Project governance and introduction of management...
Transcript of Project governance and introduction of management...
1 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
Project governance and
introduction of management team
THE ADRIARadNet PROJECT
University of L’Aquila
E. Picciotti ,V. Colaiuda, F. Marzano
2 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
ADRIARadNet Work Plan
The overall project objective will be carried out through 7 WP,
each WP is subdivided into one or more actions:
WP0: Project preparation (DONE!!!)
WP1: Project management and coordination
WP2: Communication and dissemination
WP3: User-oriented requirements and guidelines for Adriatic
hydrometeorological decision support systems
WP4: Integrated system for Adriatic hydro-meteorological radar-
based monitoring and model-based forecasting
WP5: Design and implementation of Adriatic web-based
information network and data-sharing platform
WP6: Demonstration and assessment campaign in Italian central
Adriatic area
WP7: Demonstration and assessment campaign in Balkan southern
Adriatic area
3 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
WP Action Amount Start date End date Duration
1 1.1 170.000 OCT 2012 SEP 2014 24 Months
WP Action Amount Start date End date Duration
1 1.2 160.000 OCT 2012 SEP 2014 24 Months
Managements activities are performed during
the entire lifecycle of the project
WP1 Has two action
4 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
Deliverables for Management WP1
The foreseen meeting as write in AF::
- kick-off meeting in L'Aquila at month 1;
- first interim meeting in Tirana at month 6;
- progress meeting in Ancona at month 12;
- second interim meeting in Dubrovnik at month 18;
- final meeting in L'Aquila at month 24.
Deliverables: :
All meeting requires to write a report (minutes) that
to be submitted to IPA
5 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
• Efficient and effective management of the project to ensure all deliverables are met within the proposed timescale.
• To ensure that the necessary resources are made available to carry out the aims and objectives of the project.
• To coordinate communications internally within the Consortium, between the Consortium and IPA Managing Authority
Management and Coordination Objectives
6 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
General Assembly (Steering Committe)
Project Coordinator
WP1 Leader
WP3 Leader
WP4 Leader
WP5 Leader
WP6 Leader
WP2 Leader
All Partners
WP7 Leader
Management Team
LB FB7 FB6 LB FB1 FB2 FB3
Project Governance structure
To reach the objective the management governance
has been structured as shown below
Financial Team
7 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
The General Assembly shall consist of one representative of each Partner, the following decisions shall be taken by the General Assembly:
• Any technical change in the Application Form
• Any financial change in the Application Form
• Proposal to the European Commission for suspension of all or part of the Project
• Proposal to the European Commission for termination of the project and the Partnership agreement
The General Assembly shall not deliberate and decide validly, unless the majority (5/8) of its members are present or represented (quorum)
General Assembly role
General Assembly is the decision making boby of the Consortium
and assists the the Coordinator for technical and management issues
8 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
• Leadership of the consortium
• Oversee collaboration between partners
• Interaction with the IPA
• Oversee “Advertisement” of the project
• Resolve any kind of issues
• To solve the possible conflicts within the partners
• Verification of time schedule of the work
• Intermediary between IPA and the Partners
• Check real use of partner funds against plans
Project Coordinator role
9 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
• Design of Web-site, logo and brochures
• Internal and External communication
• Write all project and meeting report
• Provide all reports to IPA Managing Authority
• The day to day contact for any question of the
partners and support in reporting activities
• Responsible for the handling of funds received
by the IPA
Management team role
10 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
• Financial and administrative management
• Overseeing of all IPA regulations regarding
use of funds and administrative framework
• Has overview of the planned use of each
partner funds
• The day to day contact for any question of
the partners and support in financial activities
Financial Team role
11 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
Current Project Governance people
• Frank Marzano (CETEMPS, Project Coordinator)
• Valentina Colaiuda (CETEMPS, Management Team)
• Errico Picciotti (CETEMPS, Management Team)
• Roberto Olivieri (BEEP, Financial Team)
• Marcella Rezzolla (BEEP, Financial Team)
• Paolo Sala (BEEP, Financial Team)
12 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
• Design of Web-site, logo and brochures
• Internal and External communication
• Write all project and meeting report
• Provide all reports to IPA Managing Authority
• The day to day contact for any question of the
partners and support in reporting activities
• Responsible for the handling of funds received
by the IPA
Focus on Reports
13 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
REPORTING REQUIREMENTS
During the course of our project we must
submit to IPA:
1. Progress Report
2. Progress Project Report
3. Deliverables
14 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
1.Progress Report
WHEN: Each Final Beneficiaries can report their
expenditures whenever they want
The Progress Report is composed of:
• Activity Report that provides information on the activities
implemented in the related period of reporting,
• Financial Report which provides information on project’s
expenditure per budget lines and WP.
WHO: Each Final Beneficiaries, LB and FBn
HOW: both in electronic (by MIS) and paper format (to
FLCO)
15 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
Step for Reimbursement procedure
16 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
2.Progress Project Report
WHEN: on a six-monthly basis: by 30th April and by 31st
October
The Project Progress Report is composed of:
• Progress report detailing project activities as a whole,
achievement of outputs, results and deliverables produced
• Financial reporting regarding validated expenditures (DVE)
and the submitted applications for reimbursement (AR)
• Relevant enclosures as communication and publicity
documents, deliverables and so on…
WHO: Only Lead Beneficiaries, LB
HOW: both in electronic (by e-mail) and paper format (to
IPA-JTS premises)
17 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
3.Deliverables
• Each significant element of the project should
conclude with a deliverable which is the concrete output
and evidence of the work.
•A Deliverable may be a report, or an action such as the
construction of a prototype, the installation of a
demonstrator, the organisation of a conference with the
production of related proceedings, the publication of a
book, the completion of a specification, etc.
WHEN: Within the Project Progress Report (every six months)
WHO Only LB also those carried out by FBn
HOW: Each FBn send his deliverable to LB, then LB send
the deliverables in paper format to IPA-JTS premises
18 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
• Design of Web-site, logo and brochures
• Internal and External communication
• Write all project and meeting report
• Provide all reports to IPA Managing Authority
• The day to day contact for any question of the
partners and support in reporting activities
• Responsible for the handling of funds received
by the IPA
Focus on Web site and logo
19 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
About Project Website and logo......
20 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
Design of Web-site http://cetemps.aquila.infn.it/adriaradnet/
21 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
Partner Contact Section
partner to contact
22 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
Web-site reserved area
Reserved area
23 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
Web site: Reserved Area
In the reserved area you can find all relevant
documentations about ADRIARadNet:
1. Grand Agreement
2. General Conditions
3. Partnership Agreement
4. Funding Allocation Letter (FAL)
5. Application Form (AF)
6. Programme Management and Control Manual
7. Guideline for MIS and Procurement
8. Brochures and other dissemination material
9. Template for reporting and project change
10. Any deliverables submitted to IPA
11. Meeting Reports and related presentation
24 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
Official Logo
radar antenna
.
drop
.
adriatic map
.
25 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
Brochure
Have been carried out in close collaboration with
ABRUZZO REGION in 4 different languages
26 E. PICCIOTTTI THE ADRIARADNET PROJECT KICK-OFF MEETING
Thanks for your Attention
For more detail Please check the
Programme Management and Control Manual