Project Managent - Power Point

203
PROJECT MANAGEMENT 1

Transcript of Project Managent - Power Point

Page 1: Project Managent - Power Point

1

PROJECT MANAGEMENT

Page 2: Project Managent - Power Point

2

Presentation at CEPT UniversityTo

Post Graduate Students

byJay Pandya, P.E.

January - April 2012

Page 3: Project Managent - Power Point

3

PROJECT MANAGEMENT

CONTENT• Introduction

• Definition

• History

• Lifecycle

• Stakeholders and Their Roles

• Organization

• Delivery Alternates

Page 4: Project Managent - Power Point

4

PROJECT MANAGEMENT

CONTENT contd.

• Project Control

• Work Breakdown Structure

• Scope Management

• Budget and Cost Control

• Schedule Control

• Quality Control

Page 5: Project Managent - Power Point

5

PROJECT MANAGEMENT

CONTENT contd.

• Change Orders Management

• Documents Management

• Software

• Project Reporting

• Project Governance

• Risk Management

• Success Factors

Page 6: Project Managent - Power Point

6

INTRODUCTION

Page 7: Project Managent - Power Point

7

It’s the Law

Project Management Law #1

“A Capital Project is rarely installed on time, or within budget and the Owner is not happy with Quality of Design and Construction”

Page 8: Project Managent - Power Point

8

Introduction

• 90% of projects do not meet time/cost/quality targets.

• Only 9% of large, 16% of medium and 28% of small company projects were completed on time, within budget and delivered measurable business and stakeholder benefits*.

• There are many reasons for such failures. *Standish Group Chaos Report, 1995

Page 9: Project Managent - Power Point

9

Introduction contd.

As per a Major Accounting Firm survey of 252 organizations, technology is not the most critical factor. Inadequate project management implementation constitutes 32% of project failures, lack of communication constitutes 20% and unfamiliarity with scope and complexity constitutes 17%.

Page 10: Project Managent - Power Point

10

Introduction contd.

Accordingly 69% of project failures are due to lack and/or improper implementation of project management methodologies

Page 11: Project Managent - Power Point

11

DEFINITION

Page 12: Project Managent - Power Point

12

Definition

• Project , defined:

A Project is a Unique Endeavor with –

Page 13: Project Managent - Power Point

13

Definition

• Project , defined:

A Project is a Unique Endeavor with –

Defined Scope of Work

Page 14: Project Managent - Power Point

14

Definition

• Project , defined:

A Project is a Unique Endeavor with –

Defined Scope of Work

Specific Start and End

Page 15: Project Managent - Power Point

15

Definition

• Project , defined:

A Project is a Unique Endeavor with –

Defined Scope of Work

Specific Start and End

Defined Budget

Page 16: Project Managent - Power Point

16

Definition contd.

• Management – Discipline of :– Planning– Organizing– Securing– Managing Resources

• Process of using a series of Objectives to achieve specific goals

Page 17: Project Managent - Power Point

17

Definition contd.

• Project Management Challenges– Competing Demands for –

ScopeBudgetTimeQualityRisk

– Stakeholders with Differing Needs and Expectations

Page 18: Project Managent - Power Point

18

HISTORY

Page 19: Project Managent - Power Point

19

It’s the Law

Project Management Law #2

“A person that doesn’t learn from history is doomed to repeat it”

Page 20: Project Managent - Power Point

20

Page 21: Project Managent - Power Point

21

Project Management History

• The Great Pyramids of Giza – Completed – 2570 BC – Records show – Managers for each of the four faces – Responsible for overseeing their Completion (WBS)

• The Design is simple on the outside but complex on the inside

Page 22: Project Managent - Power Point

22

Page 23: Project Managent - Power Point

23

Page 24: Project Managent - Power Point

24

Project Management History contd.

• Great Wall of China – 208 BC – Qin Dynasty (221 BC – 206BC)

• Force was Organized into three Groups – Soldiers, Common People and Criminals

• Qin Shihuang ordered millions of people for this Project

Page 25: Project Managent - Power Point

25

Page 26: Project Managent - Power Point

26

• Taj Mahal – Construction took approximately 22 Years from 1631 to 1653.

• Approximately 22000 laborers and 1000 Elephants were used in construction of this monument.

Project Management History contd.

Page 27: Project Managent - Power Point

27

Page 28: Project Managent - Power Point

28

• Eiffel Tower – Entrance Arch for the World’s Fair – Constructed during 1887 – 1889 and was Inaugurated on March 31, 1889.

• Approximately 300 workers were involved. • 18,038 pieces of Steel and 2.5 m rivets were

required.

Project Management History contd.

Page 29: Project Managent - Power Point

29

Page 30: Project Managent - Power Point

30

• Gantt Charts – Developed by Henry Gantt 1917

• Worldwide Importance in 1920s • Used on the Hoover Dam Project Started in

1931 • Still being used today

Project Management History contd.

Page 31: Project Managent - Power Point

31

Page 32: Project Managent - Power Point

32

• Hoover Dam – 726.4 ft high • Second tallest Dam in USA • Five Years to Build – 1931 to 1936 • 3,250,000 cft. Of Concrete was used

Project Management History contd.

Page 33: Project Managent - Power Point

33

Page 34: Project Managent - Power Point

34

• Empire State Building – 102 Story Building • 1,250 ft. from Base to the Top Floor and

1472 ft. to the Antenna Spire • Excavation Started on January 22, 1930 • Steel and Masonry were Completed on

May 1, 1931 • Approx. 15 Months to erect.

