Project Procurement and Risk

download Project Procurement and Risk

of 200

Transcript of Project Procurement and Risk

  • 8/3/2019 Project Procurement and Risk

    1/200

    Chapter 12

  • 8/3/2019 Project Procurement and Risk

    2/200

    12.1 Plan Procurements

    12.2 Conduct Procurements

    12.3 Administer Procurements

    12.4 Close Procurements

  • 8/3/2019 Project Procurement and Risk

    3/200

    Project Procurement Managementincludes the processes to purchase or

    acquire the products, services, or resultsneeded from outside the project team toperform the work. This chapter presentstwo perspectives of procurement. The

    organization can be either the buyer orseller of the product, service, or resultsunder a contract.

  • 8/3/2019 Project Procurement and Risk

    4/200

    Project Procurement Management includesthe contract management and change

    control processes required to administercontracts or purchase orders issued byauthorized project team members.

  • 8/3/2019 Project Procurement and Risk

    5/200

    Project Procurement Management alsoincludes administering any contract issued byan outside organization (the buyer) that is

    acquiring the project from the performingorganization (the seller), and administeringcontractual obligations placed on the project

    team by the contract.

  • 8/3/2019 Project Procurement and Risk

    6/200

  • 8/3/2019 Project Procurement and Risk

    7/200

    Buyer The customer

    Seller Contractor; vendor; supplier external

    to the performing organization The terms and conditions of the contract

    become key inputs to many of the sellers

    processes

  • 8/3/2019 Project Procurement and Risk

    8/200

    Scope Baseline Requirements

    Documentation TeamingAgreements

    Risk Register Risk RelatedContractDecisions

    ActivityResourceRequirements

    ProjectSchedule

    Activity Cost

    Estimates Cost

    Inputs1 Tools andTechniques2 Outputs3

    Process 12.1

    Reference: Figure 12.2.PMBOK Guide 4th Ed

    Make-or-BuyAnalysis

    ExpertJudgment

    ContractTypes

    ___________

    9Procurement 2Planning

    ProcurementManagement

    Plan

    ProcurementStatementsof Work

    Make-or-BuyDecisions

    ProcurementDocuments

    Source

    SelectionCriteria

  • 8/3/2019 Project Procurement and Risk

    9/200

    Plan Procurements

    The process of documenting projectpurchasing decisions, specifying theapproach and identifying the potential sellers.

    It identifies those project needs which canbest be, or must be, met by acquiringproducts, services or results outside of the

    project organization, versus those projectneeds which can be accomplished by theproject team.

  • 8/3/2019 Project Procurement and Risk

    10/200

    Plan Procurements: Inputs

    1. Scope Baseline

    Scope statement. The scope statement containsthe product scope description, service

    description and result description and the list ofdeliverable and the acceptance criteria.

    WBS

    WBS Dictionary

  • 8/3/2019 Project Procurement and Risk

    11/200

    Plan Procurements: Inputs

    2. Requirements Documentation

    Requirements documentation may include:

    Important information about projectrequirements that is considered during planningfor procurements.

    Requirements with contractual and legalimplications that may include health, safety,security etc .

  • 8/3/2019 Project Procurement and Risk

    12/200

    Plan Procurements: Inputs

    3. Teaming Agreements

    Teaming agreements are legal contractualagreements between two or more entities to

    form a partnership or joint venture, or someother arrangement as defined by the parties.

    The agreement defines buyer-seller roles for

    each party.

  • 8/3/2019 Project Procurement and Risk

    13/200

    Plan Procurements: Inputs

    4. Risk Register

    5. Risk Related Contract Decisions

    6. Activity Resources Requirements

    7. Project Schedule

    8. Activity Cost Estimates

    9.

    Cost Performance Baseline10. Enterprise Environmental Factors

  • 8/3/2019 Project Procurement and Risk

    14/200

    Plan Procurements: Inputs

    10. Organizational Process Assets

    The organizational process includes

    Formal procurement policies, procedures and

    guidelines. Management systems that are considered in

    developing the procurement management plan andselecting the contract types to be used.

    An established multi-tier system of pre qualifiedsellers based on previous experience.

  • 8/3/2019 Project Procurement and Risk

    15/200

    Plan Procurements: Tools and

    Techniques1. Make-or-Buy Decision

    A make-or-buy decision is a generalmanagement technique used to determine

    whether particular work can be bestaccomplished by the project team or mustbe purchased from outside sources.

  • 8/3/2019 Project Procurement and Risk

    16/200

    Plan Procurements: Tools and

    Techniques2. Expert Judgment

    Expert technical Judgment will often be usedto assess the inputs from this process.

    Expert purchasing judgment can also beused to develop or modify the criteria thatwill be used to evaluate seller proposal.

  • 8/3/2019 Project Procurement and Risk

    17/200

    Plan Procurements: Tools and

    Techniques3. Contract Types

    The risk shared between the buyer and seller isdetermined by the contract type.

    All legal contractual relationships generally fallinto one of two broad families, either Fixed-Priceor Cost-reimbursable.

  • 8/3/2019 Project Procurement and Risk

    18/200

    Plan Procurements: Tools and

    Techniques Fixed Price Contracts

    This category of contracts involves setting afixed total price for a defined product or

    service to be provided. It further includesfollowing types based amount of risk involvedand amount of incentive included.

    Firm Fixed Price Contracts (FFP) Firm Fixed Incentive Fee contracts (FPIP)

    Fixed Price with Economic Price Adjustment Contracts(FP-EPA)

  • 8/3/2019 Project Procurement and Risk

    19/200

    Spectrum of risk (For contracts)

    CPPC CPFF CPIF FPI FFP

    Cost Plus FixedFee (CPFF)

    Cost PlusIncentive Fee(CPIF)

    Variable Sharing Ratio

    Firm Fixed Price

    0 100

    Cost PlusPercentage ofCosts (CPPC)

    100 0

    Fixed PriceIncentive (FPI)

    Seller RiskLOW HIGH

    Buyer RiskHIGH LOW

  • 8/3/2019 Project Procurement and Risk

    20/200

    Plan Procurements: Tools and

    Techniques Cost-reimbursable Contracts

    This category of contracts involves payments(Cost reimbursements) to the seller for all

    legitimate actual cost incurred for thecompleted work, plus a fee representingseller profit.

