PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

download PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

of 29

Transcript of PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    1/29

    Sl.No. Dscription Reference Amount (Rs.)

    1 PART - A :- Road Works Estimate Pt.-A Rs.69,431,690.00

    2 PART - B :- Building Works Estimate Pt.-B Rs.5,335,502.00

    3 PART -C :- Mechanical Works Estimate Pt.-C Rs.30,192,334.00

    Rs.104,959,526.00

    4PART -D :- Elctrical Works @ 10% of Estimated

    Cost of Sl. 1, 2, 3.Rs.10,495,952.60

    5 PART -E :- Computerization (Lumpsum) Rs.5,000,000.00

    6 Total of all Works (Sum of Sl. Nos.1 to 5) Rs.120,455,478.60

    7 Contingencies @ 2.8% of Sl.6 Rs.3,372,753.00

    8 Total Estimated Cost Rs.123,828,231.60

    9 Quality Control @ 1% of Sl.8 Rs.1,238,282.00

    10 Agency Charges @ 9% of Sl.8 Rs.11,144,541.00

    11 Estimated Cost of works (Sum of Sl: 8,9,10) Rs.136,211,054.60

    12PART -F :- Land Acquisition & Utility Shifting (

    Lumpsum)Rs.4,000,000.00

    13Total Estimated Cost of the project (Sum of Sl.

    11,12)Rs.140,211,054.60

    Say Rs.140,200,000.00

    For four nos. of sites (4x Rs. 14,02,00,000.00) Rs.560,800,000.00

    Executive Engineer, NH (BRD-R) Superintending Engineer, NH (P)

    O/o the C. E., PWD, NH(Works), Assam, O/o the C. E., PWD, NH(Works), Assam,

    Chandmari, Guwahati-3. Chandmari, Guwahati-3.

    Chief Engineer, PWD, NH (Works),

    Assam, Chandmari, Guwahati-3.

    (Rupees Fifty-six Crore, eight lakh) only.

    GOVERNMENT OF ASSAM

    PUBLIC WORKS (BUILDING & NH) DEPARTMENT

    General Abstract of Cost

    Installation of Four Weigh Bridges at Jorabat on NH-37, NH-44 between Badarpur-Silchar, NH-53 between

    Silchar-Jiribamin the State of Assam & NH-53 between Jirighat-Makru in the State of Manipur under

    Guwahati & Silchar NH Division in Assam.

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    2/29

    ANALYSIS B-2 (BUILDING WORKS)

    (A) Composite Rate for Assam Type Building Grade-I

    Sr. No. Description Rate Amount

    1 Basic Floor Area Rate 7,790.00Rs. 7,790.00Rs.

    2 Additional Rate for Steel Truss 450.00Rs. Per Sqm of Area 450.00Rs.

    3

    Additional Rate for Aluminum Window 700.00Rs. Per Sqm of Area 700.00Rs.

    4 Additional Rate for Weather Coat 1% of Basic Rate 77.90Rs.

    5 Additional Rate for plastic paint 1% of Basic Rate 77.90Rs.

    6 Additional Rate for Normal

    preparation of site 1% of Basic Rate 77.90Rs.

    7

    Additional Rate for Extra plinth height 75.00Rs. 75.00Rs.

    8 Additional Rate for Deeper

    Foundation 480.00Rs.

    Additional depth of

    1.0 M 480.00Rs.

    9 Additional rate for Ceramic tiles

    flooring 1,240.57Rs. Per Sqm of Area 1,240.57Rs.10 Extra Rate for Zypboard false ceiling (

    =1024-292.15) 731.85Rs. Per Sqm of Area 731.85Rs.

    11 Extra Rate for precoated roofing

    sheet (=(769.94-425.09)*1.65) 569.00Rs. Per Sqm of Area 569.00Rs.

    12 Extra Rate for precoated roofing

    sheet ridging (=(401.74-148.88)) 252.86Rs. Per Sqm of Area 252.86Rs.

    13 Extra for difference of cost of steel

    (=3*10.76*14.64) 472.58Rs. Per Sqm of Area 472.58Rs.

    14 Extra for differnce of cost of cement

    (=4*65) 260.00Rs. Per Sqm of Area 260.00Rs.

    Total 13,255.56Rs.

    (B) Sanitary Rate for Assam Type

    Building 8% of Basic Rate 623.20Rs.

    (C) Water Supply Rate for Assam Type

    Building 5% of Basic Rate 389.50Rs.

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    3/29

    (A) Composite Rate for Assam Type Building Grade-II

    Sr. No. Description Rate Amount

    1 Basic Floor Area Rate 7,790.00Rs. 7,790.00Rs.

    2 Additional Rate for Steel Truss 450.00Rs. Per Sqm of Area 450.00Rs.

    3

    Additional Rate for Aluminum Window 700.00Rs. Per Sqm of Area 700.00Rs.

    4 Additional Rate for Weather Coat 1% of Basic Rate 77.90Rs.

    5 Additional Rate for plastic paint 1% of Basic Rate 77.90Rs.

    6 Additional Rate for Normal

    preparation of site 1% of Basic Rate 77.90Rs.

    7

    Additional Rate for Extra plinth height 75.00Rs. 75.00Rs.

    8 Additional Rate for DeeperFoundation 480.00Rs.

    Additional depth of1.0 M 480.00Rs.

    9 Additional rate for Ceramic tiles

    flooring 1,030.99Rs. Per Sqm of Area 1,030.99Rs.

    10 Extra Rate for Zypboard false ceiling (

    =1024-292.15) 731.85Rs. Per Sqm of Area 731.85Rs.

    11 Extra Rate for precoated roofing

    sheet (=(769.94-425.09)*1.65) 569.00Rs. Per Sqm of Area 569.00Rs.

    12 Extra Rate for precoated roofing

    sheet ridging (=(401.74-148.88)) 252.86Rs. Per Sqm of Area 252.86Rs.

    13 Extra for difference of cost of steel

    (=3*10.76*14.64) 472.58Rs. Per Sqm of Area 472.58Rs.

    14 Extra for differnce of cost of cement

    (=4*65) 260.00Rs. Per Sqm of Area 260.00Rs.

    Total 13,045.98Rs.

    (A) Composite Rate for Assam Type Building Grade-III

    Sr. No. Description Rate Amount

    1 Basic Floor Area Rate 7,790.00Rs. 7,790.00Rs.

    2 Additional Rate for Steel Truss 450.00Rs. Per Sqm of Area 450.00Rs.

    3

    Additional Rate for Aluminum Window 700.00Rs. Per Sqm of Area 700.00Rs.

    4 Additional Rate for Weather Coat 1% of Basic Rate 77.90Rs.5 Additional Rate for Normal

    preparation of site 1% of Basic Rate 77.90Rs.

    6 Additional Rate for Deeper

    Foundation 480.00Rs.

    Additional depth of

    1.0 M 480.00Rs.

    7 Additional rate for Ceramic tiles

    flooring 877.73Rs. Per Sqm of Area 877.73Rs.

    8 Extra Rate for Zypboard false ceiling (

    =1024-292.15) 731.85Rs. Per Sqm of Area 731.85Rs.

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    4/29

    9 Extra Rate for precoated roofing

    sheet (=(769.94-425.09)*1.65) 569.00Rs. Per Sqm of Area 569.00Rs.

    10 Extra Rate for precoated roofing

    sheet ridging (=(401.74-148.88)) 252.86Rs. Per Sqm of Area 252.86Rs.