Project Management History contd.

Page 35: Project Managent - Power Point

35

• Project Management in Modern sense began in the 1950s. Time and Motion Study, Work Study, Industrial Engineering etc.

Project Management History contd.

Page 36: Project Managent - Power Point

36

• American Association of Cost Engineers was formed in 1956 – Cost and Schedule Control

• Critical Path Method (CPM) was developed in 1957 – DuPont – Complex Process Plant – Turnaround – Shutdown and Restart

• Project Evaluation and Review Technique (PERT) – US Navy’s Polaris – 1958 – Polaris Mobile Submarine Launched Ballistic Missile Project

Project Management History contd.

Page 37: Project Managent - Power Point

37

LIFECYCLE

Page 38: Project Managent - Power Point

38

It’s the Law

Project Management Law #3

“The work expands to fill the time available ”

Page 39: Project Managent - Power Point

39

Lifecycle

• Program Study• Planning• Design / Engineering• Procurement• Construction• Commissioning & Closeout

Page 40: Project Managent - Power Point

40

Lifecycle contd.

• Program Study – – Define Owner Goals, needs– Scope Charter– Program Budget – Capital and Operating Costs– Program Schedule – Capital and Project Life– Financing Strategy– Risk Evaluation– Due Diligence – Go/No Go Decision

Page 41: Project Managent - Power Point

41

Lifecycle contd.

• Project Planning – – Scope Definition –

(Scope Statement at the highest level)– Concept Development– Project Delivery Strategy– Project Site & Infrastructure Plan

Page 42: Project Managent - Power Point

42

Lifecycle contd.

• Project Planning contd. –– Project Budget & Cash Flow Development– Develop Risk Management Strategy– Master Schedule Development– Financing Feasibility & Funding Resources– Regulatory review & Approval

Page 43: Project Managent - Power Point

43

COST Vs. TIMEOpportunities to control Cost and Schedule occur early in the project.

100%

Project Time0%

100%

Start

Op

po

rtu

nit

y to

In

flu

ence

Pro

ject

G

oal

s(C

ost

, Sch

edu

le, a

nd

Qu

alit

y)

Cash Flow

StrategicPlanning

TacticalImplementation/

Reactive Position

Complete

Lifecycle contd.

Page 44: Project Managent - Power Point

44

It’s the Law

Project Management Law #4

“The more you plan, the luckier you get”

Page 45: Project Managent - Power Point

45

Lifecycle contd.

• Design - Engineering– Design Criteria & Standards– Schematic Design – Process Standardization– Constructability Review– Value Engineering

Page 46: Project Managent - Power Point

46

Lifecycle contd.

• Design – Engineering contd.– Identify Long Lead Items– Input of Operation & Maintenance– Develop Detailed Design & Construction

Documents– Scope Control as Design Develops (Scope

Creep)– Periodic Progress Reports – Budget, Schedule,

Progress, Problems and Recommended Solutions

Page 47: Project Managent - Power Point

47

Lifecycle contd.

• Procurement– Contracting Strategy – Insure Adequate Competition– Bid Process – RFP, Pre-Bid Meetings, Bid

Submittal, Bid Evaluation, Negotiations, Contract Award

– Subcontract Evaluation & Subcontractor Bonding

Page 48: Project Managent - Power Point

48

Lifecycle contd.

• Procurement contd.– Long Lead Items Procurement Management– Monitoring of Consultant Contracts– Contract Compliance– Pre – Construction Meeting

Page 49: Project Managent - Power Point

49

Lifecycle contd.

• Construction– Pre-Construction Meetings– Subcontract Execution Plans– Shop Drawings & Submittal Requirements– Shop Drawings & Fabrication Management– Construction Schedule Development /

Monitoring

Page 50: Project Managent - Power Point

50

Lifecycle contd.

• Construction contd.– Quality Control & Assurance– Safety Planning & Monitoring– Cost Control & Budget Monitoring– Contractors Coordination

Page 51: Project Managent - Power Point

51

Lifecycle contd.

• Commissioning and Closeout

– Commissioning Planning

– Punch List Development

– Pressure / Loop / Equipment Function Testing

– Turnover Requirements

(such as Maintenance Procedures , As Built

Drawings, Catalogues, Spare Parts and

Warranties).

Page 52: Project Managent - Power Point

52

Lifecycle contd.

• Commissioning & Closeout contd. – Project Document Archive

– Regulatory Agencies Approvals– Closeout Audit

Page 53: Project Managent - Power Point

53

STAKEHOLDERS AND THEIR ROLES

Page 54: Project Managent - Power Point

54

It’s the Law

Project Management Law #5

“Too many cooks spoil the broth”

Page 55: Project Managent - Power Point

55

Stakeholders And Their Roles

• Stakeholders are those individuals and organizations that are actively involved in the Project and who influence the Project outcome

• Different Stakeholders have different Roles

Page 56: Project Managent - Power Point

56

Stakeholders And Their Roles

• Stakeholders include:– Owners– Operations & Maintenance– Financer– Specialty Consultants– Project Manager/Construction Manager– Architects– Engineers

Page 57: Project Managent - Power Point

57

• Stakeholders include contd.– Contractors– Subcontractors– Suppliers– Regulatory Agencies

Stakeholders And Their Roles contd.

