Project Cost Management

38
Chapter 5: Project Cost Management Stevbros Training & Consultancy www.stevbros.edu.vn Copyright@STEVBROS Project Management Fundamentals 1 PMI, PMP and PMBOK are registered marks of the Project Management Ins9tute, Inc.

Transcript of Project Cost Management

Chapter  5:    Project  Cost  Management  

Stevbros  Training  &  Consultancy  www.stevbros.edu.vn  

Copyright@STEVBROS   Project  Management  Fundamentals   1  

PMI,  PMP  and  PMBOK  are  registered  marks  of  the  Project  Management  Ins9tute,  Inc.  

Overview       Ini%a%ng  

process  group  

Planning  process  group  

Execu%ng  process  group  

Monitoring  &  controlling  process  group  

Closing  process  group  

Project  cost  management  

    •  Plan  Cost  Management  

•  EsHmate  Costs  

•  Determine  Budget  

    •  Control  Costs  

   

Copyright@STEVBROS   Project  Management  Fundamentals   2  

Cost  Concepts  

Life  cycle  cosHng  •  Looking  at  the  cost  of  whole  life  of  the  product  (include  maintenance)  

 Value  analysis  (value  engineering)  •  Looking  at  less  costly  way  to  do  the  same  work  within  the  same  scope  

Copyright@STEVBROS   Project  Management  Fundamentals   3  

Cost  Concepts  A  Cost  can  be  either  variable  or  fixed:  

•  Variable   cost:   cost   that   change   with   the   amount   of  producHon   or   the   amount   of   work.   Ex.,   cost   of   material,  supplies,  wages…  •  Fixed  cost:  cost  that  do  not  change  as  producHon  changes.  Ex.,  set-­‐up,  rental…  

A  Cost  can  be  either  direct  or  indirect:  •  Direct  cost:  cost  that  are  directly  aVributable  to  the  work  on  the  project,  Ex.,   team  travel,   team  wages,   recogniHon,  and  costs  of  material  used  on  the  project…  •  Indirect   cost:   overhead   items   or   costs   incurred   for   the  benefit  of  more  than  one  project,  Ex.,  taxes,  fringe  benefits  and  janitorial  services  

Copyright@STEVBROS   Project  Management  Fundamentals   4  

Plan  cost  management  

•  The   process   that   establishes   the   policies,   procedures,   and  documentaHon   for   planning,   managing,   expending,   and  controlling   project   costs.   The   key   benefit   of   this   process   is  that   it   provides   guidance   and   direcHon   on   how   the   project  costs  will  be  managed  throughout  the  project.  

Copyright@STEVBROS   Project  Management  Fundamentals   5  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐2  Page  195.  

Inputs  1.   Project  Management  Plan    

•  contains   informaHon   used   to   develop   the   cost   management  plan:  Scope  baseline,  Schedule  baseline,  Other  informaHon.  

2.   Project  Charter    •  provides   the  summary  budget   from  which   the  detailed  project  costs  are  developed.    

3.   Enterprise  Environmental  Factors    •  organizaHonal   culture   and   structure   can   all   influence   cost  management;   market   condiHons;   currency   exchange   rates;  published  commercial  informaHon;  PMIS.  

4.   Organiza%onal  Process  Assets    •  financial  controls  procedures;  historical  informaHon  and  lessons  learned   knowledge   bases;   financial   databases;   and   exisHng  formal   and   informal   cost   esHmaHng   and   budgeHng-­‐related  policies,  procedures,  and  guidelines.    

Copyright@STEVBROS   Project  Management  Fundamentals   6  

Tools  and  techniques  

1.   Expert  Judgment    •  guided  by  historical   informaHon,  provides   valuable   insight   about  the  environment  and  informaHon  from  prior  similar  projects.  

2.   Analy%cal  Techniques    •  involve   choosing   strategic   opHons   to   fund   the   project   such   as:  self-­‐funding,   funding  with  equity,  or   funding  with  debt.  The  cost  management   plan   may   also   detail   ways   to   finance   project  resources  such  as  making,  purchasing,  renHng,  or  leasing.  

•  techniques   may   include:   payback   period,   return   on   investment,  internal   rate   of   return,   discounted   cash   flow,   and   net   present  value.    