    11 Extra for difference of cost of steel

    (=3*10.76*14.64) 472.58Rs. Per Sqm of Area 472.58Rs.

    12 Extra for differnce of cost of cement

    (=4*65) 260.00Rs. Per Sqm of Area 260.00Rs.

    Total 12,739.82Rs.

    (A) Composite Rate for Assam Type Building Grade-IV

    Sr. No. Description Rate Amount

    1 Basic Floor Area Rate 7,790.00Rs. 7,790.00Rs.

    2 Additional Rate for Steel Truss 450.00Rs. Per Sqm of Area 450.00Rs.

    3

    Additional Rate for Aluminum Window 700.00Rs. Per Sqm of Area 700.00Rs.

    4 Additional Rate for Weather Coat 1% of Basic Rate 77.90Rs.

    5 Additional Rate for Normalpreparation of site 1% of Basic Rate 77.90Rs.

    6 Additional Rate for Deeper

    Foundation 480.00Rs.

    Additional depth of

    1.0 M 480.00Rs.

    7 Additional rate for Ceramic tiles

    flooring 754.61Rs. Per Sqm of Area 754.61Rs.

    8 Extra Rate for Zypboard false ceiling (

    =1024-292.15) 731.85Rs. Per Sqm of Area 731.85Rs.

    9 Extra Rate for precoated roofing

    sheet (=(769.94-425.09)*1.65) 569.00Rs. Per Sqm of Area 569.00Rs.

    10 Extra Rate for precoated roofing

    sheet ridging (=(401.74-148.88)) 252.86Rs. Per Sqm of Area 252.86Rs.

    11 Extra for difference of cost of steel

    (=3*10.76*14.64) 472.58Rs. Per Sqm of Area 472.58Rs.

    12 Extra for differnce of cost of cement(=4*65) 260.00Rs. Per Sqm of Area 260.00Rs.

    Total 12,616.70Rs.

    (A) Composite Rate for R.C.C. Building Grade-I ( G+1 ) Ground Floor

    Sr. No. Description Rate Amount

    1 Basic Floor Area Rate 9,150.00Rs. 9,150.00Rs.

    2 Additional Rate for Weather Coat 1% of Basic Rate 91.50Rs.

    3 Additional Rate for plastic paint 1% of Basic Rate 91.50Rs.

    4 Additional Rate for Normal

    preparation of site 1% of Basic Rate 91.50Rs.5

    Additional Rate for Extra plinth height 112.50Rs. 112.50Rs.

    6

    Additional Rate for Aluminum Window 700.00Rs. Per Sqm of Area 700.00Rs.

    7 Additional Rate for Pile Foundation 2,000.00Rs. Per Sqm of Area 2,000.00Rs.

    8 Additional Rate for Vitrified tiles

    flooring 1,240.57Rs. Per Sqm of Area 1,240.57Rs.

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    5/29

    9 Extra for difference of cost of steel

    (=6*10.76*14.64) 945.16Rs. Per Sqm of Area 945.16Rs.

    10 Extra for differnce of cost of cement

    (=7*65) 455.00Rs. Per Sqm of Area 455.00Rs.

    Total 14,877.73Rs.

    (B) Sanitary Rate for R.C.C. Building 8% of Basic Rate 732.00Rs.

    (C) Water Supply Rate for R.C.C. Type

    Building 5% of Basic Rate 457.50Rs.

    (A) Composite Rate for R.C.C. Building Grade-I ( G+1 ) First Floor

    Sr. No. Description Rate Amount

    1 Basic Floor Area Rate 7,610.00Rs. 7,610.00Rs.

    2 Additional Rate for Weather Coat 1% of Basic Rate 76.10Rs.

    3 Additional Rate for plastic paint 1% of Basic Rate 76.10Rs.

    4

    Additional Rate for Aluminum Window 700.00Rs. Per Sqm of Area 700.00Rs.

    5 Additional Rate for Vitrified tiles

    flooring 1,240.57Rs. Per Sqm of Area 1,240.57Rs.

    6 Extra for difference of cost of steel

    (=4.5*10.76*14.64) 708.87Rs. Per Sqm of Area 708.87Rs.

    7 Extra for differnce of cost of cement(=5.5*65) 357.50Rs. Per Sqm of Area 357.50Rs.

    Total 10,769.14Rs.

    (B) Sanitary Rate for R.C.C. Building 8% of Basic Rate 608.80Rs.

    (C) Water Supply Rate for R.C.C. Type

    Building 5% of Basic Rate 380.50Rs.

    (A) Composite Rate for R.C.C. Building Grade-I ( G+2 ) Ground Floor

    Sr. No. Description Rate Amount

    1 Basic Floor Area Rate 9,985.00Rs. 9,985.00Rs.

    2 Additional Rate for Weather Coat 1% of Basic Rate 99.85Rs.

    3 Additional Rate for plastic paint 1% of Basic Rate 99.85Rs.

    4 Additional Rate for Normal

    preparation of site 1% of Basic Rate 99.85Rs.

    5

    Additional Rate for Extra plinth height 112.50Rs. 112.50Rs.

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    6/29

    6

    Additional Rate for Aluminum Window 700.00Rs. Per Sqm of Area 700.00Rs.

    7 Additional Rate for Pile Foundation 2,000.00Rs. Per Sqm of Area 2,000.00Rs.

    9 Additional Rate for Vitrified tiles

    flooring 1,240.57Rs. Per Sqm of Area 1,240.57Rs.

    10 Extra for difference of cost of steel

    (=7*10.76*14.64) 1,102.68Rs. Per Sqm of Area 1,102.68Rs.

    11 Extra for differnce of cost of cement

    (=8*65) 520.00Rs. Per Sqm of Area 520.00Rs.

    Total 15,960.30Rs.

    (B) Sanitary Rate for R.C.C. Building 8% of Basic Rate 798.80Rs.

    (C) Water Supply Rate for R.C.C. Type

    Building 5% of Basic Rate 499.25Rs.

    (A) Composite Rate for R.C.C. Building Grade-I ( G+2 ) First Floor

    Sr. No. Description Rate Amount

    1 Basic Floor Area Rate 7,830.00Rs. 7,830.00Rs.

    2 Additional Rate for Weather Coat 1% of Basic Rate 78.30Rs.

    3 Additional Rate for plastic paint 1% of Basic Rate 78.30Rs.

    4

    Additional Rate for Aluminum Window 700.00Rs. Per Sqm of Area 700.00Rs.

    6 Additional Rate for Vitrified tiles

    flooring 1,240.57Rs. Per Sqm of Area 1,240.57Rs.

    7 Extra for difference of cost of steel

    (=5.5*10.76*14.64) 866.40Rs. Per Sqm of Area 866.40Rs.

    8 Extra for differnce of cost of cement

    (=6.5*65) 422.50Rs. Per Sqm of Area 422.50Rs.

    Total 11,216.07Rs.

    (B) Sanitary Rate for R.C.C. Building 8% of Basic Rate 626.40Rs.

    (C) Water Supply Rate for R.C.C. Type

    Building 5% of Basic Rate 391.50Rs.

    (A) Composite Rate for R.C.C. Building Grade-I ( G+2 ) Second Floor

    Sr. No. Description Rate Amount

    1 Basic Floor Area Rate 7,955.00Rs. 7,955.00Rs.

    2 Additional Rate for Weather Coat 1% of Basic Rate 79.55Rs.

    3 Additional Rate for plastic paint 1% of Basic Rate 79.55Rs.4

    Additional Rate for Aluminum Window 700.00Rs. Per Sqm of Area 700.00Rs.

