Project Cost Management Questions

download Project Cost Management Questions

of 29

Transcript of Project Cost Management Questions

  • 8/10/2019 Project Cost Management Questions

    1/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-q uestions/project-cost-manag ement-q uestions/ 1/29

    Project Cost Management Questions

    Results0 of 105 questions answered correctly

    Your time: 00:00:07

    You have reached 0 o f 105 points, (0%)

    Keep Trying!

    Restart quiz View questions

    HOME PMBOK 5 EXAM QUESTIONS PAY & REGISTER LOGIN PROFILE CONTACT

    1. QuestionYour project has a budget of $10,000 and is expected to last for 1 year, with the work and budget spread evenly across all months. Right now CPI is 0.8. What

    is Variance at Completion in this case?

    $12,500

    -$2,500

    $10,000

    $12,000

    Incorrect

    Variance at Completion = BAC EAC Estimate at Completion (EAC) =BAC / CPI = $10,000 / .8 = $12,500 Variance at Completion = $10,000 $12,500 = -$2,500

    2. Question

    In an underground highway construction project, the project stakeholders have suggested many changes to the project scope. As you have already defined

    the cost baseline in your project, you would like to revisit the baseline to see how these changes impact the overall cost of the project. So, you have started

    an impact analysis to determine the impact, and inform the concerned stakeholders of all approved changes and the corresponding costs. You must use the

    following to carry out such process:

    Control Costs

    Control Scope

    Control Communications

    Control Risks

    Incorrect

    The Control Costs process involves many activities such as influencing the factors that change the cost baseline, managing the actual changes, and

    informing stakeholders of approved changes and corresponding costs. Since you are in the process of managing the cost changes and informing them to

    the stakeholders, you are in the Control Costs process. [PMBOK 5th edition, Page 215]

    3. Question

    Lucy is currently preparing a high-level cost estimate for her project in the initiation phase. Given the limited detail available to her, what would you expect

    the range of her estimate to be and what would you call such an estimate?

    http://www.pmpden.com/http://www.pmpden.com/pmbok-5-exam-questions/http://www.pmpden.com/http://www.pmpden.com/premise-membership/contact/http://www.pmpden.com/premise-membership/member-profile/http://www.pmpden.com/premise-membership/login/http://www.pmpden.com/checkout-option/http://www.pmpden.com/pmbok-5-exam-questions/http://www.pmpden.com/http://www.pmpden.com/
  • 8/10/2019 Project Cost Management Questions

    2/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-q uestions/project-cost-manag ement-q uestions/ 2/29

    -5 to +10 %, Narrow

    -25 to +25 %, Rough Order of Magnitude

    -25 to +75 %, Rough Order of Magnitude

    -1 to +1 %, Definitive

    Incorrect

    During the initial stages of the project, the level of information available will be limited. Hence the Rough Order of Magnitude (ROM) estimate is usually

    prepared and has an accuracy range of -25% to +75%. [PMBOK 5th edition, Page 201]

    4. Question

    The most recent analysis of Microcorps new fabrication facility renovation shows a CPI value of less than 1.0 What does this indicate?

    The cost has underrun estimates

    The co st has overrun es timates.

    The schedule has slipped.

    The project is running ahead of schedule.

    Incorrect

    A CPI value o f less than 1.0 indicates a cost overrun o f the estimates. A CPI value greater than 1.0 indicates a cost underrun of the estimates. [PMBOK 5th

    edition, Page 219]

    5. Question

    Variance analysis refers to cost performance measurements used to assess the magnitude of variation in comparison to the original cost baseline. What is

    the trend on the percentage range of acceptable variances as the project progresses?

    The percentage range of acceptable variances will tend to decrease first and then increase as the project progresses beyond 50% completion.

    The percentage range of acceptable variances remain the same as the project progresses.

    The percentage range of acceptable variances will tend to increase as the project progresses.

    The percentage range of acceptable variances will tend to decrease as the project progresses.

    Incorrect

    During the start of the project, larger percentage variances are allowed. However, as more work is accomplished, the percentage range o f acceptable

    variances will tend to decrease. [PMBOK 5th edition, Page 222]

    6. Question

    If you would like to base your project cost estimate on historical data and statistical analysis, which cost estimation technique would you use?