  • 8/3/2019 Project Procurement and Risk

    21/200

    Plan Procurements: Tools and

    Techniques Three of more common types of cost

    reimbursable in use are: Cost Plus Fixed Fee Contracts (CPFF)

    Cost Plus Incentive Fee Contracts(CPIF) Cost Plus Award Fee Contracts (CPAF)

  • 8/3/2019 Project Procurement and Risk

    22/200

    Plan Procurements: Outputs

    1. Procurement Management Plan

    The procurement management plan describes

    how the procurement will be managed fromdeveloping procurement document throughcontract closure.

  • 8/3/2019 Project Procurement and Risk

    23/200

    Plan Procurements: Outputs

    The procurement management plan caninclude guidance for types of contracts to beused, risk management issues etc

    A procurement management plan can formalor informal, can be highly detailed or broadlyfarmed, and is based on the needs of each

    project.

  • 8/3/2019 Project Procurement and Risk

    24/200

    Plan Procurements: Outputs

    2. Procurement Statement of Work

    The statement of work describes theprocurement item in sufficient detail to allow

    prospective sellers to determine if they arecapable of providing the products, services.

    3. Make-or-Buy Decisions

    4.

    Procurement Documents Procurement document is used to solicit

    proposals from prospective sellers.

  • 8/3/2019 Project Procurement and Risk

    25/200

    Plan Procurements: Outputs

    Common terms are used for different types ofprocurement documents and may includerequest for information (RFI), invitation for bid

    (IFB), request for proposal (RFP), request forquotation (RFQ) etc.

    5. Change Request

  • 8/3/2019 Project Procurement and Risk

    26/200

    9 3

  • 8/3/2019 Project Procurement and Risk

    27/200

    ProjectManagement

    PlanProcurementDocuments

    SourceSelection

    CriteriaQualifiedSeller List

    SellerProposals

    ProjectDocuments

    Inputs1 Tools andTechniques2 Outputs3

    Process 12.2

    Reference: Figure 12.4.PMBOK Guide 4th Ed

    BidderConferences

    ProposalEvaluationTechniques

    IndependentEstimates

    ExpertJudgment

    Advertising

    Internet

    Search

    9Procurement

    SelectedSellers

    ProcurementContractAward

    ResourceCalendars

    ChangeRequests

    ProjectManagement

    Plan UpdatesPro ect

    3Executing

  • 8/3/2019 Project Procurement and Risk

    28/200

    Conduct Procurement

    Conduct procurement is the process ofobtaining seller responses, selecting a sellerand awarding a contract.

    On major procurement items, the overallprocess of requesting responses from sellersand evaluating those responses can be

    repeated.

  • 8/3/2019 Project Procurement and Risk

    29/200

    Conduct Procurement

    A short list of qualified sellers can beestablished based on a preliminary proposal.

    A more detailed evaluation can then be

    conducted based on a more specific andcomprehensive requirements documentrequested from the sellers on the short list.

  • 8/3/2019 Project Procurement and Risk

    30/200

    Conduct Procurement: Inputs

    1. Project Management Plan

    2. Procurement Documents

    3. Source Selection Criteria

    4. Qualified Seller List

  • 8/3/2019 Project Procurement and Risk

    31/200

    Conduct Procurement: Inputs

    5. Seller Proposals

    6. Project Documents

    7. Make-or-Buy Decisions

    8. Teaming Agreements

    9. Organizational Process Assets

  • 8/3/2019 Project Procurement and Risk

    32/200

    Conduct Procurement: Tools and

    Techniques1. Bidder Conferences

    Bidder Conferences (sometimes calledcontractor conferences, vendor conferences)

    are meeting with all perspective sellers andbuyers prior to submittal of bid or proposal. Theyare used to ensure that all perspective sellershave a clear and common understanding of the

    procurement.

  • 8/3/2019 Project Procurement and Risk

    33/200

    Conduct Procurement: Tools and

    Techniques2. Proposal Evaluation Techniques

    On complex procurement, when sourceselection will be made based on seller

    responses to previously defined weightedcriteria, a formal evaluation review process willbe defined by the buyers procurement policies.

    The evaluation committee will make their

    selection for approval by management prior tothe award.

  • 8/3/2019 Project Procurement and Risk

    34/200

    Conduct Procurement: Tools and

    Techniques3. Independent Estimates

    For many procurement items, the procuringorganization may elect to either prepare its own

    independent estimates, or have an estimate ofcosts prepared by an outside professionalestimator, to serve as a benchmark on proposedresponses.

  • 8/3/2019 Project Procurement and Risk

    35/200

    Conduct Procurement: Tools and

    Techniques4. Expert Judgment

    5. Advertising

    Existing lists of potential sellers can often be

    expanded by placing advertisements in generalcirculation publications such as newspapers orin specially trade publications.

    6. Internet Search

  • 8/3/2019 Project Procurement and Risk

    36/200

    Conduct Procurement: Tools and

    Techniques7. Procurement Negotiations

    Negotiations clarify the structure, requirementsand other terms of the purchases so that mutual

    agreement can be reached prior to signing thecontract.

    Final contract language reflects all agreementsreached.

  • 8/3/2019 Project Procurement and Risk

    37/200

    Conduct Procurement: Outputs

    1. Selected Sellers

    The sellers selected are those sellers who havebeen judged to be in a competitive range based

    upon the outcome of the proposal or bidevaluation, and who have negotiated a draftcontract that will become the actual contractwhen award is made.

  • 8/3/2019 Project Procurement and Risk

    38/200

    Conduct Procurement: Outputs

    2. Procurement Contract Award

    A procurement contract is awarded to eachselected seller.

    The contract can be in the form of simplepurchase order or complex document.

    A contract is a mutually binding legal documentthat obligates the seller to provide the specified

    product or service and obligates the buyer tocompensate the seller.

  • 8/3/2019 Project Procurement and Risk

    39/200

    Conduct Procurement: Outputs

    3. Resource Calendars

    The quantity and availability of contractedresources and those dates on which each

    specific resource can be active or idle isdocumented.

    4. Change Requests

    5. Project Management Plan Updates

    6. Project Document Updates

  • 8/3/2019 Project Procurement and Risk

    40/200

    9 3

  • 8/3/2019 Project Procurement and Risk

    41/200

    ProjectManagement

    PlanProcurementDocuments

    ContractsPerformance

    ReportApprovedChangesReport

    WorkPerformanceInformation

    Inputs1 Tools andTechniques2 Outputs3

    Process 12.2

    Reference: Figure 12.4.PMBOK Guide 4th Ed

    ContractChange

    ControlSystem

    ProcurementPerformanceReview

    Inspection andAuditing

    PerformanceReporting

    PaymentsSystems

    9Procurement

    ProcurementDocumentation

    Org: Processassets Updates

    ChangeRequests

    ProjectManagementPlan Updates

    ____________

    3Executing

  • 8/3/2019 Project Procurement and Risk

    42/200

    Administer Procurement

    Administer procurement is the process ofmanaging procurement relationships,monitoring contract performance, and making

    changes and corrections as needed. Both the buyer and seller will administer the

    procurement contract for similar purposes.