    6 Additional Rate for Vitrified tiles

    flooring 1,240.57Rs. Per Sqm of Area 1,240.57Rs.

    7 Extra for difference of cost of steel

    (=4.5*10.76*14.64) 708.87Rs. Per Sqm of Area 708.87Rs.

    8 Extra for differnce of cost of cement

    (=5.5*65) 357.50Rs. Per Sqm of Area 357.50Rs.

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    7/29

    Total 11,121.04Rs.

    (B) Sanitary Rate for R.C.C. Building 8% of Basic Rate 636.40Rs.

    (C) Water Supply Rate for R.C.C. Type

    Building 5% of Basic Rate 397.75Rs.

    (A) Composite Rate for R.C.C. Building Grade-II ( G+2 ) Ground Floor

    Sr. No. Description Rate Amount

    1 Basic Floor Area Rate 9,985.00Rs. 9,985.00Rs.

    2 Additional Rate for Weather Coat 1% of Basic Rate 99.85Rs.

    3 Additional Rate for Normal

    preparation of site 1% of Basic Rate 99.85Rs.

    4

    Additional Rate for Extra plinth height 112.50Rs. 112.50Rs.

    5

    Additional Rate for Aluminum Window 700.00Rs. Per Sqm of Area 700.00Rs.

    6 Additional Rate for Pile Foundation 2,000.00Rs. Per Sqm of Area 2,000.00Rs.

    7 Additional Rate for Vitrified tiles

    flooring 1,030.99Rs. Per Sqm of Area 1,030.99Rs.

    8 Extra for difference of cost of steel

    (=7*10.76*14.64) 1,102.68Rs. Per Sqm of Area 1,102.68Rs.

    9 Extra for differnce of cost of cement(=8*65) 520.00Rs. Per Sqm of Area 520.00Rs.

    Total 15,650.87Rs.

    (A) Composite Rate for R.C.C. Building Grade-II ( G+2 ) First Floor

    Sr. No. Description Rate Amount

    1 Basic Floor Area Rate 7,830.00Rs. 7,830.00Rs.

    2 Additional Rate for Weather Coat 1% of Basic Rate 78.30Rs.

    3 Additional Rate for plastic paint 1% of Basic Rate 78.30Rs.4

    Additional Rate for Aluminum Window 700.00Rs. Per Sqm of Area 700.00Rs.

    6 Additional Rate for Vitrified tiles

    flooring 1,030.99Rs. Per Sqm of Area 1,030.99Rs.

    7 Extra for difference of cost of steel

    (=5.5*10.76*14.64) 866.40Rs. Per Sqm of Area 866.40Rs.

    8 Extra for differnce of cost of cement

    (=6.5*65) 422.50Rs. Per Sqm of Area 422.50Rs.

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    8/29

    Total 11,006.49Rs.

    (A) Composite Rate for R.C.C. Building Grade-II ( G+2 ) Second Floor

    Sr. No. Description Rate Amount

    1 Basic Floor Area Rate 7,955.00Rs. 7,955.00Rs.

    2 Additional Rate for Weather Coat 1% of Basic Rate 79.55Rs.

    3 Additional Rate for plastic paint 1% of Basic Rate 79.55Rs.

    4

    Additional Rate for Aluminum Window 700.00Rs. Per Sqm of Area 700.00Rs.

    6 Additional Rate for Vitrified tiles

    flooring 1,030.99Rs. Per Sqm of Area 1,030.99Rs.7 Extra for difference of cost of steel

    (=4.5*10.76*14.64) 708.87Rs. Per Sqm of Area 708.87Rs.

    8 Extra for differnce of cost of cement

    (=5.5*65) 357.50Rs. Per Sqm of Area 357.50Rs.

    Total 10,911.46Rs.

    (A) Composite Rate for Assam Type Building over R.C.C. Building Grade-I

    Sr. No. Description Rate Amount

    1 Basic Floor Area Rate 6,290.00Rs. 6,290.00Rs.

    2 Additional Rate for Steel Truss 500.00Rs. Per Sqm of Area 500.00Rs.3

    Additional Rate for Aluminum Window 700.00Rs. Per Sqm of Area 700.00Rs.

    4 Additional Rate for Weather Coat 1% of Basic Rate 62.90Rs.

    5 Additional Rate for plastic paint 1% of Basic Rate 62.90Rs.

    6 Additional Rate for Ceramic tiles

    flooring 1,240.57Rs. Per Sqm of Area 1,240.57Rs.

    7 Extra Rate for Zypboard false ceiling (

    =1024-292.15) 731.85Rs. Per Sqm of Area 731.85Rs.

    8 Extra Rate for precoated roofing

    sheet (=(769.94-425.09)*1.65) 569.00Rs. Per Sqm of Area 569.00Rs.

    9 Extra Rate for precoated roofing

    sheet ridging (=(401.74-148.88)) 252.86Rs. Per Sqm of Area 252.86Rs.

    10 Extra for difference of cost of steel(=3*10.76*14.64) 472.58Rs. Per Sqm of Area 472.58Rs.

    11 Extra for differnce of cost of cement

    (=4*65) 260.00Rs. Per Sqm of Area 260.00Rs.

    Total 11,142.66Rs.

    (B) Sanitary Rate for Assam Type

    Building 8% of Basic Rate 503.20Rs.

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    9/29

    (C) Water Supply Rate for Assam Type

    Building 5% of Basic Rate 314.50Rs.

    (A) Composite Rate for Parapet and Super roof of R.C.C. Building

    Sr. No. Description Rate Amount

    1 Basic Floor Area Rate 450.00Rs. 450.00Rs.

    2 Additional Rate for Weather Coat 1% of Basic Rate 4.50Rs.

    3 Extra for difference of cost of steel

    (=1.5*10.76*14.64) 236.29Rs. Per Sqm of Area 236.29Rs.

    4 Extra for differnce of cost of cement

    (=2*65) 130.00Rs. Per Sqm of Area 130.00Rs.Total 820.79Rs.

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    10/29

    OTHER WORKS

    Sl.

    NoItem Unit

    Total

    Quantity

    proposed

    1

    Supplying, installation, testing, commissioning of Externalwater supply including Rig Boring ( 200mm diameter )

    .connection with P.H.E.

    Deptt. Water supply source.

    a) Boring including fitting & fixing Each 4.00

    b) For overhaed RCC water reservoir (Capacity=75,000

    Lt., Stagging height= 15m)Each 2.00

    c) Distribution pipe lines with fittings

    .overhead water tanks on roof if required).Rm 3500.00

    2 Providing fire protection and fire fighting works

    . design and specifications.

    a) For Fire Extinguishing works with CO D.C.P. Soda-

    Acid and Foam type fire extinguisher

    No.100.00

    b) Under ground water tank (capacity=75,000Lt.) No. 2.00

    c) Piping network with fire hydrant Rm 3000.00

    d)Fire alarm and automatic suppression system No. 1.00

    3 Raising low sitearound the building

    ... forest authority duly

    countersigned by D.F.O. concerned).Cu.m 237524.00

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    11/29

    Sl No.

    Ref. of

    MoSRT&H Items of work Unit Qnty.