    Parametric Estimating

    Analogous Estimating

    Vendor Bid Analysis

    Bottom-up Estimating

    Incorrect

    Parametric estimating is the process of using historical data to compare against your project to determine a correlation and thereby a cost estimate for

    your current project. [PMBOK 5th Edition, Page 205]

  • 8/10/2019 Project Cost Management Questions

    3/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-q uestions/project-cost-manag ement-q uestions/ 3/29

    7. Question

    You have just started a project. A project team member reports that 20 percent of the project is done. You agree with the completion status, but do not

    change any of the progress in your report to the customer. This is an example of which one of the following?

    50/50 Rule

    Percent Complete Rule

    0/100 Rule

    20/20 rule

    Incorrect

    The 0/100 Rule allows for zero percent credit on an activity until it is 100 percent complete. B is wrong (50/50 rule): 50 percent completion when the work

    begins and 50 percent when the work is completed.

    8. Question

    A project manager is trying to p lan for a contingency reserve as part of the cost estimates for the project. Which of these would be an incorrect way to plan

    for contingency reserves?

    Start the project with a zero value for co ntingency reserve.

    Plan for contingency reserve as a fixed number.

    Plan for contingency reserve as a percentage of the estimated cost

    Use quantitative analysis methods to arrive at the contingency reserve.

    Incorrect

    It would be incorrect to start the project with a zero value for contingency reserves. One of the three methods listed could be used to arrive at a

    contingency reserve number. As more precise information about the project is available, the contingency reserve may be used, reduced or eliminated.

    [PMBOK 5th edition, Page 206]

    9. Question

    You have a piece of equipment that was purchased for your project recently for $5,000 and is expected to last 5 years in production. At the end of the five

    years, the expected worth of the equipment is $2,000. Using the straight-line depreciation, what is the amount that can be written off each year?

    $600

    $1200

    $3000

    Zero

    Incorrect

    The straight-line depreciation takes the purchase value of the item, minus the salvage price of the item, divided by the number of time periods. Calculation

    is (5000-2000)/5 = $600.

    10. Question

    What is the present value if the organization expects to make $500,000 three years from now and the annual interest rate is 4 percent?

    $26000

    $25000

    $4000

    $5000

  • 8/10/2019 Project Cost Management Questions

    4/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-q uestions/project-cost-manag ement-q uestions/ 4/29

    Incorrect

    Present Value = FV/(1+R)n. FV is the future value, R is the interest rate, and n is the number of time periods. 500000/(5*5*5) = 4000.

    11. Question

    An estimating technique that uses a statistical relationship between historical data and other variables (for example, square footage in construction, lines o f

    code in software development) is known as:

    Analogous Estimating

    Bottom-up Estimating

    Parametric Estimating

    Historical Analysis

    Incorrect

    This technique is known as Parametric Estimating and can produce higher levels of accuracy depending on the sophistication, as well as the underlying

    resource quantity and cost data built into the model. [PMBOK 5th edition, Page 205]

    12. Question

    Which of the below statement is true about Earned Value (EV)?

    Earned Value (EV) is the physical work completed to date and the authorized budget for that

    A ll

    It is also called as BCWP (Budgeted Cost of Work Performed.)

    It compares the amount of work that was planned with what was actually accomplished to determine if cost and schedule performance is as planned

    Incorrect

    It compares the amount of work that was planned with what was actually accomplished to determine if cost and schedule performance is as planned.

    Earned Value (EV) is the physical work completed to date and the authorized budget for that. It is also called as BCWP (Budgeted Cost of Work Performed).

    13. Question

    The formula for Cost Variance is:

    CV=BAC-(AC-EV)

    CV=EV-AC

    CV=SV-BC

    CV=AC-EV

    Incorrect

    CV equals earned value (EV) minus actual cost (AC). [PMBOK 5th edition, Page 218]

    14. Question

    Which of the below statement is true about Cost Variance (CV)?

    Negative CV, this means that the project is over budget

    Any difference between the estimated cost of an activity and the actual cost of that activity

  • 8/10/2019 Project Cost Management Questions

    5/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-q uestions/project-cost-manag ement-q uestions/ 5/29

    Negative CV, this means that the p roject is over bu dget and Any difference between the estimated cos t of an activity and the

    actual cost o f that activity

    None

    Incorrect

    Any difference between the estimated cost of an activity and the actual cost of that activity.

    15. Question

    You are a project manager who is in charge of an important project for your company. The project is 40% complete after 3 months and has cost $350,000.

    The budget for the project is $950,000 and is scheduled to last 8 months. How is the project performing?

