PROJECT REPORT On - Welcome to...
Transcript of PROJECT REPORT On - Welcome to...
1
PROJECT REPORT
On
Modification of Value Added Products In the Existing Pig Iron Complex
At
Narayandevarakere Village, Hagaribommanahalli Taluk, Bellary District, Karnataka State.
For
M/s. SLR Metaliks Limited Bellary
Environmental Consultants
M/s. Aqua Tech Enviro Engineers,
(Environmental Engineers & Consultants)
# 3391, 6th Main, 3rd Cross, RPC Layout,
Vijayanagar II Stage, Bangalore – 560 040
Tele Phone: 080: 23141679
Fax: 080:23148166
E-mail: [email protected]
2
1. INTRODUCTION
M/s SLR Metaliks Ltd is established and operating with valid Environmental Clearance from
MOEF, New Delhi and Consent for Establishment and operation from KSPCB, Karnataka
with an iron making industry consisting of 262 m3 blast furnace with 2,00,000 TPA capacity,
33 m2 sinter plant (3,31,000 TPA) and 6 MW Blast Furnace off gas based power plant at
Narayanadevarakere Village, Hagaribommanahalli Taluk, Bellary District, Karnataka State.
Presently, the pig iron produced in the industry is sold to other industries for use in steel
making and foundries. Sinter produced is completely utilized as a captive source of blast
furnace raw material. Power generated from captive source is completely utilized in the
industry it-self.
All the existing units are fully operational. M/s SLR Metaliks Ltd is establishing expansion
projects to improve viability of the plant by value addition to the existing hot metal
production by installing additional and balancing facilities to produce more valuable
downstream products with ready market opportunity. Towards this objective, the company is
establishing 3.0 Lakh TPA Steel Plant, 3.2 Lakh TPA Rolling Mill, 1.2 Lakh TPA Coke
Oven Plant, 9.0 MW Coke Oven Off Gas Based Power Plant, 120 TPD Oxygen Plant,
10 TPH Pulverized Coal Injection and 15000NM3/hr Producer Gas Plant, for which EC from
MoEF and CFE from KSPCB is obtained. Now to improve the economics & effective
resource utilization,
Change of fuel is proposed in existing power plant from Blast furnace gas to imported
coal and
Change of fuel in Reheating furnace from FO to Blast furnace gas
Capacity reduction of producer gas plant from 15000 Nm3/hr to 5500 Nm3/hr.
1.1 Salient Features
The salient features of the proposed project are given below:
Table-1.1 Salient Features of the Proposed Project
Sl.
No. Parameter Details
1 Project
(i)Change of fuel in existing power plant from Blast furnace
gas to imported coal (ii) change of fuel in Reheating furnace
from FO to Blast furnace gas and (iii) Capacity reduction of
producer gas plant from 15000Nm3/hr to 5500 Nm3/hr
2 Project Proponents
M/s S L R METALIKS LIMITED Narayandevarakere
Village- 583 222, Lokappanahola Near Mariyammanhalli,
Hagaribommanahalli Tq. Bellary Dist., Karnataka State.
3 Location of the site
Plot / Survey No. R.S. No.:633,646, 643 & others
Village Narayandevarakere,
Lokappanahola- 583 222,
Tehsil Hagaribommanahalli
District Bellary
State Karnataka
3
4
Proposed
modifications BF Gas based captive
Power Plant. 1 x 6 MW
( existing unit)
Change of fuel from Blast
furnace gas to imported coal.