    Rate as per

    SOR 2013--14& Analysis (Rs)

    Amount

    (Rs)

    1 2 3 4 5 6.00 7

    A.1/2.3 201 Clearing and grubbing road land including uprooting

    rank vegetation, grass, bushes, shrubs, saplings

    and trees girth up to 300 mm, removal of stumps of

    trees cut earlier and disposal of unserviceable

    materials and stacking of serviceable material to be

    used or auctioned upto lead of 1000m including

    removal and disposal of top organic soil not

    eceddeing 150mm thickness

    By Manual Means:-

    In area of light jungle

    Hect. 3.32 26019.00 86,331.00

    A.2/3.11 305 Removal of unserviceable soil including excavation,

    loading and disposal upto 1000 metres lead but

    excluding replacement by suitable soil which shall

    be paid separately as per clause 305.

    cum 16590.00 52.00 862,680.00

    A.3/3.16 305 Embankment Construction with Material

    Obtained from Borrow Pits (Construction of

    embankment with approved material obtained from

    borrow pits with all lifts and leads, transporting to

    site, spreading, grading to required slope and

    compacting to meet requirment of table 300-2 (

    including compensation of earth.)( Including cost of

    testing of materials at site and laboratory as

    directed by the deptt.)

    From private land Cum 72463.00 241.20 17,478,076.00

    A.4/3.18 305 Construction of Subgrade and Earthen

    Shoulders (Construction of subgrade and earthen

    shoulders with approved material obtained from

    borrow pits with all lifts & leads, transporting to site,

    spreading, grading to required slope and

    compacted to meet requirement of table (300-2) (

    including compensation of earth.)(a), ( Including

    cost of testing of materials at site and laboratory as

    directed by the deptt.)

    a. from Private land

    Cum 12842.00 282.00 3,621,444.00

    A.5/3.22 307 Furnishing & laying of the live sods of perennial turf

    forming grass on embankment slopes, verges over

    the locations shown on the drawings or as directed

    by the Engineer including preparation of ground,

    fetching of sods and watering.

    Sqm 10586.00 27.00 285,822.00

    NAME OF WORK :-

    PART-A: ROAD WORKS

    DETAIL PROJECT EATIMATE

    Installation of Four Weigh Bridges at Jorabat on NH-37, NH-44 between Badarpur-

    Silchar, NH-53 between Silchar-Jiribamin the State of Assam & NH-53 between Jirighat-

    Makru in the State of Manipur under Guwahati & Silchar NH Division in Assam.

    Estimate for one site with 2 Nos. weighbridges at either sides

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    12/29

    Sl No.Ref. of

    MoSRT&HItems of work Unit Qnty.

    Rate as per

    SOR 2013--14

    & Analysis (Rs)

    Amount

    (Rs)

    1 2 3 4 5 6.00 7A.6/4.2 401 Granular Sub-Base with Coarse Graded Material

    (Table: 400-2) (Construction of granular sub-base

    by providing coarse graded material, spreading in

    uniform layers with motor grader on prepared

    surface, mixing by mix in place method with

    rotavator at OMC,and compacting with vibratory

    roller to achieve the desired density,complete as

    per cl. 401( with an initial lead of 5 Km.)

    For Grading I material. Cum 2844.00 2353.20 6,692,501.00

    A.7/4.9 404 Water Bound Macadam (Providing, laying,

    spreading and compacting stone aggregates of

    specific sizes to water bound macadam

    specification including spreading in uniform

    thickness, hand packing, rolling with vibratory roller

    8-10 tonnes in stages to proper grade and camber,

    applying and brooming requisite type of

    screening/binding material to fillup the interstices ofcoarse aggregate,watering and compacting to the

    reqd. density ( with an initial lead of 5.0 km. )

    By Manual Means

    Grading- II

    Using Screening Type-B (11.2mm Agg.) Cum 877.00 2965.20 2,600,480.00

    Grading- III

    Using Screening Type-B (11.2mm Agg.) Cum 877.00 3054.00 2,678,358.00

    A.8/5.1B 502 Prime coat (Providing and applying primer coat

    with bitumen emulsion on prepared surface of

    granular Base including clearing of road surfaceand spraying primer at the rate of specified quantity

    using mechanical means.)( Including cost of testing

    of materials at site and laboratory as directed by the

    deptt.)

    B. Primer @ 1.00Kg per sqm

    ii) With bitumen emulsion-CSS-1 Sqm. 18960.00 75.00 1,422,000.00

    A.9/5.2 503 Tack coat

    Providing and applying tack coat with bitumen

    emulsion using emulsion pressure distributor at the

    rate of 0.20 kg per sqm on the prepared

    bituminous/granular surface cleaned with

    mechanical broom.( Including cost of testing of materials at site and laboratory as directed by the

    deptt.)

    I. With Bitumen emulsion CSS-1h

    c) Granular surface treated with primer Sqm 56880.00 15.00 853,200.00

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    13/29

    Sl No.Ref. of

    MoSRT&HItems of work Unit Qnty.

    Rate as per

    SOR 2013--14

    & Analysis (Rs)

    Amount

    (Rs)

    1 2 3 4 5 6.00 7A.10/5.3 504 Bituminous macadam

    Providing and laying bituminous macadam with 100

    120 TPH hot mix plant producing an average output

    of 75 tonnes per hour using crushed aggregates of

    specified grading premixed with bituminous binder,

    transported to site, laid over a previously prepared

    surface with paver f inisher to the required grade,

    level and alignment and rolled as per clause 501.6

    and 501.7 to achieve the desired compaction)

    (including carriage upto initial lead of 5.00 km from

    quarry and carriage of mixed materials upto 10.00

    km initial lead from mixing plant ( Including cost of

    testing of material at site and laboratory as directed

    by the department)

    (b) With anti stripping agent as per IS:14982 (Refer

    Appendix-5 of MoRT&H specification)

    (I) with 60/70 or VG-30 grade paved bitumen

    ii) for GradingII(19 mm nominal size) Cum 561.00 9520.80 5,341,169.00

    A.11/5.6 507 Dense Graded Bituminous Macadam (Providing

    and laying dense bituminous macadam with 100-

    120 TPH batch type HMP producing an average

    output of 75 tonnes per hour using crushed

    aggregates of specified grading, premixed with

    bituminous binder @ 4.0 to 4.5% by weight of total

    mix and filler transporting the hot miox to work

    site, laying with a hydrostatic paver f inisher with

    sensor control to the reqd. grade, lavel and

    alignment,rolling with smooth wheeled,vibratory and

    tandem rollers to achieve the desired compaction

    as per MoSRT&H cl. no. 507. complete in all

    respect. ( including carriage up to initial lead of 5.0

    km from quarry and carriage of mixed materials up

    to 10.0 Km initial lead from mixing plant )( Including

    cost of testing of materials at site and laboratory as

    directed by the deptt.)

    (c) With hydrated lime / cement as filler (refer table

    500-9 of MoRT&H specif icat ion) & anti str ipping

    agent as per IS:14982 (Refer Appendix-5 of

    MoRT&H specification)

    (III) with 30/40 or VG-40 grade Bitumen (msa>30)

    ii. for Grading-II(19 mm nominal size) Cum 674.00 13390.80 9,025,399.00

    A.12/5.8 509 Bituminous Concrete (Providing and layingbituminous concrete with 100-120 TPH batch type

    hot mix plant producing an average output of 75

    tonnes per hour using crushed aggregates of

    specified grading, premixed with bituminous binder

    @ 5.4 to 5.6 % of mix and fil ler transporting the hot

    mix to work site, laying with a hydrostatic paver

    finisher with sensor control to the reqd. grade, lavel

    and alignment,rolling with smooth wheeled,vibratory

    and tandem rollers to achieve the desired

    compaction as per MoSRT&H cl. no.509. complete

    in all respect. ( including carriage up to initial lead of

    5.0 km from quarry and carriage of mixed materials

    up to 10.0 Km initial lead from mixing plant )(

    Including cost of testing of materials at si te and

    laboratory as directed by the deptt.)