    The project is behind schedule and over budget.

    The project is ahead of schedule and under budget

    The project is behind schedule and under budget

    The project is ahead of schedule and over budget

    Incorrect

    CPI=EV/AC CPI=(950,00*40%)/350,000 CPI=380,000/350,000 CPI=1.09(under budget); SPI=EV/PV SPI=380,000/(950,00 x 0.375) SPI=380,000/36,250 SPI=1.07

    (ahead of schedule). [PMBOK 5th edition, Page 224]

    16. Question

    Two efficiency indicators that reflect the cost and schedule performance of a project are:

    Cost Performance Index (CPI) and Schedule Performance Index (SPI)

    Actual Cost (AC) and Planned Value (PV)

    Cost Projection Index (CPI) and Schedule Projection Index (SPI)

    Cost Pricing Index (CPI) and Schedule Performance Index (SPI)

    Incorrect

    The Cost Performance Index (CPI) and the Schedule Performance Index (SPI) are two efficiency indicators in the project to reflect the cost and schedule

    performance of the project. [PMBOK 5th edition, Page 219]

    17. Question

    The Cost Management Plan is an output o f the Plan Cost Management process. This plan is then integrated with other project plans in which of these

    processes?

    Develop Project Management Plan

    Monitor and Control Project Work

    Direct and Manage Project Work

    Perform Integrated Change Control

    Incorrect

    The cost management plan is a component o f the project management plan. Once the cost management plan is developed, it is integrated to the projectmanagement plan during the Develop Project Management Plan process. [PMBOK 5th edition, Page 198]

    18. Question

  • 8/10/2019 Project Cost Management Questions

    6/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-q uestions/project-cost-manag ement-q uestions/ 6/29

    Which of the below statement is true about Cost Performance Index (CPI)?

    If CPI is less than 1, this means that the project is over budget

    If CPI is less than 1, this means that the project is over budget and also CPI = EV (Earned Value) / AC (Actual Cost)

    CPI = EV (Earned Value) / AC (Actual Cost)

    None are true

    Incorrect

    CPI = EV (Earned Value) / AC (Actual Cost) If CPI is less than 1, this means that the project is over budget.

    19. Question

    You have just been informed by your manager that you must present your project budget at a monthly executive level project review meeting prior to

    submitting it for approval by the sponsor. This meeting is nex t week. However, the scope for this project has not yet been finalized, nor has the project

    schedule. When you inform your manager of this fact, he advises you to just ballpark your budget. What do you do?

    Come up with a rough order of magnitude estimate using parametric estimating technique

    Come up with a rough o rder of magnitude estimate using analogo us estimating technique

    Come up with a narrow estimate using parametric estimating technique

    Come up with a narrow estimate using analogous estimating technique

    Incorrect

    You should come up with a rough order o f magnitude estimate that is usually referred to as -25% to +75% estimate. You can quickly do this by using

    analogous estimating technique. [PMBOK 5th edition, Page 201, 204]

    20. Question

    You have elected to use bottom-up estimating and will base your estimates on the WBS. Which one of the following is not an attribute of bottom-up

    estimating?

    People do ing the work create the estimates

    Less expensive to do than other methods of estimations

    More expensive to do than other methods of estimations

    Creates a more accurate estimate

    Incorrect

    The bottom-up estimating is expensive. It is accurate. Estimating the cost of individual work items and then rolling up the costs to arrive at a project total

    is more accurate.

    21. Question

    What does it mean if the Earned Value is equal to Actual Cost?

    Project is on budget and on schedule

    There is no co st variance

    Schedule Variance Index is 1

    There is no schedule variance

    Incorrect

  • 8/10/2019 Project Cost Management Questions

    7/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-q uestions/project-cost-manag ement-q uestions/ 7/29

    CV = EV AC. If the EV is equal to the AC then there is no cost variance on the project. [PMBOK 5th edition, Page 218]

    22. Question

    The Earned Value Management methodology can be used as a means to:

    Calculate the profitability of the project

    Calculate the number of days left in the project

    Forecast future performance based on past performance

    Calculate the value provided to the customer

    Incorrect

    The Earned Value Management methodology can be used as a means to forecast future performance based on past performance. [PMBOK 5th edition,

    Page 217]

    23. Question

    A large construction project for a logistics company will require the expenditure of a large amount of capital. The finance group works with the project

    manager to project set limits when expenses will be incurred in a g iven project, and determine if there are ways to smooth out or level the spending to avoid

    a single large expenditure one quarter and none the next. This is an example of:

    Funding Limit Reconciliation

    Rescheduling

    Levelized Billing

    A financial review

    Incorrect

    Large variations in the periodic expenditure of funds are usually undesirable for organizational operations. Therefore, the expenditure of funds is

    reconciled with the funding limits set by the customer or performing organization on the d isbursement of funds for the project. [PMBOK 5th edition, Page

    212]

    24. Question

    A project manager is performing Reserve Analysis as a technique in one of the project management process that he is currently working on. Which of these is

    likely to be that process?