( change of 40 TPH boiler to 32
TPH AFBC boiler)
Rolling mill. 3,20,000
TPA ( expansion unit)
change of fuel in Reheating
furnace from FO to Blast
furnace gas
Producer gas plant 15,000
Nm3/hr ( expansion unit)
Change of capacity to 5,500
Nm3/hr
5
Existing capacity PRODUCTS QUANTITY
Pig Iron 2,00,000 TPA Granulated Slag 60,000 TPA
UNITS CAPACITY
Blast Furnace 1 x 262 m3
Sinter Plant 1 x 33 m2
Pig Casting Machine 2 x 500 TPD
BF Gas based captive
Power Plant 1 x 6 MW
6
Expansion units Steel plant 3,00,000 TPA
Rolling mill 3,20,000 TPA
Coke oven plant 1,20,000 TPA
Coke oven off gas based
power plant 1 x 9.0 MW
Air separation plant 120 TPD Oxygen capacity
Pulverized coal injection 10 Ton/h
7
Sl. No. in the
Schedule
Schedule-3(a) for Metallurgical industries (ferrous &
nonferrous) as per EIA Notification dated 14th September
2006 and as amended in December 2009.
8
Location Features The location of the proposed site and its immediate
surroundings is a barren land and moderately undulated with
shrubs. It is consisting of rocky & sandy soil, not suitable for
cultivation. Nearest village Lokappanahola is 1.5km, nearest
town Hospet is 10 km and nearest high way SH-25 is 4.29
km from the site.
9 Total man power Construction phase : 40 Nos
Operation phase : 80 Nos
10 Land area The above said modification is in the existing industry
premises.
11 12
13
Raw material
requirement Plant Raw material Quantity
Captive power
plant. 1 x 6 MW Indonesian coal
70,000 TPA
Producer gas
plant
5,500 nm3/hr
C grade coal 17,240 TPA
4
14
Water requirement
& Source
150 m3/d. Source: Water drawl permission from single
window clearance is 9012 m3/d. Further Permission is
available to draw 0.19 TMC of water flood period & stored
in reservoir.
15 Power requirement
& source 10-11 % of rated capacity: 660kwh
16 Project Investment INR 19 Crore (for AFBC boiler & 5,500 Nm3/hr PGP)
17 Investment for
EMP
Capital investment on EMP : Rs. 90.00 Lakh
Operating/running cost on EMP : Rs. 9.00 Lakh
18
Effluent and their
treatment &
utilization
No additional waste water generated
19
Sources of air
pollution & control
measures
1. Flue gases from 28 T/h boiler (reheating furnace). These
gases are vented through stacks of adequate height.
2. Fugitive emission at screens, conveyors, coal handing area
etc. These are sucked through vacuum suction hoods,
dedusted and vented through stacks of sufficient height.
20 Sources of solid
waste &
management
Solid waste obtained are,
1. Fly ash & bottom ash from coal fired boiler & PGP will be
used for brick manufacturing.
5
Figure - 1.1 Location of the Project
6
Figure - 1.2 Google Map of Project
3. Details of proposed modifications
3.1 Captive power plant
The process involved in iron making generate considerable quantity of gas as fuels. The energy
content of these gases can effectively be utilized to generate electrical power as well as steam for
various needs. In the existing unit power is generated from blast furnace gas. Now it is proposed to
change the fuel from BF gas to imported coal. To achieve this, it is required to install 1x32 TPH
AFBC boiler with additional coal handling system. As already provisons are made for ash handling
in the producer gas plant the same facilities will be used for ash handling. Hence no additional
waste management system is required.
3.2 Rolling mill
Steel manufactured in the steel shop will be sent to rolling mill unit for products of specified
sizes. The process includes pre-heating in the furnace and hot rolling followed by shot
blasting, mechanical surface finishing before inspection and stacking. Instead of using
7
Furnace oil for reheating furnace it is proposed to use the Blast furnace gas generated from
blast furnace unit.