3.   Mee%ngs    •  aVendees   at   these   meeHngs   may   include   the   project   manager,  the   project   sponsor,   selected   project   team   members,   selected  stakeholders,   anyone   with   responsibility   for   project   costs,   and  others  as  needed.    

Copyright@STEVBROS   Project  Management  Fundamentals   7  

Outputs  1.  Cost  Management  Plan  

•  describes   how   the   project   costs   will   be   planned,   structured,   and  controlled.  the  cost  management  plan  can  establish  the  following:    ü units  of  measure.    ü Level   of   precision:   the   degree   to   which   acHvity   cost   esHmates   will   be  rounded   up   or   down   (e.g.,   US$100.49   to   US$100,   or   US$995.59   to   US$1,000)  

ü Level  of  accuracy:  the  acceptable  range  (e.g.,  ±10%)  ü OrganizaHonal  procedures   links:  the  WBS  provides  the  framework  for  the  cost   management   plan,   allowing   for   consistency   with   the   esHmates,  budgets,  and  control  of  costs.  

ü control  thresholds.  ü Rules  of  performance  measurement:  EVM  rules  of  performance  ü ReporHng  formats  ü Process  descripHons  ü AddiHonal  details  

Copyright@STEVBROS   Project  Management  Fundamentals   8  

EsHmate  costs  •  The  process  of  developing  an  approximaHon  of  the  monetary  

resources   needed   to   complete   project   acHviHes.   The   key  benefit   of   this   process   is   that   it   determines   the   amount   of  cost  required  to  complete  project  work.  

Copyright@STEVBROS   Project  Management  Fundamentals   9  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐4  Page  200.  

EsHmaHng    techniques  

•  The   accuracy   of   a   project   esHmate  will   increase  as  the  project  progresses  through  the  project  life  cycle.   For   example,   a   project   in   the   iniHaHon  phase   may   have   a   rough   order   of   magnitude  (ROM)   esHmate   in   the   range   of   −25%   to   +75%.  Later   in   the   project,   as   more   informaHon   is  known,   definiHve   esHmates   could   narrow   the  range  of  accuracy  to  -­‐5%  to  +10%.  

•  EsHmaHng  techniques:  analogous  esHmaHng  (top  down  esHmaHng),  parametric  esHmaHng,  boVom  up  esHmaHng,  three  point  esHmaHng.  

Copyright@STEVBROS   Project  Management  Fundamentals   10  

Inputs(1/2)  1.   Cost  Management  Plan  •  defines  how  project  costs  will  be  managed  and  controlled.    

2.   Human  Resource  Management  Plan    •  provides   project   staffing   aVributes,   personnel   rates,   and  related  rewards/recogniHon,  which  are  necessary  components  for  developing  the  project  cost  esHmates.  

3.   Scope  Baseline    •  addiHonal   informaHon   that   may   be   found   in   the   scope  baseline   with   contractual   and   legal   implicaHons,   such   as  health,   safety,   security,   performance,   environmental,  insurance,   intellectual   property   rights,   licenses,   and   permits.  All  of  this  informaHon  should  be  considered  when  developing  the  cost  esHmates.    

Copyright@STEVBROS   Project  Management  Fundamentals   11  

Inputs(2/2)  4.   Project  Schedule    

•  the   type   and  quanHty  of   resources   and   the   amount  of  Hme  which   those  resources   are   applied   to   complete   the   work   of   the   project   are   major  factors   in   determining   the   project   cost.   Schedule   acHvity   resources   and  their  respecHve  duraHons  are  used  as  key  inputs  to  this  process.  

5.   Risk  Register    •  as  a  general  rule,  when  the  project  experiences  a  negaHve  risk  event,  the  

near-­‐term   cost   of   the   project   will   usually   increase,   and   there   will  someHmes  be  a  delay  in  the  project  schedule.  In  a  similar  way,  the  project  team   should   be   sensiHve   to   potenHal   opportuniHes   that   can   benefit   the  business   either   by   directly   reducing   acHvity   costs   or   by   acceleraHng   the  schedule.  

6.   Enterprise  Environmental  Factors    •  market  condiHons,  published  commercial  informaHon.    

7.   Organiza%onal  Process  Assets    •  cost  esHmaHng  policies,  cost  esHmaHng  templates,  historical   informaHon,  

and  lessons  learned.    Copyright@STEVBROS   Project  Management  Fundamentals   12  

Tools  and  techniques(1/3)  

1.   Expert  Judgment    •  guided   by   historical   informaHon,   provides   valuable   insight   about  the  environment  and  informaHon  from  prior  similar  projects.  