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    14/29

    Sl No.Ref. of

    MoSRT&HItems of work Unit Qnty.

    Rate as per

    SOR 2013--14

    & Analysis (Rs)

    Amount

    (Rs)

    1 2 3 4 5 6.00 7(c) With hydrated lime / cement as filler (refer table

    500-9 of MoRT&H specification) & anti stripping

    agent as per IS:14982 (Refer Appendix-5 of

    MoRT&H specification)

    (III) with 30/40 or VG-40 grade Bitumen (msa>30)

    ii. for Grading-II(13 mm nominal size) Cum 449.00 16048.80 7,205,911.00

    A.13/4.14 407 Construction of Median and Island with Soil Taken

    from Borrow Areas

    Construction of median and Island above road level with

    approved material brought from borrow pits, spread,

    sloped and compacted as per clause 407 Cum 2133.00 224.00 477,792.00

    A.14/8.2 408 Cast in Situ Cement Concrete M 20 Kerb with

    Channel (Construction of cement concrete kerb with

    channel with top and bottom width 115 and 165 mm

    respectively, 250 mm high in M 20 grade PCC on M10

    grade foundation 150 mm thick, kerb channel 300 mmwide, 50 mm thick in PCC M20 grade , sloped towards

    the kerb, kerb stone with channel laid with kerb laying

    machine,foundation concrete manually all complete as

    per clause 408.)

    A. Using Concrete Mixer Rm 1964.00 591.00 1,160,724.00

    A.15/3.29 309 Underground Drain at Edge of Pavement

    (Construction of an underground drain 1 m x 1 m

    (inside dimensions) lined with RCC-20 cm thick and

    covered with RCC slab 10 cm in thickness on urban

    roads) Rm 1539.00 4157.00 6,397,623.00

    A.16/12.1 304 Excavation for Structures

    (Earth work in excavation of foundation of

    structures as per drawing and technical

    specification, including setting out, construction ofshoring and bracing, removal of stumps and other

    deleterious matter, dressing of sides and bottom

    and backfilling with approved material.

    I. Ordianry Soil

    A. By Manual Means

    (I) W ithout Dewatering

    (i). upto 3m depth. cum 4740.00 65.00 308,100.00

    A.17/12.8 1500,1700

    & 2100

    Plain/Reinforced cement concrete, in open

    foundation complete as per drawing and technical

    specification including steel shuttering formwork.

    N. without plasticizer

    A. PCC Grade M15 cum 316.000 5605.00 1,771,180.00

    A.18/9.2 2900 Labour for laying Reinforced cement concrete pipeNP4/NP3/prestressed concrete pipe for culverts on

    first class bedding of granular material /cc M-15 in

    single row including fixing collar with cement mortar

    1:2,and cost of granular bedding but excluding

    excavation, protection works, backfilling, concrete

    and masonry work in head wall and parapet,cost of

    pipe and cost of CC bedding.

    '(II) With 1st class bedding of cc M-15

    A. 1200mm dia

    meter 50.00 172.00 8,600.00

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    15/29

    Sl No.Ref. of

    MoSRT&HItems of work Unit Qnty.

    Rate as per

    SOR 2013--14

    & Analysis (Rs)

    Amount

    (Rs)

    1 2 3 4 5 6.00 7A.19 Supply of of RCC Hume-pipe of NP4 1200mm dia

    of length 2.5m as per IRC, ISI specification IS:458-

    1971 including transportation to the site, loadind &

    unloading complete.meter 50.00 7770.00 388,500.00

    A.20/8.5 801 Direction and place identif ication sign upto

    0.9sqm size board.

    Providing and erecting direction and place

    identi fication retro-Ref lectrorised sign as per

    IRC:67 made of encapsulated lens type reflective

    sheeting vide clause 801.3 f ixed over aluminium

    sheeting, 2mm thick with area not exceeding

    0.9sqm fixed on an angle iron of 25x25x4mm

    supported on a mild steel angle iron post 75mm x

    75mm x 6mm firmly fixed to the ground by means of

    properly design foundation with M-15 grade Cement

    concrete 45cm x 45cm x 60cm, 60cm below ground

    level as per approved drawing and sign. ( All the

    Steel work must be Tata/Sail/or any other approved

    brand)

    Sqm 10.00 10000.00 100,000.00

    A.21/8.6 801 Direction and place identification sign more

    than 0.9sqm size board.

    Providing and erecting direction and place

    identi fication retro-Ref lectrorised sign as per

    IRC:67 made of encapsulated lens type reflective

    sheeting vide clause 801.3 f ixed over aluminium

    sheeting, 2mm thick with area exceeding 0.9sqm

    fixed on an angle iron of 25x25x4mm supported on

    a mild steel angle iron post 75mm x 75mm x 6mm,

    2 nos. firmly fixed to the ground by means of

    properly design foundation with M-15 grade Cement

    concrete 45cm x 45cm x 60cm, 60cm below ground

    level as per approved drawing and sign. . ( Al l the

    Steel work must be Tata/Sail/or any other approved

    brand)

    Sq.m 6.00 11000.00 66,000.00

    A.22/8.4 801 Retro reflectorised Traffic sign:

    Providing and erect ing of Retro-Reflectrorised

    cautionary, mandatory & informatory sign as per

    IRC: 67 made of high intensity encapsulated lens

    type ref lective sheeting vide clause 801.3, f ixed

    over aluminium sheeting, 2 mm thick fixed on an

    angle iron of 25x25x4mm supported on a mild steel

    angle iron post 75mm x 75mm x 6mm firmly fixed to

    the ground by means of properly design foundation

    with M-15 grade Cement concrete 45cm x 45cm x

    60cm, 60cm below ground level as per approved

    drawing and sign. ( All the Steel work must be

    Tata/Sail/or any other approved brand)

    90cm equilateral traingle Each 6.00 4900.00 29,400.00

    60cm x60cm square Each 6.00 5200.00 31,200.00

    60cm circular Each 6.00 4200.00 25,200.00

    80cmm x 60 cm rectangular Each 6.00 5300.00 31,800.00

    60cmm x 45 cm rectangular Each 6.00 5200.00 31,200.00

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    16/29

    Sl No.Ref. of

    MoSRT&HItems of work Unit Qnty.

    Rate as per

    SOR 2013--14

    & Analysis (Rs)

    Amount

    (Rs)

    1 2 3 4 5 6.00 7A.23/8.51 810 Providing reflective pavement marker with Micro

    prismatic lens in both direction having thermoplastic

    body adhering to the specification and guidelines of

    MoSRT&Hs fixed to the road surface using the

    adhesives and the procedures recommended by the

    manufacturers with three months replacement

    warranty and free maintenance.

    Each 500.00 298.00 149,000.00

    A.24/8.52 810 Traffic cones: With rubber base and reflective of 7

    inch sleeve, height= 750mm, bottom square:

    385mm and weight 4.00 kgEach 30.00 700.00 21,000.00

    A.25/8.53 810 Providing Inter linking chain link for traffic cones Rm 20.00 45.00 900.00

    A.26/8.53 810 Providing metal tubular delineator (50mm dia and

    1.25mm thick) with 15cm reflector made of heighintensity grade retro reflectorised sheeting around

    the pipe at top covered with wire mesh of 20cm

    length with two nos of similar reflective bands and

    bottom fastener M.S. angle including firmly fixing

    the delineator to the ground by means of CC(M-15)

    foundation of size-(25cmx25cmx25cm), 25cm

    below ground to the true line and level as directed

    by the deptt. With six months replacement warranty

    and free maintenance.

