1 5. alaaurlaaaali f( 1 lio-aai...O i Aus t
NoaodshlarLtstituldeo
Nlrt•tbia Loo-tu hq h.
F4.la 7 r6" o;s6 7sa on"a"40 ac 1
aat. l CI af5 4l 0 11 a 1 03 1 7aO 31`3 3IITABLa I125 t aim Et Solar-a 3alO l.aoi 20 2103I (sr l 4r. -s 10 rý1• ,I t 17D I-1iRady I ,L1 ttn a 45I aa• ! 0t "NOL 210c 1ýattT. III tW3 r",~ L 3t10 Z)t 40 ý:12
nL. 1 12 l1i la -1 -)5 31 1£2ka. 1) ta IVa i. c3a xL 70 74
Mr~ IM, t-r 12 t- 3M S 37 15.3m52s-o.I Im II , I) Its) 03- 1w 3 . 173 I-tWWsa.locCI.o it") 50 Zi 5M 0 2 7) '14
• Fiaaaaa3Ih-4iaii5'oa ala ictiaai7 lia CaaaaiktJiaaalliaai (a.tk1 Otitla cal| •,. a., i•l~lS.Ssaa'l-r
SLa-aali• o1l•af sI na'-al Io|aivla Otiasa44ln lca f la' olamare.
Caap7tlj9 ti 1999 tiy iMMGrc-ltill Caopcani. Ito•. All ilata rlcm n- d;i-c 4ftlis pomda.ta is schjcsi to !Ih tooctos oit. li-cotic netccaat clictk bIr- to i-st,
No. TXUT-001-PR-017O E N E R C 0 N PROJECT REPORT REV. I
the Evaluation of Lake Attachment AGranbury Water Temperature Page 2 of 3
Due to the Operation of CPNPPUnits 3 and 4
12-24 PSYCHROMETRY, EVAPORATIVE COOUNG, AND SOUDS DRYING
0
Add
£ -65
T. 80 w' Scce 0
Key
E twu--V. -- ,ef. so*1o aol add OSN"w aMl.-- V.-E. okakE oat.w - EatS a
II
b40-
5O-
60-
70-
90-
I0"-
nQ 1-2 N
-3.0 -0
-20
-0.
-04
-03
-,2
#
-.
A=PxQ, 145x16=232ft^2/gpm
232 ftA2 i gpm x 22312 gpm = 5176384 ftA2
5176384 ft^2 / 43560 are / ftA2 = 118.83 acres
Cof+wilfU - Is, 1"9 k, The ima-Eil Compmaao.. Ia. UI tighbM ri 4 , d U'a rthit. p S iý ki I 1aj .t it. tka , toe f it. lIsoo Wpoaaat ChA hor to-i-.
'No. TXUT-001-PR-017PROJECT REPORT REV. I
.._ N for- £ . the EValuation of Lake AttachmentA
Granbury Water Temperature Page 3 of 3Due to the Operation of CPNPP
Units 3_and 4
.Mpac utiktt ,
SOLIDS-ORYING FUNDAMENTALS 12-25
iitsil ,• .r ,rnf t ,.josulrairi " ,s,.++ d,••ii ' airlSt•iji flare are": rlia. i-ilptiliif-5 Early i c, ilis i sv-a atli liii- :liigiti ilh f] -rltiiit u at iiin it tp ,-a
phll Iil flirt.a+' rlil .miill5s.- + l s %.•ii- lith sallin ,iaidisrlai, h hfl.Hld-mla. ait fithyl aerI~a ili- iiidypiiisli~i a1." i v! Ie 15 niis 4r1 1to.
SOLtOS-DRYiNG FUNDAMENTALS
(:;r-t1tns IIElT ~i-.P.t Ct-i1 r-al L)"Iiltii fair',s hiei. ;i41r."4Nfii,as.~v-flill+ lltiff, Uaii r~~ltn lvhislapr-.ttt t, hararrittiil J•tairss. MlsstslTDk~lelaNy. slal.+1 IIAp- 1.i -ii p-IS . irs Slitit. hetLie • 5.. 55115,
hlelsttla! ftteiie., S+isrl ~Ite' lats. N.%+.i< VI IS7. Vititlalai~l sail Meat i rri++I iei.Si-Pals a sh. irw•+apa slpl+tii, C~lsC Piest• |hi-i .1+ Se+ nt's Lard; lii attival
ý NI 1p 0t t~rl D t.N S, IN'S.
INTRODUCTION
'lii ijsin• Ira l iil • I i i I at I, . riI ,si'i- ii IuIhtls-
t'dias lacsres' pui salilaal ill," it,-isa l p f l i sl sarii- ii a fl;l lii' Ihlta.Vari
f1u iirt iit ,wii. ' .1.. .Stalh', Tii i i nhdh,-i'1 s t- l l erln si t t6iia1 I~i• sl+Ttiidi rlit'l+ ,pslrb+iide ea
iip,; riiiiiiiiliiriii l +ilhteiistii h lt flt ,si w e lalilt-it•,si"s l• ,r slp e l "tis hae
ll tuu•iii is d .lsti t tlir l ii~l~t i+•1i, -i l m+I' d t. hilily lii -si',.liflu- pta
fl~ileria-p•t p-l-il• +i tiiil r irracl, sic • f ire sit- ish-- i ce- itr Lriclly+ flipflat Iis ds-ssiaa rd ]1iiaIi-i lip Ihis.+-is0h sitii5 I+ itrplti~ iisi+prilte,
eruiipliei5 id l ilttlit " I es itu ii d -p -rt~ts ii, fAl- 1i'llth e PisIlrsusiLr 1al. TI -'reri ii~si hi-li-iik ils illiii.i au -Pte p-n
0,s-i,.Spa +aglsss ,iru ,,ti tp f 1i, dFit I I I,-i, -Isid- ri. hutpR- I& bi Itpill ,I slsii , i toad slt train It
FIG.dsae Thiiesl iliahflasr-seiissrl 2i- sIhih i li2a2 pisss Iiiflicalci flu' >lafefl•its.at•hisetft{. *lilsss.lt bv it l. tiiiii i htiil -lsutt~ ~Illlisisiiiflll ++ilp sslssiisite• d. tltsrl' i p t a• l•ilelat-+ht'spiis {l c fi.ss ls5' -'rshss isl + Is
hist4 i=ii flip< st,+iriii AI h• sjiii sp• .laiih', ~f t ls.'r•lit li +afsjit ,s; flit tzit;
Ff0. 12-2 .talelr ip il Ill atar ritliiiairsis Irf~' rt{.
-44kseif " i salIIrupIi I f iti iit] h l .. u•'-riss 's l i l , I- Ii t,st dltI.Mtile~s f lip siiri s-lii-i'.- ph5551- isl +ilhii ih l~ iltini u-h' ca. ith-ldit
t h i gh rfisa.lllii-ll aiýf l feulll flirt ihii pasli.lhr, the, ai+ l ltf'itise-i iiC trlaitiIs nraiiiiimlllk sipisrasi assl fallllitsi hlipk. Sjsp.tifssil~lksdir rlie +la pliata. aiilf Ili,' tZis pii5%s ts,- sirs i ' i iisp~ I~tl si tl s I!rJls"t irb,'h llit l dmi: .Plln17•tIdl~i'. He -'~ ... -
)rihfs- 1 l li+ is i l -iulls't'pailil] iaslaitisa iii isuh lt ii Sh t O i litý lid r+'sitIps astp se, asdtlpl +,• lld-t Ils t r t~ se l flt -~-spsn isspfssll, lit+ sillllii•t
1ipS1 i a, ( fli t•-ii .• -l illst slip 551i1.1 phitit" - is st frills, , isp.l I s i_,ip ga la~s l hslullll+ bttsi1
t+si , sltasppacuriti,+ is ,pttestitlldh Slatsi s~lip.cutpltsphrss. (Fsg•Oi,. Ic---2ip. ('kistuit.iuv+lhu llliis sti itaip+it 55 s|liii di, ciasi-kIs. ai al Isslift ili ,2 lu s isl epilr iii fenusIsri l (..i.li. ....... ..
slti al•dlt asi •i p l t-I t l i iuid lti'd-s t l+| ,his s Ite atls,usst lietll;. hii`l is ips ,ulesis ir~mi---k Statist s;-sllsiie.s-|•s'llilri!li+ siis'l'las (~lltie si -it rusl r$ tlt •issietsur sl~ itu !liac; S luft slf••.rc 1un l~ ,si tiissspliu~issh stihssl h "ligtu ,i'slt~uvtis(ll• susTllit'ss-sss )11ililsit sit-,l.ulst .iiiig l.fl ,. .
• " si.s-i~lsfr{siit fi ( t fnalir .l~rli~is a~c illtii jutl~i l l{ai~
f~lip+ st ir-flilts is- r + .lu~'hIs +I I, ca-s t csssu-Iit a I~s-Il trilalst sap flilt'>tlul iI. Slitalrdb•flultti. hip+ slisi-fttisi~r ill.' cs t•s Is laiahll fi ilir•siir.
far.e stfl~ sie•litls ,plieat. Csispl ish g l is l•piuiiaitls~ as lip l iss|IIi~~~ftsse
;-sisi p fll li p aa;•t~lsulis isi-ti f lips rarp hlir_ •1 i•tilslit. h,-s is ssiallpix isl~ t"safttt i'dissls•IstFll', . 11451).
Ffl0. 12-28 fltusllalels lass
Ff0. 12-29 St nliiadhstu'salisrarusserslera tassr f,1-sFf0. 12-27 NI~.-ga-alW0.1u ai,ase las:eistr
,TfpsssuarilpSaasrslC5-arts~Aite5sisrjL Isis, fsstsuse Npiia-tiisraflfi.rsti.pairriiilaitiititiairlfrrtrlit usstlu-ilisratiaastrseerleulgics t5s-Suulsl)s's-iitiii
Csupssitsi itt i h)-'1si-eC trrts-tfill (rrfpaisk•. 4j-,. \1lishrra-ser. i..ae1Ibis jrrtafsiul i s• itthjts is flu fherrs a•t f ifs license agADriesss lii. t liak t h ii- {ietist
No. TXUT-001-PR-017PROJECT REPORT REV. I
ENE RCON forExcd1mce-Every rjertL - the Evaluation of Lake Attachment B
Granbury Water Temperature Page 1 of IDue to the Operation of CPNPP
__ Units 3 and 4
BIN INFORMATION(Reference 1)
D.,B.n 8Bin 9
Bin 10
Bin 22Bin 13
I..Bin aBin 9Bin 10Sin 11Bsin 12Bin 13
Feb
Bin 9Bin 9
Bin 10Bin 11Bin 12Bin 13
IntawB floww.t b.l diob.rs. t.rnp di0h-n flow pa Unit •tr •ntu.
('F) P., paU&. UP.) (zpn. flowtap.)77 11956 27095 32019.206
52 12 196540 25945 32019.3,65'46 71 10117 24593 32039.3W545 69 9539 23203 32019.396S
34 65 193S 21&77 32019389637 64 6749 21309 32019.165
U394dibaJ'rp.
flaw
UP.)27312212102023429D781797217492
22312232103023419078
1797217490
s9S2
4640
3432
52'
464D3432
777s71686564
7779
71686564
111561064910117
9539
1749
1064020117?3931
.89S6
8749
2709525945
34591232032117"1
21306
07035
2514524591
732332187721393
28324X999
293240999
28324299929324.999283242799
711.933471ef63334
713,93334.719,83134,
7128.333471&&3334
US i4dix~harp:
- flowjlbr/dav)
2.6SE-032.56E--02.431-0t2.29E-09
2.161-01
2.10E-03
2.391•9E2.56E.-0
2.29E-052.16E-05
2.GBE -082.56E-'08
2.43E 1 32. 29E-092. 16E-032.10E-08
flow total Inako(lpm) flow (UPw)
S45170 ulzs1 .lu •
51690 93709.3284449182 89203.3964646406 7042-S-3B9643754 75779.36&4642616 74625.•3646
54379 924942998951690 90014.8991949162 77505.993946406 74730529943754 72076.8996942636 70940.59999
54170 54692.93334.51690 5240321339.