    Each must sure that both parties meet theircontractual obligations and that their ownlegal rights are protected.

  • 8/3/2019 Project Procurement and Risk

    43/200

    Administer Procurement: Inputs

    1. Procurement Documents

    Procurement documents contain completesupporting records for administration of the

    procurement processes. This includes procurement awards and the

    statement of work.

    2. Project Management Plan

    3. Contracts

  • 8/3/2019 Project Procurement and Risk

    44/200

    Administer Procurement: Inputs

    4. Performance Report

    5. Approved Changes Requests

    Approved changes request can include

    modifications to the terms and conditions of thecontract including the procurement statement ofwork, pricing, and description of the products,services to be provided.

    6. Work Performance Information

  • 8/3/2019 Project Procurement and Risk

    45/200

    Administer Procurement: Tools and

    Techniques1. Contract Change Control System

    A contract change control system defines theprocess by which the procurement can be

    modified. It includes the paperwork, tracking systems,

    disputes resolution procedures, and approvallevels necessary for authorizing changes.

  • 8/3/2019 Project Procurement and Risk

    46/200

    Administer Procurement: Tools and

    Techniques2. Procurement Performance Review

    A procurement performance review is astructured review of the sellers progress todeliver project scope and quality, within cost and

    on schedule, as compared to the contract.

    3. Inspections and Audits Inspections and audits required by the buyer

    and supported by seller as specified in theprocurement contract can be conducted duringexecution of the project to verify compliance inthe sellers work process or deliverables.

  • 8/3/2019 Project Procurement and Risk

    47/200

    Administer Procurement: Tools and

    Techniques4. Performance Reporting

    5. Payment Systems

    6. Claims Administration

    7. Record Management System

  • 8/3/2019 Project Procurement and Risk

    48/200

    Administer Procurement: Outputs

    1. Procurement Documentation

    Procurement documentation includes, but notlimited to, the procurement contract with all

    supporting schedule, requested unapprovedcontract changes and approved changesrequests.

    Procurement documentation also includes any

    seller-developed technical documentation andother work performance information such as,deliverables, seller performance report etc.

  • 8/3/2019 Project Procurement and Risk

    49/200

    Administer Procurement: Outputs

    2. Organizational Process Assets Updates

    Elements of organizational process assets thatmay be updated include:

    Correspondence Payments Schedules and requests

    Seller performance evaluation documentation

    3. Change Requests

    4. Project Management Plan Updates

    9 3E i

  • 8/3/2019 Project Procurement and Risk

    50/200

    ProjectManagement

    PlanProcurementDocuments

    Inputs1 Tools andTechniques2 Outputs3

    Process 12.2

    Reference: Figure 12.4.PMBOK Guide 4th Ed

    ProcurementAudits

    NegotiationSettlement

    RecordManagementSystem

    9Procurement

    Close

    Procurements

    Org: Processassets Updates

    ______

    3Executing

  • 8/3/2019 Project Procurement and Risk

    51/200

    Close Procurement

    Close procurement is the process ofcompleting each procurement.

    It supports the close project or phase

    process, since it involves verification that allwork and deliverables were acceptable.

    The close procurement also involves

    administrative activities.

  • 8/3/2019 Project Procurement and Risk

    52/200

    Close Procurement

    Close procurements addresses each contractapplicable to the project or project phase.

    Early termination of a contract is a special

    case of procurement closure that result froma mutual agreement of both parties, from thedefault of one party, or for convenience of the

    buyer if provided for in the contract.

  • 8/3/2019 Project Procurement and Risk

    53/200

    Close Procurement: Inputs

    1. Project Management Plan

    2. Procurement Documentation

    To close the contract, all procurement

    documentation is collected, indexed and filled. This information can be used for the lesson

    learned information and as a basis forevaluating contractors for future contracts.

  • 8/3/2019 Project Procurement and Risk

    54/200

    Close Procurement: Tools and

    Techniques1. Procurement Audits

    The procurement audit is a structured review ofthe procurement process originating from the

    Plan procurement process through AdministerProcurements

    The purpose of a procurement audit is to identifysuccesses and failures that warrant recognition

    in the preparation or administration of otherprocurement contracts on the project.

  • 8/3/2019 Project Procurement and Risk

    55/200

    Close Procurement: Tools and

    Techniques2. Negotiated Settlement

    In all procurement relationships, the finalequitable settlement of all outstanding issues,

    claims, and disputes by negotiation is primarygoal.

    Whenever settlement can not be achievedthrough direct negotiation, some form of

    alternative dispute resolution (ADR) includingmediation or arbitration may be explored.

  • 8/3/2019 Project Procurement and Risk

    56/200

    Close Procurement: Outputs

    1. Closed Procurements

    2. Organizational Process Assets Updates

    Procurement File

    Deliverable Acceptance

    Lessons Learned Documentation

  • 8/3/2019 Project Procurement and Risk

    57/200

    Warranty

    Implied Warranty

    Act of sale implies:

    General fitness for use

    Fitness for special uses

    Express Warranty

    Beyond the mere act of the sale

    Seller makes specific representations

    P l ( P)

  • 8/3/2019 Project Procurement and Risk

    58/200

    Request For Proposal (RFP)

    The purpose of preparing a request forproposal is to state, comprehensively and indetail, what is required , from customer point

    of view, to address the identified need.

    58

    R F P l (RFP)

  • 8/3/2019 Project Procurement and Risk

    59/200

    Request For Proposal (RFP)

    A good RFP allows contractors or projectteam to understand what the customerexpects so that they can prepare a thorough

    proposal that will satisfy customers needsand requirements at a realistic price.

    59

    R F P l (RFP)

  • 8/3/2019 Project Procurement and Risk

    60/200

    Request For Proposal (RFP)

    60

    R F P l (RFP)

  • 8/3/2019 Project Procurement and Risk

    61/200

    Request For Proposal (RFP)

    61

    R F P l (RFP)

  • 8/3/2019 Project Procurement and Risk

    62/200

    Request For Proposal (RFP)

    Following are some guidelines for draftinga formal request for proposal to external

    contractors: An RFP must provide a statement of

    work. An SOW deals with the scope of theproject, outlining the tasks or workelements the customers wants thecontractor or project team to perform.