    1000mm height. Each 200.00 596.00 119,200.00

    A.27/8.47 810 ProvidingSparkle Solar Road Studs, manufactured

    by Tata B.P. Solar India Ltd. Of size(125mmx125mm), 90mm height (from bottom of

    shank to the top of stud) with detachable battery,

    m6LEDs-three on each side for Bi-directional

    studs/3 LEDs on one side for unidirectional studs,

    ultra bright LED in amber and red colour, weight per

    stud 700+25 gms, flash rate of 50-65 times per

    minute completely water resistant and weather

    proof with replacement warranty and free

    maintenance fro one year from the date of

    installation of stud on road-(installation should be

    made using adhesives and procedures

    recommended by manufacturer under the

    supervision of their competent technician).

    Bi-directional Stud- Each 20.00 3500.00 70,000.00

    A.28/8.13 803 Providing and laying of hot applied thermoplastic

    compound 2.5 mm thick including ref lectorising

    glass beads @ 250 gms per sqm area, thickness of

    2.5 mm is exclusive of surface applied glass beads

    as per IRC:35 .The finished surface to be level,

    uniform and free from streaks and holes and

    conforming to the MoRT&H specifications

    sq.m 70.00 750.00 52,500.00

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    17/29

    Sl No.Ref. of

    MoSRT&HItems of work Unit Qnty.

    Rate as per

    SOR 2013--14

    & Analysis (Rs)

    Amount

    (Rs)

    1 2 3 4 5 6.00 7A.29/8.50 Providing Linear Delineator System with Diamond

    grade reflective sheeting of size 80cmx10cm, fixing

    over thin gauge crimped aluminium sheeting with

    single colour panels of Yellow/Red/White and fixing

    to the object as per specification of the

    manufacturer.

    each 80.00 480.00 38,400.00

    TOTAL (ROAD WORKS) 69,431,690.00

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    18/29

    Sl No.Ref. of

    MoSRT&HItems of work Unit Qnty.

    Rate as per

    SOR 2013--14

    & Analysis (Rs)

    Amount

    (Rs)

    1 2 3 4 5 6.00 7

    Sl No. Items of work Unit Qnty.

    Rate as per

    SOR 2004-05/

    Analysis (Rs)

    Amount

    (Rs)

    B1 Construction of Civil works of the Assam type

    buildings as per approved structural &

    architectural drawings and specifications

    complete.

    a) For Grade-I Buildings Sq.m. 78.00 13255.56 1,033,934.00

    B.2 Providing anti-termite treatment work of the

    buildings as per approved specification

    complete.

    (III) In Assam Type buildings

    a) For Grade-I Buildings Sq.m. 78.00 165.00 12,870.00

    B.3 Providing sanitary arrangements of the

    building as per approved drawings, design

    specification complete.(III) In Assam Type buildings

    a) For Grade-I Buildings Sq.m. 78.00 623.20 48,610.00

    B.4 Providing external sanitary arrangements of

    the building (septic of 50 users with 110mm

    dia PVC soil pipes and 450 x 450 mm inside

    inspection chamber where necessary with

    necessary arrangement for connection with

    future sewerage system line) as per approved

    drawings, design specification complete.

    (I) In R.C.C/Assam type buildings No. 4 80000.00 320,000.00

    B.13 Providing internal water supply works as perapproved drawings, design and specification

    complete.

    (III) In Assam Type buildings

    a) For Grade-I Buildings Sq.m. 78.00 389.50 30,381.00

    B.14 Supplying, installation, testing, commissioning

    of External water supply including Rig Boring (

    200mm diameter ) to meet the demand of

    water requirement, consisting of works for

    overhead water reservoirs (RCC), distribution

    pipe lines with fittings, as per site condition,

    including provision of future service

    connection with P.H.E. Deptt. Water supply

    source.a) Boring including fitting & fixing Each 1 42500.00 42,500.00

    b) For overhaed RCC water reservoir

    (Capacity=75,000 Lt., Stagging height= 15m)

    Each 1 2000000.00 2,000,000.00

    c) For distribution pipe lines with fittings

    including connection with water source/(Up to

    overhead water tanks on roof if required). Rm 150.00 1614.71 242,207.00

    .

    PART-B BUILDING WORKS

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    19/29

    Sl No.Ref. of

    MoSRT&HItems of work Unit Qnty.

    Rate as per

    SOR 2013--14

    & Analysis (Rs)

    Amount

    (Rs)

    1 2 3 4 5 6.00 7

    B.15 Providing fire protection and fire fighting works

    as per relevant I.S. Code of practices, local

    authorities regulations etc. complete as per

    approved drawing, design and specifications.

    a) Under ground water tank(capacity=75,000Lt.)

    No. 1 1200000.00 1,200,000.00

    b) Piping network with fire hydrant spout as

    per I.S. Specification, approved design and

    drawing. Rm 150.00 2700.00 405,000.00

    5,335,502.00

    C.1 Supply, installation and commissioning of

    close cercuit television monitoring system

    with day and night camera, digital video

    recording system ... 30 days storage

    minimum, Ethernet video server for LAN/WAN/ internet with all required cabling and

    comprising of the following as per

    specification complete including providing

    necessary training and after sales service

    during the warranty period as directed by the

    Department . (Rate to be quoted considering

    all taxes and duties payment of which shall be

    the responsibility of the contractor).

    a. Outdoor fixed day / night camera ( 2 each

    for 6 weighbridges) 12 Nos.

    b. Verifocal lens 12 Nos.

    c. Housing for outdoor use 12Nos.

    d. Network DVR Nos.2

    e. Video server 2 Nos.

    f. RG 11 armoured video cable 450mg. 2 core armoured power cable 450m

    h. Control cabin with lateral clearance as per

    IRC norms , with allied electricals

    Each 1.00 1808614.80 1,808,615.00

    C.2 Supply, installation and commissioning of

    remote operatedelectro-mechanical

    barriers along with operating / control

    systems and necessary cablings including

    providing pedestal/ foundation and control

    cabin for the boom barriers with lateral

    clearance as per IRC norms , as per

    specification complete including providing

    necessary training and after sales serviceduring the warranty periodas directed by the

    Department.(Rate to be quoted considering all

    taxes and duties payment of which shall be

    the responsibility of the contractor).

    a.Eelectro-mechanical boom barrier for

    carriageways having a clear width of 5.00 m ,

    with all control system as per

    specification.(Low barrier) Nos 4.00 522447.60 2,089,790.00

    PART-C :: MECHANICAL AND ALLIED WORKS

    CLOSE CIRCUIT TV MONITORING SYSTEM, ELECTROMEHANICAL

    BARRIERS & WEIGH BRIDGES.

    TOTAL OF BLDG. WORKS

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    20/29

    Sl No.Ref. of

    MoSRT&HItems of work Unit Qnty.

