Project Kick-off MeetingProfessor Robin Smith
Process Integration Limited
Manchester 17 December 2010
![Page 2: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/2.jpg)
History of the Project
• Background research and collaboration: EPSRC project (UK) in heat transfer intensification (2009 – 2011)
• Initiated by UNIMAN, PIL and CALGAVIN mid 2009• PIL assumed coordinating role (mid 2009)• Submitted to FP7-SME-2010-1 (Dec 2009)• Invitation to commence contract negotiations
(March 2010)• Negotiations completed end September 2010• Project commenced 1 December 2010
![Page 3: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/3.jpg)
Project Overview
Intensified Heat Transfer Technologiesfor Enhanced Heat Recovery - INTHEAT
Contract number: 262205
Starting date: 1 December 2010
Duration: 24 months
![Page 4: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/4.jpg)
Project Objectives• Enhancing our understanding of heat exchange under
fouling • Technical innovation for heat transfer intensification for
heat recovery • Proposing new materials of improved economic and
environmental performance as heat transfer media (with focus on advanced heat exchanger with polymer materials
• Combining enhanced heat transfer innovative design with process integration to achieve the synergy of novel technologies
• Demonstration of applicability and economic-environmental benefit of novel heat-transfer enhancement techniques and the new design methods proposed
• Effective technology transfer to the wide range academic and industrial communities
![Page 5: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/5.jpg)
Partners
• Process Integration Limited (PIL), UK• Cal Gavin Limited (CALGAVIN), UK• Akstionernoe Obshchestvo ‘Sodrugestvo-T’ (SODRU),
Ukraine• Makatec Apparate GmbH (MAKATEC), Germany• Oikos, svetovanje za razvoj, d.o.o. (OIKOS), Slovenia• The University of Manchester (UNIMAN), UK• University of Bath (UNIBATH), UK• Paderborn University (UPB), Germany• University of Pannonia (UNIPAN), Hungary• EMbaffle B.V. (EMBAFFLE), The Netherlands
![Page 6: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/6.jpg)
Work Package Structure
Demonstration
WP 1Analysis of intensified heat
transfer under fouling
WP 2Combined tube-side and shell-side heat exchanger
enhancement
WP 3Heat Exchangers made of
Plastic Materials
WP 4Design, retrofit and control of
intensified heat recovery networks
WP 5Putting into practice
WP 6Technology transfer
WP 7Management
RTD
Exploitation
Management
![Page 7: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/7.jpg)
Contract specific terms
• Duration of the project is 24 months• Commencement date: 1 December 2010• Maximum financial contribution by EC:
EUR 1,155,000• Pre-financing at the level of EUR 693,000
(minus Guarantee Fund EUR 57,750)• Reporting periods:
– P1 from month 1 to month 9– P2 from month 10 to the last month of the project
![Page 8: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/8.jpg)
Contract specific terms
• Applicable law: terms of GA, EC and EU acts related to FP7, Financial Regulation application to the general budget and other EC and EU law, and on subsidiary basis, the law of Belgium
• Communication with EC through the coordinator
![Page 9: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/9.jpg)
Contract specific terms
Review number
Tentative timing Planned venue of review
Comments, if any
1Mid-term review meeting to be done after Month 11
Brussels
RP1 (Month 9) + 75 days Go/No-go decisions will be based on the performance of the developed materials by Month 9 Overall project review Monitoring WP progress and collaboration Risk analysis/contingency measures Corrective actions if neededWPs involved: WP1, WP2, WP3, WP6, WP7
2Final review meeting within Month 26
Manchester
Fine tuning of draft final reports (submitted in advance - 10 days berore) will be discussed Overall project review WP outcome (research, dissemination) review Exploitation WPs involved: WP4, WP5, WP6, WP7
![Page 10: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/10.jpg)
MilestonesMilestone number
Milestone name WP numbers Lead benefi ciary number
Delivery date from Annex
Comments
M1.1 Fouling mitigation research completed
WP1
7 UNIBATH
Month 12 Complete set of experiments
accomplished and mathematical models
verified
M2.1 Software modules implementing tube- and shell side enhancement developed
WP2
CALGAVIN
Month 18 Beta version tested
M3.1 Optimised design spiral wound plastic heat exchanger
WP3
MAKATEC
Month20 Experimental comparison of prototype with
standard type , and mathematical models
verified
M4.1 Retrofit methodology for heat exchanger networks prone to fouling deposition developed
WP4
6 UNIMAN
Month 20 Report submitted
![Page 11: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/11.jpg)
MilestonesM4.2 Software tool for
screening and analysis design and retrofit HEN options taking into account the intensified heat exchanger parameters
WP4
6 UNIMAN
Month 24 Beta version developed and tested, user guide printed
M5.1 Case studies for methodology application in chemical, refinery and food industries carried out
WP5
1 PIL
Month 24 Report submitted
M6.1 Training Workshop WP6 9 UNIPAN Month 18 Workshop completed
M6.2 Four Dissemination events attracting the European clusters carried out
WP6
9 UNIPAN
Month 8, 12, 18, 22
Four Dissemination event completed
![Page 12: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/12.jpg)
Project Deliverables
• 19 deliverables of them 7 confidential, 12 public
• Deliverables shall be submitted to EU within 45 days following the end of the planned date
• The coordinator will distribute the template for the project deliverables in January
• Lead participant: Coordinates the preparation of the Deliverables, ensures contribution from partners is prepared on time, ensures quality of Deliverable
![Page 13: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/13.jpg)
Project Deliverables
Need to be submitted using the electronic system
![Page 14: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/14.jpg)
Financial Guidelines
• Each SME (Contractor) should sign a sub-contracting agreement with RTD Partners (Sub-Contractors) who carry out the research work for them.