    62

    R F P l (RFP)

  • 8/3/2019 Project Procurement and Risk

    63/200

    Request For Proposal (RFP)

    The RFP must include the customerrequirements, which define specifications and

    attributes. Requirements cover size, quantity,color, weight, speed, and other physical oroperational parameters the contractors

    proposed solution must satisfy.

    63

    R F P l (RFP)

  • 8/3/2019 Project Procurement and Risk

    64/200

    Request For Proposal (RFP)

    The RFP should state that what deliverablesthe customer expects the contractors orproject team to provide. Deliverables are the

    tangible items that the contractor is to supply.

    64

    R F P l (RFP)

  • 8/3/2019 Project Procurement and Risk

    65/200

    Request For Proposal (RFP)

    The RFP should list any customer-supplieditems. For example, the RFP might state thatthe customer will supply a copy of its logo for

    use on the brochure.

    65

    R F P l (RFP)

  • 8/3/2019 Project Procurement and Risk

    66/200

    Request For Proposal (RFP)

    The RFP might stat that the approvalsrequired by the customer. For example, thehousing customer may want to review and

    approve the plans before construction isstarted.

    66

    R F P l (RFP)

  • 8/3/2019 Project Procurement and Risk

    67/200

    Request For Proposal (RFP)

    Some RFPs mention the type of contractthe customer intends to use. It could be

    fixed price, in which case the customer willpay the contractor a fixed amountregardless of how much the work actuallycosts the contractor.

    See figure on next slide.

    67

  • 8/3/2019 Project Procurement and Risk

    68/200

    Spectrum of risk (For contracts)

    CPPC CPFF CPIF FPI FFP

    Cost Plus FixedFee (CPFF)

    Cost PlusIncentive Fee

    (CPIF)

    Variable Sharing Ratio

    Firm Fixed Price

    0 100

    Cost PlusPercentage of

    Costs (CPPC)

    100 0

    Fixed PriceIncentive (FPI)

    Seller RiskLOW HIGH

    Buyer RiskHIGH LOW

    R t F P l (RFP)

  • 8/3/2019 Project Procurement and Risk

    69/200

    Request For Proposal (RFP)

    The RFP should stat the required schedulefor the completion of the project. It mightsimply stat that the house will complete within

    six months, or it may include more detailedschedule.

    69

    R t F P l (RFP)

  • 8/3/2019 Project Procurement and Risk

    70/200

    Request For Proposal (RFP)

    The RFP should provide instructions for theformat and contents of the contractorproposals.

    The RFP should indicate thedue datebywhich the customer expects potentialcontractors to submit proposals.

    70

    R t F r Pr p l (RFP)

  • 8/3/2019 Project Procurement and Risk

    71/200

    Request For Proposal (RFP)

    An RFP may include theevaluation criteria.These are criteria that the customer will useto evaluate proposals from competing

    contractors in order to select the one toperform the project.

    71

    R q st F r Pr p s l (RFP)

  • 8/3/2019 Project Procurement and Risk

    72/200

    Request For Proposal (RFP)

    In rare case an RFP will indicate the fundsthe customer has available to spend onproject.

    72

    BID/NO BID DECISION

  • 8/3/2019 Project Procurement and Risk

    73/200

    BID/NO BID DECISION

    Because the development and preparation ofa proposal takes time and can be costly,contractors interested in submitting a

    proposal in the response to an RFP must berealistic about the probability of beingselected as the wining contractor.

    73

    BID/NO BID DECISION

  • 8/3/2019 Project Procurement and Risk

    74/200

    BID/NO BID DECISION

    Evaluating whether to go forward with thepreparation of a proposal is some timereferred to as the bid/no-bid decision.

    74

    BID/NO BID DECISION

  • 8/3/2019 Project Procurement and Risk

    75/200

    BID/NO BID DECISION

    Some factors that contractor might considerin making a bid/no-bid decision are thefollowing:

    Competition. Which other contractors mightalso submit a proposal in response to theRFP?

    75

    BID/NO BID DECISION

  • 8/3/2019 Project Procurement and Risk

    76/200

    BID/NO BID DECISION

    Risk. Is there a risk that the project will beunsuccessful-technically and financially?

    Mission. Is the proposed project consistent

    with the contractors business mission?

    76

    BID/NO BID DECISION

  • 8/3/2019 Project Procurement and Risk

    77/200

    BID/NO BID DECISION

    Extension of capabilities. Would the proposedproject provide the contractor with anopportunity to extend and enhance its

    capabilities? Reputation. Has the contractor successfully

    completed projects for the same customer inthe past?

    77

    BID/NO BID DECISION

  • 8/3/2019 Project Procurement and Risk

    78/200

    BID/NO BID DECISION

    Customer funds. Does the customer reallyhave funds available to go forward with theproject?

    Proposal resources. Are appropriateresources available to prepare qualityproposal?

    78

    BID/NO BID DECISION

  • 8/3/2019 Project Procurement and Risk

    79/200

    BID/NO BID DECISION

    Project resources. Are appropriate resourcesavailable to perform the project if thecontractor is selected as the winner?

    79

    Developing A Wining Proposal

  • 8/3/2019 Project Procurement and Risk

    80/200

    Developing A Wining Proposal

    A proposal is selling document; it is not atechnical report.

    It is important to remember that the proposal

    process is competitive. A customer uses a request for proposal to

    solicit competing proposals from contractors.

    80

    Developing A Wining Proposal

  • 8/3/2019 Project Procurement and Risk

    81/200

    Developing A Wining Proposal

    In the proposal the contractor mustconvince the customer that the contractor

    Understands what the customer is lookingfor.

    Can carry out the proposed project.

    Will provide the greatest value to thecustomer.

    81

    Developing A Wining Proposal

  • 8/3/2019 Project Procurement and Risk

    82/200

    Developing A Wining Proposal

    Is the best contractor to solve the problem.

    Will capitalize on successful experience withprevious related projects.

    Will do the work professionally. Will achieve the intended results.

    Will satisfy the cutomer.

    82

    Developing A Wining Proposal

  • 8/3/2019 Project Procurement and Risk

    83/200

    Developing A Wining Proposal

    The preparation of proposal can be astraightforward task performed by a singleperson or it can be a resource intensive effort

    requiring a team of organization andindividuals.

    Developing a comprehensive proposal for alarge project should be treated as a projectitself.

    83

    Proposal Contents

  • 8/3/2019 Project Procurement and Risk

    84/200

    Proposal Contents

    Proposals are often organized into threesections:

    o Technical

    o Managemento Cost

    84

    Proposal Contents

  • 8/3/2019 Project Procurement and Risk

    85/200

    Proposal Contents

    Technical section

    The technical section should contain thefollowing elements:

    o Understanding the problem.o Proposed approach or solution.

    o Benefits to the customer.

