ID Task Name Start Finish DurationAug 2014Apr 2014 May 2014 Jul 2014Jun 2014

23-3 27-725-520-4 15-6 24-813-4 20-7 10-84-527-4 13-718-5 17-88-6 22-61-66-4 29-611-530-3 6-7 3-8

1 10d04-04-201424-03-2014Project preparation – Dionex, M&M and Phadia

2 40d16-05-201424-03-2014Master Data management - Dionex

5 15d25-04-201407-04-2014Business Blueprint – Dionex, M&M & Phadia

6 1d28-04-201428-04-2014Report out of Blueprint/WOF – Dionex, M&M and Phadia

7 30d09-06-201429-04-2014Realization

8 30d20-06-201412-05-2014Final preparation – IST1, UAT, Training

9 30d01-08-201423-06-2014Cut-over - Dionex

10 1d04-08-201404-08-2014Go-Live Dionex

11 30d01-08-201423-06-2014Cut-over - Phadia

12 1d04-08-201404-08-2014Go-Live - Phadia

13 35d29-08-201414-07-2014Cut-over – M&M

14 1d01-09-201401-09-2014Go-Live – M&M

3 50d30-05-201424-03-2014Master Data management – M&M

4 30d02-05-201424-03-2014Master Data management – Phadia

Project preparation – Dionex, M&M and Phadia
Master Data management - Dionex
Business Blueprint – Dionex, M&M & Phadia
Report out of Blueprint/WOF – Dionex, M&M and Phadia
Realization
Final preparation – IST1, UAT, Training
Cut-over - Dionex
Go-Live Dionex
Cut-over - Phadia
Go-Live - Phadia
Cut-over – M&M
Go-Live – M&M
Master Data management – M&M
Master Data management – Phadia