Project Management Process for a Project
• Ensures effective flow of the project through out its existence
• These processes encompasses the tools and techniques involved in applying skills and capabilities in the knowledge areas
• Project Managers and their teams should carefully address each process and its constituent inputs and outputs
Process Groups• Initiating process group
• Planning process group
• Execution process group
• Monitoring and controlling process group
• Close out process group
Initiating process group• Define a new project or a new phase of an
existing project by obtaining authorization to start the project or phase
• Initial scope is defined and initial financial resources are committed
• Internal and external stake holders identified
• Includes the following project mgt processes
– Develop Project Charter
– Identify Stake Holders
–
Develop Project charter: Is a process of developing a document that formally authorizes a project or phase and documenting initial requirements that satisfy stakeholders need and expectations
InputProject statement of
workBusiness caseContractEnterprise
environmental factorsOrganisational process
assets
InputProject statement of
workBusiness caseContractEnterprise
environmental factorsOrganizational process
assets
OutputProject charter
Identify stakeholders: process of identifying all people or organizations impacted by the project and documenting relevant information regarding their interests, involvement and impact on the project success
Input Project charter Procurement documents Enterprise environmental
factors Organizational process
assets
OutputStakeholder register
Stakeholder management strategy
Planning Process Group
Consists of those processes performed to establish the total scope of the effort, define and refine the objectives and develop the course of action required to attain these objectives
Includes the project management process like
Develop project management plan : the process of documenting the actions necessary to define, prepare, integrate and coordinate all subsidiary plans Inputs
Project charter Output from planning
phases Enterprise environmental
factors Organizational process
assets
OutputProject management plan
Collect requirements : processes of defining and documenting the stakeholders need and to meet the objectives Inputs
Project charter Stakeholder register
OutputRequirements
documentation
Requirements management plan
Requirements traceability matrix
Define scope: process of developing a detailed description of the project and product
Inputs Project charter Requirements
documentation Organisational process
assets
OutputProject scope statement
Project document update
Create WBS: processes of subdividing project deliverable and project work into smaller, more manageable components Inputs
Project scope statement
OutputsWBS
WBS dictionary
Scope baseline
Project document updates
InputProject scope statementRequirements
documentationOrganisational process
assets
Define activities: the process of identifying the specific actions to be performed to produce the project deliverable Inputs
Scope baseline Enterprise environmental
facctors Organisational process
assets
OutputsActivity list
Activity attributes
Milestone list
Sequence activities: process of identifying and documenting relations hip among project activities
Inputs Activity list Activity attributes Milestone list Project scope statement Organisational process
assets
Outputs Project schedule network
diagrams
Project documentation updates
Estimate activity resources: the process of estimating the type and quantity of material, men, equipment or supplies required to perform each activity Inputs
Activity list Activity attributes Resource calender Enterprise environmental
factors Organizational process
assets
OutputsActivity resource
requirement
Resource breakdown structure
Project documentation update
Estimate activity durations: process of approximating the no of work periods required to complete individual activities with estimated resources
Inputs Activity list Activity attributes Activity resource requirements Resource calenders Project scope statement Enterprise environmental factors Organizational process assets
OutputsActivity duration
estimates
Project document update
Develop schedule: process of analysing activity sequences, durations, resource requirements,and schedule constraints to create the project schedule
Inputs Activity list Activity attributes Project schedule network dig Activity resource reqts Resource calender Activity duration estimates Project scope statement Enterprise environmental factors Organizational process assets
outputsProject schedule
Schedule baseline
Schedule data
Project document update
Identify stakeholders: process of identifying all people or organizations impacted by the project and documenting relevant information regarding their interests, involvement and impact on the project success
Input Project charter Procurement documents Enterprise environmental
factors Organizational process
assets
OutputStakeholder register
Stakeholder management strategy
Planning Process Group
Consists of those processes performed to establish the total scope of the effort, define and refine the objectives and develop the course of action required to attain these objectives
Includes the project management process like
Develop project management plan : the process of documenting the actions necessary to define, prepare, integrate and coordinate all subsidiary plans Inputs
Project charter Output from planning
phases Enterprise environmental
factors Organizational process
assets
OutputProject management plan
Collect requirements : processes of defining and documenting the stakeholders need and to meet the objectives Inputs
Project charter Stakeholder register
OutputRequirements
documentation
Requirements management plan
Requirements traceability matrix
Define scope: process of developing a detailed description of the project and product
Inputs Project charter Requirements
documentation Organisational process
assets
OutputProject scope statement
Project document update
Create WBS: processes of subdividing project deliverable and project work into smaller, more manageable components Inputs
Project scope statement
OutputsWBS
WBS dictionary
Scope baseline
Project document updates
InputProject scope statementRequirements
documentationOrganisational process
assets
Define activities: the process of identifying the specific actions to be performed to produce the project deliverable Inputs
Scope baseline Enterprise environmental
facctors Organisational process
assets
OutputsActivity list
Activity attributes
Milestone list
Sequence activities: process of identifying and documenting relations hip among project activities
Inputs Activity list Activity attributes Milestone list Project scope statement Organisational process
assets