    85

    Proposal Contents

  • 8/3/2019 Project Procurement and Risk

    86/200

    Proposal Contents

    Management section

    The objective of management section is toconvince the customer that the contractor can

    do the proposed work.

    86

    Proposal Contents

  • 8/3/2019 Project Procurement and Risk

    87/200

    Proposal Contents

    The management section contains thefollowing elements:

    o Description of work tasks.o Deliverables.

    o Project Schedule.

    o Project Organization.o Related Experience

    o Equipment and Facilities

    87

    Proposal Contents

  • 8/3/2019 Project Procurement and Risk

    88/200

    Proposal Contents

    Cost Section

    The objective of the cost section is toconvince the customer that contractors price

    for the proposed project is realistic andreasonable.

    88

    Proposal Contents

  • 8/3/2019 Project Procurement and Risk

    89/200

    Proposal Contents

    The cost section contains the followingelements:

    o Labor.

    o Materials.o Subcontractors and Consultants.

    o Equipments and Facilities.

    o Travel.

    89

    Proposal Contents

  • 8/3/2019 Project Procurement and Risk

    90/200

    Proposal Contents

    o Documentation.

    o Overhead.

    o Escalation

    o Contingency or Management Reserve.

    o Fee or Profit.

    90

    Proposal Submission And Follow Up

  • 8/3/2019 Project Procurement and Risk

    91/200

    Proposal Submission And Follow Up

    The customer RFPs will usually provideinstructions regarding

    o Due date, by which proposal must be

    submitted.o Name and address of the person to whom

    the proposal should be submitted.

    91

    Proposal Submission And Follow Up

  • 8/3/2019 Project Procurement and Risk

    92/200

    Proposal Submission And Follow Up

    Contractors must continue to be proactiveeven after the proposal is submitted.

    The contractor should call the customer to

    confirm that the proposal was received.

    92

    Customer Evaluation Of The

  • 8/3/2019 Project Procurement and Risk

    93/200

    Customer Evaluation Of The

    Proposals Customers evaluate contractors proposal in

    many different ways.

    Some customers initially look at the prices of

    the various proposals and select , forexample, only three lowest-priced proposalsfor further evaluation.

    93

    Customer Evaluation Of The

  • 8/3/2019 Project Procurement and Risk

    94/200

    Customer Evaluation Of The

    Proposals In large projects , customers create a

    proposal review team that uses a scorecardto determine whether each proposal meets all

    requirements in the RFP and to rank theproposal against predefined evaluationcriteria.

    94

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    95/200

    Procurement Cycle

    The procurement process can be effectivelypresented as a cycle outlining a series ofdesecrate steps .

    In practice there may be some iterationbetween certain steps and indeed the stepsmay be carried out in a different order.

    95

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    96/200

    Procurement Cycle

    Procurement Planning

    The procurement planning will be viewedfrom the buyers perspective, as the process

    of identifying what products and services arebest procured out side the projectorganization.

    96

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    97/200

    P ocu e e t Cyc e

    Procurement Planning

    This is the buy or make decision which is akey component of the execution strategy

    97

  • 8/3/2019 Project Procurement and Risk

    98/200

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    99/200

    y

    Procurement List The procurement list is developed from

    projects scope of work.

    From the procurement list the projectmanager must decide his execution strategyto buy or make.

    99

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    100/200

    y

    Procurement Schedule The procurement schedule is developed after

    the CPM network diagramand schedule Bar

    chartshave been produced but before theresource histogramsand cash flowstatementshave been considered.

    100

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    101/200

    y

    Procurement Schedule Order date = ES Lead Time JIT

    Where:

    ES (Start Date)

    JIT (just-in-time)

    101

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    102/200

    y

    Supplier and Vendor List All potential suppliers and vendors need to be

    identified and pre-qualified according to the

    project quality plan

    102

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    103/200

    y

    Supplier and Vendor List The buyer need to be satisfied that the

    supplier has the production and quality

    management systems to deliver the productto the required specification, qualitystandards and schedule.

    103

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    104/200

    y

    Invite to Tender Compile a bid package (enquiry document)

    for the suppliers to quote against.

    104

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    105/200

    y

    Invite to Tender The initial enquiry document is the basis for

    the contract, it should be progressively

    adjusted and marked up as more informationbecomes available.

    105

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    106/200

    y

    Tender Adjudication Scrutinize the quotations (Tenders), and

    compile a technical and commercial bid

    tabulation to ensure you are comparingApples with Apples

    106

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    107/200

    y

    Tender Adjudication Consider suppliers suggestions and negotiate

    to achieve the best price and conditions,

    while striving for a win-win arrangement .

    107

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    108/200

    y

    Tender Adjudication This process should take advantage of

    market conditions, but should also be govern

    by companys ethics policy.

    108

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    109/200

    y

    Raise the Order Comply with corporate standard terms and

    conditions of contract.

    The purchase order should be a stand alonedocument superseding all previousdocumentation and correspondence, andmust be formally accepted by the supplier.

    109

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    110/200

    y

    Raise the Order Where possible pass on any contractual

    requirements from client with a back to back

    agreement with suppliers.

    110

  • 8/3/2019 Project Procurement and Risk

    111/200

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    112/200

    Transport

    Always consider the different methods of

    transport. Where possible the products quality

    should be checked and confirmed beforeliving the factory.

    This particularly applies to items beingexported.

    112

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    113/200

    Insurance

    Consider placing the order for the

    transport and insuring yourself so that ifthere is a problem or claim you can dealwith the transport and insurancecompanies directly.

    113

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    114/200

    Receiving

    Checking the goods against delivery note,

    check the delivery note against the orderand the check the quality of productsagainst the required condition.

    114

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    115/200

    Receiving (Case)

    A project I was working on received to

    counter rotating gearboxes for an OffshoreSupply Vessel, but on inspection the werefound to both rotate the same way!Fortunately this was picked up by the

    receiving inspection which gave the shipyardtime to have the correct type shipped over.

    115

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    116/200

    Warehousing

    Store the delivered (Received) items for safe

    keeping and retrieval. Check if warehousing requires any special

    handling equipment and storage facilities.

    Issue the stock against the required internal

    requisition order.

    116

    Procurement Cycle

  • 8/3/2019 Project Procurement and Risk

    117/200

    Accounts (Last step of procurement cycle)

    The accounts should check the budget ,

    purchase order, invoice and delivery notefor variances before making payments.