2.   Analogous  Es%ma%ng    •  uses   the   values   such   as   scope,   cost,   budget,   and   duraHon   or  measures   of   scale   such   as   size,   weight,   and   complexity   from   a  previous,   similar   project   as   the   basis   for   esHmaHng   the   same  parameter  or  measurement  for  a  current  project.  

3.   Parametric  Es%ma%ng    •  uses  a  staHsHcal  relaHonship  between  relevant  historical  data  and  other  variables  (e.g.,  square  footage  in  construcHon)  to  calculate  a  cost  esHmate  for  project  work.  This  technique  can  produce  higher  levels   of   accuracy   depending   upon   the   sophisHcaHon   and  underlying  data  built  into  the  model.  

Copyright@STEVBROS   Project  Management  Fundamentals   13  

Tools  and  techniques(2/3)  

4.   BoVom-­‐Up  Es%ma%ng    •  is   a  method  of   esHmaHng   a   component   of  work.   The   cost   of   individual  

work  packages  or  acHviHes  is  esHmated  to  the  greatest  level  of  specified  detail.   The   detailed   cost   is   then   summarized   or   “rolled   up”   to   higher  levels  for  subsequent  reporHng  and  tracking  purposes.  

5.   Three-­‐Point  Es%ma%ng    •  Most   likely   (cM).   The   cost   of   the   acHvity,   based   on   realisHc   effort  

assessment  for  the  required  work  and  any  predicted  expenses.    •  OpHmisHc   (cO).   The   acHvity   cost   based   on   analysis   of   the   best-­‐case  

scenario  for  the  acHvity.    •  PessimisHc   (cP).   The   acHvity   cost   based   on   analysis   of   the   worst-­‐case  

scenario  for  the  acHvity.    •  Two  commonly  used  formulas  are  triangular  and  beta  distribuHons:  

ü Triangular  DistribuHon.  cE  =  (cO  +  cM  +  cP)  /  3    ü Beta  DistribuHon  (from  a  tradiHonal  PERT  analysis).  cE  =  (cO  +  4cM  +  cP)  /  6    

Copyright@STEVBROS   Project  Management  Fundamentals   14  

Tools  and  techniques(3/3)  

6.   Reserve  Analysis    •  Cost   esHmates   may   include   conHngency   reserves   (someHmes   called  

conHngency  allowances)  to  account  for  cost  uncertainty.  7.   Cost  of  Quality  (COQ)  (details  in  next  slide)  8.   Project  Management  So^ware    9.   Vendor  Bid  Analysis    

•  include  analysis  of  what  the  project  should  cost,  based  on  the  responsive  bids   from   qualified   vendors.   When   projects   are   awarded   to   a   vendor  under   compeHHve   processes,   addiHonal   cost   esHmaHng   work   may   be  required   of   the   project   team   to   examine   the   price   of   individual  deliverables   and   to   derive   a   cost   that   supports   the   final   total   project  cost.  

10.   Group  Decision-­‐Making  Techniques  •  team-­‐based   approaches,   such   as   brainstorming,   the   Delphi   or   nominal  

group   techniques,   are   useful   for   engaging   team   members   to   improve  esHmate  accuracy  and  commitment  to  the  emerging  esHmates.    

Copyright@STEVBROS   Project  Management  Fundamentals   15  

Cost  of  quality  

Copyright@STEVBROS   Project  Management  Fundamentals   16  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  8-­‐5  Page  235.  

Outputs  1.   Ac%vity  Cost  Es%mates  

•  Direct  Cost:   costs   that  are  directly  aVribute   to  work  on   the  project.  eg.  training  cost,  travel  cost,  wages,  cost  of  material  used  in  the  project,  etc  

•  Indirect  Cost:  overhead   items  or   costs   incurred   for   the  benefit  of  more  than  one  project.  eg.  taxes,  fringe  benefits,  etc  

•  Variable   Cost:   change   with   the   amount   of   producHon/work.   e.g.   material,  supplies,  wages  

•  Fixed  Cost:  do  not  change  as  producHon  change.  e.g.  set-­‐up,  rental  2.   Basis  of  Es%mates    

•  DocumentaHon  of  the  basis  of  the  esHmate  (i.e.,  how  it  was  developed),    •  DocumentaHon  of  all  assumpHons  made,    •  DocumentaHon  of  any  known  constraints,    •  IndicaHon   of   the   range   of   possible   esHmates   (e.g.,   €10,000   (±10%)   to  

indicate  that  the  item  is  expected  to  cost  between  a  range  of  values),  and    •  IndicaHon  of  the  confidence  level  of  the  final  esHmate.    