49182 49990.933446490 47124.a3334437W4 44472.8333442616 43234.83334
3o3.3
3,31ko
1.0-E-09
93.01-099.752-09
9.426-36
9.96E-03
9.31E-99
9.97E.,098.66E-031.,529-09
6.59E1.99
5.995-035.34E-OB
,5.20E-01
2231221280
20234
19078
1797211499
No. TXUT-OO1-PR-017PROJECT REPORT REV. 1ENERCON for
Er•-M-w-veryp .Everyify the Evaluation of Lake Attachment CGranbury Water Temperature Page 1 of 37
Due to the Operation of CPNPPUnits3 and 4
WET BULB CONDITIONS
year month2001 12
2001 12
2001 12
2001 12
2001 12
20Ol 122001 12
2001 122001 12
2001 122001 12
2001 12
2001 122001 12
2001 12
2001 12
2001 12
20o0 122001 12
2001 12
,2001 12
2001 12
2001 12
20D1 122001 12
2001 12
2001 122001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 122001 12
2001 12
day11
11
11
11
11
11
11
11
12
11
11
11
11
11
11
1111
11
'11
*11
11
11
1v
1212
12
1212
12
12
1212
12
12
12
12
12
12
121212
hour
2
34567
89
11
12
13
14
15
16-17
18
19
20
21
22
23
241
2
34567
8
9
1011
1213
14
15
16171819
Total Average,Daily wb Daily wb
db (`F) wb (,F) (TFD) (*F) (AFD) (F)
48.02 39.7414766
46.04 39.0879985
44.96 38.5084443
42.98 37.4319376
41 36.3370491
39.92 36.0979503
41 36.6996181
39.02: 35.592298737.94 34.9803588
39.02 35.5922987
37.94 34.980358839.92. 36.0979503
41 37.151072
41 37.151072
42.98 38.98391.33
42.08 40.151558542.08 41.0474107
42.98 42.0162294
44.96 43.963390444.96 44.5008883
46.04 45.4805862
46.94 46.4661008
48.02 47.4429532
46 .94 46194. 952.4429 39.68512
46.94 46.4661008
46.94 46.94
48.02 47.442953248.02 47.4429532
48.02 48.02
48.92 48.9248.92 4892
50 50
50 50
50 50
51.08 51.08
51.98 51.4693368
51.98 51.9851.98 51.98
53.06 53.06
53.96 53.96
55.94 55.9457.92 56.188185
57.92 54.4579185
No. TXUT-001-PR-017NPROJECT REPORT
.,A ENERCO N for REV. 1I_'Ex ce it•n c--t'e,;y 4 ect Ei- d• the Evaluation of Lake A ttachm ent C
Granbury Water Temperature Page 2 of 37Due to the Operation of CPNPP
Units 3 and 4
WET BULB CONDITIONS
year month2001 122001 122001 122001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001. 12
2001 12
2001 12
-2001 12
2001 12
2001 12
'2001 12
2001 12
2001 12
2001 122001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 122001 12
2001 12
2001 12
2001 122001 12
2001 12
2001 12
2001 12
2001 '12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 122001 12
2001 12
day12
12
1212
12
13
13
13
13
13
13
13
13
13
13
13
13
13
1313
13
13
13
1313
13
13
13
13
14
1414
14
14
14
14
14
14
14
14
14
1414
hour20
2122
23
241
23
4
5
67
8
9'10
11
12
13
1415
16'
17
18
19
20
21
,22
23'241
2
3
4
5
6
78
9
10
11
1213
14
Total Average
Daily wb Daily wb
db ('F) wb (*F) (TFD) (*F) (AFD) (*F)
60.98 53.6669405
62.96 53.9675641
62.96 53.967564162.96 53.06314
55.94 50.0427753 1228.975 51.20731
55.04 44.4377008
53.06 42.7278978
51.08 42055574248.02. 40.9029544
46I94 40.3402492
44.96 39.6928797
39.92 37.3255343
39.02 36.4702663
39.02 36.470266339.02 37.2730675
37:94 36.676902
37.94 37.0607235
39.92 38.1430127
39.92 38.143012739.92 377656923
39.92 37.7656923
39.92 38.6086088
39.92 39.0074214
39.92 39.0074214
42.98 40.6221217
44.06 41.1820768
44.06 '40.3478349
'42.98 39.780131
42.08 39.7600737 941.5671 39.23196
39.02' 37.273067537.94 36.2291524
35.96 34.7452334
33.98 33.167405733.08 32.1557166
35.06 34.2292343
32 31.537664
30.92 30.5169255
28,94 28.1082289
30.02 29.5475892
30.92 30.5169255
28.04 27.589602128.94 28.5552937
28.94 28.5552937
No. TXUT-001-PR-017
PROJECT REPORT REV. IE E CO N for RVL1c-E.-&rCp jLE•,ydcy the Evaluation of Lake Attachment C
Granbury Water Temperature Page 3 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month2001 12
2001 12
2001 122001 12
:2001 12
2001 12
2001 12
2001 12
2001, 122001 12
2001 122001 12
2001 12
2001 122001 12
2001 122001r 12
2001, 122001 12
2001 12
2001. 12
2001 122001 12
.2001, 122001 12
2001 12
2001 12
2001 12
2001t 12
2001 122001 12
2001. 122001 122001 12
2001 122001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 12
day14
14
1414
14
14
14
14
14
14
1515
1515
1515
15
15
15
15
15
15
15
15
15
1515
15
15
15
15
15
15.16
16
1616
16
16
16
16
16
16
hour15
16
17
18
19
20
21
22
23
241
2
3
45
67
89
10
11
12
1314
15
16
17
18
19202122230
2
3
4
5
6
78
9
Total Average
Daily wb Daily wbdb (*F) wb ('F) (TFD) (*F) (AFD) ('F)
33.08 33.08
37.04 36.1758824
46.94 42.650512151.98 44.7762103
57.92 46.85683687
60.98 45.9447598
60.98 45.6154206
60.98 46.2293946
57192 45.828531751.98 42.922648 872:8191 36,36745
51.08 42.469554648.92 41.752454
46.94 40.7313288
46.04 41,017196444.06 40.7971704,
44.96 41.262848844.06: 40.7971704
42.98 40.233643542.98 40.6221217
4298 40.6221217
42.98 40.6221217
44.06 41.65568544.96 42.5189284
46.04 43.061595948.02 44.0437802
48.92 45.882020151.08 46.0018159
50 46.9097761
50 478914289
48.92 48.4314941
50 49.405552150 49.4055521
50 5050 50 1056.136 44.00568
50 "5051.08 50.4761694
51.08 51.08
51.08 51.08
51.98 51.98
53.06 52.4391857
51.98 51.9851.98 51.98
53.06 52.4391857
No. TXUT-001-PR-017N . .PROJECT REPORT REV________... . . ____
F'3 E N ERCON for _____
£ •a raf- c~. Evydi the Evaluation of Lake Attachment C
Granbury Water Temperature Page 4 of 37Pue to the Operation of CPNPP
___ ___ ___ ___ ___ _ . Units 3 and 4 .. ........ _ ,
WET BULB CONDITIONS
Total Average
Daily wb Daily wbyear month day hour. db (*F) wb (F) (TFD)(*F) (AFD) (°F)
2001 12 16 10 5395 53.96:2001 12- 168 11 55ý94 55,4015376
2001 12 16 12 55.04 54.4025064.2001 12 16 13 57.02 56.3661548
2001 12 16 14 57.02 57.02
2001 12 .16 15 57.02 5702
2001 12. 16 116 57.02 56.3661548
2001 12 16 17 55.04 54.40250642001 12. 16 18 55.04 54.4025064
2001 12. 16 19 55.04 54.4025064
2001 12 16 20 53.96 53.4353048
2001 12 16 21 55.04 53.8821935
2001 12 16 22 55.94' 54.2517349
2001 12. 16 23 55.04 53.2709261
2001 12 16 .24 53.96 53.4353048 1285.474 53.56141
2001 12 17 1 53.96 52.81885772001 12 17 2 53.06 51.9328714
2001 12, 17 3 51.98 50.2847T87
2001 12: 17 4. 50 49.4055521
2001 12 17 5 48.92 48.43149412001 12 17 6, 48.02 47.4429532
2001 12 17 7 46.94 45.9108555
2001 12 17 '8 46.04 45.0256022
2001 12 17 9 46.04 44.4929522
2001 12 17 101 46.04 43.5537733
2001 12 17 11 44.06 42.0629177.2001 12, .17 "' 12 42.08 39.7600737
2001 ,12 17 13 39.92 38.1430127
2001 12 17 14 39.92 37.7656923
2001 12 17 15 42.08 39.3030453.2001 12 17 16 46.04 41.8169971
2001 12 17 17 48.92 "42.83913212001- 12 17 18 51.98 44.3560997
2001 12 17 19, 53.96 45.3171226
2001- 12 17 20 55.94 45.2382354
200'1 12 17 21 57.92 46.490547
2001 12 17 22 59 45.6946745
2001 12 17 23 57.92 4V.490847
2001 12 17 24 51.98 44.0157068 1079.594 44.98307
2001 12 I8 1 48,02 42.0334664
2001 12 .18 2 44.96 40.8169591
2001 12 18 3 44.06 39.9837116
2001 12 18 4 42,98 39.780131
No. TXUT-001-PR-017PROJECT REPORT REV.,
for _ _ _ _ _
-.xce:eme- -Eve-• "the Evaluation of Lake Attachment CGranbury Water Temperature Page 5 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year monthf day
2001 12 182001 12 18
2001 12 -182001 12 18
2001 12 18
2001 122 182001 12 18
2001 12 18
2001 12 18
2001 12 18
2001 12 18
2001 12 18
2001 12 18
2001 12 18
2001- 12 18
2001 12 182001, 12 18
2001 12 18
2001 12 182001 12 182001 12 19
2001 12 19
2001 12 19
2001 12 192001 12 19
2001 12 19
2001 12 19
2001 12 192001 12 19
2001 12 19
2001 12 19.2001 12 19'
2001 12 192001 12 19
2001 12 192001 12 19
2001 12 192001 12 19
2001 12 192001 12 19
2001 12 19
2001 12 19
2001 12 19
Total Average
Daily wb Dally wbhour db (*F) wb ('F) (TFD) (-F) (AFD) ('F)
5 41 38,72569716 39.92 37.7656923
7 37.04 35.72453628 39.92 37.7656923
9 3902 37.273067510 37.04 361758824
11 35.06 34.600961412 33.08 32.1557166
13 35.06 34.2292343
14 35.96 35:114077215 39.92 37.7656923
16 44.96 41L6448092
17 53.96 46.0843237
18 62.06 49.805777919 64.94 50.0639635'
20 68 51.699139821: 68 51.0529316
22 66.92 51.233675
23 64.94 50.747277324 59 48.4288836 1000.671 41.69464
1 57.02 47.9450865'
2 53.06 46.09515493 50 44.6234648
4 53.96 44.59.191375 51.08 43.5709862
6 48.92 41.3679468
7 ,48.92 4i.36794688 46.04 39.86736249 44.06 38.8141593
10 44.06 38.374482
11 42.08 37,2957552,12 39.92 36.5536425'
13 39.02 36.0515549
14 39.02 36:4702663
15 41 37.5626765
16 44.06 38.8141593
17 46.94 39.911338118 48.92 40.6076231
19 51.08 41.3381199
20 53.06 41.6928003
21 53.96 41.5465468
22 53.96 41.5465468
23 51.98 40.8517116
No. TXUT-001-PR-017E- N ERNPROJECT REPORT R IENERCo N for REV._1
Exce*,c-Ewy project &-•-r day the Evaluation of Lake Attachment CGranbury Water Temperature Page 6 of 37
Due to the Operation of CPNPPI Units 3 and 4 .
WET BULB CONDITIONS
year month2001 12
2001 122001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001. 12
2001 12
2001 12
2001 12
2001 122001 122001 12
2001 122001 12
2001 12
2001 12
200.1 122001 12
2001 122001 12
2001 122001 12
2001 122001 12
2001 12
2001 12
2001 122001 12
2001 12
2001 122001 12
2001 12
2001 12
2001 12
2001 122001 122001 - 12
2001 12
2001 12
2001 12
day
19
20
20
20
20
20
20
20
20
20
20
20
20
2020
2020
20
20
20
20
2020
2620
2121
21
21
21
21
21
2121
2121
21.
212121
21
21
21,
Total AverageDaily wb Daily wb
hour db ('F) wb (*F) (TFD) (*F) (AFD) (*F)
24 48.02 38.418&535 975.2801 40.636671 44.06 36.9029639
2 44.95 35.4529446,
3 39.02 34.0551124 37.94 33.106302
5 35.98 32.26519796 35M9 32.6734665
7 33.08 31.00915758 3092 29.2321615
9 30.92 29.2321615
10 30.92 29.6701719
11 28.94 28.1082289
12 28.94 27.748459713 32 30.7332181
14 33.08 31.7802191
15 35.96 33.843897116 42.98 37.7883489
17 50 41.5034574
18 55.94 44.4786645
19 60.08 46.1581191
20 64.04 48.0062904
21 64.94 48.713911822 64.94 .48.4179672
23 62.96 47.159910124 53.96 43.5034506 882.5536 36.773071 51.98 42.5118279
2 50 41.5034574
3 48,02 40.478000M4 44.96 38.8588129
5 42.08 37.29575526 41 37.9157949
7 39.02 35.4702663
8 39.92 36.9691073
9 39.02 36.051554910 35.96 34.315285211 35.06 31.430612.