Producer gas plant
Extended shaft gasifier technology will be used to produce 5,500Nm3/hr producer gas from C
grade coal.
i) Coal is lifted and delivered to the bunker by a skip-hoist or Bucket-Elevator.
ii) From the Bunker, coal is fed to the Extended shaft through double-bell feeder system
either manually or semi-automatically or fully automatically as per the exit temperature of
gas exceeding 120oC.
iii) Fed coal travels downwards and gets dried and preheated up to the distillation
temperature as per the temperature profile . Due to prolonged stay of coal in the Extended
Shaft and the gas getting better physical contact with coal interface, substantial heat transfer from
gas to coal takes place and at the same time high volatile-matters of coal get stripped off
and enter the gas-phase in turn auto-carbureting the latter.
iv)When the coal enters the generator proper, reaction between coal and air along with steam occurs
3.3 RAW MATERIALS
Sl no. Unit Raw material Quantity in TPA
1 Captive power plant 1X6
MW
Indonasian coal 70,000
2 Producer gas plant
5500 Nm3/hr
C grade coal 17,300
3.4 Water requirement
Sl. No.
Purpose Unit Quantity
Coal based power plant 1X6MW
1 DM water m3 /d 50
2 Cooling water for condenser and
auxiliaries and gas fired boiler
m3 /d 56
Producer gas plant 5,500 Nm3/hr
3 Process water m3 /d 31.2
4 Soft water m3 /d 18.0
8
3.5 SOURCE OF POLLUTION & THEIR MANAGEMENT / DISPOSAL
3.5.1 WASTE WATER MANAGEMENT
3.6 GASEOUS EMISSIONS AND APC MEASURES
3.6.1 FUGITIVE EMISSIONS
Fugitive emissions are generated in the industry mainly due to the handling of coal, solid raw
material and solid waste products and also due to vehicular movement. Dust emissions also
arise during loading and unloading of solid material. The location and source of fugitive
emission is given below
Sources of Fugitive Dust
Sl.
No. Area Monitoring Location
1 Raw Material Handling area Tippler, Screen area, transfer points, stock bin
area
2 Crusher area Coal crusher plant, vibrating screen , transfer points
3 Raw material feed area Coal feeder area, mixing area, transfer points
3.6.2. CONTROL MEASURES
Details of Dust Extraction System
Sl.
No. Location / shop Facilities
1 Coal fired boiler ESP
2 Raw material
handling area,
material transfer
points
Dust suppression system comprising of spray nozzles, piping
network, valves, solenoid valves, pumps , instrumentation
and controls , electrics, water tank etc.
3 PGP plant Cyclone/ scrubber
Sl.No Purpose Unit Quantity
Utilization
Coal based power plant 1X6MW
1 Blow down water m3 /d 18 Will be used in
slag granulation
plant Producer gas plant 5,500 Nm3/hr 2 Cooling waste water m3 /d 10 Will be used in
slag granulation
9
3.7 Control measures in coal fired boiler area:
Crusher screen in fuel handling system
Dedusting system
Bag filter
Pulsate type bag filters will be used for cleaning the dust laden gas.
Design and material specification of bag filter are
Casing and hopper: 3.15 mm steel sheet
Tube sheet : 3.15 mm steel sheet
Bag case : 4 mm dia galvanized Wire net
Fasteners : Galvanized
Gaskets : Neoprene rubber
Filter bags : Polyester needle felt, Antistatic
Filtering velocity : 25-30 mm/s
3.8 WASTES GENERATED & THEIR MANAGEMENT / DISPOSAL
3.8.1 SOLID WASTE MANAGEMENT
The solid waste generated are bottom ash (925 TPA) & fly ash (12,922 TPA) which will be
utilized for brick making. The tar generated will be sold to authorized vendor.
3.9 ASH HANDLING SYSTEM
Dense phase pneumatic conveying system will be envisaged for conveying fly ash collected
from economizer, air pre-heater and ESP hoppers. Surge hopper of adequate capacity will be
provided at the collection point of economizer and air preheater zones.
Fly ash collection equipment and disposal from Power Plant
Dust separators will be provided immediately at the outlet of the furnace and before the ID
fan. The dust will be collected in hoppers below them. They will be emptied periodically by
air suction system and the ash will be taken to a silo located at a higher level for loading into
trucks from bottom of silo. The fly ash will be sold to cement plants.