Page 58: Project Managent - Power Point

58

Stakeholders And Their Roles contd.

• Each Stakeholder has Differing Needs and Expectations

Page 59: Project Managent - Power Point

Project Stakeholder Roles

59

Programing PlanningDesign &

Engineering Procurement Construction Commission &

Closeout

Owners X X X X X X Oper. & Maint X X X X

Financer X X Specialty

Consultants X X X X X X

PM / CM X X X X X Architects X X X X Engineers X X X X X

Contractors X X X Subcontractors X X

Suppliers X X X X Regulatory

Agencies X X X X

Page 60: Project Managent - Power Point

60

• Roles: – Owners

Program StudyPlanningDesign and EngineeringProcurementConstructionCommission and Closeout

Stakeholders And Their Roles contd.

Page 61: Project Managent - Power Point

61

Stakeholders And Their Roles Contd.

• Roles:– Operations and Maintenance

Design and EngineeringProcurementConstructionCommission and Closeout

Page 62: Project Managent - Power Point

62

Stakeholders And Their Roles Contd.

• Roles: – Financer

Program StudyPlanning

Page 63: Project Managent - Power Point

63

Stakeholders And Their Roles Contd.

• Roles: – Specialty Consultants

Program StudyPlanningDesign and EngineeringProcurementConstructionCommission and Closeout

Page 64: Project Managent - Power Point

64

Stakeholders And Their Roles Contd.

• Roles:

– Project Manager/Construction Manager

Planning

Design and Engineering

Procurement

Construction

Commission and Closeout

Page 65: Project Managent - Power Point

65

Stakeholders And Their Roles Contd.

• Roles: – Architects

Planning

Design and Engineering

Procurement

Construction

Commission and Closeout

Page 66: Project Managent - Power Point

66

Stakeholders And Their Roles Contd.

• Roles: – Engineers

PlanningDesign and EngineeringProcurementConstructionCommission and Closeout

Page 67: Project Managent - Power Point

67

Stakeholders And Their Roles Contd.

• Roles:– Contractors

ProcurementConstructionCommission and Closeout

Page 68: Project Managent - Power Point

68

Stakeholders And Their Roles Contd.

• Roles: – Subcontractors

ConstructionCommission and Closeout

Page 69: Project Managent - Power Point

69

Stakeholders And Their Roles Contd.

• Roles:– Suppliers

Design and EngineeringProcurementConstructionCommission and Closeout

Page 70: Project Managent - Power Point

70

Stakeholders And Their Roles Contd.

• Roles:– Regulatory Agencies

PlanningDesign and EngineeringConstructionCommission and Closeout

• Managing Stakeholders' Expectations – a Challenge – Conflicting Interests

Page 71: Project Managent - Power Point

71

ORGANIZATION

Page 72: Project Managent - Power Point

72

Page 73: Project Managent - Power Point

73

Organization

Management Functions – • Planning• Organizing• Leadership• Control

To Accomplish Project Goals And Objectives

Page 74: Project Managent - Power Point

74

Organization Contd.

Create An Organization Structure Which Includes –• Policies• Procedures• Reporting Patterns• Communication Channels

Page 75: Project Managent - Power Point

75

Organization Contd.

Organizations Like Any Complex System Are Hierarchical – Composed Of Lower Level To Higher Order Structures – • Technical Core Level• Organizational Level• Institutional Level

Page 76: Project Managent - Power Point

76

Organization Contd.

The Most Appropriate Organization Structure Depends On – • Project Goals• Type Of Project• Environment/Culture

Page 77: Project Managent - Power Point

77

Organization Contd.

• Organizations – – Project Organizations are Normally Part Of Larger

Organizations– Company Or Project Based Organizations– Different Levels and Types Of Organization

Structures– Every Stakeholder – Part Of The Project

Organization Structure– Defined By Roles, Responsibility And Authority

Page 78: Project Managent - Power Point

78

Organization Contd.

• Factors to be Considered In Developing An Organization Structure – – Single Point Of Accountability and Authority– Command Structure– Reporting Relationships– Communication– Coordination Among Stakeholders

Page 79: Project Managent - Power Point

79

Organization Contd.

• Factors to be Considered In Developing An Organization Structure contd. –– Culture– Functional v. Matrix– Constant State Of Flux– Resource Allocation– Formal/Informal

Page 80: Project Managent - Power Point

80

Organization Contd.

• Organization Structure Types & Responsibilities–– Owner/ Company Level– Project Level– Design / Engineering Level– Procurement Level

Page 81: Project Managent - Power Point

81

Organization Contd.

• Organization Structure Types & Responsibilities contd. –– Construction/Site Office– Subcontractor– Commissioning– Closeout

Page 82: Project Managent - Power Point

82

Organization Contd.

• Organization Structure At Company Level – Project Management Finance Design/Engineering Procurement Personnel

Page 83: Project Managent - Power Point

83

Organization Contd.

• Organization Structure At Company Level – Information System Project Control Business Development

Page 84: Project Managent - Power Point

84

DELIVERY ALTERNATES

Page 85: Project Managent - Power Point

Delivery Alternatives

DESIGN ENGINEERING PROCUREMENT

COMMISSIONINGCONSTRUCTION

85

Traditional Delivery

Page 86: Project Managent - Power Point

86

Delivery Alternatives contd.