    Estimate Costs

    Report Costs

    Estimate Reserves

    Plan Costs

    Incorrect

    Many cost estimators include reserves (also called contingency allowances), as costs in their schedule activity cost estimates. Contingency reserves are

    estimated costs to be used at the discretion of the project manager to deal with anticipated but not certain events. These events are known unknowns

    and are part of the project scope and cost baselines. [PMBOK 5th edition, Page 206]

    25. Question

    Variance Analysis is an important tool used in the Control Costs Process. Which of the following statements regarding variances is correct?

    The percentage rang e of acceptable variances will tend to decrease as more work is accomplished

  • 8/10/2019 Project Cost Management Questions

    8/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-q uestions/project-cost-manag ement-q uestions/ 8/29

    The percentage range of acceptable variances will tend to increase as more work is accomplished

    The percentage range of acceptable variances is high at the start of a project, tends to decrease in the middle of a project, and then tends to increase

    as the project nears completion

    The percentage range of acceptable variances is a constant all through the project

    Incorrect

    Variances assess the magnitude of variation to the original cost baseline. The percentage range of acceptable variances will tend to decrease as more work

    is accomplished and the project nears completion. [PMBOK 5th edition, Page 222]

    26. Question

    You are a senior project manager working for RETAMART, a retail shopping network that sells various consumer products. As part of the expansion p lan

    approved by the board o f directors, you have been assigned as a project manager for a new plant. Due to transportation problems, the project has

    undergone delays and the Schedule Performance Index (SPI) is found to be at 0.6 and the cost performance index (CPI) at 0.7. However, you expect some

    improvements over next few weeks that may change schedule performance index to 1.1 and cost performance index to 0.9. Which of the following

    statements will be true if your anticipated changes materialize?

    The project will be on schedule and under budget

    The project will be under budget but behind schedule

    The project will be overspent but ahead o f schedule

    The project will be overspent and behind schedule

    Incorrect

    The cost performance index above 1 indicates that the project is under budget and the schedule performance index above 1 indicates that the project is

    ahead of schedule. If all of your anticipated changes happen to be true, the project will be overspent but ahead of schedule because the schedule

    performance index will be greater than 1. [PMBOK 5th edition, Page 219]

    27. Question

    Which of these are not inputs to the Determine Budget process?

    Project schedule, agreements

    Co st baseline, requirements traceability matrix

    Basis of estimates, activity cost estimates

    Project schedule, resource calendars

    Incorrect

    The cost baseline and the requirements traceability matrix are not inputs to the Determine Budget process. The rest are valid inputs. [PMBOK 5th edition,

    Page 208]

    28. Question

    You are the project manager for the construction of a new Building. Before you begin to determine the budgeting process, which of the following inputs will

    help you?

    A ll

    Activity Costs estimates and project schedule

    Contracts

    Scope Baseline

    Incorrect

  • 8/10/2019 Project Cost Management Questions

    9/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-q uestions/project-cost-manag ement-q uestions/ 9/29

    Four determine budget, inputs are: Activity Costs estimates and project schedule, Scope Baseline, Contracts, Basis of estimates and Organizational process

    assets.

    29. Question

    An estimating technique that uses a statistical relationship between historical data and other variables (for example, square footage in construction, lines o f

    code in software development) is known as:

    Historical Analysis

    Bottom-up Estimating

    Parametric Estimating

    Analogous Estimating

    Incorrect

    This technique is known as Parametric Estimating and can produce higher levels of accuracy depending on the sophistication, as well as the underlying

    resource quantity and cost data built into the model. [PMBOK 5th edition, Page 205]

    30. Question

    Funding requirements for a project are usually in incremental amounts that are not continuous, and these appear as a step function in the graph depicting

    Cash flow, Cost baseline and Funding. Any gap at the end o f the project, between the funds allocated and the cost baseline represents:

    Contingency reserves

    Charting error

    Management reserves

    Cost variance

    Incorrect

    Management reserves are included in the pro jects total funds but they are not included in the pro jects cost performance baseline. [PMBOK 5th edition,

    Page 214]

    31. Question

    Megawatt is estimating the overall expected cost of a new ERP system deployment project using the actual costs of an earlier similar ERP system deployment

    project as the basis for the cost. This is what type of estimating?