Bottom ash collection and disposal
At the bottom of the boiler, a hopper will be provided with a sealing arrangement with water
between boiler furnace and the hopper. This will give a seal against slightly negative pressure
maintenance in the furnace and also for the expansion of the furnace walls downwards on
furnace heat up. This hopper will always be filled with water, overflowing continuously at the
top seal to quench the ash and clinkers falling down from the furnace.
Ash pond
The type of construction for the ash pond is earthen bund. Earth for dyke formation will be in
layers not exceeding 200 mm thickness and compacted with sheep foot roller. The
10
compaction of earth will be done to achieve 95% maximum dry density at optimum moisture
content by number if passes. The earth will be free from roots, sods, wood, other organic
matters and any unsuitable matter for formation of dyke. The dyke will have a slope of 1 in
2.25, in both upstream and downstream side of the pond. A minimum width of 4 m will be
provided at the top of the dyke wall to facilitate man and vehicular movement. The geo-
textile lining will be provided over a sand layer followed by a sand layer along the brick on-
edge layer. The seepage water if any will be collected through the rock toe, drains and
stoneware pipe arrangements at the edge of the ash pond. A free board of 0.5 m is considered
to avoid overflow of the stored slurry and the other reason is to fill the top free board depth
with earth cover for afforestation. The bottom area will be made impervious by compacting
the earth and clay.
3.9.1 GENERAL MITIGATION MEASURES
The impacts of fugitive emissions in the industry are controlled by following measures
Haulage roads are sprinkled with water at regular intervals for which water tankers with
sprinkler arrangement are deployed.
Trucks carrying coal and other raw material are covered with tarpaulin to prevent
spreading of dust during transportation.
Green belt and greenery development around storage yards, around plants, either side of
roads and around the periphery of the industry.
The conveyors of fuel are suitably covered with hood or enclosures to control fugitive
emissions.
Dust respirators are provided for the people working dust generating locations.
All internal roads in the premise are paved /tarred.
Regular sweeping of roads is practiced with vacuum sweeping machine or water flushing
to minimize dust.
The air pollution control measures will ensure the ambient air quality to be within the
NAAQ standards for industrial areas as indicated below.
11
4.0 ENVIRONMENTAL MANAGEMENT PLAN
A comprehensive environmental management plan will be adopted consisting of
environmental protection and monitoring measures as indicated below.
Establishment of pollution control facilities.
Green belt and greenery development in and around the factory site
Paving and lining of roads and fuel storage yards so as to avoid fugitive emissions.
Fugitive emissions within the factory and storage yards are controlled by good
housekeeping, water spraying and sprinkling.
Regular Monitoring of stack emissions.
Dust extraction at dust generating machinery/equipment.
Safety & Occupational health care programmes, emergency management plan and
safety management systems will be implemented in the industry.
4.1. ENVIRONMENTAL MANAGEMENT SYSTEM
The existing industry has already established Environmental Management System to
implement and monitor environmental policy and programmes. It consists of the following.
4.1.1 Environmental Cell
Environmental cell consisting of Managing director and departmental heads. The
responsibility of the Environmental cell is to effectively manage the environmental activities
in the industry.
4.1.2 Environmental Department
Environmental department consisting of environmental engineer, laboratory chemists and
operators. The responsibility of the Environmental department is to implement and operate
pollution control and environmental protection measures.
4.2 ENVIRONMENTAL MONITORING PROGRAMME
The existing industry has already implemented self monitoring system with man power and facilities
to ascertain the compliances of environmental norms and standards. A laboratory is present in the
industry to analyze waste water, soil, stack emission, ambient air etc. The parameters will be regularly
monitored as per MoEF/KSPCB guidelines during operation of the industry.
4.3 INVESTMENT ON POLLUTION CONTROL FACILITIES
Total cost of the project (for 32 TPH AFBC boiler & 5500 Nm3/hr PGP plant) will be Rs. 1900
Lakhs. The investment to be made on EMP will be Rs. 90.00 Lakhs. Recurring cost on EMP will be
about Rs. 9.00 Lakhs per year.