• Traditional Delivery– No Overlap Between Phases– Owner’s Representative:

CoordinationMonitoring

– Architect / Engineer: InspectionCompliance with Contract Documents

Page 87: Project Managent - Power Point

87

Delivery Alternatives contd.

• Traditional Delivery– Single Prime Contractor with Subcontractors– Contracting Alternatives

Lump SumUnit PriceTime & Material

Page 88: Project Managent - Power Point

Delivery Alternatives contd.

DESIGN

ENGINEERING

PROCUREMENT

COMMISSIONING

CONSTRUCTION

88

Fast Track Delivery

Page 89: Project Managent - Power Point

89

Delivery Alternatives contd.

• Fast Track Delivery– Overlap Between Phases

Compresses TimeReduces Budget

– Owner as PM / CM or

– Consultant PM / CMAgentFixed Fee

Page 90: Project Managent - Power Point

90

Delivery Alternatives contd.

• Fast Track Delivery– Multiple Prime Contractors with

Subcontractors

– Contracting AlternativesMultiple Lump SumGMPUnit PriceTime & Material

Page 91: Project Managent - Power Point

Delivery Alternatives contd.

OWNER SCOPE & BUDGET DEVELPOMENT

DESIGN-BUILD CONTRACTOR

TRADITIONAL or FAST TRACK DELIVERY

91

Design Build Delivery

Page 92: Project Managent - Power Point

92

Delivery Alternatives contd.

• Design-Build Delivery– Owner Issues One Contract Only– Minimum Involvement of Owner after Scope

Development – Design-Build Contractor Responsible for All

Subsequent Phases– Design Benefits from Contractor’s Expertise

Page 93: Project Managent - Power Point

Delivery Alternatives contd.

PUBLIC OWNER

PRIVATE ORGANIZATION – SPVInvestor / Banker

Project Developer

Operations & Maintenance

FAST TRACK DELIVERY93

Public / Private Partnership Delivery (PPP)Partn

ership

Page 94: Project Managent - Power Point

94

Delivery Alternatives contd.

• Public Private Partnership (PPP) – Brings The Public And Private Sectors Together

As Partners In a Contractual Agreement For A Defined Period (Normally Asset Life)Public Sector Pays For Those ServicesRight To Generate Revenue From The Project

– Objectives – Increase The Availability Of InfrastructureGreater Efficiency – Lower Cost and Higher Level Of Service

Page 95: Project Managent - Power Point

95

Delivery Alternatives contd.

• PPP allows – – Private Financial Resources Available To Public

Sector– Private Sector Technical Expertise, Experience

And Efficiency Available To Public Sector– Project Related Risks Transferred To Private

SectorFinancialTechnicalOperational

Page 96: Project Managent - Power Point

96

Delivery Alternatives contd.

• PPP Formation – – Private Sector Forms A Special Company Known As

Special Purpose Vehicle (SPV) To – DevelopBuild OperateMaintenance

– SPV Usually Made up Of – Investor/Banker/Landing InstitutionEngineering and Construction CompanyOperation And Maintenance Compny

Page 97: Project Managent - Power Point

97

Delivery Alternatives contd.

• PPP– Benefits –

Project AccelerationCost Effective Design and ConstructionRisk And ResponsibilityUsers Rather Than Taxpayers Pay

– Potential Problems – Lack Of ControlsFear Of SPV Failing Or Not Meeting Service

Requirements

Page 98: Project Managent - Power Point

98

PROJECT CONTROL

Page 99: Project Managent - Power Point

99

It’s the Law

Project Management Law #13

“If you fail to plan… you are planning to fail”

Page 100: Project Managent - Power Point

Project Control

DEVELOP A PLAN

IMPLEMENT THE PLAN

ANALYZE PERFORMANCE

FORECAST FUTURE PERFORMANCE

REPORT VARANCES

100

UPD

ATE

PLAN

Page 101: Project Managent - Power Point

101

Project Control contd.

• Project Control: Keeping These Project Elements On Track – – Scope– Budget/Cost– Schedule– Financial

Page 102: Project Managent - Power Point

102

Project Control contd.

• Project Control Elements (Contd.) –– Quality– Risk– Change– Communication

• Project Control Begins With Planning And Ends With Project Closeout

Page 103: Project Managent - Power Point

103

WORK BREAKDOWN STRUCTURE

Page 104: Project Managent - Power Point

104

Work Breakdown Structure

• What it is:– Organized Hierarchical Representation Of The

Project Scope Broken-down Into Sufficient Detail To Support – BudgetingCost Estimating Cost ControlSchedule ControlAssignment of Roles And Responsibilities

Page 105: Project Managent - Power Point

105

Work Breakdown Structure contd.

• What it is contd.:– Method Of Reducing The Project Into Lower

Levels Of Greater Detail – Project Manager Should Have The Responsibility Of

Determining Number Of LevelsCore Team Should be Involved In Determining Number

Of LevelsNumber Of Levels Depend On The Size And

Complexity Of The Project

Page 106: Project Managent - Power Point

106

Work Breakdown Structure Contd.

• Work Breakdown Structure Development Approach – – Top-Down Approach –

Specify All Work Assignments To Complete The ProjectSpecify All Tasks To Complete Each AssignmentSubtasks/Activities To Complete Each TaskContinue This Process Until You Reach Adequate

Detail For The Entire Project

• Work Breakdown Structure Is A Backbone Of The Project Control Process

Page 107: Project Managent - Power Point

107

SCOPE MANAGEMENT

Page 108: Project Managent - Power Point

108

Scope Management

• Project Scope – – Work That Must Be Accomplished To Deliver A

Product With Specified Functions And Features – Main Points Of A Project Which Define

Projects’ Goals– All The Work And Only The Work Required To

Complete The Project SuccessfullyAccomplish Project ObjectivesAchieve The Goal

Page 109: Project Managent - Power Point

109

Scope Management contd.

