Project Management IV1021Fö5
description
Transcript of Project Management IV1021Fö5
![Page 1: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/1.jpg)
Project Management IV1021Fö5Project Management IV1021Fö5Risk Management Risk Management
![Page 2: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/2.jpg)
AgendaAgenda
Project RiskProject Risk Management The Risk Management Process
Goal: get an understanding of basic project risk management
Project RiskProject Risk Management The Risk Management Process
Goal: get an understanding of basic project risk management
![Page 3: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/3.jpg)
Project Project
A project is a temporary organisation, separate from, but strongly dependent of the organisation, (the ordinary organisation). A project has a fixed, well defined and controllable objective. A project has its own resources (time, money, personal etc).
All projects have three interrelated objectives: to 1 meet the budget, 2 finish on time, 3 meet specifications that satisfy the client.
A project is a temporary organisation, separate from, but strongly dependent of the organisation, (the ordinary organisation). A project has a fixed, well defined and controllable objective. A project has its own resources (time, money, personal etc).
All projects have three interrelated objectives: to 1 meet the budget, 2 finish on time, 3 meet specifications that satisfy the client.
![Page 4: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/4.jpg)
Project Project
A PROJECT is an organisational formwith a defined objectivelimited in resources and time.
Objectives
TimeResources
![Page 5: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/5.jpg)
Uncertainty Uncertainty
”It must be expected that something unexpected will happen”
Arisotle (384-322 BC)
”It must be expected that something unexpected will happen”
Arisotle (384-322 BC)
![Page 6: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/6.jpg)
Risk Risk
The chance that something happens that will have an impact on objectives. It is measured in consequence and likelihood. The consequences may be positive or negative
There is no human activity which does not have risks.
The chance that something happens that will have an impact on objectives. It is measured in consequence and likelihood. The consequences may be positive or negative
There is no human activity which does not have risks.
![Page 7: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/7.jpg)
Types of risks Types of risks
Dynamic risks: positive or negative outcome. Example marketing.
Static risks: negative outcome. Example fire, flood, computer virus.
Dynamic risks: positive or negative outcome. Example marketing.
Static risks: negative outcome. Example fire, flood, computer virus.
![Page 8: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/8.jpg)
Risk Management Risk Management
Risk Management: refers to the way in which risks faced by the business are dealt with. Risks may arise from the nature of the business operations and/or the way in which the business is financed.
The purpose of (Project) Risk Management is to minimize the risk of not achieving the objectives of the project.
Risk Management: refers to the way in which risks faced by the business are dealt with. Risks may arise from the nature of the business operations and/or the way in which the business is financed.
The purpose of (Project) Risk Management is to minimize the risk of not achieving the objectives of the project.
![Page 9: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/9.jpg)
After 9/11After 9/11
Increased focus on Risk Management and Security Management.
Enterprise Risk Management (ERM) is a system of managing risk across an entire company. It should be an integral part of the governance and management of the business.
Increased focus on Risk Management and Security Management.
Enterprise Risk Management (ERM) is a system of managing risk across an entire company. It should be an integral part of the governance and management of the business.
![Page 10: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/10.jpg)
Project Risk Management Project Risk Management
Risk Management assists project managers in setting priorities, allocating resources and implementing actions and processes that reduce the risk of the project not achieving its objectives.
Risk Management facilitates better decision making and better project outcomes.
Risk Management assists project managers in setting priorities, allocating resources and implementing actions and processes that reduce the risk of the project not achieving its objectives.
Risk Management facilitates better decision making and better project outcomes.
![Page 11: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/11.jpg)
Project Risk ManagementProject Risk Management
The Project Manager must ensure that: All significant risks are identified Identified risks are understood (likelihood
and consequences)Assessment is undertaken of individual
risks relative to other risksStrategies for treating risks are
established The process itself and the risk treatment
strategies are implemented cost-effectively
The Project Manager must ensure that: All significant risks are identified Identified risks are understood (likelihood
and consequences)Assessment is undertaken of individual
risks relative to other risksStrategies for treating risks are
established The process itself and the risk treatment
strategies are implemented cost-effectively
![Page 12: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/12.jpg)
The Risk Management Process
The Risk Management Process
AS/NZS 4360
![Page 13: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/13.jpg)
Establish the contextEstablish the context
The context is a framework in which all activities of a project takes place. Strategic Context
Relationship between the organisation(s) and their environment.
Organisational Context What is the organisation all about?
Risk Management Context This level focus on the project which the Risk
Management Process is being applied. Do we understand the project (goals, time frame etc.)?
Summary: Do we clearly understand what should be the role of risk management in the project?
The context is a framework in which all activities of a project takes place. Strategic Context
Relationship between the organisation(s) and their environment.
Organisational Context What is the organisation all about?
Risk Management Context This level focus on the project which the Risk
Management Process is being applied. Do we understand the project (goals, time frame etc.)?
Summary: Do we clearly understand what should be the role of risk management in the project?
![Page 14: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/14.jpg)
Risk Identification Risk Identification
The process of determining: What could happen?How could it happen?Why can it happen?
A risk which is not identified can not be treated
The process of determining: What could happen?How could it happen?Why can it happen?