    Rate as per

    SOR 2013--14

    & Analysis (Rs)

    Amount

    (Rs)

    1 2 3 4 5 6.00 7

    b.Elelectro-mechanical boom barrier for

    carriageways having a clear width of 7.50 m ,

    with all control system as per

    specification.(High barrier) Nos 4.00 723592.80 2,894,371.00

    c.Elelectro-mechanical boom barrier for

    carriageways having a clear width of 11.00 m, with all control system as per

    specification.(High barrier) Nos 2.00 1014565.20 2,029,130.00

    C.3 Supply, installation and commissioning

    including calibration, stamping by the Weights

    and Measurement Department, of fully

    electronic road vehicle weighbridge- pitless

    type- along with structure work, load cells,

    digitiser, PC with UPS, printer, standard

    software, junction box, necessary cables etc.

    including construction of foundation, control

    cabins with lateral clearance as per IRC

    norms , with allied electricals and providing

    test weight to be kept at site as per

    requirement of Weights and Measurement

    Deptt.( Total 25.00 MT ) as per specification

    complete and providing necessary training

    and after sales service during the warranty

    period as directed by the Department. (Rate to

    be quoted considering all taxes and duties

    payment of which shall be the responsibility of

    the contractor).

    b. 100 MT capacity electronic weighbridges .Nos 6.00 3561738.00 21,370,428.00

    TOTAL (MECH & ALLIED. WORKS) 30,192,334.00

    Asstt. Executive Engineer,PWD,

    Golakganj NH Sub Division,

    Golakganj, Assam.

    Superintending Engineer, NH (P)

    O/o the C. E., PWD, NH(Works), Assam,

    Chandmari, Guwahati-3. Assam, Chandmari, Guwahati-3.

    AbhayapurI, Assam.

    Chief Engineer, PWD, NH (Works),

    Abhayapuri NH Division

    Executive Engineer,

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    21/29

    No of

    Building

    no of

    person

    Area in

    G.Floor

    no of

    person

    Area in

    F.Floor

    no of

    person

    Area in

    S.Floor

    1 DTO'S Qtr. TD 114.00 1 1 114.00

    2 Sales Tax supdt. STD 114.00 2 2 228.00

    3 Incharge of Forest FD 114.00 1 1 114.00

    4 Incharge of Excise ED 114.00 1 1 114.00

    5 Asstt. Sec. Qtr AMB 114.00 1 1 114.00

    6 Asstt. Marketing Officer AMB 63.50 1 2 127.00

    7 OFFICERS QTR.(Police Dept) PD 63.50 1 1 63.50

    8 Office Building OFFICE 620.00 1 1 620.00

    1 Marketing Officer AMB 63.50 1 2 127.00

    10 12 1621.50

    Area per

    person in

    Sqm

    STATEMENT SHOWING AREA OF RESIDENTIAL & OFFICE BUILDING OF CONSTRUCTION OF COMPOSITE CHECK GATE AT CHAGOLIA, BAXIRHAT,

    ASSAM

    ANNEXURE-2

    Dept.

    ASSAM TYPE (GRADE-I)

    Sr. No Item

    Works proposed

    TOTAL AREA =

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    22/29

    No of

    Building

    no of

    person

    Area in

    G.Floor

    no of

    person

    Area in

    F.Floor

    no of

    person

    Area in

    S.Floor

    Area per

    person in

    Sqm

    Dept.Sr. No Item

    Works proposed

    1 Staff STD 49.00 4 8 392.00

    2 Canteen ALL 100.00 5 0 500.00

    3 Insp. Of Excise ED 60 2 4 240.00

    4 Asstt. Insp. Of Excise ED 49.00 2 4 196.00

    1 POLICE THAANA CUM BARRACK PD 500 1 30 500.00

    2 Deputy Ranger FD 60 1 2 120.00

    3 Forester Gr.-I/II FD 49.00 2 4 196.00

    17 52 2144.00TOTAL AREA =

    ASSAM TYPE (GRADE-II)

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    23/29

    No of

    Building

    no of

    person

    Area in

    G.Floor

    no of

    person

    Area in

    F.Floor

    no of

    person

    Area in

    S.Floor

    Area per

    person in

    Sqm

    Dept.Sr. No Item

    Works proposed

    1 Grade-IV staff Quarter STD 35.00 7 14 490.00

    2 Staff AMB 35.00 1 2 70.00

    3 Grade-IV staff Barrack AMB 10.00 1 20 200.00

    4 staff Barrack FD 10.00 1 14 140.00

    5 Police Barrack PD 10.00 1 30 300.00

    5 Head constable/Staff ED 35.00 1 2 70.00

    6 Security Barrack ED 10.00 1 14 140.00

    6 security Booth OFFICE 16.00 8 0 128.00

    6 Toll Booth OFFICE 64.00 8 0 512.00

    7 weigh bridge/scanner booth OFFICE 24.00 6 0 144.00

    1 Toilet Block OFFICE 50.00 3 0 150.00

    ASSAM TYPE (GRADE-III)

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    24/29

    No of

    Building

    no of

    person

    Area in

    G.Floor

    no of

    person

    Area in

    F.Floor

    no of

    person

    Area in

    S.Floor

    Area per

    person in

    Sqm

    Dept.Sr. No Item

    Works proposed

    31 82 2344.00

    6 Vehicle Parking Shed OFFICE 493 4 0 1972.00

    6 GODOWN FD 150 1 0 150.00

    6 GODOWN STD 500 1 0 500.00

    6 0 2622.00

    1 Canteen cum Recreation building OFFICE 208.50 1 0 208.50 0 220.00

    Guest house STD 208.50 1 0 208.50 0 220.00

    3 inspection ramp OFFICE 120.00 2 0 240.00 0 240.00

    office building OFFICE 750.00 1 0 750.00 0 750.00

    5 0 1407.00 0 1430.00

    TOTAL AREA =

    TOTAL AREA =

    TOTAL AREA =

    R.C.C. (G+1) with Assam type roofing in first floor (GRADE-I)

    ASSAM TYPE (GRADE-IV)

    R.C.C. (G+1) (GRADE-I)

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    25/29

    No of

    Building

    no of

    person

    Area in

    G.Floor

    no of

    person

    Area in

    F.Floor

    no of

    person

    Area in

    S.Floor

    Area per

    person in

    Sqm

    Dept.Sr. No Item

    Works proposed

    1 Sales tax Inspector's Qtr STD 76.00 3 6 456.00 6 456.00

    3 6 456.00 6 456.00

    1 Marketing Inspector (WF) AMB 63.50 1 2 127.00 2 127.00 2 127.00

    Enforcement inspector Hostel TD 47.00 1 4 188.00 4 188.00 4 188.00

    assictant enforceemnt inspector TD 35.00 1 4 140.00 4 140.00 4 140.00

    guest house TD 208.50 1 0 208.50 0 220.00 0 220.00

    4 10 663.50 10 675.00 10 675.00

    1 enforce checker hostel TD 27.00 1 4 108.00 4 108.00 4 108.00

    2 Gr. IV staff hostel TD 20.00 1 4 80.00 4 80.00 4 80.00

    2 8 188.00 8 188.00 8 188.00

    TOTAL AREA =

    R.C.C. (G+2) Ground Floor (GRADE-I)

    TOTAL AREA =

    TOTAL AREA =

    R.C.C. (G+2) (GRADE-II)

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    26/29

    A. BITUMEN/BITUMEN EMULSION

    Sl.No. Items of work Type of

    Bitumen/

    Emulsion

    utilised

    Quantity of works Unit Quantity of

    bitumen per unit

    of work in MT.