Outputs Project schedule network
diagrams
Project documentation updates
Estimate activity resources: the process of estimating the type and quantity of material, men, equipment or supplies required to perform each activity Inputs
Activity list Activity attributes Resource calender Enterprise environmental
factors Organizational process
assets
OutputsActivity resource
requirement
Resource breakdown structure
Project documentation update
Estimate activity duration: process of estimating the number of work periods needed to complete the individual activity with the estimated resources Inputs
Activity list Activity attributes Resource calender Activity resource requirement Project scope statement Enterprise environmental
factors Organizational process assets
OutputsActivity duration
estimates
Project document updates
Develop schedule: process of analysing activity sequences, durations, resource requirements and schedule constraints to create project schedule
Input Activity list Activity attributes Project schedule network diagram Activity resource requirement Resource calender Activity resource estimates Project scope statement Enterprise environmental factors Organizational process assets
OutputProject schedule
Schedule baseline
Schedule data
Project doc update
Estimate costs: process of developing an approximation of the monetary resources needed to complete the project activities Inputs
Scope base lines Project schedule Human resource plan Risk register Enterprise environmental
factors Organizational process
assets
OutputsActivity cost estimates
Basis of estimates
Project doc updates
Determine budget: process of aggregating the estimated cost of individual activity or work packages to establish an authorized cost baseline Inputs
Activity cost estimates Basis of estimates Scope baseline Project schedule Resource calender Contracts Organizational process
assets
OutputsCost performance baseline
Project funding requirements
Project doc updates
Plan quality: process of identifying quality requirement and/or standards for the project and product, and documenting how the project will demonstrate compliance
Inputs Scope baseline Stakeholder register Cost performance
baseline Schedule baseline Risk register Enterprise environmental
factors Organizational process
assets
Outputs Quality management plan
Quality metrics
Quality checklists
Process improvement plan
Project doc update
Develop human resource plan: process of identifying and documenting human resource roles, responsibilities, and required skills, reporting relationships and creating a staff management plans Inputs
Activity resource requirement
Enterprise environmental factors
Organizational process assets
OutputsHuman resource plan
Plan communications: process of determining stakeholder information needs and defining a communication approach
Inputs Stakeholder register Stakeholder
management strategy Enterprise environmental
factors Organizational process
assets
OutputsCommunication
management plan
Project doc update
Plan risk management: process of defining how to conduct risk management activities of a project
Inputs Project scope statement Cost management plan Schedule management
plan Communications
management plan Enterprise environmental
factors Organizational process
assets
OutputsRisk management plan
Identify risks: process of determining which risks may affect the project and documenting their characteristics
Inputs Risk management plans Activity cost estimates Activity duration estimates Scope baseline Stakeholder register Cost management plan Schedule management plan Quality management plan Project documents Enterprise environmental factors Organizational process assets
OutputsRisk register
Perform qualitative risk analysis: process of prioritizing risk for further analysis or actions by assessing and combining their probability of occurrence and impact
Inputs Risk statement Risk management plan Project scope statement Organizational process
assets
OutputRisk register updates
Performing quantitative analysis: process of numerically analyzing the effect of identified risk on the projects overall objective Inputs
Risk register Risk management plan Cost management plan Schedule management
plan Organizational process
assets
Output Risk register updates
Plan risk responses: process of developing options and actions to enhance opportunities and reduce threats to project objective Inputs
Risk register Risk management plan
OutputRisk register updates
Risk related contract decisions
Project management plan update
Project doc update
Plan procurements: process of documenting project procurement decisions, specifying the approach and identifying potential sellers
Inputs Scope baseline Requirements documentation Teaming agreements Risk register Risk-related contract decisions Activity resource requirements Project schedule Activity cost estimates Cost performance baseline Enterprise environmental factors Organizational process assets
OutputsProcurement
management plan
Procurement statements of work
Make or buy decisions
Procurement documents
Source selection criteria
Change requests
Executing process group Coordinating people and resources Integrating and performing the activities During execution may require planning updates
and re-baselining Any variance in activity duration, changes in
resource productivity and availability, unanticipated risk affect project management plan/documents and require detailed analysis and develop appropriate project baselines
Large portion of budget spend in this process
Direct and mange project execution: process of performing the work defined in the project management plan to achieve project objective Inputs
Project management plan
Approved change requests
Enterprise environmental factors
Organizational process assets
Outputs Deliverables
Work performance information
Change requests
Project management plan updates
Project doc updates
Perform quality assurance: process of auditing the quality requirements and results from quality control measurements to ensure appropriate quality standards and operational definitions are used Inputs
Project management plan
Quality metrics Work performance
information Quality control
measurements
OutputOrganizational process
updates
Change request
Project management plan update
Project doc update
Acquire project team: process of confirming human resource availability and obtain the team necessary to complete project assignments
Inputs Project management
plan Enterprise environmental
factors Organizational process
assets
OutputProject staff assignments
Resource calender
Project management plan update
Develop project teams: process of improving competencies, team interactions and overall team environment to enhance project performance Inputs
Project staff assignments Project management
plan Resource calenders
OutputTeam performance
assessment
Enterprise environmental factors update