3.   Project  Documents  Updates    Copyright@STEVBROS   Project  Management  Fundamentals   17  

Determine  budget  •  The  process  of   aggregaHng   the  esHmated   costs  of   individual  

acHviHes   or   work   packages   to   establish   an   authorized   cost  baseline.  The  key  benefit  of  this  process  is  that  it  determines  the   cost   baseline   against  which   project   performance   can   be  monitored  and  controlled.  

Copyright@STEVBROS   Project  Management  Fundamentals   18  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐6  Page  208.  

Inputs(1/2)  1.   Cost  Management  Plan  

•  describes  how  the  project  costs  will  be  managed  and  controlled.      2.   Scope  Baseline    

•  includes  project  scope  statement,  WBS,  WBS  dicHonary.  3.   Ac%vity  Cost  Es%mates    

•  cost   esHmates   for   each   acHvity   within   a   work   package   are  aggregated  to  obtain  a  cost  esHmate  for  each  work  package.    

4.   Basis  of  Es%mates    •  supporHng   detail   for   cost   esHmates   contained   in   the   basis   for  esHmates  should  specify  any  basic  assumpHons  dealing  with  the  inclusion   or   exclusion   of   indirect   or   other   costs   in   the   project  budget.    

Copyright@STEVBROS   Project  Management  Fundamentals   19  

Inputs(2/2)  5.   Project  Schedule  

•  This   informaHon   can   be   used   to   aggregate   costs   to   the   calendar  periods  in  which  the  costs  are  planned  to  be  incurred.    

6.   Resource  Calendars    7.   Risk  Register    

•  The   risk   register   should  be   reviewed   to   consider  how   to   aggregate  the  risk  response  costs.  

8.   Agreements    •  Applicable   agreement   informaHon   and   costs   relaHng   to   products,  services,  or  results  that  have  been  or  will  be  purchased  are  included  when  determining  the  budget.    

9.   Organiza%onal  Process  Assets  •  ExisHng   formal   and   informal   cost   budgeHng-­‐related   policies,  procedures,   and   guidelines;   cost   budgeHng   tools;   and   reporHng  methods.  

Copyright@STEVBROS   Project  Management  Fundamentals   20  

Tools  and  techniques  

1.   Cost  Aggrega%on    •  Cost  esHmates  are  aggregated  by  work  packages  in  accordance  with  the  WBS.  The  

work  package  cost  esHmates  are  then  aggregated  for  the  higher  component   levels  of  the  WBS  (such  as  control  accounts)  and  ulHmately  for  the  enHre  project.    

2.   Reserve  Analysis    •  Budget   reserve   analysis   can   establish   both   the   conHngency   reserves   and   the  

management  reserves  for  the  project.  3.   Expert  Judgment    

•  guided  by  experience  in  an  applicaHon  area,  knowledge  area,  discipline,  industry,  or  similar  project,  aids  in  determining  the  budget.  

4.   Historical  Rela%onships    •  Any   historical   relaHonships   that   result   in   parametric   esHmates   or   analogous  

esHmates   involve   the   use   of   project   characterisHcs   (parameters)   to   develop  mathemaHcal  models  to  predict  total  project  costs.  

5.   Funding  Limit  Reconcilia%on  •  The   expenditure   of   funds   should   be   reconciled   with   any   funding   limits   on   the  

commitment  of  funds  for  the  project.  A  variance  between  the  funding  limits  and  the  planned  expenditures  will  someHmes  necessitate  the  rescheduling  of  work  to  level  out  the  rate  of  expenditures.  

Copyright@STEVBROS   Project  Management  Fundamentals   21  

Outputs  1.   Cost  Baseline  

•  is  the  approved  version  of  the  Hme-­‐phased  project  budget,  excluding  any  management  reserves  (details  at  next  slide)  

2.   Project  Funding  Requirements    •  total   funding   requirements   and   periodic   funding  requirements   (e.g.,   quarterly,   annually)   are   derived   from  the  cost  baseline.  The  cost  baseline  will   include  projected  expenditures  plus  anHcipated  liabiliHes.    