12
5. Conclusion
The modification will be done in the vicinity of the existing & expansion project area.
Administrative and ancillary infrastructure facility will be made use of in expansion of the
project. Hence, the modification will be achieved with minimum resources. The solid waste
handling facilities reserved for the producer gas plant will be utilized for the proposed coal
fired boiler.
With the proposed modification, the air pollution load will reduce marginally by about 1.3%
and reduced solid waste considerably by about 84 %.
Area vel Flow
conc.
with
APC Area vel Flow
conc.
expected
with APC
m2 m/s m3/hr mg/nm3 mg/hr kg/d m2 m/s m3/hr mg/nm3 mg/hr kg/d
PM 4.91 8.30 146597.26 44.00 6450279.26 154.81 PM (Boiler chimney ) 4.91 4.60 82800.00 50.00 4140000.00 99.36
Sox 4.91 4.60 82800.00 40.00 3312000.00 79.49
Nox 4.91 4.60 82800.00 10.00 828000.00 19.87
PM (dedusting
chimeny) 1.25 9.28 41760.00 50.00 2088000.00 50.11
PM 3.80 13.80 188873.42 35.00 6610569.84 158.65 PM 3.80 5.00 68432.40 50.00 3421620.00 82.12
SOx 3.80 13.80 188873.42 10.00 1888734.24 45.33 SOx 3.80 5.00 68432.40 40.00 2737296.00 65.70
NOx3.80 13.80 188873.42 5.00 944367.12 22.66
NOx3.80 5.00 68432.40 20.00 1368648.00 32.85
PM 0.79 10.00 28278.00 50.00 1413900.00 33.93 PM 0.79 10.00 28278.00 50.00 1413900.00 33.93
SOx 0.79 10.00 28278.00 50.00 1413900.00 33.93 Sox 0.79 10.00 28278.00 10.00 282780.00 6.79
NOx 0.79 10.00 28278.00 50.00 1413900.00 33.93 Nox 0.79 10.00 28278.00 10.00 282780.00 6.79
Point source emissons Total kg/d 483.26 Point source emissons Total 477.00
-6.26
% reduction -1.29
Note: Sox, Nox were not considered in the 1st EC presentation.
Qty Unit Qty
in T/A in T/A
Fly ash 8666.00
Bottom ash 925.00
Fly Ash 16000.00 Fly Ash 4256.00
Tar 77000.00 Tar 730.00
Solid waste quantity 93000.00 TPA Solid waste quantity 14577.00 TPA
Difference between two options T/A 78423.00 TPA
% reduction 84.33
SL no Unit Fuel ParameterEmissions Emissions
Unit
Changed scenario
Fuel Parameter
Comparison of pollution load between two configurations
As per EC-1 vide J-11011/766/2008-IA II (I) dtd 30/08/10 & EC-2 vide J-11011/257/2013-IA II (I) dtd 31/03/15
1Captive Power
Plant
Blast furnace
gas Imported coal
Captive
Power Plant
Air pollution Point
sources
2
Producer Gas
Plant 15000
Nm3/hr
B grade coal
3Reheating
Furnace
Difference between two options kg/d
Blast furnace gas
NA
C grade coal
Producer Gas
Plant (5500
Nm3/hr)
C grade coal
Fuel Solid wasteSolid waste
Imported coal
Reheating
FurnaceFO
Reheating
FurnaceFO
1Captive Power
Plant
Blast furnace
gas
SL no Unit Fuel
Solid waste Point
sources
Present configuration Proposed configuration
Captive
Power Plant
Producer Gas
Plant (5500
Nm3/hr)
Reheating
Furnace
NA
NA
2
Producer Gas
Plant 15000
Nm3/hr
B grade coal
NA NA Blast furnace gas NA3