• Project Scope Contd. –– Definition of Scope

Level of DetailClarity

– Technology IssuesExistence of Required TechnologyLicensing

– Site Issues

Page 110: Project Managent - Power Point

110

Scope Management contd.

• Scope Management Process – – Project Initiation– Scope Planning– Scope Definition– Scope Verification– Scope Change Control

Page 111: Project Managent - Power Point

111

Scope Management contd.

• Scope Management Process cont.– – Initiation Input –

Project DescriptionStrategic PlanSelection CriteriaHistorical Information

– Initiation Output – Charter – Project Description And Business Needs Being

AddressedIdentify The Project ManagerConstraints Assumptions

Page 112: Project Managent - Power Point

112

Scope Management contd.

• Scope Management Process cont.– – Planning Input – Same As Initiation– Planning Output –

Scope Statement – Project Justification, Description, Deliverables, Objectives

Supporting DetailsAssumptionsScope Management Plan

Page 113: Project Managent - Power Point

113

Scope Management contd.

• Scope Management Process cont.– – Scope Definition Input –

Output Received From Planning Statement Supporting Details, Assumptions and Management Plan

– Scope Definition Output –Work Breakdown StructureScope Statement Update

Page 114: Project Managent - Power Point

114

Scope Management contd.

• Scope Management Process cont.– – Scope Verification Input –

Project StatusDocumentationWork Breakdown StructureScope StatementProject Plan

– Scope Verification Output – Formal Acceptance Of The Project

Page 115: Project Managent - Power Point

115

Scope Management contd.

• Scope Management Process cont.– – Scope Change Control –

Scope CreepContingency ManagementCorrective ActionLessons LearnedAdjusted Baseline

Page 116: Project Managent - Power Point

116

BUDGET AND COST CONTROL

Page 117: Project Managent - Power Point

117

It’s the Law

Project Management Law #19

“Anything can be changed… until there is no time (or $$) left to change anything”

Page 118: Project Managent - Power Point

118

Budget And Cost Control

• Cost Estimate – – Program Level – Conceptual– Utilize Work Breakdown Structure Levels– Schematics– Value Management

Page 119: Project Managent - Power Point

119

Budget And Cost Control contd.

• Cost Estimate contd. –– Design Development– Construction Documents Level (Bid Documents)– Change Order Estimates– Special Estimates

Page 120: Project Managent - Power Point

120

Budget And Cost Control contd.

• Considerations In Cost Estimating –– Historical Data– Industry Standards– Lessons Learned – Economic Trends

Page 121: Project Managent - Power Point

121

Budget And Cost Control contd.

• Budget Preparation – – Top Down Process– Responsibility for Budget Development– Budget Development Issues

Past ExperienceLevel of Scope DetailFactors ConsideredEmerging Technologies

– Budget and Reality

Page 122: Project Managent - Power Point

122

Budget And Cost Control contd.

• Budget Preparation Contd. –– Sources Of Funds :

InternalExternal

– Availability from each SourceAmountTimingReliability

– Currency Exchange Rate Issues

Page 123: Project Managent - Power Point

123

Budget And Cost Control contd.

• Budget Preparation Contd. –– Different Budget Levels– Utilize Work Breakdown Structure Levels – Line Item Budgets– Historical Data– Contingency

Page 124: Project Managent - Power Point

124

Budget And Cost Control contd.

• Cost Control – – Cost Monitoring and Control – Bottom up

Process– Cost Management Plan– Cost Tracking– Comparison against The Baseline Estimate– Trending

Page 125: Project Managent - Power Point

125

Budget And Cost Control contd.

• Cost Control contd. –– Cost Updates– Estimated Cost To Complete– Accounting / Cost Control Software – Cost Reporting– Corrective Actions

Page 126: Project Managent - Power Point

126

SCHEDULE CONTROL

Page 127: Project Managent - Power Point

127

It’s the Law

Project Management Law #23

“Everything takes longer than you think”

Page 128: Project Managent - Power Point

128

Schedule Control

• Project Schedule – – Goal Definition vs. Timing– Define Major Scope Elements– High Order Schedule Considerations

Site AcquisitionConceptual Design DevelopmentProcurement IssuesConstruction PhaseCommissioning

Page 129: Project Managent - Power Point

129

Schedule Control contd.

• Scheduling Tools – – Activity List With Start And End Dates– Bar Chart Schedules– Arrow Diagramming Method (ADM)– Precedence Diagramming Method (PDM)– Line Of Balance(LOB)/Linear Scheduling

Method(LOM)– Location Based Scheduling

Page 130: Project Managent - Power Point

130

Schedule Control contd.

• Project Master Schedule

• Different Schedule Levels for Different Management Levels

• Design & Engineering Schedule

• Procurement Schedule

Page 131: Project Managent - Power Point

131

Schedule Control contd.

• Construction Schedule

• Commissioning & Closeout Schedule

• Integrated Project Schedule

• Base Line Schedule

Page 132: Project Managent - Power Point

132

Schedule Control contd.