12 35.06 33.3206472
13 35.06 33.3206472'14 35.06 ,33.3206472
15 39.92 36.0979503.
16 45.04 39.435120317 51.08 .42.0555742
18 57.02 .45.0038044
0
No. TXUT-001 -PR-01 7PROJECT REPORT REV. IfEN E RCO N for REV._ _
Eelnce-vey poject Elevy d the Evaluation of Lake Attachment CGranbury Water Temperature Page 7 of 37
Due to the Operation of CPNPPUnits 3 and4 4
WET BULB CONDITIONS
year month day
2001 12 21
2001 12 21
2001 12 21
2001 12 21
2001 12 21
2001 12 21
2001 12 222001 12 22
2001 12 22
2001 12 22
2001 12 22
2001 12 22
2001 12 222001 12 222001 12 22
2001 12 222001 12 22
2001 12 222001 12 22
2001 12 222001 12 22
2001 12 22
2001 12 22
2001 12 22
2001 12 22
2001 12 22
2001 12 22
2001 12 22
2001 12 22
2001 12 22
2001 12 23
2001 12 23
2001 12 23
2001 12 232001 12 232001 .12 23
2001 12 23
2001 12 23
2001 12 232001 12 23
2001 12 232001 12 23
2001 12 23
hour
19
20
21
2223
241
2
3
4
6
7
89
10
11
12
13
1415'
.161718
19
2021
22
23
241
234
5g
78
910
11
12
13
Total Average
Daily wb Daily wb
db (*F) wb (F), (TFD) (°F) (AFD) ('F)
57.92 45.4378081
62.06 "47.3928424
62.96 47.8082338
62.96 47.508233860.08 46.158119157.02 44.6877056 955.0478 39.79366
57.92 45.124092157.02 44.6877056.5594 44.4786645
55.94 43.7902509
55.94 44.1596747
57.02 54.089844
59 54.896227,
60.08 55.918842760.98 55.6903573.
60.98 56.2742914
59 54.896227
55.94 53.1497494
53.96 51.7259831
50 48.921318357,02 51.4665351
59 48.847695460.98 46.2293946.
62.06 46.456763762.96 46.5559981
62.96 46.555998162196 47.1599101
62.06 47.0897798
59 45.9543244
53.06 43.0547675 1177.174 49.04893
50 41.5034574
46.94 39.5668955
42.98 37.431937642.98 .37.4319376
41 35.337049137.94 34.1767887
37.04 33.3067446
37,04 33.306744633.98 31.523659533.08 31.0091575
32 30.3855404
30.02 28.7241711
32 29.9827441
No. TXUT-01-PR-017PROJECT REPORT REV. I
for _ _V.arqje--F ,-,O f. Evy d the Evaluation of Lake Attachment C
Granbury Water Temperature Page 8 of 37Due to the Operation of CPNPP
Units 3_and 4
WET BULB CONDITIONS
year month2001 12
2001 12
2001 122001 12
2001 12
2001 12
2001 122001 12
2001 12
2001 12
2001 122001 12
2001 12
2001 122001 12
2001 122001 12
2001 12
2001 12
2001 122001 12
2001 122001 12
2001 122001 12
2001 122001 12
2001 122001 12
2001 12
2001 12
2001 12
2001 122001 12
2001 122001 12
2001 122001 122001 12
2001 12
2001 122001 12
2001 12
day
23
23
2323
23
23
23
2323
23
23
24
24
.24
24
2424
24
24
24
24
2424
2424
2424
24
24
24
24
242424
24
25
2525
25
2525
25
25
hour
14
15
1i
17
18
1920
2122
23
241
23
4
56
7
89
10
1112
1314
1516
17
18
19
20
2122
23
241*2
3
4
56
78,
Total Average
Daily wb Daily wbdb VF) wb (*F) (TFD) (*F) (AFD) (tF)
30.92 28.8796746
35.96 326734665
44.96 35.2865118
48.02 36.513957
48.92 37.77323
50 38.5993244
51.08 39.178284451.98 39.6556795
51.98 39.4212432
50 37.8619766
44.06 35.0652481 845.5964 35.23318
41 322657756
37.94 30.2567769
35.06 28.811729435.96 28.4293846
30.92 25.408276530.92 25.6404659
28.94 24:2057178
28.04 24.4474545
28,04 24.447454528.04 24.4474545
26.96 24.393005528,04 26.0764562
26.96 25.050692428.94 26.6090371
33.08 29.6217205
35.06 30.7753174,
39.92 33.5951162
44.96 33.5147944
44.96 ,32.8272013
46.94 34.30594548.02 35.4425781
46.94 35.264595344.06 35.3174227
41 33.5603533 704.7147 29.3631137.94 31.7700379
37.94 31.770037937.94 32.0883523
37.94 32.434176
37.04 31.9060192
37.04 30.70839235.96 30.0811171
35.96 29.842503
No. TXUT-001-PR-017PROJECT REPORT REV. fE E C N-for RV
c.-r--Evry plojcL Eday. the Evaluation of Lake Attachment C
GranburY Water Temperature Page 9 of 37
Due to the Operation of CPNPPUnits 3 and_4 4 .
WET BULB CONDITIONS
year month
2001 122001 12
2001 12
2001 122001 1226(11 122001 12
2001 122001 12
2001 12
2001 12
2001 122001 12
2001 12
2001 122001 12
2001 122001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 122001 12
2061. 122001 12
2001 12
2001 122001 12
2001 122001 12
2001 12
.2001 12
201 12
2001 12
2001 12200.1 12
2001 12
2001 12
2001 12
day
2525
2525
25
25
25
25
25
25
2525
2525
262526
26
26
26
26
26
26
26
26
26
26.
26
26
2626
26
26
26
26
26
26
26
2626
27
272V
Total AverageDally wb Dally wb
hour db ('F) wb (ýF) (TFD) ('F) (AFD) (°F)
9 33.08 '28.94643810 32 27.7217069
11 28.94 25.59211112 28.04 25.0501052
13 2894 25.592111
14 28.04 25.3988146
15 32 28.982702
16 37.04 31.9050192
17 .42.98 33.1796043
18 46.94 34.6583104
19 48.92 36.378446720 53,06 39.9926623
21 53.96 41.871151822 55.04 42.0984035
23 53.96 41.5465468
24 48.92 39.535144 779.0509 32A46045
1 44.96 37.7763238
2 4208 36.1859654
3 44.96 37.3987
-4 . 42.08 34.50575415 37.94' 31.5175384
6 35.96 30.6364232
7 33.08 28.6810505
8 33.08 28.1287924
9 .28.94 25.314967510 30.02 25.9617827
11 26.96 24.1.102047
12 28.04 24.770400213 26.96 2421102047
14 28.04 25.050105215 33.08 28.946438
16 37.04 30,70839217 39.92 32.3660107
18 44.06 35.065.248119 46.94 36.683594
20 48,92 38.0149832
21 50 38.593324422 51.08 39.11782844
23 50 38.599324424 46.04 36.4300234 768.7398 32.03083
1 42.98 34.7025368
2 41 33.563533
3 37.04 31.5751879
No. TXUT-001-PR-017PROJECT REPORT REV.I
E N E R CI0 Nfor REV'_Ex e-Eorý.7-ct Every day,• the Evaluation of Lake Attachment C
Granbury Water Temperature Page 10 of 37Due to the Operation of CPNPP
Units 3 and 4
r
WET BULB CONDITIONS
year month day
2001; 12 272001 12 27
2001 12 27
2001 12 272001 12 27
2001 12 27
2001 12 272001 12 27
2001 12 272001 12 27
2001 12 27
2001 12 27
2001 12 272001 12 272001 12 27
2001 12 272001 12 27
2001 12 272001 12 27
2001 12 27
2001 12 27
2001 12 28
2001 12 28
2001 12 282001 12 28'
2001 12 282001 12 28
2001 12 282001 12 28
2001 12 28
2001 12 282001 12. 28
2001 .12 282001 12, 282001 12 28
2001 12 28
2001 12 28:
2001 12 28t
2001 12 28
2001 12 28
2001 12 28
2001 12 28
2001 12 28
hour
4
5
67
8910
11
12
13
14
15
161718
192021.
22
23
241
2
34
5
67
8
91011
12
1314
15
1617
18
19
20
21
22
Total AverageDaily wb Daily wb
db.(F) wb (F) (TFD) (°F) (AFD) ('F)
33.08 29.6217205
33.08 29§8217205
32 28.98270230.92 27.763282
28.94 26.6090371
2894 26.6090371
28.04 26.0764562
28.94 26.6090371
30.02 27.241580430.92 27.763282
26.06 24.503549837.94 33.4287123
42.08 36.185965448.02 39.741476651.98 42.181939
55.04 43.7159724
57.02 45.003804457.92 45.4378081
59 45.643436
55.04 44.037398
.51.98 42.5118279 819.1278 34.13033
51.98 42.5118279
50 41.5034574
48.02 40.4780006',48.02 40.9029544
46.94 40.3402492
46.04 41.017196444.96 39.2950925
42.08 36.9365592
39.02 35.223458737.04 34.0908548
35.96 33.4649485
35.06 32.938935533.98 31.8643811
32 30.7332181
37.04 34'0908548
41 36.3370491
46.04 39.4351203
51.08 '417231425
S55.94 44.478664559 45.643438
59 45.643438
60.08 46.8499547
No. TXUT-001-PR-017PROJECT REPORT REV. 1F E NER C O N ' ... for ", .
the Evaluation of Lake Attachment C
Granbury Water Temperature Page II of 37Due to the Operation of CPNPP
_ _ __ Units 3 and 4 _
WET BULB CONDITIONS
Total Average
Dally wb Daily wbyear month day hour db (F) wb (-F) (TFD) (-F) (AFD) (F)
2001 12. 28 23 59 45.643435,2001. 12 28 24 55.04 44.037398 945:1836 39.38265
2001, 12: 29 1 53.05 43.05476752001 12 29 2 51.08 42-055742
2001 12 29 3 44.96 38-85881292001' 12 29 4 44.06 38:8141593
2001 12 29 5 42.98 3823214322001 12 29 6 4208- 38.1507967
2001 12 29 7 37.04 34.933275
2001 12 29 8 35.06 32.9389355'
2001 12 29 9 42.98, 37:78834892001 12 29 10 A4298 35.0200334
2001 12 29 11 41 33.56035332001 12 29 12 39.02 32.7272529
2001 12 29 13 35.08 29.8535056
2001 12 29 14 32 28.29993782001 12 29 15 32 28.0316134
2001 12 29 16 3506 29.8535056
2001 12 29 1? 35.06 29.55312642001 12 -29 18 37.04 30.47240552001' 12 29 19 37.94 30.7222412
-2001 12 29 20 39.92 31.85439232001 12 29 21 39.92 3,1.3983027
2001 12 29 22 39.92 312027641
'2001 12 29 23 39.02, 30.88227141
2001 12 29 24 37.94 30.5060675 808.7646 33.69,8522001 12 30` 1 35.98 29.346517
2001 12 30 2 .35.96 28,88846932001 12 30 3 35.08 28.8117294
2001 12 30 4 3398 2838866V72001 12 30 5 ,33.98 28,3886667
.2001 12 30 6 32 27,16652172001 12 30 7 30.92' 26.18171672001 12. 30 8 30.02 25.3916862
2001 12 30 9 28.04 24.44745452001 12 . 130 10 ;28,04 24.1886321
2001 12 30 11 28,04 24A44745452001 12 30 12 28.94 24.7385164
2001 12 30 13 2894 24.9949752
2001 12 30 14 30.02 .25.09904432001 12 30 15 3092 25,9304035
2001 12 30 16 32 26.6919566
2001 12 30 17 "33.98 27,9039548
No. TXUT-001-PR-017E~ N E R C 0 N PROJECToREPORT REV. f
Excelife--'Very q,ý-CL Ev. the Evaluation of Lake Attachment CGranbury Water Temperature Page 12 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month
2001 12
2001 122001 12
2001 12
2001 122001 122001 12
2001 12
2001 122001 12
2001 122001 12
2001 12
2001 12
2001 12
2001 12
2001 12
2001 122001 12
2001 12
2001 12
2001 12
2001 12
2001 122001 12
2001 122001 12
2001 12
2001 12
2001 12
2001 12
2002 12002 12002 1
2002 12002 1
2002 1
2002 .1
2002 12002 1
2002 12002 1
2002 1
day
30
30
3030
30
30
30
31
3131
3131
31
31.
31
31
31
3131
31
3131
31
3131
31
31
31
31
31.31
.1
1~
hour
1819
2021
22
23241
23
4
5
67
8
910
12
13
14
15
16
1718
19
20
21
22
23
24.1
23
4'5.