Manage project team: process of tracking team member performance, providing feedback, resolving issues and managing changes to optimize project performance
Inputs Project staff assignments Project management
plan Team performance
assessments performance reports Organizational process
assets
OutputEnterprise environmental
factors updates
Organizational process assets updates
Change requests
Project management plan updates
Distribute information: process of making relevant information to stakeholders as planned
Inputs Project management
plans Performance reports Organizational process
assets
OutputsOrganizational process
assets updates
Manage stakeholder expectations: process of communicating and working with stakeholders to meet their needs and addressing issues as they occur
Inputs Stakeholder register Stakeholder management
strategy Project management
paln Change log Issue log rganizational process
assets
OutputOrganizational process
assets updates
Change request
Project management plan update
Project doc update
Conduct procurement: process of obtaining seller responses, selecting seller and awarding a contract
Inputs Project management plan Procurement documents Source selection criteria Seller proposals Qualified seller list Project documents Make or buy decisions Teaming agreements Organizational process assets
OutputSelected sellers
Procurement contract award
Resource calendar
Change request
Project management plan update
Project doc update
Monitoring and controlling process group Project performance is observed and measured
regularly and consistently to identify variances from the project management plan
Controlling changes and recommending preventive actions in anticipation of possible problems
Monitoring the project activities against the project management plan and project performance baseline
Influencing the factors that would circumvent integrated change control so only approved changes are implemented
Monitor and control project work: process of tracking, reviewing and regulating the progress to meet the performance objectives defined in the project management plan
Inputs Project management
plan Performance Reports Enterprise environmental
factors Organizational process
assets
OutputChange request
Project management plan update
Project doc update
Perform integrated change control: process of reviewing all change requests, approving changes, and managing changes to the deliverables, organizational process assets, project document and project management plan Inputs
Project management plan
Work performance information
Change requests Enterprise environmental
factors Organizational process
assets
OutputChange request status
update
Project management plan updates
Project doc updates
Verify scope: process of formalizing acceptance of the completed project deliverables
Inputs Project management
plan Requirements
documentation Requirements
traceability matrix Validated deliverables
OutputAccepted deliverables
Change request
Project doc update
Control scope: process of monitoring the status of project and product scope and managing changes to the scope baseline Inputs
Project management plan
Work performance documentation
Requirements documentation
Requirement traceability matrix
Organizational process assets
OutputWork performance
measurements
Change request
Organizational process assets updates
Project management plan updates
Project doc updates
Control schedules: monitoring the status of projects to update project progress and managing changes to the schedule baseline
Inputs Project management
plan Project schedule Work performance
information Organizational process
assets
OutputWork performance
measurements
Change request
Organizational process assets update
Project management update
Project doc update
Control Costs: process of monitoring the status of project to update the project budget and managing the changes to the cost baseline Input
Project management plan
Project funding information
Work performance information
Organizational process assets
OutputWork performance
measurements
Budget forecast
Organizational process assets update
Change request
Project management plan update
Project doc update
Perform quality control: process of monitoring and recording the results of executing the quality activities to asses performance and recommend necessary changes
Inputs Project management plan Quality metrics Quality checklist Work performance
measurements Approved change
requests Deliverables Organizational process
assets
OutputQuality control
measurements
Validated changes
Validated deliverables
Organizational process assets updates
Change request
Project management plan update
Project doc update
Report performance: processes of collecting and disturbing performance information including status reports, progress measurements and forecasts
Inputs
• Project management plan
• Work performance information
• Work performance measurements
• Budget forecast
• Organisational assets
Outputs
• Performance reports
• Organisational assets update
• Change request
Monitor and Control risk: process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks and evaluating risk processes effectiveness through out the project
Inputs
• Risk register
• Project management plan
• Work performance information
• Performance reports
Outputs
• Risk register updates
• Organisational assets update
• Change request
• Project management plan updates
• Project doc updates
Administer procurement: process of managing procurement relationship, monitoring contract performance, making changes and corrections as needed
Inputs
• Procurement doc
• Project management plan
• Work performance information
• Performance reports
• Contracts
• Approved change requests
Outputs
• Procurement documentation
• Organisational process assets update
• Change request
• Project management plan updates
Closing Process Group • Consists of those processes performed to finalize all
activities across all project management groups to formally complete the project, phase or contractual obligations
• At project or phase closure the following may occur: • Obtain acceptance from the customer or sponsor
• Conduct post-project or phase-end review
• Record impact of tailoring to any process
• Document lessons learned
• Apply appropriate updates to organisation process assets
• Archive all project doc
• Close out procurement s
Close project or phase: process of finalising all activities across all of the management process groups to formally complete the project or phase
Inputs
• Project management plan
• Procurement documentation
Outputs
• Closed procurements
• Organisational process assets update
Close Procurements: process of completing each project procurement
Inputs
• Project management plan
• Acceped deliverables
• Organisational process assets
Outputs
• Final product, serivces or result transition
• Organisational process assets update