    117

  • 8/3/2019 Project Procurement and Risk

    118/200

    E di i

  • 8/3/2019 Project Procurement and Risk

    119/200

    Expediting

    On a large project theexpeditor becomes the

    project managers eyesand ears as he takeson a criminalinvestigating approach.

    Monitoring & Control, Basic Concepts,

    Lecture by Mumtaz Meer

    Expediting

  • 8/3/2019 Project Procurement and Risk

    120/200

    Consider asking the following questions: Have you received the order?

    Is the order understood?

    What is your job number? Who is your project manager?

    Has the job been planned into your

    production system?(Show me)

    120

    Expediting

  • 8/3/2019 Project Procurement and Risk

    121/200

    Have the instructions been received byproject manager?

    Are their suitably qualified resourcesavailable?(Name them and showqualification)

    121

    Expediting

  • 8/3/2019 Project Procurement and Risk

    122/200

    Is the work progressing as planned?

    Are there any problem?

    Will you meet the contracted deliverydate?

    122

    Expediting

  • 8/3/2019 Project Procurement and Risk

    123/200

    By asking all these questions the expeditorbecomes an invaluable source of progressinformation giving early warning of any supply

    problems so that the project manager hastime to respond.

    123

    B2B

    P t

  • 8/3/2019 Project Procurement and Risk

    124/200

    Procurement

    B2B (business to business)procurement platforms are anew type of business facilityoffered by the internet.

    B2B market places are juston-line catalogues

    Monitoring & Control, Basic Concepts,

    Lecture by Mumtaz Meer

    B2B Procurement

  • 8/3/2019 Project Procurement and Risk

    125/200

    Sellers list their products with prices,specifications and delivery terms.

    Buyers scan the catalogues, place their

    orders electronically, and can even makepayment online

    125

    B2B Procurement

  • 8/3/2019 Project Procurement and Risk

    126/200

    The potential benefit for buyers includedramatically reducing procurementadministration costs and time, lower material

    prices, faster supply chains, and reducedinventory requirements.

    126

    B2B Procurement

  • 8/3/2019 Project Procurement and Risk

    127/200

    The benefit for the sellers include increasedsales volume, lower cost of making a sale,and reduced inventory requirements.

    127

    B2B Procurement

  • 8/3/2019 Project Procurement and Risk

    128/200

    The B2B procurement system are beingsuccessfully driven by large companies whoare collaborating on a market sector basis.

    128

    B2B Procurement

  • 8/3/2019 Project Procurement and Risk

    129/200

    For example, Boeing, Lockheed Martin, BAESystems, and Raytheon have combined toform a global B2B website for their

    industry.

    129

    B2B Procurement

  • 8/3/2019 Project Procurement and Risk

    130/200

    B2B procurement offers project managerthe opportunity to:

    Reduce transaction cost. Generate less paper work.

    Provide an economy of scale through

    consolidating purchasing. Reduce the level of unapproved Rough

    purchases.

    130

    B2B Procurement

  • 8/3/2019 Project Procurement and Risk

    131/200

    The project managers also needs to beaware of the associated risks of accessingthese global market.

    131

    B2B Procurement

  • 8/3/2019 Project Procurement and Risk

    132/200

    Although web browsing will identify a widerrange of products, if these are procuredfrom overseas there will be more links inthe supply chain and longer lead times.

    132

    Just in Time

  • 8/3/2019 Project Procurement and Risk

    133/200

    Just in Time is a procurementmanagement system that provides theproduction line with components as theyneed them.

    This will reduce stock levels and stockinvestment, but will also increase the risk

    of production disruption.

    133

    Just in Time

  • 8/3/2019 Project Procurement and Risk

    134/200

    Toyota cars developed the KanbanSystem, Which is known in the West asJust-in-Time (JIT).

    This was one of the most spectacularfeatures of the Toyota car productionsystem.

    134

    Just in Time

  • 8/3/2019 Project Procurement and Risk

    135/200

    The Toyota system created a greaterattention to both the customer who couldorder their special car with out extra cost,and the worker who was much moreinvolved in maintaining quality much moreaware and better educated than their

    western contemporaries

    135

    Just in Time

  • 8/3/2019 Project Procurement and Risk

    136/200

    The down side of JIT as that it makescompanies far more sensitive tointerruption

    136

  • 8/3/2019 Project Procurement and Risk

    137/200

  • 8/3/2019 Project Procurement and Risk

    138/200

    Project Risk Management includes theprocesses concerned with conducting riskmanagement planning, identification, analysis,responses, and monitoring and control on aproject; most of these processes are updatedthroughout the project.

    138

  • 8/3/2019 Project Procurement and Risk

    139/200

    The objectives of Project Risk Managementare to increase the probability and impact ofpositive events, and decrease the probabilityand impact of events adverse to the project.

    139

    Risk Management

  • 8/3/2019 Project Procurement and Risk

    140/200

    Risk Management is the act or practice ofdealing with risk.

    It includes planningfor risk, assessing

    (identifying and analyzing) risk issues,developing risk handlingoptions, andmonitoringrisks to determine how risks havechanged

    140

    Risk Management

  • 8/3/2019 Project Procurement and Risk

    141/200

    Proper risk management is proactive ratherthan reactive.

    Risk management is not a separate project

    office activity assigned to a risk managementdepartment, but rather it is one aspect ofsound project management.

    141

    Risk Management Process

  • 8/3/2019 Project Procurement and Risk

    142/200

    Risk Management includes several relatedactions involving risk:

    Risk Planning

    Risk Assessment Risk Handling

    Risk Monitoring

    142

  • 8/3/2019 Project Procurement and Risk

    143/200

    Process 11.18Risk 2Planning

  • 8/3/2019 Project Procurement and Risk

    144/200

    ProjectScopeStatement

    CostManagementPlan

    ScheduleManagement

    PlanCommunicationsManagementPlan

    Enterprise

    Inputs1 Tools andTechniques2 Outputs3RiskManagementPlan

    ____________

    PlanningMeetings andAnalysis

    ___________

    Reference: Figure 11.2.

    PMBOK Guide 4th Ed

  • 8/3/2019 Project Procurement and Risk

    145/200

  • 8/3/2019 Project Procurement and Risk

    146/200

  • 8/3/2019 Project Procurement and Risk

    147/200

    Process 11.28Risk 2Planning

  • 8/3/2019 Project Procurement and Risk

    148/200

    RiskManagementPlan

    Activity CostEstimates

    ActivityDurationEstimates

    Scope

    Baseline StakeholderRegister

    CostManagementPlan

    Inputs1 Tools andTechniques2 Outputs3Risk Register

    ___________

    _

    Reference: Figure 11.6.