• Pre-Bid Schedule

• Schedule Update

• Short Term Look-Ahead Schedules

• Detailed Schedule for Specific Project Area

Page 133: Project Managent - Power Point

133

Schedule Control contd.• Example: Conceptual Master Schedules

Page 134: Project Managent - Power Point

134

Schedule Control contd.

• Software

• Fundamental Requirements For Any Software

• Optional Requirements – Cost, Resource etc.

• Contract Requirements

• Implementation of Contract Requirements

Page 135: Project Managent - Power Point

135

It’s the Law

Project Management Law #29

“The 80 / 20 Rule: the first 80% of the work takes 20% of the time, but the last 20% of the

work takes 80% of the time”

Page 136: Project Managent - Power Point

136

QUALITY CONTROL

Page 137: Project Managent - Power Point

137

It’s the Law

Project Management Law #31

“You don’t get what you expect, you get what you inspect”

Page 138: Project Managent - Power Point

138

Quality Control contd.

• Quality Control – – Process Which Reviews All The Factors

Involved In The Project – Emphasis On – Elements Such As Controls, Job Performance, Integrity

Criteria, DocumentationCompetence Such As Knowledge, Experience,

Qualifications, SkillsSoft Elements Such As Organization Culture,

Motivation, Team Spirit, Confidence

– Inspect The Work Accomplished To Ensure Its Alignment With The Project Scope

Page 139: Project Managent - Power Point

139

Quality Control contd.

• Quality Control by Contractor:– Quality Control Program/Manual– Materials Testing– Inspections– Reports & Documentation

Page 140: Project Managent - Power Point

140

Quality Control contd.

• Quality Assurance by Owner:– Oversee Implementation Of Q/C Procedures– Inspection by Owner

You Get What You Inspect And Not What You Expect– Records review– Documentation review

• Collaboration Software

Page 141: Project Managent - Power Point

141

Quality Control

“There is never enough time to do it right…. but there is always time to do it over”

Page 142: Project Managent - Power Point

142

CHANGE ORDER MANAGEMENT

Page 143: Project Managent - Power Point

143

It’s the Law

Project Management Law #17

“If project content is allowed to change freely, the rate of change will exceed the rate of progress ”

Page 144: Project Managent - Power Point

144

Change Order Management

• Change Order – – Work that is Added Or Deleted From The

Original Contract Scope Of Work Which Alters The Contract Amount Or Completion Date

– Common to Most Projects – Prime Reason for The Project Budget And Schedule Overrun

– Change Orders Can Only Be Mitigated, They Cannot Be Eliminated

Page 145: Project Managent - Power Point

145

Change Order Management contd.

• Common Reasons For Change Orders –– Increase/Alteration Of Owner’s Needs– Omissions/ Errors In Contract Documents– Changes In Regulatory Requirements– Differing Site Conditions– Differing Work Performance Conditions

Page 146: Project Managent - Power Point

146

Change Order Management contd.

• Change Order Process – – Change Identification– Change Request By Owner/AE/Contractor– Contract Document Review & Scope

Identification– Change Estimate By The Contractor/AE/PM/CM– Change Order Proposal – Cost Amount & Time– Proposal Review – Negotiations – Determination – Change Order Approval/Denial

Page 147: Project Managent - Power Point

147

Change Order Management contd.

• Change Order Monitoring –– Periodic Review Of Contract– Change Order Log Containing –

Approved Change OrdersOutstanding But Waiting To Be ApprovedProposals Submitted But No Other Action TakenChanges Identified And Proposals In ProgressPotential/Disputed Change Orders

Page 148: Project Managent - Power Point

148

Change Order Management contd.

• Change Order Control –– Detailed Review of Scope At The Planning Stage– Clearly Define The Scope During The Planning Stage To

Avoid Any Ambiguity– Involvement Of Operations And Maintenance

Personnel During The Scope Development And Design Development And Construction Documents Stages

– Ensure Coordination Of Various Disciplines During Design Development And Construction Documents Stage

Page 149: Project Managent - Power Point

149

Change Order Management contd.

• Change Order Control contd. –– Review Of Contract Requirements By The Legal As

well As Technical Personnel– A Thorough Investigation Of Subsurface And Site

Conditions AS Well As Any Constraints– Conduct Meetings with Regulatory Agencies,

Determine Their Requirements And Incorporate Them Into Contract Requirements

– Conduct Pre-Bid And Pre Construction Meetings With Contractors And Review Contract Requirements In Detail

Page 150: Project Managent - Power Point

150

Change Order Management contd.

• Change Order Control Contd. –– Select Financially Sound And Experienced

Contractor– Implement Contract Requirements Strictly With

Respect To :SubmittalsChange Order ProposalsCoordination MeetingsProgress Reports

Page 151: Project Managent - Power Point

151

DOCUMENTS MANAGEMENT

Page 152: Project Managent - Power Point

152

It’s the Law

Project Management Law #37

“When the weight of the paperwork equals the weight of the aircraft, the plane is ready to fly”

Page 153: Project Managent - Power Point

153

Documents Management

• Documents Management – Record Keeping – – Backbone Of Successful Project Management Process– Tool For The Communication – Formal/Informal– During The Entire Project Period, All Stakeholders

Should Establish And Maintain Good, Accurate And Complete Records

– Easier To Maintain If Planned Properly With The Advancements In The Telecommunication And Photographic Industry

– Extremely Important Source For The Dispute Resolution

Page 154: Project Managent - Power Point

154

Documents Management contd.