    Analogous

    Bottom-up

    Expert Judgment

    Parametric

    Incorrect

    Analogous cost estimating means using the actual cost of previous, similar projects as the basis for estimating the cost of the current project. Analogous

    cost estimating is frequently used to estimate costs when there is a limited amount of detailed information about the project (e.g., in the early phases).

    [PMBOK 5th edition, Page 204]

    32. Question

    You are the project manager of an AC Installation Project for a new building. Your BAC is $500,000. You are now 50 percent done with the project, though

    your plan called for you to be 55 percent done with the work at this time. What is your earned value?

  • 8/10/2019 Project Cost Management Questions

    10/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 10/29

    $250,000

    $275,000

    $500,000

    $345,000

    Incorrect

    The earned value is calculated by multiplying the percentage of completion, 50 percent, by the BAC, which is $500,000, for a value of $250,000.

    33. Question

    Which statement is true about project cost?

    All of the above

    The cost of the equipment and materials needed to complete the project work must be factored into the project expenses

    Costs associated with projects are not just the costs of goods procured to complete the project.

    The cost of the labour may be one of the biggest expenses o f a project.

    Incorrect

    All are true

    34. Question

    You will be reporting to management, for the week of 07/15, that your project has an EV of $7700 and a PV of $9600. What is the status of your project?

    Ahead of Schedule

    On schedule

    Not enough information provided

    Behind Schedule

    Incorrect

    Your project is behind schedule. You had expected to have $9600 worth of work completed, that is your planned value (PV). However, you completed

    $7700 (EV) worth of work. Your schedule variance is -$1900, SV=EV-PV. [PMBOK 5th Edition, Page 218]

    35. Question

    You are the Project Manager for Wicked Fast Cars, Corp. You are working on a project for the Human Resources department that is scheduled to take one

    year. After three months into the project, you calculate the EV at $35,000 and the PV at $45,000. Which option below represents the value for the SV?

    0.78

    1.29

    $10,000

    -$10,000

    Incorrect

    SV = Earned Value (EV) Planned Value (PV) SV = $35,000-$45,000 SV = -$10,000. [PMBOK 5th edition, Page 218]

    36. Question

    Which of the below statement is true?

  • 8/10/2019 Project Cost Management Questions

    11/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 11/29

    Actual Cost (AC): AC is the total cost incurred in accomplishing work on the schedule activity or WBS component during a g iven time period

    Budget At Completion (BAC): The estimated total cost of the project when done

    Determine Budget: Allocating the cost estimates to individual project components

    A ll

    Incorrect

    Budget At Completion (BAC): The estimated total cost of the project when done. Actual Cost (AC): AC is the total cost incurred in accomplishing work on the

    schedule activity or WBS component during a given time period. Determine Budget: Allocating the cost estimates to individual project components.

    37. Question

    Which of the following statements are NOT true considering the planned value, the earned value, the schedule variance and the cost variance of a project?

    The cost variance is the difference between the earned value and the actual cost

    The planned value is the budget authorized to the work to be performed

    The schedule variance is the difference between the earned value and the planned value

    The earned value is the value of work to be completed in terms of the approved b udget

    Incorrect

    Earned value is the value of the work already completed. This value is often expressed in terms of the approved budget assigned to the work completed.

    The earned value is measured against the performance measurement baseline. [PMBOK 5th edition, Page 218]

    38. Question

    Which statement is true about Bottom-up estimating?

    Estimating the cost o f individual work items and then rolling up the costs to arrive at a project total.

    None of the above

    Uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project.

    Both of the above are true.

    Incorrect

    Estimating the cost o f individual work items and then rolling up the costs to arrive at a project total is more accurate.

    39. Question

    Which of the following statement is true about Schedule Variance?