    PMBOK Guide 4th Ed

    Documentation Reviews

    InformationGatheringTechniques

    ChecklistAnalysis

    AssumptionsAnalysis

    DiagrammingTechniques

    SWOT

    Anal sis

  • 8/3/2019 Project Procurement and Risk

    149/200

  • 8/3/2019 Project Procurement and Risk

    150/200

    Risk is a measure of the probability andconsequences of not achieving a defined

    project goal. Risk has two primary components for a given

    event:

    A probability of occurrence of that event. Impact of the event occurring (Amount at

    stake)

  • 8/3/2019 Project Procurement and Risk

    151/200

    Conceptually, risk for each event can bedefined as a function of likelihood and impact:that is,

    Risk= function of(Likelihood, Impact)

    151

  • 8/3/2019 Project Procurement and Risk

    152/200

    Risk Events or consequences that have theprobability of occurring during a project and that aremeasured by their impacts on the project

    Components Risk event Risk event probability Risk outcome or consequence

    (Amount at stake) Risk event status

    (Probability x amount at stake)

  • 8/3/2019 Project Procurement and Risk

    153/200

    Methodology defines approaches,tools, and data sources that might beused to perform risk management on theproject

    Roles & Responsibilities defines thelead, support, and risk managementteam membership for each type of actionin the plan

    Budget - $ Timing Describes how often the risk

    management process will be performedthroughout the project life cycle.

  • 8/3/2019 Project Procurement and Risk

    154/200

  • 8/3/2019 Project Procurement and Risk

    155/200

    Reporting formats - defines how theresults of the risk managementprocesses will be documented, analyzed,and communicated to the project team

    and stakeholders Tracking Documents all facets of risk

    activities and how the risk process will

    be audited

    155

    Risk Identification

  • 8/3/2019 Project Procurement and Risk

    156/200

    Risk identification includesdetermining which risk mayadversely affect the projectobjective and whatconsequences of each risk

    might be if they occur

    156

    Risk Identification

  • 8/3/2019 Project Procurement and Risk

    157/200

    The most commonapproachidentifying thesource of risk isbrainstorming.

    157

    Brainstorming

  • 8/3/2019 Project Procurement and Risk

    158/200

    158

    Risk Identification

  • 8/3/2019 Project Procurement and Risk

    159/200

    The project manager should involve the keyproject team members in identifying potentialsources of risk.

    Identifying things that would negativelyimpact achieving the project objectives.

    Historical information of past project alsohelpful in identifying possible risks.

    159

  • 8/3/2019 Project Procurement and Risk

    160/200

    Types

    Business (profit or loss) and insurable(loss)

    Known known Total certainty Known unknown Degree of uncertainty

    Unknown unknown Total uncertainty

  • 8/3/2019 Project Procurement and Risk

    161/200

    Categories External, unpredictable Regulatory,

    etc.

    External, predictable Market risks Internal, non-technical Management

    Technical Design

    Legal Contractual

    161

    Process 11.38Risk 2Planning

  • 8/3/2019 Project Procurement and Risk

    162/200

    Risk Register

    Risk

    ManagementPlan

    ProjectScopeStatement

    Organizational ProcessAssets

    ___________

    Inputs1 Tools andTechniques2 Outputs3Risk RegisterUpdates

    ____________

    Reference: Figure 11.8.

    PMBOK Guide 4th Ed

    RiskProbabilityand Impact

    Assessment

    Probabilityand ImpactMatrix

    Risk DataQualityAssessment

    RiskCategorization

    Risk Assessment

  • 8/3/2019 Project Procurement and Risk

    163/200

    Assessing each risk involves determining thelikelihood that the risk event will occurand

    the degree of impact the eventwill have onthe project objectives.

    163

    Risk Assessment

  • 8/3/2019 Project Procurement and Risk

    164/200

    Both of these factors can be assigned arating of High, Medium, or Low.

    Project manager, in consultation with

    appropriate team member who the mostknowledgeable about the potential risk,should determine a rating for each risk.

    164

    Risk Assessment

  • 8/3/2019 Project Procurement and Risk

    165/200

    A tool for assessingrisk is a riskassessment matrix.

    165

    Risk Response Planning

  • 8/3/2019 Project Procurement and Risk

    166/200

    Risk response planning involves developingan action plan to reduce the impact orlikelihood of each risk, establishing a triggerpoint for when to implement the actions toaddress each risk and assigningresponsibilities to specific individuals forimplementing each response plan.

    166

    Risk Response Planning

  • 8/3/2019 Project Procurement and Risk

    167/200

    A risk response plan can be to Avoidtherisk, Mitigatethe risk, or Acceptthe risk.

    A Contingency plan is a predefined set of

    actions that would be implemented, if riskevent occurs.

    167

  • 8/3/2019 Project Procurement and Risk

    168/200

    Mitigation(Corrective action)

    Avoidance

    (Prevention)

    Acceptance

    (Accept consequences)

    Transference

    (Shift Responsibility)

    Risk Monitoring

  • 8/3/2019 Project Procurement and Risk

    169/200

    Risk monitoring involves regular reviewing ofthe risk management matrix throughout theproject.

    It is important to evaluate all the risk todetermine if there are any changes to thelikelihood of occurrence or the potentialimpact of any of the risks.

    169

    Risk Monitoring

  • 8/3/2019 Project Procurement and Risk

    170/200

    170

  • 8/3/2019 Project Procurement and Risk

    171/200

  • 8/3/2019 Project Procurement and Risk

    172/200

    Process 11.48Risk 2

    Planning

  • 8/3/2019 Project Procurement and Risk

    173/200

    Risk Register

    Risk

    ManagementPlan

    CostManagementPlan

    ScheduleManagementPlan

    Organization

    al Process

    Inputs1 Tools andTechniques2 Outputs3Risk RegisterUpdates

    ____________

    Reference: Figure 11.11.