• The Project Record Keeping System Should:– Identify The Documents Type– Utilize The Standard System– Establish Project Record Index For Quick

Document Retrieval – Preserve Records Daily For Each Project

Element

Page 155: Project Managent - Power Point

155

Documents Management contd.

• The Project Record–Keeping System Should Normally Consist Of:– Correspondence– Project Execution Plan– Project Procedures Manual– Budget Documents– Project Baseline Schedule

Page 156: Project Managent - Power Point

156

Documents Management contd.

• The Project Record–Keeping System Should Normally Consist Of:– Project Cost Estimate– Project Risk Assessment– Project Quality Control Plan– Project Procurement and Material Control Plan– Materials Purchase Orders and Delivery

Schedules

Page 157: Project Managent - Power Point

157

Documents Management contd.

• The Project Record–Keeping System Should Normally Consist Of:– Engineering Contract– Value Engineering Analysis– Engineering Drawing Log– Engineering Services Invoices– Project Cost and Schedule Reports

Page 158: Project Managent - Power Point

158

Documents Management contd.

• The Project Record–Keeping System Should Normally Consist Of:– Constructability Reviews– ROW Logs– Construction and/or Letters of Intent and Term

Sheets– Construction Contracts– Subcontracts

Page 159: Project Managent - Power Point

159

Documents Management contd.

• The Project Record–Keeping System Should Normally Consist Of:– Project Safety Plan– Project Security Plan– Construction Contract Invoices– Subcontractor Invoices– Meeting Minutes

Page 160: Project Managent - Power Point

160

Documents Management contd.

• The Project Record–Keeping System Should Normally Consist Of:– Daily Field Reports– Material Invoices– Change Orders– Commissioning Logs– Closeout And Warranty Reports

Page 161: Project Managent - Power Point

161

SOFTWARE

Page 162: Project Managent - Power Point

162

It’s the Law

Project Management Law #41

“GIGO”

Page 163: Project Managent - Power Point

163

Software

• Major Categories – – Engineering– Procurement– Planning And Control– Construction– Collaboration

Page 164: Project Managent - Power Point

164

Software

• Planning And Control – – Cost Engineering– Finance & Accounting– Scheduling– Resource Control– Bulk Material

Page 165: Project Managent - Power Point

165

Software

• Project Control Software Examples– Prima Vera– MS Project– ARTEMIS– Prologue

Page 166: Project Managent - Power Point

166

PROJECT REPORTING

Page 167: Project Managent - Power Point

167

It’s the Law

Project Management Law #43

“You can fool all of the people some of the time, and you can fool some of the people all

of the time, but you can’t fool all of the people all of the time”

Page 168: Project Managent - Power Point

168

Project Reporting

• Project Reporting Purpose – – Status – Communicate Progress Against Plan And

Highlight Any Variances– Coordination – Assist All levels Of Management

For Coordination– Corrective Action – Timely Information Could

Assist The Management In Taking Corrective Action And Avoid Disaster

Page 169: Project Managent - Power Point

169

Project Reporting contd.

• Status Reports – – ALL Management Levels Within Management– Level Of Detail And Frequencies Differ Depending

On The Management Level– Summary Reports And Less Frequent For The Top

Management– Action Oriented More Frequent (Weekly Or Daily)

And Detailed For The Team Members

Page 170: Project Managent - Power Point

170

Project Reporting contd.

• Status Reports Should Address – – Where Is The Project – Work Accomplished To

Date And During The Last Period– Where Should The Project Be – Compare The

Performance Against The Plan– How Do You Plan To Get There – Identification Of

Problem Areas And Recommended Corrective Actions

Page 171: Project Managent - Power Point

171

Project Reporting contd.

• Status Reports Should Address Contd. –– When Do You Plan To Get There – Schedule Of

Corrective Actions– Assistance Needed – Financial, Manpower,

Equipment or Any Other Assistance Required To Take Corrective Actions

– Overall Project – When And At What Cost

Page 172: Project Managent - Power Point

172

Project Reporting contd.

• Project Status Report Should Also Address –– Overall Project– Engineering– Procurement– Construction– Commissioning– Closeout

Page 173: Project Managent - Power Point

173

Project Reporting contd.

• Information Contained In The Project Status Report – – Project Identification– Financial – Approved Budget, Current Cost Paid

And Committed To Date, Estimated Cost to Complete And Total Estimated Cost

– Schedule – Major Milestone Information, Original And Current Approved, Projected Schedule Completion,

Page 174: Project Managent - Power Point

174

Project Reporting contd.

• Information Contained In The Project Status Report Contd. –– Progress Since Last Period And Major

Accomplishments– Approved Scope Changes– Issues– Plans For The Next Period– Assistance Needed– Lessons Learned

Page 175: Project Managent - Power Point

175

PROJECT GOVERNANCE

Page 176: Project Managent - Power Point

176

Project Governance

• Project Goals– Owner defined– Realistic– Adequately Communicated

• Accountability– Clear Definition of Roles and Responsibilities– Buy-in by Stakeholders

Page 177: Project Managent - Power Point

177

Project Governance contd.

• Stakeholders– Stakeholder Goals align with Project Goals– Appropriate Policies & Procedures– Project Control Tools

• Relationships– Defined by Responsibilities– Coordination of Contract Documents

Page 178: Project Managent - Power Point

178

Project Governance contd.