    Schedule Variance (SV): Any difference between the scheduled completion o f an activity and the actual completion of that activity

    Schedule Variance (SV): Any difference between the sched uled completion of an activity and the actual completion of that activity

    and a negative result means less work has been performed than was planned

    A negative result means less work has been performed than was planned

    None

    Incorrect

    Schedule Variance (SV): Any difference between the scheduled completion of an activity and the actual completion of that activity. SV = EV PV

  • 8/10/2019 Project Cost Management Questions

    12/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 12/29

    40. Question

    You are the project manager of a project which is scheduled to last for 18 months. You have elected to rent a piece of equipment for the duration o f a

    project, even though you will need the equipment only for 6 months. The costs of the equipment rental per month are $120. This is an example of ___________.

    None

    Parametric Costs

    Fixed Costs

    Variable Costs

    Incorrect

    This is an example of Fixed Costs because $120 per month is fixed.

    41. Question

    You are in the initiation phase of your project and believe the project can be completed for $100,000. However, you are an experienced project manager and

    know that many things can happen between the initiation phase and the closure of the project. You have provided an estimate in the project charter of

    $75,000 $175,000. This is an example of?

    True Estimate

    Narrow Estimate

    Absolute Estimate

    Rough Order of Magnitude Estimate

    Incorrect

    A ROM estimate is given in the beginning of a project and is defined as -25% to +75% of the estimated cost. [PMBOK 5th edition, Page 201]

    42. Question

    As a project manager, you periodically do project performance reviews to compare cost performance over time, schedule activities or work packages over-

    running and under-running budget, milestones due, and milestones met. Which of the following is not a valid analytical technique?

    Earned Value Performance

    Trend Analysis

    Variance Analysis

    Interpersonal skills

    Incorrect

    Interpersonal skills is not a valid choice. The other three choices, namely Variance Analysis, Trend Analysis and Earned Value Performance, are analytical

    techniques. [PMBOK 5th edition, Page 91, 92]

    43. Question

    Which of the following are inputs of Estimate Costs?

    Risk Register

    Human Resource Plan

    A ll

    Scope Baseline

    Incorrect

  • 8/10/2019 Project Cost Management Questions

    13/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 13/29

    Input of Estimate Costs: Scope Baseline, Human Resource Plan, Risk Register, Organizational process assets and Enterprise environmental factors.

    44. Question

    If You are the project manager for a Project. You are about to create the cost estimates for the project. Which of the following inputs will help you?

    All of the above

    Human Resource Plan

    Risk Register

    Scope Baseline

    Incorrect

    Input of Estimate Costs are: Scope Baseline, Human Resource Plan, Risk Register, Organizational process assets and Enterprise environmental factors.

    45. Question

    If you want to print more than 25000 workbooks, printing of workbooks may be go up to 50000 workbooks . For every 5000 workbooks created, the cost isreduced a percentage of the original printing cost. The workbook expense is an example of which one of the following?

    Variable Costs

    None

    Fixed Costs

    Parametric Costs

    Incorrect

    This is an example of Variable Costs.

    46. Question

    Which of the following is the output of Estimate Costs process?

    Activity Cost Estimates

    WBS

    Project Scope Statement

    Output of Cost Estimation is Activity Cost Estimates.

    Incorrect

    47. Question

    20% of the work was completed in a project. At this stage the project manager determined that the budget at completion (BAC) was no longer viable and

    developed a forecasted estimate at completion (EAC). What index can the project manager use to look at the calculated projection of cost performance that

    must be achieved on the remaining work

    Schedule Performance Index (SPI)

    Cost Performance Index (CPI)

    Cost Variance (CV)

    To-Complete Performance Ind ex (TCPI)

    Incorrect

  • 8/10/2019 Project Cost Management Questions

    14/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 14/29

    The to-complete performance index (TCPI) is the calculated projection of cost performance that must be achieved on the remaining work to meet a

    specified goal such as the BAC or EAC. I t is defined as the work remaining divided by the funds remaining. [PMBOK 5th edition, Page 221]

    48. Question

    How would you calculate your EAC if the ETC work will be performed at the budgeted rate?

    EAC=(BAC-EV)*CPI

    EAC = BAC/CPI

    EAC= BAC-EV

    EAC = AC + BAC - E V

    Incorrect

    If the remaining project work is expected to be performed at the budgeted rate, the formula for EAC is AC + (BAC EV). [PMBOK 5th edition, Page 220]

    49. Question

    Large variations in the periodic expenditure of funds are undesirable for organizational operations. Therefore the expenditure of funds is frequently

    reconciled with the disbursement of funds for the project. According to the PMBOK, this is known as:

    Disbursement reconciliation

    Expenditure Reconciliation

    Budget Reconciliation

    Funding Limit Reconciliation

    Incorrect

    This is known as Funding Limit reconciliation. This will necessitate the scheduling o f work to be adjusted to smooth or regulate those expenditures.