    PMBOK Guide 4th Ed

    DataGatheringand

    Representation Techniques

    QuantitativeRisk Analysisand Modeling

    TechniquesExpertJudgment

    ___________

  • 8/3/2019 Project Procurement and Risk

    174/200

  • 8/3/2019 Project Procurement and Risk

    175/200

  • 8/3/2019 Project Procurement and Risk

    176/200

  • 8/3/2019 Project Procurement and Risk

    177/200

    Strengths Weaknesses

    Opportunities Threats

    Internal

    External

    Build On Eliminate or Reduce

    MitigateExploit

  • 8/3/2019 Project Procurement and Risk

    178/200

    Probability

    Likelihood of occurrence. (Number of

    occurrences of an event divided by thetotal number of all possible occurrences)

  • 8/3/2019 Project Procurement and Risk

    179/200

    Statistics Mean Average of the values of events

    Mode Value which occurs most often

    Median Value in middle of the range ofordered values

    179

  • 8/3/2019 Project Procurement and Risk

    180/200

    Variance Average of the squared deviations from

    the mean

    Standard deviation Square Root ofthe Variance

    Range Values between upper &

    lower limits

    180

  • 8/3/2019 Project Procurement and Risk

    181/200

    Interviewing project stakeholders andsubject-matter experts to quantify theprobability and consequences of risks on

    project objectives The information needed depends upon the

    type of probability distributions that will beused

  • 8/3/2019 Project Procurement and Risk

    182/200

    Probability distribution (Method ofmoments) Calculates project rangeestimates

    Expected monetary value Probabilitytimes cost

    Three values low (a) , most likely (m),and high (b) with probabilities for each;used to calculate expected value

  • 8/3/2019 Project Procurement and Risk

    183/200

    Sensitivity Analysis determines whichrisks have the most potential impact on

    the project Decision Tree Analysis use of a

    diagram that describes a decision

    under consideration and theimplications of choosing one or anotherof the available alternatives

  • 8/3/2019 Project Procurement and Risk

    184/200

    Incorporates probabilities of risks andthe costs or rewards of each logical pathof events and future decisions

    Solving the decision tree indicates whichdecision yields the greatest expectedvalue when all the uncertain implications,

    costs, rewards, and subsequentdecisions are quantified

    184

  • 8/3/2019 Project Procurement and Risk

    185/200

    Three values with probabilities; used tocalculate expected values

    Optimistic Most likely Pessimistic

    e.g. Optimistic 0.2 x $ 100 K = $ 20 K

    Most Likely 0.6 x $ 130 K = $ 78 KPessimistic 0.2 x $ 180 K = $ 36 K

    Expected Value = $ 134 K

  • 8/3/2019 Project Procurement and Risk

    186/200

    Project A

    Project B

    0.5

    0.5

    0.6

    0.4

    0.7

    0.3

    Success

    Failure

    Success

    Failure

    What is the probability that Project B willbe selected and will be successful?

    Example

    Answer: 0.35

    High Demand

    P b bili 0 3

  • 8/3/2019 Project Procurement and Risk

    187/200

    Decide not to pursue

    $ 0

    Production Successful

    Probability = 0.7

    Probability =0.3

    $ 550,000

    Production Unsuccessful

    Probability = 0.3

    Terminate = - $ 200,000

    Decide to pursue

    Low Demand

    Probability = 0.7- $100,000

    Expect Value of Pursuing Project A0.7 x 0.3 x $ 550,000 = $ 115,500

    0.7 x 0.7 x $ 100,000 = $ 49,000

    0.3 x $ 200,000 = $ 60,000

    $ 6,500

    The expected value of Project A is $6,500. The expected value of

    not preceding is $0. Preceding is the lucrative option.

  • 8/3/2019 Project Procurement and Risk

    188/200

  • 8/3/2019 Project Procurement and Risk

    189/200

  • 8/3/2019 Project Procurement and Risk

    190/200

    Simulation Uses a model or copyof a system to analyze the behavior

    or performance of the system

  • 8/3/2019 Project Procurement and Risk

    191/200

    Monte Carlo Perform project many times to provide a

    statistical distribution of calculated results

    Uses results to quantify the risk of various

    schedule alternatives, different project strategies,different paths through the network, and individualactivities

    Can be used to assess the range of possible cost

    options

    191

    Process 11.5

    8Risk

    2Planning

  • 8/3/2019 Project Procurement and Risk

    192/200

    Risk Register

    RiskManagementPlan

    ____________

    Inputs1Tools andTechniques2 Outputs3

    Risk RegisterUpdates

    Risk RelatedContractDecisions

    ProjectManagement

    Plan UpdatesProjectDocumentUpdates

    ___________Reference: Figure 11.17.

    PMBOK Guide 4th

    Ed

    Strategies forNegativeRisks or

    ThreatsStrategies forPositiveRisks orOpportunities

    ContingentResponseStrategies

    ExpertJudgment

  • 8/3/2019 Project Procurement and Risk

    193/200

    Process 11.6

    8Risk

    4Monitoring& Control

  • 8/3/2019 Project Procurement and Risk

    194/200

    Risk Register

    RiskManagementPlan

    WorkPerformanceInformation

    PerformanceReports

    ____________

    Inputs1Tools andTechniques2 Outputs3

    Risk RegisterUpdates

    Organizational ProcessAssetsUpdates

    Change

    RequestsProjectManagementPlan Updates

    ProjectReference: Figure 11.19.

    PMBOK Guide 4th

    Ed

    RiskReassessment

    Risk Audits

    Variance andTrendAnalysis

    TechnicalPerformanceMeasurement

    ReserveAnalysis

    Stat s

  • 8/3/2019 Project Procurement and Risk

    195/200

  • 8/3/2019 Project Procurement and Risk

    196/200

    Hazard Prevention

    Likelihood Reduction

    Risk Avoidance Risk Transfer

    Contingency Planning

  • 8/3/2019 Project Procurement and Risk

    197/200

    Risk Exposure

    Confidence of the risk assessment

    Compound Risks

    The number of Risks

    Cost of Action

    Risk Reduction Leverage CostBenefit

  • 8/3/2019 Project Procurement and Risk

    198/200

    Spectrum of risk

    CPPC CPFF CPIF FPI FFP

    Cost Plus FixedFee (CPFF)

    Cost PlusIncentive Fee(CPIF)

    Variable Sharing Ratio

    Firm Fixed Price

    0 100

    Cost PlusPercentage ofCosts (CPPC)

    100 0

    Fixed PriceIncentive (FPI)

    Seller Risk LOW HIGH

    Buyer RiskHIGH LOW

  • 8/3/2019 Project Procurement and Risk

    199/200

    Direct property damage Insurance ofprincipal assets, e.g., equipment, materials,

    property, auto Indirect consequential loss Indirect loss

    suffered by third party, resulting from actions

    by the contractor

  • 8/3/2019 Project Procurement and Risk

    200/200

    Legal liability Design errors, public bodilyinjury, project-performance failure

    Personnel Bodily injury

    Wrap-up insurance All the aboveintegrated into one agreement usuallyprovided by the owner