• Planning– Organization (Command Structure)– Resource Allocation– Coordination among Stakeholders– Government Regulations

• Monitoring– Design Stages & Procurement– Construction– Budget / Schedule

Page 179: Project Managent - Power Point

179

RISK MANAGEMENT

Page 180: Project Managent - Power Point

180

It’s the Law

Project Management Law #47

“If you don’t attack the risks, the risks will attack you”

Page 181: Project Managent - Power Point

181

Risk Management

• Identify Project Risk

• Assess Project Risk

• Mitigate Project Risk

Page 182: Project Managent - Power Point

182

Risk Management contd.

• Identify Risks– Planning Risks

Technical Feasibility of ConceptInsufficient Scope DefinitionAggressive Project ScheduleInaccurate / Overly Optimistic BudgetingFailure to account for Regulatory Requirements

Page 183: Project Managent - Power Point

183

Risk Management contd.

• Identify Risks contd.– Design & Engineering Risks

Coordination Among Engineering DisciplinesInsufficient Input from Operations & MaintenanceScope CreepConstructabilityControl of Design Budget & Schedule

Page 184: Project Managent - Power Point

184

Risk Management contd.

• Identify Risks contd.– Procurement Risks

Transparency of Contractor Selection ProcessMisevaluation of Prime or Sub ContractorsProper Contract Formation & ElementsLong Lead Item Procurement Issues

Page 185: Project Managent - Power Point

185

Risk Management contd.

• Identify Risks contd.– Construction Risks

Improper Mobilization Planning & ExecutionDiffering Site ConditionsAvailability of Skilled LaborSpecialized Construction Equipment IssuesInadequate Coordination of the TradesQuality Assurance / ControlChange Order Management

Page 186: Project Managent - Power Point

186

Risk Management contd.

• Identify Risks contd.– Construction Risks contd.

Rite of Way IssuesCommunity RelationsSafety ManagementSubcontractor / Supplier IssuesGrowth of Budget & ScheduleCommunication Issues

Page 187: Project Managent - Power Point

187

Risk Management contd.

• Identify Risks contd.– Commissioning & Closeout Risks

Adequacy of Commissioning PlanCommissioning Communication & CoordinationTimely & Accurate Development of Punch ListsAvailability of Specialized Commissioning CrewsContamination of Equipment During ConstructionIncomplete Punch List Execution Inaccurate As-Built Drawings & Process PlansIncomplete Documentation of Installed

Equipment

Page 188: Project Managent - Power Point

188

Risk Management contd.

• Assess Project Risks– Probability of Risk Occurrence– Evaluate Risk Impact on:

BudgetScheduleFunctionalityRegulatory ReviewRelationships

– Prioritize Risks for Resource Allocation

Page 189: Project Managent - Power Point

189

Risk Management contd.

• Mitigate Project Risks– Obtain Appropriate & Adequate Insurance– Develop Robust Information Flow

Comprehensive Reporting: Daily, Weekly & Monthly

Institutionalize Risk Awareness & Discussion

– Monitor Costs for Abnormal Trends

Page 190: Project Managent - Power Point

190

Risk Management contd.

• Mitigate Project Risks– Keep Schedules Current; Identify Anomalies– Develop Quality Control Systems– Monitor Safety Performance– Incentive Plans – Owner & Contractor Personnel– Proactive vs. Reactive

Page 191: Project Managent - Power Point

191

Risk Management contd.

• Mitigate Project Risks– Co-ordination during Design and Construction– Top Management Commitment– Competent Staff– Line Management Commitment– Contract Requirements Implementation

Page 192: Project Managent - Power Point

192

Risk Management contd.

• Conclusions– Pro-active rather than Reactive– Forward Looking– Open Communication

Page 193: Project Managent - Power Point

193

It’s the Law

Project Management Law #51

“Project Risk can never be eliminated, it can only be mitigated”

Page 194: Project Managent - Power Point

194

SUCCESS FACTORS

Page 195: Project Managent - Power Point

195

It’s the Law

Project Management Law #49

“Success depends on People, Procedures & Tools”

Page 196: Project Managent - Power Point

196

Success Factors

• Functionality

• Quality

• Budget

• Schedule

• No Residual Problems – Disputes

Page 197: Project Managent - Power Point

197

Functionality

• Implies performance consistent with Original Concept

• Requires complete and accurate communication among the Project Participants

Page 198: Project Managent - Power Point

Functionality• Performance consistent with Original Concept

198

How the Project Manager scoped

the Project

How the Engineer designed it

How the Procurement

Dept. ordered it

How the Contractor installed it

Page 199: Project Managent - Power Point

Functionality

What the Owner actually wanted

199

Page 200: Project Managent - Power Point

200

Functionality

• Communication:– Clear– Concise– Meets Participants’/Stakeholders’

expectations– Properly Documented

Page 201: Project Managent - Power Point

201

Assuring Project Success

• Organization & PM Team – Parent Organization / Culture– Customer Organization / Commitment– Qualification / Dedication of Team Members

• Planning– Goal Definition / Concept Development– Project Delivery Strategy– Project Resource Plan

Page 202: Project Managent - Power Point

202

Assuring Project Success

• Implementation

• Monitoring / Updating (all of above)

Page 203: Project Managent - Power Point

203

It’s the Law

Project Management Law #53

“Things always work out in the end…

…If they haven’t worked out yet, you’re not at the end”