    [PMBOK 5th edition, Page 212]

    50. Question

    Which is the least accurate approach in estimating?

    Rough Order of Magnitude

    Budget Estimate

    WBS Estimate

    Definitive Estimate

    Incorrect

    The Rough Order of Magnitude is the least accurate approach; it may vary from -25 percent to +75 percent.

    51. Question

    In the earned value management technique, the cost performance baseline is referred to as:

    Performance Base Value (PBV)

    Performance Cost Baseline (PCB)

    Cost Measurement Baseline (CMB)

    Performance Measurement Baseline (PMB)

  • 8/10/2019 Project Cost Management Questions

    15/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 15/29

    Incorrect

    The cost performance baseline is an authorized time-phased budget at completion (BAC). It is used measure, monitor, and control overall cost

    performance on the project. In the earned value management technique, it is referred to as the performance measurement baseline (PMB). [PMBOK 5th

    edition, Page 218, 223]

    52. Question

    You are the project manager of the MKTG Project. The project has a budget of $200,000 and is expected to last for 2 years. The project is now 20 percent

    complete and is on schedule. What is the BAC?

    $200,000

    $20,000

    $50,000

    $60,000

    Incorrect

    The BAC is the budget at completion (Total budgeted cost), which is $200,000.

    53. Question

    Which of the following are parts of Project Cost Management?

    A ll

    Estimate Costs

    Determine Budget

    Control Costs

    Incorrect

    Parts of Project Cost Management are: Plan Cost Management,Estimate Costs, Determine Budget and Control Costs.

    54. Question

    You are a project manager who is in charge of a technical documentation project. The project is 30% complete after 2 months and has cost $53,000. The

    budget for the project is $90,000 and is scheduled to last 6 months. How is the project performing?

    The project is ahead of schedule and under budget

    The project is behind schedule and under budget.

    The project is ahead of schedule and over budget.

    The project is behind schedule and over budget.

    Incorrect

    CPI=EV/AC CPI=(90,000*30%)/53,000 CPI=27,000/53,000 CPI=0.51(over budget) SPI=EV/PV SPI=27,000/(90,0000.33) SPI=27,000/29,970 SPI=0.9 (behind

    schedule). [PMBOK 5th edition, Page 219]

    55. QuestionWhich of the following statement is true ?

    Schedule Variance (SV): Any difference between the scheduled completion o f an activity and the actual completion of that activity

    A ll

  • 8/10/2019 Project Cost Management Questions

    16/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 16/29

    Cost Variance (CV): Any difference between the estimated cost of an activity and the actual cost of that activity.

    Schedule Performance Index (SPI): The ratio of work performed to work scheduled

    Incorrect

    Schedule Variance (SV): Any difference between the scheduled completion of an activity and the actual completion of that activity. Cost Variance (CV):

    Any difference between the estimated cost of an activity and the actual cost o f that activity. Schedule Performance Index (SPI): The ratio of work performed

    to work scheduled.

    56. Question

    Which of the following is the output of Determining Budget ?

    A ll

    Project Funding Requirements

    Cost Performance Baseline

    Project Document Updates

    Incorrect

    Outputs of Determine Budget: Cost Performance Baseline, Project Funding Requirements and Project Document updates.

    57. Question

    You are the project manager of an AC Installation Project for a new building. Your BAC is $500,000. You have spent $270,000 of your budget. You are now 50

    percent done with the project, though your plan called for you to be 55 percent done with the work at this time. What is the CPI?

    0.92

    0.82

    0.72

    0.45

    Incorrect

    CPI = EV / AC Earned Value/ Actual Cost The EV of $250,000 is divided by the AC of $270,000 for a value of .92.

    58. Question

    Your project is mid-way through a delivery schedule. As the project manager, you want to determine how much work is still left. Which is the most accurate

    way to determine the remaining work to be carried out by the project team?

    Earned Value Technique

    Rolling wave method

    A Manual forecast

    Future analysis

    Incorrect

    Although the Earned value technique of determining the balance work in the project is quick and automatic, it is not as valuable or accurate as the manual

    forecasting of the remaining work by the project team. This however is more time-consuming. [PMBOK 5th edition, Page 220]

    59. Question

    You have two possible projects to manage, but you can only choose one. Project MKTG is worth $23,000, while Project SALESPTR is worth $25,000.