67
89-10
11
12
Total Average
Daily wb Daily wbdb (F) -b (*F) (TFD) (^F) (AFD) ('F)
35.96 29.346517
39,02 31.342M004
37.94 30.722241237.04 30.2000579
3596 29,34651735.96 29.346517
33.98 27.9039548 659.2348 27.46811
33.08 27.1463074
33.08 27.356020732 26.6919566
30.92 27.1054066
30.02 27.2415804
28.94 26.6090371
28.94 26.2366133
28.94 26.6090371
28.04 26.0764562
28.04 26.0764562.
28.04 26.076456228.04 25.7005764
28.04 25703576428.04 25.3988146
28094 .25.937622630.02 26.2358753
30.92 26.1817167-32 27.1865217
35.06 29.034376437.04 29.9818787
37.94 30.5060675
37.04 29.9816787'
35.96 29.0921158T
33.98 27.6961517 651.8595 27.16081
33.08 27.146307430.92 26.7668511
32 26.9568284
30.92 27.398371532 28982702
32 28.299937833.08 28.6810505
33.08 26.374533232 27.4732511
32 27.186521730.92 26.4952811
30.92 26.7668511
No. TXUT-001-PR-017PROJECT REPORT
ENERCON for REV. 1Er-nder, e- -,eEvery ,.;y. the Evaluation of Lake Attachment C
Granbury Water Temperature Page 13 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month day
2002 1
2002 1 1
2002 1 12002 1 t
2002 1 I2002 1
2002 1 1
2002 12002 1 I
2002 1 1
2002 1 1
2002 1 1
2002 1 2
2002 1 2
2002 1 2
2002 1 2
2002 1 2
2002 1 2
2002 1 22002 1 2
2002 1 .2
2002 1 22002 1, 2
2002 1, 22002 1 2
2002 1. *22002 1 22002 1 2
2002 1 2
2002 1 22002 1 2
2002 1 2
2002 1 2
2002 1, 2
2002 1 22002 1 22002 1 3
2002 1 32002 1V 32002 1 32002 1 3
2002 1 3
2002 1 3
hour13141516i7181920212223.241
23
45
67
8910-111213141516171819202f2223241
23
45
6
7
Total Average
Daily wb Daily wb
db (F) wb (F) (TFD) (T) (AFD) (*F)
30.92 26.7668511
32 27.473251132 27.4732511
33.98 28.388666737.04 29.9818787
356.96 29.346517
37.94 30.606067539.02 31.342600442.08 33,395894
39.92 31.6425728
39.02 31.3426004
35.96 28.8884693 687.0771 28.62821
35.06 .28.554976735.06 29,0343764
33,98 28.6696764
33.98 28.6696764
32 2737217069
30.92 26.1817167
28.04 24.770400228.94 25.3149675
28,94 24.9949752
28.04 ,24.1886321
26.06 22.9608294
26.06 22.960829424.98 22.547531
28.04 24.4474545
28.94 24.9949752
33.08 28.1287924
33.98 29.8075717
35.06 31.744530933.98 31.1289432.
30.92 30.0479526
30.92 28.8796746
30,02 .2&5775788
30.02 25.961782726.06 23.2249019 641.5145 26.72977
26.06 23.5544096
23 21.2862036
24.08 21.9773366
21.92 20.312266721.02 19.4014463
19.94 18,4232554
19.04 17.5146339
No. TXUT-001 -PR-01 7NPROJECT REPORT R-J EN ER C O N for REV. IE-ecl-n-Erypqi Ev-e y the Evaluation of Lake Attachment C
Granbury Water Temperature Page 14 of 37Due to the Operation of CPNPP
Units 3 and 4
WET BULB CONDITIONS
year month day
2002 1 32002 1 3
2002 1 32002 1 3
2002 1 3
2002 1 3
2002 1 3
2002 1 3
,2002 1 32002 1 3
2002 1 32002 1 3
2002 1 3
2002 1 32002 1 3
2002 1 3
.2002 1 3
2002 1 4
2002 1 4
2002 1 42002 1 4
2002 1 42002 1 42002 1 42002 1 4
2002 1 42002 1 4
2002 1 4
2002 1 42002 1 4
2002 1 4
2002 1 42002 1 42002 1 4
202 1 42002 1 4
2002 1 4
2002 1 4
20O2 1 42002 1 4
2002 1 42002 1 5
200 1 5
hour
89
101112
13
1415
16
171819
20
2122
23
241
2
3
456
78
910
111213
14
1516
171519
2021
2223
24
12
Total Average
Daily Wb Daily wbdb (,F) wb ('F) (TFD) (*F) (AFD) ("F)
15.98 14.8570564
19.04 17.5146339
15,98 15.104271
15.98 i5,104271
17.05 16.1540151
17.96 17.0801431
17.96 17.3443205
21.02 19,9994572
26.06 23.839807530.02 25.9617827
33.08 27.84519353598 29842503
39.02 31,609466441 33.002490641 33.0024906
39.92 32.3560107
35.96 30.3787402 543.4862 22.64526
33.08 28.3745332
30.92 26.76851.130.92 26.7M66811
30.02* 26.2358753
28.94 26.230613326s96 24.3930.055
26s96 24.393005526.96 24.393005526.96 24.393005
26.96 24.3930055
26.06 24.195626126.06 24.096626126.96 24.7455804
28.94 26,2366133
32 28.634354
37.94 32.43417642.08, 34.8393668
42.98 35.6375194
44.96 37T3987
48.02 39.423690950 41.1679421
50 41.5034574
50 41.921270548.92 40.946257 729.6259 30.40108
46.94 39.9113381
46.04 39.4351203
No. TXUT-O01 -PR-01 7PROJECT, REPORT REV.IF, E N, E R C 0 N for R __.__
c e-•Evrcf Every• dry, the Evaluation of Lake Attachment CGranbury Water Temperature Page 15 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month day
2002 1 5
2002 1 5
2002 1 52002 1 5
2002 1 5
2002 1 5
202 1 52002 1 5
2002 1 52002 1 5
;002 1 52002 1 52002 1 52002 1 52002 1 52002 12002 1 5
2002 1 52002 1 5
2002 1 52002 1 52002 1 5
2002 1 62002 1 62002 1 6
2002 1 62002 1 6
2002 1 62002 1 6
2002 1 62002 1 6
2002 1 62002 1 62002 1 6
2002 1 62002 1 6
2002 1 62002 1 6
2002 1 62002 1 6
'20.2 1 62002 1 62002 I 6
hour
3
4
6678
910
11
12
1314
15
16
1718
19
2021
2223
24
2
3
4
5
6
7
89
101112
13
14
1516
17
18
19
20
21
Total Average
Daily wb Daily wbdb ('F) wb (=F) (TFD) (-F) (AFD) ('F)
44,06 38.374482
42.98 37.7883489
42.98 38.232143242.98 42.0162294,
42,98 42.016229442.08' "42.08
42.98 42.535828242.98 42.5358282
44.06 43.5184182
44.06 43,5184182
44.06 43.518418244.06 43.5184182
44.06 43.5184182
44.96 44.500888346.04 45.0256022
44.96 43.5265842
44.06 42.5634196
46.04 42.6621362
46.94 42.6505121
46.04 42.662136248.02 43.65095144.96 41.6448092 101L405 42.14186
42.08 39.7600737
42.98 39.780131'41 37.9157949
39.92 36.553642537.04 34.933275
37.04 34.4660767
'3596 33.843697137.04 34.090854835.96 33.4649485
35.06 32.496777233.98 31.523659533.98 31.1289432
33.98 31.1289432
3398 31.1289432
3704 33656215
44.06 38.0213811
48.92 40.94625753.06 42.0449878
57-02 43.666850857.92 43.5455515
59 43.2647684
No. TXUT-001-PR-017PROJECT REPORT REV 1
for REV._ _Exrelenre--Ewy,,rajcm ftE"-ydy. the Evaluation of Lake Attachment C
Granbury Water Temperature Page 16 of 37Due to the Operation of CPNPP
Units 3 and 4
WET BULB CONDITIONS
year month day
2002 1 6
2002 1 62002 1 62002 '1 7
2002 1 72002 ,1 7
2002 1 7.2002 1 7
2002 ,1 7
2002 1 7
2002 1 7
2002 1 7
2002 1, 72002 1 72002 1 7
2002 1 72002 .1 7
2002 .1. 72A02 1 7
2002 1 7
2002 1. 7
2002 1 7
2002 .1 7
2002 1 72002 7,
2002 1 72002 1 7
2002 1 82002 1 8
2002 1 8
2002 1 82002 1 8
2002 1" 82002 1 8
2002 .1 82002 1 8
2002 1 8
2002 1 8
2002 1 8
2002 1 8
2002 1 8
2002 1 8
2002 1 8
Total AverageDaily wb Dally wb
hour db (*F) wb (*F) (TFD) ('F) (AFD) ('F)
22 57.02 42,0433633
23 55.04 41.542017
24 51.08 38.6671759 889.6343 37.06811 46.94 36.9295361
2 42.98 3502003343 42.08 34.83936M8
4 39.02 33.36634565 37.04 32.5773427
6 33.98 30.4441289
7 33.08 29.62172058 37.04 31.2575805
9 32 28.299937810 30.02 27.241580411 .28.94 26.609037112 28.04 26.0764562
13 28194 26.9967226
14 26.06 24.503549815 32 29.6588364
16 37.04 31.575187917 39.§2 33.2551846
18 44.06 35.6319531
19 46.94 36.9295361
20 50 38.5993244
21. 51.98 40.256539522 53.06 40.8202212
23 53.06 41.0827795
24 46.04 37.6880244 789.2809 32.88671'
1 44.00 36,5972264
2 44.06 36.2436745
3 42.98 35.6375194
4 42.08 35.48776655 39.92 34.2557918.6 35.98 31.94136237 33.98 31.1289432
8, 3398 30.8115306
9 35.06 31.744530910 35.06 31.7445309
11 35.06 32.141261112 35.06 32.1412611
13 33.98 31.5236595
14 35.06 32.1412611
15 39.92 35.3080503
16 46.94 39.5668955
No. TXUT-001-PR-017
PROJECT REPORT REV. 11.JENERCON for RV
the Evaluation of Lake Attachment CGranbury Water Temperature Page 17 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month
2002 12002 1
2002 1
2002 1
2002 t
2002 1
2002 1
2002 1
2002 12002 12002 12002 1
2002 1
2002 12002 1
2002 1
2002 1
2002 12002 1
2002 1
2002 1
2002 1
2002 1
2002 .1
2002 1
2002 1
2002 12002 12002 1
2002 1
?002 12002 12002 1
2002 12002 1
2002 12002 1
2002 1
2002 12002 1
day
88
88
88
8
r89
9
9
9
99
9
9
9
9
9
999
99
99
99
9
9
101010
•10
101010101010
10
Total Average
Daily wb Daily wbhour db (*F) 'wb ('F) (TFD) (*F) (AFD) ('F)
17 59 45.954324418 62.96 48.1837405
19 65.92 49.966955520 69.08 50.5592302
21 71.98 52,15524222 73.04 52.2674404
23 69.98 51.306124424 60.98 46.889294 935.6976 38.9874
1 59 46.341535
2 57.02 45.0038044
3 51.08 42.0555742
4 48.92 40,946257
5 46.94 . 39.91133816 44.08 40.3478349
7 44.06- 40.34783498 44.06 40.34783499 42.98 40.2336435'
10 42.08 38.9326777
11 39.92 37.325534312 41 37.9157949
13 42.08 38.9326777
14 42.08 38.932677715 48.02 42.8198886
i' 53.06 45.6552661
17 62.06 50.5640886
18 69.08 52.838850819 71.96 54.412591
20 77 55.14891
21 77 55.42690122 77 56.064533623 :73.94 54.841796624 69.08 -53.2250708 1088;573 45.3572
1 66.02 52.69005232 64.04 52.6598231
3 62.06 52.285914
4 59 50.4921234
5 57.92 50.911916 53.96 48.234593
7 57.02 49.61623568 53.96 48.234596
9 53.96 47.8293123
10 50 45.9756505
11 48.92 45.4594761
No. TXUT-001-PR-017PROJECT REPORT REV. IF E EN ER CON for REV._1
Ev-efknce-E.ery poje•t E "m.. the Evaluation of Lake Attachment CGranbury Water Temperature Page 18 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month
2002 12002 12002 12602 12002 12002 12002 1
202 1
2002 12002 12002 1
2002 12002 1
2002 12002 I2002 1
2002 12002 12002 I,2002 12002
2002 12002 12002 12002 .12002 I12002 1
2002 12002 12002 1
2002 12002 12002 12002 11
2002 12002 12002 12002 12002 12002 12002 1
day
1010
10
10
10
101010
1010
l010
10
11
11
11
11
11
1111
1111
1.1
I111
11,
11
11.