A risk which is not identified can not be treated
![Page 15: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/15.jpg)
Risk Identification Risk Identification
Make a list of all potential risks and classify, for example:
Financial: inflation, currency deflation Legal: contracts (SLA), liability claims Technical: computer virus, hacking, loss
of data Personnel: accident, death, illness,
resignation Organisational: theft, property, ignorance Political: taxes, war, legislation, terrorism Natural: earth quaque, flood, storm
Make a list of all potential risks and classify, for example:
Financial: inflation, currency deflation Legal: contracts (SLA), liability claims Technical: computer virus, hacking, loss
of data Personnel: accident, death, illness,
resignation Organisational: theft, property, ignorance Political: taxes, war, legislation, terrorism Natural: earth quaque, flood, storm
![Page 16: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/16.jpg)
Risk IdentificationRisk Identification
Methods: Brainstorming Examination of previous similar projects Standard Questioners and Surveys
(sources: insurance companies) Scenario analysis Checklists Interviews and focus group discussions Personal inspections Work Breakdown Structure analysis
Methods: Brainstorming Examination of previous similar projects Standard Questioners and Surveys
(sources: insurance companies) Scenario analysis Checklists Interviews and focus group discussions Personal inspections Work Breakdown Structure analysis
![Page 17: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/17.jpg)
Risk Assessment Risk Assessment
Risk assessment is the overall process of risk analysis and risk evaluation. Its purpose is to develop agreed priorities from identified risks.
Risk assessment is the overall process of risk analysis and risk evaluation. Its purpose is to develop agreed priorities from identified risks.
![Page 18: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/18.jpg)
Risk Analysis Risk Analysis
The systematic use of available information to determine how often specific events may occur and the magnitude of their likely consequences.
Determine likelihood and consequence Two types of methods:
Qualitative: expresses in word form or in descriptive scales the likelihood and consequences of an event
Quantitative: using numerical values to determine likelihood and consequences
The systematic use of available information to determine how often specific events may occur and the magnitude of their likely consequences.
Determine likelihood and consequence Two types of methods:
Qualitative: expresses in word form or in descriptive scales the likelihood and consequences of an event
Quantitative: using numerical values to determine likelihood and consequences
![Page 19: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/19.jpg)
Risk AnalysisRisk Analysis
Likelihood How likely is the loss to occur? Rare Remote Likely Certain
What is the probability of this loss? .0 .1 .8 1.0
Likelihood How likely is the loss to occur? Rare Remote Likely Certain
What is the probability of this loss? .0 .1 .8 1.0
![Page 20: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/20.jpg)
Risk AnalysisRisk Analysis
Consequence: the outcome of an event or situation expressed quantitatively or qualitatively, being a loss, injury, disadvantage or a gain. If the loss occurred, how would it affect the
project?Financially?Operationally?The ability of the project to meet its
objectives?
Insignificant Minor Moderate Major Catastrophic
Consequence: the outcome of an event or situation expressed quantitatively or qualitatively, being a loss, injury, disadvantage or a gain. If the loss occurred, how would it affect the
project?Financially?Operationally?The ability of the project to meet its
objectives?
Insignificant Minor Moderate Major Catastrophic
![Page 21: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/21.jpg)
Risk EvaluationRisk Evaluation
Likelihood
Consequence
High
Low
Low High
Medium risk High risk
Low risk Medium risk
![Page 22: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/22.jpg)
Risk EvaluationRisk Evaluation
Consequence
Likelihood
Insignificant Minor Moderate Major CarastrophicCertain Medium Medium High High KillerLikely Low Medium Medium High HighRemote Low Medium Medium Medium HighUnlikely Low Low Medium Medium HighRare Low Low Low Medium Medium
![Page 23: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/23.jpg)
Risk Treatment Risk Treatment
Identify the options for reducing the likelihood or consequence for each risk
Determine potential benefits and costs of the options
Select the best options for the project Develop and implement a detailed Risk
Treatment Plan Make appropriate provisions in project
budgets
Identify the options for reducing the likelihood or consequence for each risk
Determine potential benefits and costs of the options
Select the best options for the project Develop and implement a detailed Risk
Treatment Plan Make appropriate provisions in project
budgets
![Page 24: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/24.jpg)
Risk Treatment Risk Treatment
Risk avoidance Possible?
Loss control options Reduce likelihood Reduce the expected consequence Transfer the risk to another entity
Contractual Insurance Joint ventures
Risk avoidance Possible?
Loss control options Reduce likelihood Reduce the expected consequence Transfer the risk to another entity
Contractual Insurance Joint ventures
![Page 25: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/25.jpg)
Monitoring and reviewMonitoring and review
Continuous monitoring and review of risks ensures new risks are detected and managed, and that treatment plans are implemented and progressed effectively.
Method Implement a review process as part of the
regular management meeting cycle. Undertake major reviews at significant
project phases and milestones.
Continuous monitoring and review of risks ensures new risks are detected and managed, and that treatment plans are implemented and progressed effectively.
Method Implement a review process as part of the
regular management meeting cycle. Undertake major reviews at significant
project phases and milestones.
![Page 26: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/26.jpg)
Communication and reporting
Communication and reporting
Senior managers need to understand the risks they face, and risk reports provide a complement to other project reports in developing this understanding.
MethodSubmit reports on a regular basis or as
required, as part of standard project reporting.
Senior managers need to understand the risks they face, and risk reports provide a complement to other project reports in developing this understanding.
MethodSubmit reports on a regular basis or as
required, as part of standard project reporting.
![Page 27: Project Management IV1021Fö5](https://reader036.fdocuments.in/reader036/viewer/2022062422/56813e24550346895da80288/html5/thumbnails/27.jpg)
Summary Summary
How do we define a project? What is a risk?How can we analyse risks?How can we treat risks? Questions?
How do we define a project? What is a risk?How can we analyse risks?How can we treat risks? Questions?