•  the   total   funds   required   are   those   included   in   the   cost  baseline,  plus  management  reserves,  if  any.    

3.   Project  Documents  Updates    •  such   as   risk   register,   acHvity   cost   esHmates,   and   project  schedule.    

Copyright@STEVBROS   Project  Management  Fundamentals   22  

Project  budget  

Copyright@STEVBROS   Project  Management  Fundamentals   23  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐8  Page  213.  

Project  budget  

Copyright@STEVBROS   Project  Management  Fundamentals   24  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐9  Page  214.  

Control  cost  •  The  process  of  monitoring  the  status  of  the  project  to  update  

the  project  costs  and  managing  changes  to  the  cost  baseline.  The  key  benefit  of  this  process  is  that  it  provides  the  means  to  recognize   variance   from   the  plan   in  order   to   take   correcHve  acHon  and  minimize  risk.    

Copyright@STEVBROS   Project  Management  Fundamentals   25  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐10  Page  215.  

Inputs  1.  Project  Management  Plan    

•  contains  cost  baseline  and  cost  management  plan.  2.  Project  Funding  Requirements    

•  requirements   include   projected   expenditures   plus   anHcipated  liabiliHes.    

3.  Work  Performance  Data  •  data  includes  informaHon  about  project  progress,  such  as  which  acHviHes   have   started,   their   progress,   and   which   deliverables  have   finished.   InformaHon   also   includes   costs   that   have   been  authorized  and  incurred.    

4.  OrganizaHonal  Process  Assets    •  include   exisHng   formal   and   informal   cost   control-­‐related  policies,   procedures,   and   guidelines;   cost   control   tools;   and  monitoring  and  reporHng  methods  to  be  used.    

Copyright@STEVBROS   Project  Management  Fundamentals   26  

Tools  and  techniques  

1.   Earned  Value  Management  (next  slides)  2.   Forecas%ng  (next  slides)  3.   To-­‐Complete  Performance  Index  (TCPI)  (next  slides)  4.   Performance  Reviews  (next  slides)  5.   Project  Management  So^ware    6.   Reserve  Analysis    

•  During  cost  control,  reserve  analysis  is  used  to  monitor  the  status  of  conHngency  and  management  reserves    for  the  project  to  determine  if  these  reserves  are  sHll  needed  or  if  addiHonal  reserves  need  to  be  requested.    

Copyright@STEVBROS   Project  Management  Fundamentals   27  

EVM  •  Earned   Value   Management   (EVM):   is   the   most  common   tool   which   help   project   managers  measure   project   performance   and   determine  where   the   project   stands   in   relaHon   to   the  budget  and  the  schedule  at  a  point  in  Hme.  

•  Work  performance  informaHon:  BAC,  PV,  EV,  AC.  •  Work   performance   measurement:   CPI,   CV,   SPI,  SV.  

•  ForecasHng:  ETC,  EAC.  •  To-­‐Complete  Performance  Index:  TCPI.  

Copyright@STEVBROS   Project  Management  Fundamentals   28  

EVM  

• Work  performance  informaHon:  o BAC-­‐  Budget  At  CompleHon  (project  budget).  o PV  -­‐  Planned  Value  (value  of  work  schedule):    PV  =  BAC  *  planned  %  complete.  o EV  -­‐  Earned  Value  (value  of  work  performed):    EV  =BAC  *  actual  %  complete.  o AC—Actual  Cost  (spent  cost).  

Copyright@STEVBROS   Project  Management  Fundamentals   29  

EVM  

•  Work  performance  measurement:  o  SPI—Schedule  Performance  Index  =  EV/PV.      If  SPI    >  1,  you’re  ahead  of  schedule.  If  SPI  <  1,  you’re  behind  schedule.  

o  SV—Schedule  Variance  =  EV-­‐PV.      If  SV  >  0,  it  tells  you  how  many  dollars  you’re  ahead.  If  SV  <  0,  it  tells  you  how  many  dollars  you’re  behind.  

o  CPI—Cost  Performance  Index  =  EV/AC.      If  CPI    >  1,  you’re  under  budget.  If  CPI  <  1,  you’re  over  budget.  

o  CV—Cost  Variance  =  EV-­‐AC.        If  CV  >  0,  it  tells  you  how  many  dollars  you’re  above.  If  CV  <  0,  it  tells  you  how  many  dollars  you’re  below.  