1111
11
11
111111
121
1212
12
12
12
hour'
12
1314
15
1517
1819
20
21
22
23
241
2
34
56
7
9
10
lii.12
i314
Is16
171819
2021
22
2324
23
4
5
6
Total Average
Daily wb DWilywbdb,(*F) wb ('F) (TFD) (*F) (AFD) (*F)
4892 45.4594761
53.06 46.9358181
51198 44*7762103
51.08 43.170941751.08 43.1709417
51.08 44.3372825
53.08 46.471743455.04 47,8546783
55.04 47.3981374
55.04 47.0276819
53.96 45.7303121
53.96 45.3171226
53.96. 44.5919137 1136,632 47.3596653.96 44.275813651.98 42.922648
48.92 41.367946848.92 41.752454
48.02 41.29D4323
46.94 40.7313288
46.04 40.2614742
44,98 39.692879744106 .39.2150399
42.08 37:7430134
41, 37T151072
37.94 34.9803588
35M96 33464948535:96 33.4649485
41: 36.6996181
48702 40.1367409
51.08 41.3381199
53.06 41.692800355.04 42.0984035
55.94 43.149627457.02 43.4133407
57.02 42-843287355.94 428735953
50 39.8149349 962.3748 40.0989548.02 38.760484
44.96 37.09533794Z08 .35.4877665
42.08 35.128086639.02 33.7357084
33.98 31.1289432
No. TXUT-001-PR-017PROJECT REPORT REV.
ENERC0Nfor RV.o- , Ev d-, the Evaluation of Lake AttachmentC
Granbury Water Temperature Page 19 of 37Due to the Operation of CPNPP
Units 3 and 4
WET BULB CONDITIONS
year month
?0M2 12002 1
2002 12002 1.
2002 12002 12002 12002 1
2002 12002
2002 12002
2N02 12002 12002 12002 12002 12002 12002 12002 12002 12002 12002 I
2002 412002 1200*22002 12002 1
2002 1
2002 1
2002 12002 1
2002 12002 1
202 12002 1
2002 12002 1
20022002 12002 12002 1
day
12
12
1212
12
12
12121212
1212
12
12
12
12
12
12
13
1313
13
13.1J3
13
:131313
13
13
13
131313
13.13
13
13
1313
13
1314
hour
7
a
910
11
12
1314
151617
18
19
20
21
22
23
241
23
4
567
691011
1213
14
15
16
1718
19
20
2122
23241
Total Average
Daily wb Dally wbdb ('F) wb (*F) (TFD) ('F) (AFD) (*F)
33.98 311289432
32 29.9827441
32 29.982744130.02 27.9562926
2894 27.7484597
26.96 25.4307516
30.92 29.2321615
33.98 31.523659539.92 351731974748.92 40.2154047
51.98 41.492704
55.04 43.0444691
57.02 43:0971011
57.92 43.545551559 43.5412922
57.92 43.0026728
57.02 42.268816150 38.5993244 858.8614 35.78589
48.02 37.5238826
46.04 36.739190146.04 36.4300234
35.96 31.5813421
37.04 32.2015818
32 28.982702
32 29.2839201
32 28.982702
33.98 30.811530633.08 29.9196344
30.02 27.9562926
32 29.2839201
30,92 28.1431382
.30.92 28.471389137.04 32.902278946.94 38.847181
57.92 44.760789464.04 47.0025466
66.92 48.70490969.08 49.675606871.95 50.6427276
71.96 50.4011198
69.98 50.075044264.04 47.0625466 896,446 37.35192
59 44.9940157
No. TXUT-001-PR-017r PROJECT REPORT REV. IflENERCON for
Excefl-m-EEypiqie E•,the Evaluation of Lake Attachment CGranbury Water Temperature Page 20 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month day
2002 1 14
2002 1 14
2002 1 142002 1 14
2002 1 14
2002 1 14
2002 1 142002 1 14
2002 I 14
2002 1 142002 1 14
2002 1 14
2002 1 14
2002 1 142002 1 14
2002 1 1412002 1 14
2002 1 142002 1 14
2002 1 142002 1 14
2002 1 14
2002 1 14
2002 1 152002 1 15
2002 1 152002 1 15
2002 1 152002 .1 152002 1 152002 1 15
2002 1 152002 1 15
2002 1 15
2002 1 152002 1 15
2002 1 15
2002 1 15
2002 1 15
2002 1 152002 1 15
2002 1 15
2002 1 15
hour
2
34
5
878
9
10
1112
13
14
151617
18
20
2122
23
241
2
3
5
67
8
91011
1213
14
1516
17
18
19
20
Total AverageDaily wb Daily wb
db (*F) wb ('F) (TFD) ('F) (AFD) ('F)
53.96 4zi518848
51.98 41.137245951.98 40.8517116
44.96 385084443
44.06 36.9029639
42.98 35.9944003
44.96 36.137574442.08 34.5057541
41 33.83138
39.02 32.727252941 33.8833606
39.92 32.9291325
39.02 32.398643
42.08 34.839366850 39.2095264
53.06 40.82022125504 41.8402636
57.92 42.2416885
57.92 41.7963625
60.08. 42.70294859 41.7645172
57.92 41.385419753.96 39.3117671 922.9182 38.45492
48.02 36.3059651
46.94 35.7001354
42.98 33.647373837.04 31.0027366
35.96 30.6364232
35.96 30.378740233.08 28.946438
33.98 29A798464
37.04 31.257580530.02 26.577578828.94 2652366133;
30.02 26.873270435.06 29.8535056
35.96 30.3787402
39.02 32.398643
46.04 36.739190151:98 39.9503478
55.94 42.2982727
59 44.0792138
60.98 45.0450826
No. TXUT-001-PR-017PROJECT REPORT REV.E7 EN ERCO for _EV._1
Exce•ie-EMpfý the Evaluation of Lake Attachment CGranbury Water Temperature Page 21 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month
2002 12002 1
2002 12002 12002 1
2002 A1
2002 12002 12002 1
2002 1
2002 1'2002 12 2 12002 12002 12002 12002 1
2002 12002
2002 1
2002 1
2002 12.002 12 002 12002 1ý2002 12002
2002
2602
2002 1:2002 12002 12002 1
2002 12002 1
2002 12002 12002 1
2002 1200,2 1
2002 1
2002 1
2002 1
day15
1515
15
1616
1616
16
16
16
16
161616
1616
16
16
1616
16
16
16
16
16
16
16
1717
17
1717
17
17.*
1717
17
17
17,17
17
17
Total AverageDailywb Dallywb
hour db (*F) wb (*F) (TFD)(*F) (AFD) ('F)21 62.06 45.856254622 62.96 46.2958306
23 62.95 46.555998124 5792 44.1308143 850.6366 35.443191 57.02 43.6868508
2 55.94 42.8735953
3 53.06 41.08277954 51.98 40.5215467
5 51.98 41M1372459
6 51.98 4251182797 51.08 42.46955468 '51.98 42.5118279
9 .51.08 42.055574210 51.08 42055574211 50 41.5034574
12 51.08 42.0555742
13 50 41.5034574
14 50 41.503457415 50 41.5034574
16 55.94 44.159674717 60,98 46.5835006
18 68 49.1924
19 69.98 49.7692977
20 7196 50.6427276
21 71.06 50.0040765
22 66.02 47.725894323 59 44.994015724 53.96 42.5013753 1054.549 43i93953
1 51.08 41.028581
2 46.94 37.236297
3 44.96 35.57528464 42.98 34.44798325 41 33.8833606
6 39.02 .33.3683456
7 37.04 32.20158188 35.96 31.5813421
9 35ý96 31.292087810 35.06 30.7753174
11 37.04 322015818
12 37.04 31.5751879
13 37.94 32.43417514 39.02 32.7272529
15 39.02 32:7272529
No. TXUT-001-PR-017PROJECT REPORT
for REV. I,ceften-F-i• f-,• ythe Evaluation of Lake Attachment C
Granbury Water Temperature Page 22 of 37Due to theOperation of CPNPP
Units 3 and 4
WET BULB CONDITIONS
year month day
2002 1 17
2002 1 17
2002 1 172002 1 17
2002 1 17
2002 1 17
2002 1 17
2002 1 17
2002 1 17
2002 18
2002 1 18
2002 1 182002 1 182002 1 18
2002 1 18
2002 1 18.2002 1 18
2002 1 182002 1 18
2002 1 18
2002 1 18.
2002 182002 1 18
.20o2 I 182002 1 18
2002 1 18
2002 1 18
2002 1 18
2002 1 18
2002 1 182002 1 18
2002 1 18
2002 1 18
2002 1 19
2002 1 192002 1 192002 1 19
2002 1 19
2002 1 192002 1 192002 1 19
2002 1 19
2002 1 19
Total Average
Daily wb Daily wbhour db (*F) wb ('F) (TFD) ('F) (AFD) (*F)
16 39.92 33.2551846
17 41 33.8833606
18 42.98 '3.351047519 44.96 36.7445348
20 44.96 35.4629446
21 46.04 37.3404895
22 46.04 37.340489523 46.94 38,177597
24 44.06 36.2436745 827.8531 34.493881 39.92 33.8893032
2 37.94 32.733462
3 37.94 32.4341764 35.06 .31.0672535
5 35.96 32.2651979'6 35.06 31.0672535
7 33.98 31.52365958 30.92 28.8796746
9 33.08 31.353014110 35.06 3Z938935511 35.96 33.8436971
12 35.06 33.3206472
13 35.96 33.843697114 35.96 34.3152852
15 37.04 35.3592226
16 37.94 . 36.67690217 39.02 37.6533279
18 * 39.02 37.6533279
19 39.92 39.0074214
20 41 39.5821156
21 39.92 39.499145722 39.92 39.499145723 39.92 39.4991457
24- 39.92 39.92 837.825 34.909381 39.92 39.92
2 39.92 39.92
3 41 40.48628544 39.92 39.92.
5 41 40.0693053
6 41 40.48628547 39.92 39.928 39,92 39.4991457
9 39.92 39.4991457
10 39.92 39.0074214
No. TXUT-001-PR-017PROJECT REPORT REV. If NERC 0or NEV.or
Eetlenc-'verypioaJ EvrL fdqt the Evaluation of Lake Attachment CGranbury Water Temperature Page 23 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month day hour
2002
2002
20022002
20022002
20022002
20022002
20022002
2002
2002
2002
20022002
20022002
20022002
2002
2002.
2ý002,
2002
2002
2002
2002
2002:
2002.
20022002
20022002
20022002
20022002
20022002
2002
2002
2002
19
191919
19
1919
191919
191919
1920
20
20
2020
2020
20
20
2020
2020
20
20
20
20
20
20,20
2020.
2020
2121
21
21
21
Total Average
Daily wb Daily wbdb (F) wb (-F) (TFD) (-F) (AFD) ('F)
39.92 39.007421439.02 38.1225475
35.96 35.114077235.06 33.7959241
37.04 35.359222639.02 36.4702663
42.08 37.295755244.96 37.7763238
48.02 39.055921550 38.8980588.
51.08 38.194805151.08 37.7588583
48.92 36.56871444.96 34.5747426 916.7202 38.19668
41 32.4868676
39.02 31.3426004.
33.98 28.6696764
35.96 29.84250333.98 -28.913172
28.94 25.59211133.08 28.6810505
33.08 28,3745332
33.08 28.681050533.08 28.946438
32 282999378.
32 28.63435433.98 29.8075717
33.98 30.4441289
39.02 33.735708444.06 36.9029639
46.94 37.832922753.06 .41.4098974
57,02 42.550046259 44.0792138
62.06 45.868254664.04 46.8047101
64.04 47.062546657.92 44.46874Q2 829.431 34.55963
53.96 43.179070150 41.1679421
51.98 41.1372459
51.08 37.758858346.94 35.2645953
4/
No. TXUT-001 -PR-017PROJECT REPORT REV. I
:lEN ER C ON for RVE XVf9c,-C. -. VY67- the Evaluation of Lake Attachment C
Granbury Water Temperature Page 24 of 37Due to the Operation of CPNPP
Units 3 and 4
WET BULB CONDITIONS
year month day2002 1 212002 1 21
2002 1 21
2002 1 21
2002 1 21
2002 .1 21
2002 1 21
2002 1 21
2002 1 212002 1 21
2002 1 212002 1 21
2002 1 21
2002 1 21,2002' 1 21.
20O2 1 2 12002. 1 21
2002. 1 21200Z 1 21
2002 1 222002 1 22
2002 1 222002 1 22
202. 1 222002 1 22
2002 I 22.2002 1, 22
2002 1 22
2002 1. 22.
2002 1 22,
2002 1 22
2002 1 22.
2002 1 222002 1 22
2002 1 22
2002 1 22
2002, 1 .222002 1 .22
2002 1 222002 1 22
2002 1 22
2002 1 22
2002 1 22
hour6789
10
1112
13
141516
17
18
1920
21
22
23241
2
345
6
78
9
1011
12
131415.16
17
18
19
202122
23
24
Total AverageDaily wb Daily wb
db (*F) wb ('F) (TFD) ('F), (AFD) ('F)
41 32.0109735
42.08 32.4489227
42.08 32.216352233.08 28:1287924
32 27.4732511
28.04 24.7704002.