• The Coordinator will circulate draft sub-contracting agreement in next few days.
![Page 15: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/15.jpg)
Financial GuidelinesSuggested distribution of sub-contracting payments
in line with the DoW’s Tables A3 and B3
1,050,000
![Page 16: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/16.jpg)
Financial Guidelines
Will be circulated among Partners
![Page 17: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/17.jpg)
Financial Guidelines
• The pre-finance has been sent to the Coordinator, but due to technical issues had to be sent back to REA. The pre-finance is due to arrive in January-February.
• Pre-finance has been EUR 635,250 which is 635,250 / 1155000 = 0.55 of the overall requested EU contribution. Hence the prepayment will be distributed proportionally to the total EU contribution to each partner
![Page 18: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/18.jpg)
Financial Guidelines
Partner
Requested EU contribution,
€Prepayment
€
PIL 245,600 135,080
CALGAVIN 255,000 140,250
Sodrugestvo-T 232,000 127,600
MAKATEC 221,000 121,550
OIKOS 177,000 97,350
UNIMAN 6,800 3,740
UNIBATH 4,400 2,420
UPB 4,400 2,420
UNIPAN 8,800 4,840
EMBAFFLE 0 0
Total 1,155,000 635,250
Estimated prefinance distribution
![Page 19: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/19.jpg)
Project PM efforts
Activity type 1
PIL 2
CALGAVIN 3 SODRU 4
MAKATEC 5
OIKOS 6
UNIMAN 7
UNIBATH 8
UPB 9
UNIPAN 10 EMBAFFLE
Total
RTD/Innovation activities
WP1 1.5 4 2.5 0 0 3 14 2 6 0 33
WP2 1.5 4 2.5 0 0 14 1 0 1 0.5 24.5
WP3 0 0 0 11 0 0 0 20 0 0 31
WP4 2 3 2.5 0 0 11 9 4 9.5 0.5 41.5
Total Research 5 11 7.5 11 0 28 24 26 16.5 1 130
Demonstration activities
WP5 2 2 2.5 4 5 4 4 8 5 0.5 37
Total Demo 2 2 2.5 4 5 4 4 8 5 0.5 37
Consortium Management activities
Total Management 6
6
Other activities
WP6 0 2 1.5 0 3 3 4 0 5.5 0 19
Total other 0 2 1.5 0 3 4 4 0 4 0 18.5
Total 13 15 11.5 15 8 35 32 34 27 1.5 192
![Page 20: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/20.jpg)
Decision Making Mechanism
European Commission - Technical Officer
Exploitation and Dissemination Management
(WP 7)
Coordinator (WP 7)
Technical Management
(WP 7)
Steering Committee – decision making body(All Consortium Members)
Workpackage Management (WP Committees / WP Leaders)
![Page 21: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/21.jpg)
Consortium Agreement
An updated version of the Consortium Agreementwill be circulated at this meeting
Amendments: in Exclusions section
Please check carefully before we send the updated version to REA!
![Page 22: Project Kick-off Meeting](https://reader036.fdocuments.in/reader036/viewer/2022081503/5681311b550346895d978577/html5/thumbnails/22.jpg)
Future Meetings Planning
• June 2011 – your suggestions?
• Mid-term review meeting to be done after Month 11 (December 2011) – Brussels
• June 2012 – your suggestions?
• November 2012 – your suggestions?