Copyright@STEVBROS   Project  Management  Fundamentals   30  

EVM  

Copyright@STEVBROS   Project  Management  Fundamentals   31  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐12  Page  219.  

EVM  

•  ForecasHng:  o EsHmate   to  Complete   (ETC),  which   tells   you  how  much  more  money  you’ll  probably  spend  on  your  project.  

o EsHmate   at   CompleHon   (EAC)   is   used   to   predict  what   your   project   will   actually   cost   when   it’s  complete.  

o EAC  =  AC  +  boVom-­‐up  ETC  

 

Copyright@STEVBROS   Project  Management  Fundamentals   32  

EVM  

•  ForecasHng:  o  EAC  forecast  for  ETC  work  performed  at  the  budgeted  rate.  This  EAC  

method   accepts   the   actual   project   performance   to   date   (whether  favorable   or   unfavorable)   as   represented   by   the   actual   costs,   and  predicts  that  all  future  ETC  work  will  be  accomplished  at  the  budgeted  rate.  EquaHon:  EAC  =  AC  +  (BAC  -­‐  EV)    

o  EAC  forecast  for  ETC  work  performed  at  the  present  CPI.  This  method  assumes  what  the  project  has  experienced  to  date  can  be  expected  to  conHnue   in   the   future.  The  ETC  work   is  assumed  to  be  performed  at  the  same  cumulaHve  cost  performance  index  (CPI)  as  that  incurred  by  the  project  to  date.  EquaHon:  EAC  =  BAC  /  CPI    

o  EAC   forecast   for   ETC  work   considering   both   SPI   and   CPI   factors.   In  this  forecast,  the  ETC  work  will  be  performed  at  an  efficiency  rate  that  considers   both   the   cost   and   schedule   performance   indices.   This  method  is  most  useful  when  the  project  schedule  is  a  factor  impacHng  the  ETC  effort.  EquaHon:  EAC  =  AC  +  [(BAC  -­‐  EV)  /  (CPI  ×  SPI)]    

Copyright@STEVBROS   Project  Management  Fundamentals   33  

EVM  

•  To-­‐Complete   Performance   Index   (TCPI):   is   a  measure   of   the   cost   performance   that   is   required   to   be   achieved   with   the  remaining  resources  in  order  to  meet  a  specified  management  goal,  expressed  as  the  raHo  of  the  cost  to  finish  the  outstanding  work  to  the  remaining  budget.  

Copyright@STEVBROS   Project  Management  Fundamentals   34  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐13  Page  222.  

EVM  

Copyright@STEVBROS   Project  Management  Fundamentals   35  

Outputs  1.   Work  Performance  Informa%on  

•  The   calculated   CV,   SV,   CPI,   SPI,   TCPI,   and  VAC   values   for  WBS  components,   in   parHcular   the   work   packages   and   control  accounts,  are  documented  and  communicated  to  stakeholders.  

2.   Cost  Forecasts  •  EAC  value  is  documented  and  communicated  to  stakeholders.  

3.   Change  Requests  •  analysis  of  project  performance  may  result  in  a  change  request  to   the   cost   baseline   or   other   components   of   the   project  management  plan.  

4.   Project  Management  Plan  Updates  5.   Project  Documents  Updates  6.   Organiza%onal  Process  Assets  Updates  

Copyright@STEVBROS   Project  Management  Fundamentals   36  

Summary  

•  Cost  esHmaHng  techniques  •  The  accuracy  of  a  project  esHmate  •  Project  budget  vs.  cost  baseline  •  Management  reserve  vs.  conHngence  reserve  •  Earned   value   management:   PV,   AC,   EV,   CPI,  SPI,  CV,  SV,  ETC,  EAC,  TCPI.  

Copyright@STEVBROS   Project  Management  Fundamentals   37  

QuesHons  for  review  

Copyright@STEVBROS   Project  Management  Fundamentals   38  

•  You  did  the  good  job  at  this  chapter.    Please  complete  quesHons  for  review  before  moving  to  next  chapter.