28'94 25.3149675
28.04 24.4474545
26.96 23.783690335.06 29.5531264
44.06 34.7742062
53.06 39.9926623
60.98 42.9404938
64.04 44.664558566.92 .4,6835427
68 46.359550168 46.56"15351
66.02 45.620912160.08 42.4873113 867.7404 36.1S58S
53,96 39.736973151.98 39.4212432
53.06 40.516862748.02 38.1446324
48.02 38.144632448.02 38.1446324
46.94 37.832922744.96 37.3987
48.02 39.4236909
48.02 40.1367409
48.92 40.94625748:92 40:94625748.92 41.3679468
50 41.503457451.08 42.0555742
,57.02 45.3974884
60.08 46.4662142
66.92 49.5042166
71.96 51.6069363
71.6 55*73.4 55
73.04 623002932
73.04 62.3002932
69.08 60.4090535 1084.005 45.16688
No. TXUT-001-PR-017L PROJECT REPORTfor REV. 1
E.iLNE~R CON for _ _ _ _
Ex-/el•--EVJ~C• 7 ,ydz the Evaluation of Lake Attachment CGranbury Water Temperature Page 25 of 37
Due to the Operation of CPNPPUnits 3 and 4 . ......
WET BULB CONDITIONS
year month day
2002 1 232002 1 23
2002 1 23
2002 1 23
2002 1 23
2002 1. 23
2002 1 232002 1 23
2002 1 23
2002 1 232002 1 23
2002 1 23
2002 1 23
2002 .1 232002 1 23
2002 1 232002 1 23
2002 .1 232002 1 23
2002 1 23
2002 1 23
2002 1i 232002 1 23
2002 1 232002 1 24
2002 1 242002 1 24
2002 1 242002 1 24
2002 1 24
2002 1 24
2002 1 24
2002 1 24
2002 1 24
2002 1 24
2002 1 24
2002. 1 242002 1 24
2002 1 24
2002 1 24
2002' 1 242002 1 24
2002 1 24
Total Average
Dailywb Dallywbhour db ('F) wb (*F) (TFD) ('F) (AFD) (*F)
1 64.94 60.00405972 62.96 59.2743971
3 60.98 58.53399884 62.06 58.939198
5 60.98 58.5339988
6 60.08 57.55479417 59 56.612279
8 55.04 544025064
9 53.96 53.4353048
10 53.06 53.0611 53.06 53.06
12 55,94 "55.4015376
13 55.94 55.9414 57.02 57.02
15 60.08 60.0816 62.06 6208
17 64.04 63.3311073
18 66.02 64.7035671
19 69.08 67.001318320 75.02 66.950820421 78.08 64.5913741
22 78.08 63.032286223 75.92 61.3147914
24 68 56.9134729 1421.751 59.239621 66.02 59.2863402
2 59 55&99377443 51.98 48.2621592
4 48.02 43.19203855 46.94 41.0668613
6 44.96 39.2950925
7 44.06 38.374482
8 42.98 37.7883489
9 42.98 37.431937610 39.92 36.9691073
11 37.94 36.676902
12 37,04 36,1758824
13 37.04 35.724636214 37.04 35:7246362'
15 35.96 34.7452334
16 37.04 W35359222617 39.92 35.9691073
18 44.06 39.2150399
19 48.92 40.946257
P No. TXUT-001-PR-017F. JE N R CO NPROJECT REPORTFiENERCON for REV. I
Exe-p-t vepiL . Emny6&. the Evaluation of Lake Attachment CGranbury Water Temperature Page 26 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month day
2002 1 24
2002 1 242002 1 24
2002 1 24.
2002 1 24
2002 1 25
2002 1 25
2002 .1 25
2002 1 25
2002 1 25
2002 1 25
2002 1 25
2002 1 252002 1 25
2002 1 25
2002 1 25
2002 1 25
2002 1 252002 1 25
2002 1 25
2002 1 25
2002 1 252002 1. 25
2002 1 252002 .1 25
2002 .1 25
2002' 1 25
2002 1 252002 1 25
2002 1 262002 1 26
2002 1 26
2002 1 26
2002 1 26
2002 1 26
2002 1 262002 1 262002 1 26
2002 1 262002 1. 26
2002 1 262002 1 26
2002 1 26
Total Average
Dally wb Dailly Wbhour db ('F) wb ('F) (TFD) (*F) (AFD) (*F)
20 51,98 41.799866821 51.08 39.7828197
22 51.08 39.474243
23 51.08 39.1782844
24 46.94 37.236297 966,6686 40,27786
1 42.98 35.6375194
2 39.02 33.06985113 39.92 33.2551846
4 35.96 31.29208785 35.06 30.7753174
6 33.08 29.9196344
7 30.92 28.4713891
6 30.92 27.7632829 30.92 28.1431382
10 30.92 28.1431382
11 28.94 26.609037112 28.04 26.0764562
13 24.98 23.840243614 26.06 24.5035498
15 30.92 28.8796746
16 3902 34.055112
17 4604 37.688024418 51.08 39.1782844
19 55.04 39.496076220 55.94 40.3573721, 57.02 40.9202785
22 57.92 41.3854197
23 57.02 40.5386399
24. 51.96 38.6808287 788.6795 32.86165
1 44.96 35.5752846
2 44.96 35.2865118
3 42.98 34.44798324 41 33.5603533
5 39.02 32.7272529
6 35.96 30.6364232
7 33.98 29.8075717
6 33.08 29.62172059 32 28.634354
10 32 28.634354
11 30.92 27.76328212 30.02 27.2415804
13 30.92 27.763282
14 32 28.634354
No. TXUT-OOI-PR-a0l7EPROJECT REPORTE N E R C 0 N for REV._1
F•cellce-EveryprojeL ,y•: day. the Evaluation of Lake Attachment-CGranbury Water Temperature Page 27 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month day
2002 ,1 262002 1 26
2002 1 26
2002 1 26
2002 1 26
2002 1 26
2002 1 262002 1 26
2002 1 26
2002 ,1 26
2002 1 27
2002 1 27
2002 1 272002 1 272002 1. 27
2002 1 272002 1. 27,
2002 1 272002 1 27
2002 1 27
2002 1 27
2002 1 272002 1 27
2002 1 27
2002 .1 27
2002 1 272002 1 27
2002 1 272002 l' 27
2002 1 27
2002 1 272002 1 272002 1 272002. 1 27
2002 1 28202 1 28
2002 1 28
2002 1 28
2002 1 28
2002 1. 28
2o02 1 28
2002 1 28
2002 1 28
hour
15
16
17
1819
20
2122
2324
1
2
345
67
8
9
10
11
1213
14
1510
17
18
19
20
2122
23241
.2
3
45
67
8
9
Total Average
Daily wb Dallywbdb (*F) wb (*F) (TFD) ('F) (AFD) (*F)
37.04 31.9050192,44.06 36.2436745
51.98 41.1372459
59 43.82963395295 45.7538806
66.02 47.725M943
66.02 47.979531866.92 48.3914165
64.94 47.799873760.08 45.8013412 866.9026 36.12094
51.08 41.7231425
5108 42.0555742
48.92 41.3679468'46.94 40.340249244.96 39.6928797
42.98 38.232143239.92 36.0979503,
39.92 36.097950339.92 36.0979503
39.02 35.5922987
37.94 34.6080514
37.94 34.608051437.04 34.4660767
37.94 34.9803588
.42.98 38.232143251.98 42.922648.
60.08 46.1581191
64.04 48.6758125
66.92 '50.9327255
68 52.067509771.08 54.0443684.
69.08 53.555860668 53.5176686
66.02 53.1200907 1019.188 42.46615
80.08 50.578390560.08 50,5783905
67.92 50.016104753.96 48.234596
65.04 48.726172851.08 46.9022474
48.02 45.0257757
48.02 45.4515064
48.02 45.4515064
No. TXUT-001-PR-017NPROJECT REPORTfor REV.,_
E•tncke--E•oojfrciEv .•the Evaluation of Lake Attachment CGranbury Water Temperature Page 28 of 37
Due to the Operation of CPNPPUnits 3 and 4,
WET BULB CONDITIONS
year month2002 12002 1
2002 12002 1.
2002 1
2002 1
2002 1
2002 1
20 02 .1
2002 1
2002 42002 1
2002 12602 1
2002 1
2002 1202 0 1
2002 1
2002 12002 1.
2002 1
2002 112002. 12002 12002 1
2002 1
2002 12002 1
2002 1
2002 1
2002, 1
2002 12002 1
2002 12002 1
2002 1
2002 1
2002 12002 12002 12002 1
2002 1
day
28
28
2828
28
28
28
28
2828
2828
2828
28
2929
29
29
29
29.
2929
29"29
2929
29
29
29
29
29
2929
29
2929
29
303030
30
hour1011
121314
15
16
17
181.92021
2223
241
2
3
456
78
.910
.11
12
13
14
15
1617
1819
2021:
22
23
241
23
4
Total Average
Dallywb. Dailywbdb ('F) wb ('F) (TFD) (ýF) (AFD) ('F)
48.92 45.8820201
46.94 44.930M196
48.04 44.060097546.04 44.0600975
48.94 45.4592736'
50 47.8914289
55.94 52.001867962.96 56.4725114
69.08 60.409053571.06 61.6039291
73.04 62.3002932
75.92 63.2958371
75.92 63,295837177 64.230179
71.96 63.0068386' 1249.865 52.07769
69.98 62.320311
66.92 61.2400741
66.02 61.5544573
64.94 61,1698892
64.04 60.8471204
60.08 58.7370171
60.98 59.733793660.98 59.7337936
60.98 59.7337936-62.06 60.7983581
62.96 61.6856538
64.04 62.0663539
64.94 62.3813721
64.94 62.3813721
66.02 62.7567465.
66.92 63.0673763
68 64.103235
71.06 65.12322871.96 65.419164
75.02 65.258009875.02 64.64707,25
75.92 64.9457707
75.92 64.351534
73.04 63.9833546 1498.039 62.4182971.06 63.938116
59.98 63.571805869.08 63.2644272
68 62.2518109
No. TXUT-001 -PR-017PROJECT REPORT
ENERCON for REV.I, -- •,sjotEvely ayd the Evaluation of Lake Attachment C
Granbury Water Temperature Page 29 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS,
year month day
2002 1 30
2002 1 30
2002 11 302002 1 30
2002 1 30
2002 1 30
2002 1 '302002 1 30
2002 1 302002 1 30.