    Total quantity

    of Bitumen

    (MT)

    Col.4xCol.6

    1 2 3 4 5 6 7

    1 Prime Coat CSS-1h 110329.89 Sqm 0.001 110.33

    2 Tack coat CSS-1h 208529.16 Sqm 0.0002 41.71

    3 Surface Dressi 60/70 98199.27 Sqm 0.0012 117.84

    4 BM 60/70 0.00 Cum 0.0724 224.84

    5 DBM 60/70 5822.85 Cum 0.0981 571.22

    6 BC PMB-70 3105.52 Cum 0.12958 402.41

    7 OGPS 60/70 12130.52 Sqm 0.00146 17.718 SC 60/70 12130.52 Sqm 0.00098 11.89

    Total = 1345.912107

    B. CEMENT

    Sl.No. Quantity of work Unit Utilisation rate of

    cement in

    MT/Unit

    Total Quantity

    of cement in

    Mt

    1 3502.40 Cum 0.06 210.14

    2 848.24 Cum 0.23

    3 6765.84 Cum 0.33 2232.734 16198.60 Sqm 0.00360 58.31

    5 3474.19 Cum 0.34100 1184.70

    6 1401.19 Cum 0.344 482.01

    Total 3957.75

    C. STEEL

    1 739.31 Tonne 739.31 739.31Reinforcement(TMT-TATA)

    RCC grade M20

    PCC grade M20

    Sl.No. Item of work Quantity of work Unit Utilisation rate of

    Steel in MT/Unit

    Total Quantity

    of Steel in Mt

    Brick Masonry 1:3

    PCC grade 1:3:6

    PCC grade M15Plastering (1:3)

    Item of work/Grade of

    concrete

    STATEMENT SHOWING EXTRA COST OF BITUMEN ,CEMENT & STEEL DUE

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    27/29

    Rate as per

    SOR 2007-08

    (Rs./MT)

    Rate as per

    Present

    Market Rate

    (Rs./MT)

    Difference of

    cost in Rate

    (Rs./MT)

    Total Amount

    of Difference

    (Rs.)

    Amount as per

    SOR 2007-08

    Col.7xCol.10

    8 9 10 11 12

    0.00

    0.00

    25476.00 33045.41 7569.41 891972.64 3002069.52

    25476.00 33045.41 7569.41 1701903.48 5728014.87

    25476.00 33045.41 7569.41 4323810.38 14552441.10

    30960.00 44200.00 13240.00 5327951.85 12458715.20

    25476.00 33045.41 7569.41 134058.48 451194.2125476.00 33045.41 7569.41 89984.46 302856.38

    12469681.30 36495291.28

    Total Quantity

    of cement in

    bag

    Amount as

    per

    SOR 2007-08

    Amount as

    per Current

    Market Rate.

    Market Rate SOR Rate Difference Total cost

    79155.0062 303.00 260.00 43.00 3403665.27

    3403665.27 20580301.61 23983966.88

    Market Rate SOR Rate Difference

    43789.00 32520 11269 8331284.39 24042361.2 32373645.59

    Executive Engineer,PWD,

    Abhayapuri Construction

    Difference of cost of Steel(Rs.) Total cost Amount as per

    SOR 2007-08

    Amount as per Current

    Market Rate.

    Total difference of cost of cement=

    392840.85

    Total difference 48964972.58

    Difference of cost of cement(Rs.)

    17786667.05

    585252.69

    0.00

    0.00

    3894042.17

    TO DIFFERENCE OF PRESENT MARKET RATE WITH THE SOR OF 2007-08

    Amount as per Current

    Market Rate.

    7429918.35

    18876251.48

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    28/29

    330.22

  • 8/10/2019 PROJECT ESTMATE (weigh bridge)excl.2007-Final.xls

    29/29

    Sl No.Ref. of

    MoSRT&HItems of work Unit Nos

    Length

    (M)

    Breath

    (M)

    Height

    (M)Qnty.

    1 2 3 4 5 6 7 8 9

    A.1/2.3 201 Clearing and grubbing road land Hect. 2 790 21 3.32A.2/3.11 305 Removal of unserviceable soil cum 2 790.00 21.00 0.50 16590.00

    A.3/3.16 305 Embankment Construction with Material

    Obtained from Borrow Pits

    'From private land Cum 2 790.00 17.05 2.05 55224.95

    Add for Unserviceable soil dug out Cum 16590.00

    71815.00

    Construction of Subgrade

    a. from Private land Cum 2 790 14.5 0.5 11455.00

    Construction of Earthen Shoulders

    a. from Private land Cum 4 790 1.95 0.45 2773.00

    A.5/3.22 307 Furnishing & laying of the live sods of perennial turfSqm 2 790 6.71 10602.00

    A.6/4.2 401 Granular Sub-Base with Coarse Graded

    MaterialFor Grading I material. Cum 2 790 12 0.15 2844.00

    Water Bound Macadam Grading- II Cum 2 790 7.4 0.075 877.00

    Water Bound Macadam Grading- III Cum 2 790 7.4 0.075 877.00

    A.8/5.1B 502 Prime coat Sqm. 2 790 12 18960.00

    A.9/5.2 503 Tack coat Sqm. 6 790 12 56880.00

    A.10/5.3 504 Bituminous macadam Cum 2 790 7.1 0.05 561.00

    A.11/5.6 507 Dense Graded Bituminous Macadam Cum 2 790 7.1 0.06 673.00

    A.12/5.8 509 Bituminous Concrete Cum 2 790 7.1 0.04 449.00

    A.13/4.14 407 Construction of Median and Island with Soil Taken

    from Borrow Areas Cum 2 790 4.5 0.3 2133.00

    A.14/8.2 408 Cast in Situ Cement Concrete M 20 Kerb with

    Channel Rm 1 2000 2000.00

    A.15/3.29 309 Underground Drain at Edge of Pavement Rm 1539.00

    A.16/12.1 304 Earth work in excavation of foundation cum 2 790 1.5 2.00 4740.00

    A.17/12.8 1500,1700

    & 2100

    Plain/Reinforced cement concrete, in open

    foundation cum 2 790 2 0.10 316.00

    A.18/9.2 2900 Labour for laying Reinforced cement concrete pipe

    NP4/NP3/prestressed concrete pipe meter 2 25 50.00

    A.19 Supply of of RCC Hume-pipe of NP4 1200mm dia

    of length 2.5m meter 2 25 50.00

    A.20/8.5 801 Direction and place identification sign upto

    0.9sqm size board. Sqm 10.00

    A.21/8.6 801 Direction and place identification sign more

    than 0.9sqm size board. Sq.m 6.00

    A.22/8.4 801 Retro reflectorised Traffic sign:

    90cm equilateral traingle Each 6.00

    60cm x60cm square Each 6.00

    60cm circular Each 6.00

    80cmm x 60 cm rectangular Each 6.00

    60cmm x 45 cm rectangular Each 6.00

    A.23/8.51 810 Reflective pavement marker Each 500.00

    A.24/8.52 810 Traffic cones: Each 30.00

    A.25/8.53 810 Providing Inter linking chain link for traffic cones Rm 20.00

    A.26/8.53 810 Metal tubular delineator 1000mm height. Each 200.00

    A.27/8.47 810 Sparkle Solar Road Studs - Bi-directional StudEach 20.00

    A.28/8.13 803 Hot applied thermoplastic compound sq.m 70.00

    A.29/8.50 Linear Delineator System with Diamond grade

    reflective sheeting each 80.00

    DETAIL PROJECT EATIMATE

    NAME OF WORK :- Installation of Weigh Bridges at Jorabat on NH-37

    Estimate for one site with 2 Nos. weighbridges at either sides

    PART-A: ROAD WORKS

    S/T =

    A.4/3.18 305

    A.7/4.9 404