2002 1 30
2002 1 30
2002 1 30
2002 1 302002 1 30
2002 1 302002 1 30
2002 1 30
2002 1 30
2002 1 302002 1 31
2002 1 312002 1 31
2002 i 312002 1 31
2002 .1 312002 1 31
2002 1 312002 1 31
2002 1 312002 1 31
2002 1 312002 1 312002 1 31
2002 1 312002 1 31
2002 1 312002 1 31
2002 1 31
2002 1 312002 1 31
2002 1 31
2002 1 31
hour
56
7
8
9
10
1112
13
14i516
17
18
.192021
2223
24
23
4
5
67
8
9
101112
13
14
15
16
17
18192021
22
23
Total Average
Daily wb Daily wb
db (F) wb (*F) (TFD) (!F) (AFD) (°F)
66.92 61.8726603
66.92 62.518722
66.02 62.204630264.94 61.8250531
64.94 6Z381372151.08 47.8493961
48.92 45.4594761
46.04 43.5537733
44.06 42.5634196
39.92 39,0074214
39.92 39.0074214
41 40.069305341 40.0693053'41 40.4862854
39.92 39.9241 40.486285441 40.4862854
41 40.4862854
39.92 39.4991457
37T94 37.5343325 1180.307 49.1794537.04 36.1758824
37.94 36.67690237.94 37.0607235
39.02 38.1225475'39.92 38.1225475
39.92 39.007421439.92 39.4991457
39.92 39.0074214
37.04 37.04
35.96 35.569557
35.96 35.569557
37.04 36.1758824.35.98 35.114077233.98 33.1674057
3398 32.687666235.06 33.7959241
35.06 33.3206472
35.96 33.0262227.42.08 36.9365592
44.06 38.374482
46.94 39.9113381
48.02 39.7414766
46.04 37.6880244
No. TXUT-001-PR-017PROJECT REPORT REV. I' N E R CO N for ________
the Evaluation of Lake Attachment CGranbury Water Temperature Page 30 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month day
2002 1 31
2002 2 12002 2
2002 2 12002 2 12002 2 1
2002 2 12002 2
'2002 2 12002 2 12002 2 12002 2 1
2002 2 12D02 2 1202 2 1
2002 2
2002 2 1
2002 2 12002 2 1
2002 2 12002 2 1
20,2 2 1,2002 2 1
2002 22002 2 1
2002 2 22002 2 2
2002 2 2
2002 2 2
2002. 2 2
2002 2 2
2002 2 2
2002 2 2
202 2 2
2002 2 22002 2 2
2002 2 2
2002 2 2
2002 2 22002: 2 22002 2 2
2002 2 2
2002 2 2
Total Average
Dailywb Daily wbhour db (-F) wb ('F) ("FD) (-F) (AFD) ('F)
24 '42.98 35.6375194 877.4289 36.55954
1 39.92 33.8893032
2 39.02 33.0698511
3 35.96 31.2920878
4 35.06 310672535
5 33.08 29.9196344
6 33.08 29M6217205
7 33.08 29.62172058 30.92 27.763282
9 30.02 26.577578810 28.94 2563149675
11 28.04 24.770400212 26.06 23.5544096
13 26.06' 23.554409614 26.06 23.5544096
15 30.92 26.7668511
16 35.96 29.842503
17 41 32486867618 44.06 33.3816437
19 46.04 34.5273102
20 46.94 34.82a5909
21 48.92 35.949896322 48.92' 35.9498963
'23 .60 36.7609846
24 46.04 34:75199M9 728.8176 30.3674
1 42.98 33.17960432 39.02 31.1288118
3 37.04 29.9818787
4 33.08 28.6810505
5 32 28.03161346 32 28.0316134-
7 30.02 26.57757888 26.96 24.7455804
9 28.04 24.4474545
10 28.04 25.3988146
11 26.96 25.0506924
12 26.06 24_503549813 24.98 23.5289229
14 26.06 24.503549815 30.02 28.368390716 37.04 31.5751879
17 42.98 35.3510475
18 46.04 36.4300234
No. TXUT-001-PR-017EPROJECT REPORTE N ERC0Nfor REV._I
- , the Evaluation of Lake Attachment CGranbury Water Temperature Page 31 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month day
2002 2 22002 2 2
2002 2 22002 2 2
2002 2 2
2002 2 2
2002 2 3
2002 2 3
2002 2; 3
2002 2 3
2002 2 3
2002 2 3
2002. 2 3
2002 2 32002 2 3
2002 2 32002 2 3
2002 2 32002 2 3
,2002 2 3
2002ý 2 3
2002 2 32002 2 3
2002 2 '32002 *2 3
2002 2 3
2002 2 3
2002 2 3
2002 2 3
2002 2 3
2002 2 4
2002 2 4
2002 2 42002 2 4
2002 2 42002' 2 4
2002 2 42D02 2 4'2002 2 42002 2 4
2002 2 4
2002 2 4
2002 2 .4
hour
19
20
2122
23
24
23
45
67
8
910
11
12
1314,
151617
19
20
21
22
23
241
.2
34
5
'7
8
910
1112
13
Total Average
Dailywb Daily wb
db ,(F) wb (*F) (TFD) (*F) (AFD) ('F)
46.94 37.236297
46.94 37.23629746.94 37.23629746,94 37.236297
45.04 37.0516247
46.04 37.6880244 733.2101 30.55042
44.96 37.0953379
44.06 36.9029639
44.06 '37.2835419.42.08 37.2957552
42.08 36.9365592
42.08 37.2957552
42:08 37,2957552
42.08 37.2957552'
42.08 38.1507967
42.08 38.5006404.42.08 38.9326777
42.08 38.500640441 38.3518714
42.08 39.303045342.98 40.2336435
46.04 42.195458548.02 42.8168886
51.08 43.9139754
50 .43.0328575
48.02 ,42.38547546.94 41.4812512
48.02 41.6228798
48.92 42.4898072
48.92 42.4898072 951,8061 39.65859
48.02 .42.38547546.94 42.2749361
48.02 42.033466446.94 41.4812512
4U.94 41.481251246.04 41.017.1964
44.96 40.0341.58344.06 39.98371 16
42.98 39.412617142.08 38.5006404
42.08 38.50W5404
42.08 .38.50640441 37.9157949
No. TXUT-001-PR-017PROJECT REPORT REV 1I~E N E R C ON for RE_.__
E•tence-•-,p rqq. Every day. the Evaluation of Lake Attachment CGranbury Water Temperature Page 32,of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month day
2002 2 4
2002 2 4
2002 2 42002 2 4
2002 2 4
2002 2 4
2002 2 42002 2 4
20 02 2 4
2002 2 4
2002 2 42002 2 5
2002 2 52002 2 52002 2 5
2002 2 52002 2 5
2002 2 5
2002 2 5
2002 2 52002 2 5
2002 2 5
2002 2 5
2002 2 5
2002 2 5
2002 2 52002 2 5
2002 2 52002 2 5
2002 2 5
2002 2 5
2002 2 52002 2 52002 2 5
2002 2 52002 2 6
2002 2 6
2002 2 6
2002 2 6
2002 2 6
2002 2 6
2002 2 6
2002 2 6
hour14
15
16
17
18
19
2021
22
23
24
234
56
7
8
9
10
11
12
13
1415
16
1718
19202122
23
241
2
3
4
65
7
8
Total Average
Daltywb Daily wbdb (*F) wb (F) (TFD) (*F) (AFD) ('F)
41 37.9157949
42.98 38.983913344.96 39.6928797
48.02 39.7414766
50 39.8149349
51.08 40.0498887
51.08 40.049888751.08 40.382619
51.08 40.6703689
50 41.1679421
46.04 40.5996042 962.5911 40.10796
44.96 39.6928797
44.06 40-347834942.08 397600737
41 40.0693053
41 40.0693053
41 40.063053
41 40.0693053
39.92 39.4991457
39.92 39.499145739.92 39:4991457
39.92 39.499145739.92 39:0074214
39.02 38:1225475-37.94 37.0607235
35.96 35.56955735.96 35.1140772
35.96 35.569557
35.96 35.1140772.
35.06 34.6009614
33.98 33.6047839
33.98 33.604783933.98 33.604783933.8 33.1674057
32 32 894.2153 37.2589732 31.537664
32 31537864
32 31.537664
32 31.537664
32 31.53766432 31.537684
32 31.537664
32 31.1651715
No. TXUT-001-PR-017PROJECT REPORT REV IE N E R C0 N for R _V_
Exre•,•E•*D-frv a Ey d the Evaluation of Lake Attachment CGranbury Water Temperature Page 33 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month
2002 22002. 2
2002 22002' 22002 2
2002 2
2002 22002 2
2002 .2
2002 2
2002 2
2002 2
2002 2
2002 .22002 2z
2002 22002 2
2002 22002 22002 2
2002' 2
2002 22002 2,
2002 .22002 2
2002 2
2002 2
2002 22002 2
2002 2
2002 .2
2002 2
2002 22002 2
2002 22002 2.
2002 2
2002 2
2002 :22002 22002 2
2002 2
-2002 2
day
66
6
666
6
6
6
6
6
6
6
6
6
777777777
7
7
'77
77
777
77
7
7
8
88
hour
910
11
12
13
1415161718
1920
2122
23
i41
2
34
5
678
9
10
1112
13
14
1516
17
18
1920
2122
23241
2
3
Total AverageDaily wb Daily wb
db (*F) wb (F) (TFD) (F) (AFD) ('F)
32 31.165171532 31.1651715
32 31.1651715
32 31.165171532 31.537664
32 31.1651715.
32 31.53766433.08 32.1557166
35.06 33.795924135.96 34.3152852
37.04 34.466076737.94 35.4439299
37.94 35.443929939.02 36.0515549
39A02 36,4702663
39.02 36.4702663, 785.443 32.7267937.94 35.8665725
37.04 35.359222633.08 32.1557166
32 31.537664:30.02 30.0209482
28.94 28,940887230.02 30.0209482
30.02 30.0209482
30.02 29.1662759
26.96 '26.1683069
28.04 27.5898021
26,96 26.593598826.06 25.28642.18
26.96 26.5935988
28.94 28.9408872
32 3239.02 38.1225475
44.06 39.9837116
48.02 42.033466451.08 .43,9139754
53.06 44.882266155.04 45.5029021
55.94, 45.9331272.53.96 44.9823513 821,6159 34.23448.02 420334664
44.98 40.4556329
42.98 39,4126171
No. TXUT-001 -PR-017PROJECT REPORT REV. IoJCT
Etre-ece-E), ct Every ,dcy the.Evaluation of Lake. Attachment CGran bury Water Temperature Page 34 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month day
2002 2 82002- 2 8
2002 *2 82002 2 82002 2 8
2002 2 8
2002 2 8
2002 2 8
2002 2 8
2002 2 82002 2 82002 2 8
2002 2 82002 2 82002 2 8.
2002 2 82002 2 8
2002 2 82002 2 8
2002 2 8
2002 2 8
2002 2 92002 2 9
2002 2 92002 2 9
2002 2 92002 2 9
2002 2 9
2002 2 92002 2 9
2002 2 9
202 2 9
2002 2 92002 2 9
2002 2 92002 2 9
2i02 2 9
2002 2 9
2002 2 92002 2 92002 2 9
2002 2 9
2002 2 9
Total Average
Daily wb Dailywbhour db (*F) wb (F) (TFD) (F) (AFD').('F)
4: 42.98 39,4126171
5 42.08 38.9326777
6 39.02 36.8294762
7 37T94. 36.229.1524
8 35.96 35,1140772
9 35.06 34.6009614
10 33.98 33.604783911 33.08 33.08
12 33.08 33.0813 32 32
14 32 3215 35:08 35.08
16 42.08 41.047410717 50 45.009805
18 57.92 48,718957519 62.06 50.5640886
20 64.04 51.0806781
21 64.94 51.0708181
22 66.02 50.5395558
23 64.04 50.3527526
24 60.98 48.5997799 978.8293 40.78455
1 57,02 47.1742801
2 53.06 48.3241429
3 51.98 47.82900554 51.08 46.9022474
5 48.92 45.45947616 48.92 45.4594761
7 48.02 44.527809
8 46.94 43.5100679
9 46.04 43.061595910 46.04 43.0615959
11 44.96 42.518928412 44.96 42.518928413 42.08 40.1515586
14 39.92 38.6086088*15 48.92 42.0823572
16 53.96 43.503450617 57.92 43.8593831
18 59 43.541292219 60.98 44.2441783
20 60,08 44.350734121 60.98 44.7996448
22 62.06 45.3219783
No. TXUT-001 -PR-01 7PROJECT REPORT REV.I
for REV.Exce•fence--E•ery Pjec, Eteiydq,: the Evaluation of Lake Attachment C
Granbury Water Temperature Page 35 of 37Due to the Operation of CPNPP
Units 3 and 4
WET BULB CONDITIONS
year month day hour
20022002
2002
20022002
2002
20022002
2002
2002
2002
2002
.200220022002
220022002
-20022002
2002
2002
20022002
20022002
20022002
2002
2002
2002
20022002
2002
2002
20022002
20022002
2002
200220022002
2002
Total Average
Daily wb Dailywbdb ('F) wb (*F) (TFD) (*F) (AFD) ('F)
60.08 43.581373255.94 42.5544347 1056.957 44.03986
51.98 41.492704
48.92 39.900071546.04 38.3526749
44.06 36.9029639
44,06' 36.902963944.06 37,2835419
42.98 36.303014542.08 35.4877665
41 34.220118341 34.5115591
41 34.8746274
39.92 33.889303239.02 32.7272529
3794 311770037939.92 32.9291325
41 33.8833606'
42.98 35M0200334
44.96. 36.4629446
48.02 38.760484
44.96 35.744534844.06 36.2436745
44.96 36.7445348
46.04 37.3404895
44M05 362436745 865.0015 36.0417342408 34.83093668
39.92 32.3660107
35.96 29.5671239
35.96 29.5671239
33.08 27.618005830292 25.6404659
30.02 25.0990443
28.94 24,2057178
28.94 24.2057178
28.04 23:3753039
24.98 21.726001623 20.4482698
21.92 19.447561624.98 21.972604
28.94 25,314967535.06 295531264
39.02 31.1288118
No. TXUT-0O1-PR-017PROJECT REPORT REV. 1EJ ENERCON for REV._1
- p E Zý;Y the Evaluation of Lake Attachment CGranbury Water Temperature Page 36 of 37
Due to the Operation of CPNPPUnits 3 and 4
WET BULB CONDITIONS
year month day
2002 2 112002 2 11
2002 2 112002 2 11
2002 2 11
2002 2 11
2002 2 112002 2 12
2002 2 12
2002 2 12
2002 2 122002 2 12
2002 2 122002 2 122002 2 12
2002 2 122002 2 12
2002 2 12
2002 2 122002 2 12
2002 2 12
2002 2 122002 12
2002 2 12
2002 2 122002 2 12
2002 2 12
2002 2 12
2002 2 12
2002 2 12
2002 2 12,2002 2 13
2002 2 132002 2 13
2002 2 132602 2 13
2002 2 132002 2 132002 2 13
2002 2 13
2002 2 13
2002 2 13
2002 2 13
Total AverageDaily wb Daily wb
hour db (*F) wb ('F) (TFD) ('F) (AFD) (*F)
18 42.98 32,5279339
19 4.04 34.7519989
,20 51.08 3 7.357085121 51.98 37.4827307
22 55.04 39.1387916
23 55.04 3911387916
24 51.98 38.0829968 7045356 29,355651 46.04 34.7519989
2 46.04 34.7519989
3 42.98 33.4300563
4 42.98 33.17960435 35.96. 291346517
6 33.08 27.84519357 33.08 27:6180058
8 30.92 26.1817167
9 28.94. 24.994975210 26.96 23.7836903
11 28.94 24.9949752
12 28.94 25.3149675
13 30.02 25.961782714 30.92 26.4952811
15 35.96 30.081.1171
16 42.98 33.9188242
17 51.08 38.9410101
18. 57.92 41.094142
19 60.08 42.4873113
20 62.08 43.4797665
21 64.94 44.7282126
22 96.02 45.4155436
23 64.94. 44.5373155
24 62.96 43.7568271 807:2051 33.633591 55.94 41.4909266
2 51,98 39.65687953 48.02 37.8277834
4 44.96 36.4629446
5 "44,08 35.9598763
6 42.08 34.8393668
7 41 34.2201183
8 42.08 35.1280866
9 41 34.220118310 39.92 33.5951162
11 39.02 32.7272529
12 37.94 31.7700379
No. TXUT-001-PR-017PROJECT REPORT REV. 1
F E N E R CO N for-e, y Edoy. the Evaluation of Lake Attachment C
Granbury Water Temperature Page 37 of 37Due to the Operation of CPNPP
Units 3 and 4
WET BULB CONDITIONS
Total Average
Dailywb Daily wb
year month day hour db (*F) wb ('F) (TFD) (*F) (AFD) (*F)
2002 2 13 13 37.94 31.7700379
2002 2 13 14 37.94 31.77003792002 2 13 15 44.06 3513174227
2002. 2 13 16 44.06 35.0662481
2002 2 Q3 17 48.02 37.5238826
2002 2 13 18 51.98 39.9503478
2002 2 13 19 55.04 41.8402636
2002 2 13 20 55.04 41.5420172002 2 13 21 57.02 42,5500462
2002 2 13 22 57.02 42.2688161
2002 2 13 23 55.94 41.4909266
2002 2 13 24 53.08 39,7234738 888.7108 37,02962
No. TXUT-001 -PR-01 7PROJECT REPORT REV. I, ENERCON forREV.1
the Evaluation of Lake Attachment DGranbury Water Temperature Page I of I
Due to the Operation of CPNPPUnits 3 and 4
DECORDOVA READINGS(References 3 and 6)
717 12/11201 "47 27A7 550
G1YT2 12/11/2001 21P4 27A7 0Gem9 11/1V200 272AS 2746 a
Gem7 121140M01 27 46 27A6 00M 11/16101 .7" 2749 0197 W291V17, V 27- 009M 1Z/1S/201 PM 275 01 212 4 0/ 1 PM 27.52 019371 11/MWI0 X7.51 2741 QGem1 12/1/2001m 19 27.51 a0 M 12/22/20) 731 27.51 00*912 142201 1752 27S2 0G9772 1Z124n1201 11 U 27•51GS0T2 12/25•/200 27,51 00CA1M 12Z/6/2001 27. .S 00992 1Z/27/2001 Z734 275 009702 12 /202 01 ?1A% 2749 00970 1712912"1 27%* 275G0YT2 121192l020 7 27749 0G0 2 1/11/2001 27A4 009012r 1/1/2002 224 27,41 0G099 112/2002 7348 2704 00GTZ 1/32W002 27A7 2747 0GYT72 1/4/2002 PM 27A6 0G191 1/I/2002 "A7 27 7 0G•192 1/6/2002 7?46 2746 0091T2 1/7/0Z 02 * S4 274 0G0YT2 L/6/2002 P i 217A aG YT 1/9/2002 I 12 274" 12.G5T'2 1119/2002 VAG 27?46 009YZ 1/1/2002 -7• 2749 009YT1 1/12/2002 2747 2747 09O772 /11/002 2747 277A 0
GBYT2 1/4/ 2 Z7 2747 0G0972 1/1512002 Z?4" 27A6 49A09912 1/6,2002 27 2746 009112 1/17/2002 22.4 2747 0G0912 1/10/2002 ý724I 27-- 009912 1/191,2002 27 50 275GBYT2 1120/=2 27% 27.5 009772 M/21/2O00 2759 27,1 0G0992 1/2,/200 17s4 275. 0Gum 20/W2002 27M 275 0G97m 1/24/2002 *2752 27.52 0G09T2 1/25/2002 :751 2751 009717 1/29/200 '2.31 27.51 009912 1/217/22= 75 2751 009772 1/20/2002 Z112 1752 0G0992 /20/2002 2 7vS4 27.54 0GB092 1/10/2002 27V, 27.57 009712 1/300202 21.6 27.4 0'Sam1 2/1/200 Of)9 27961009712 2/2/200 v241 27.91 009712 2/5202 -'I& 27A61 019702 714/2002 17&1 27.61 009702 2/5/2002 2746 27.62 0Gem9 119/2002 :148 27,6609702 2/7/202 22004 27.60 006777 2/9/2002 22-6 27 ,07 009712 2/10/2002 21767 27.71 0
09a1 2/19/200 Z7.71 27.71 00Gam 12/1/2002 27J0 2.6 009772 M31=/02 27.79 277 4924A $1.764
f)
No. TXUT-001-PR-017ERN PROJECT REPORT REV.E E C Nfor RV
. -,. j.. the Evaluation of Lake Attachment E
Granbury Water Temperature Page 1 of IDue to the Operation of CPNPP
Units 3 and 4
OTHER INTAKE FLOWS(Reference 7)
13niv, I and M" M ion I Ws I. Uf tporm
Jai lI J 113,4177 5 77 7
Month OV-mth|..o.sirno= Iffelin./day gilons•um I ionsi
.;:2r1.0 'll 08('114717; 2954)AI 123099P]J61 (JOSIAS" ,• ,•4,41''0 81 ')•6"A1 H 19%M i 1O R461?151 13.%.71112 N
D•, blid Jin hnsot Fob t0tS|32019.59 ISS34.9 118.9$33
.... No. TXUT-001-PR-017PROJECT REPORT REV.I
rý.ENERCON for___for REV., _________
fie-f--E, rm c' the Evaluation of Lake Attachment FGranbury Water Temperature Page I of 5
Due to the Oper ation of CPNPPUnits 3 and 4
REVISED ELEVATION-AREA-VOLUME ESTIMATES FOR LAKE GRANBURY,HOOD COUNTY, TEXAS
(Reference 10)
Revised Elevntion.4rca-Volurne Estimates for Lake Granbun,,: Hood County, Texas
Stephen K. Boss, Ph.D., P.C.Department of GCeosciencesUniversity of ArkansasFayettevile, AR
SUMMARY":
Mr. DarTen Lovvom requested revised estimates for elevation-aren-volume relations for amodified region of Lake Grabnbur. corresponding to a pool elevation of 691 fl.on 8 May 2009(Fig. 1). Theic modified area is reduced somewhat from the original mapped area of LakeGranbury. 'the normal conservation pool of Lake Granhurv is 693 ft a~d-lihe original studiedarea was 577 acres. "llie modified area that is subject.of this brief amalysis is3 1 0-acres (53.7%.ofthe original.area) and 2 feel below the normal conservation pool.
The are~a for which calculations hav\e been completed includes the main body of the reservoirlessthe area ol'the prdminent ahn imniediately northwest or D)e Cordova liend l)Dm. Bathymetriedata were not available for the prominent lake ann immediately northwest of the De CordovaBend Dam. 'T'his arm is approximately 30 acres and presumed to be relatively shallow (<6 11).As such. it very likely represents a relaitvely small volume ofthe studied area (less than 180 acreIcet at 691 Rt. elevation). Note that no data for this ann were reported on prior reports. so resultsreported here will be compamrable to prioi reporis.
'The area l'ur wvljiit result', me reported here haes a uttitsured surfaee ar'eii of 281.6 acrrs. '1he
estitiialed voltime storage of this a.rea at 691 fl. elevation is 9,.668 acre-feet, This volumne is ca.62% of the volum elstimated for the original study area. Again, the proimtin3t lake arm NW ofLhe darn site may contribute an additional 100-200 acre-feet to this toalaif included. *fhougli thearea that is subject of this analysis is only slightly more than 501% of the original area, it contains62% of the storage volume owing to the fact that it includes the deepest. portions of tle reservoiralong an incised portion of the forner course of the Brazos River.
Figure 2 of this report illustrates area versus elevation•relations for this portion of the reservoir.The overall tonn of this Curve is comparable to that inthe original report for the larger mappedarea. Thie piromineiit ciangcs -in slope of tlhe curve apparently refleet the presence of now-s1bmerged stream terraces of the Brazos River..
Figure 3 illustrates area versus volumne relations within this portioeof the reservoir. Note that.area becomes constant as the reservoir is bound along its margins by outcrops with nearlyvertical walls. 'ltus, reservoir area does not increase as volume increases due to rising lakelevel.
Figure 4 shows the relation of reservoir volume to elevation. This curve is quite typical ofriverimpourndments. and is comparable to that front the original report for this reservoir.
No. TXUT-001-PR-017PROJECT REPORTENERCONfor REV. I
the Evaluation of Lake Attachment FGranbury Water Temperature Page 2 of 5
Due to the Operation of CPNPPUnits 3 and 4
REVISED ELEVATION-AREA-VOLUME ESTIMATES FOR LAKE GRANBURY,HOOD COUNTY, TEXAS
(Reference 10)
Ytg. I False cdoroifrared image of Lake UJanburyimapping a•e, hood Cowtly, TX. The aea for wvtchreservoir elevationk waes, and volumes was calculatedindicated bythe wee oetlinedwithyellow boudm bythe geen dahed lines (area limits provided by Mr. Duren Lovvom, P.G, Eaercoi, Inc. on OS May 2009).
No. TXUT-001-PR-017LT.I__ E N E R C. O N PROJECT REPORT REV. r
ExceIlence--•ay ProjrcL clydn.ý the Evaluation of Lake Attachment FGranbury Water Temperature Page 3 of 5
Due to the Operation of CPNPPUnits 3 and 4
REVISED ELEVATION-AREA-VOLUME ESTIMATES FOR-LAKE GRANBURY,HOOD COUNTY, TEXAS
(Reference 10)
GRANBURY LAKE MODIFIED MAPPING AREA vs ELEVATION
7W.00.90
670.0 -
: 660.000
640900
63090
610.00000 5000.06M 10000 150 0000 200o00 250o000P 300.0000
AREA acres)
Fig. 2 Rt- 'ora e• v- elg'wkm fr thw ,,fnified - d-pideod in Fiý I, This co'e compares favornbIy lotIhi pe nrm d in the alioinIl repoal onbzobyicuic ma.ppiq in tiso Inl.
No. TXUT-001-PR-017PROJECT REPORT REV. I
ENE RCO N for REV,_1.E*ezkce- 'ee/ProkCL v -" the Evaluation of Lake ' Attachment F
Granbury WaterTemperature Page 4 of 5Due to the Operation of CPNPP
Units 3 and 4
REVISED ELEVATION-AREA-VOLUME ESTIMATES FORHOOD COUNTY, TEXAS
(Reference 10)
LAKE, GRANBURY,
GRANBURY LAKE MODIFIED MAPPING AREA vs VOLUME
S
w
0
0,0000 50.0000 100.0000 150 0000
AREA (acres)
Rg.3, ba.era ve'rsus vulurre cut.w, for the modirie.d study" war
200,0000 250,0000 300.0000
No. TXUT-001 -PR-017• E N E R C 0 N PROJECT REPORT REV. Ifor REV._1
the Evaluation of Lake Attachment FGranbury Water Temperature Page 5 of 5
Due to the Operation of CPNPPUnits 3 and 4
REVISED ELEVATiON-AREA-VOLUME ESTIMATES FOR LAKE GRANBURY,HOOD COUNTY, TEXAS
(Reference 10)
GRANBURY LAKE ELEVATION vs VOLUME FOR MODIFIED MAPPING AREA
12000.00
600000
4000,00
2000.00
0.00626.00 631.00 636.00 641.00 646.00 651.00 65600 661.00 666.00 671,00 .676.00 681.00 6B6.00 691.00
ELEVATION (ft)
.Fv., 4, Clvi 0, vl t o- mcfij ir d ,,wa