  • 8/10/2019 Project Cost Management Questions

    17/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 17/29

    Management elects to choose Project SALESPTR. Which one of the following is the opportunity cost of this choice?

    $27,000

    $4000

    $23,000

    $50,000

    Incorrect

    The opportunity cost is the amount of the project that was not chosen.

    60. Question

    If you are influencing factors that create changes to the cost of the project, which process are you using?

    Determine Budget

    Estimate Costs

    Negotiate Costs

    Control Costs

    Incorrect

    Control Costs is the process of managing the projects costs and the changes that threaten the bottom line. [PMBOK 5th edition, Page 215]

    61. Question

    What is the BEST way to make an accurate forecasting of ETC?

    EAC - AC

    BAC EV

    Manual forecasting of cost of the remaining work.

    (BAC EV)/CPI

    Incorrect

    Manual forecasting of costs for remaining work is generally the best means of generating an accurate forecast. [PMBOK 5th edition, Page 220]

    62. QuestionA project is estimated to cost $ 50,000 with a timeline of 50 days. After 25 days, the project manager finds that 50% of the project is complete and Actual costs

    are $ 50,000. What is the Cost Performance Index (CPI) ?

    The CPI is 2

    The CPI is 1

    The CPI is 1.5

    The CPI is 0.5

    Incorrect

    The correct answer is 0.5. The Cost performance Index (CPI) is g iven by the formula CPI = EV/AC where EV is the Earned Value and AC is the Actual Cost.

    Earned Value = 50% of $ 50,000 = $ 25,000 since 50% of the project is complete. Hence CPI = 25,000 / 50,000 = 0.5. [PMBOK 5th edition, Page 219]

  • 8/10/2019 Project Cost Management Questions

    18/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 18/29

    63. Question

    Which one of the following best describes analogous estimating?

    Reserve analysis

    Less accurate

    Three-points estimates

    Bottom up estimating

    Incorrect

    Analogous estimating is less accurate than other estimating methods.

    64. Question

    The Cost Performance Baseline is a time-phased budget and is used as a basis to measure, monitor, and control overall cost performance of the project. It is

    usually displayed in the form of:

    An inverted S curve.

    An S-curve

    Pie-chart

    A Z curve

    Incorrect

    The correct response is S curve. The Cost Performance Baseline is a time-phased budget and is used as a basis to measure, monitor, and control overall

    cost performance of the project. It is usually displayed in the form of: an S curve and is developed by summing estimated costs by period. [PMBOK 5th

    edition, Page 213]

    65. Question

    Your project has a budget of $240,000 and is expected to last for 1 year, with the work and budget spread evenly across all months. The project is now in the

    fourth month, but the actual work completed is 20% of the total work. What is Schedule Performance Index (SPI) in this case?

    2.5

    1.66

    1.9

    1

    Incorrect

    Schedule Performance Index (SPI) = Earn Value / Planned Value Earn Value = (Total Cost / total project months) * total months completed = ($240,000 / 12)

    * 4 = $80,000 Planned Value = Total Cost *percentage actually completed = $240,000 * 20 / 100 = $48,000 SPI = $80,000 / $48,000 = 1.66

    66. Question

    Which of the following methods o f forecasting EAC and ETC is the most accurate?

    ETC based on BAC

    ETC based on CPI and SPI

    ETC based on CPI

    ETC based o n new estimate

    Incorrect

  • 8/10/2019 Project Cost Management Questions

    19/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 19/29

    The bottom-up ETC gives the most accurate results. [PMBOK 5th edition, Page 220]

    67. Question

    Your project has a budget of $10,000 and is expected to last for 1 year, with the work and budget spread evenly across all months. Right now CPI is 0.8. What

    is Estimate at Completion (EAC) in this case?

    2.5

    $12,500

    $10,000

    3.0

    Incorrect

    Estimate at Completion (EAC) = BAC / CPI = $10,000 / .8 = $12,500

    68. Question

    Which of the following statement is true about Project Scope Statement?

    It provides important information about project requirements that are considered during Estimating Costs

    The pro ject scope statement describes the business need, justification, requirements, and current boundaries of the project.

    A ll

    Contains project justification and the project objectives, which need to be considered

    Incorrect

    Project Scope Statement: The project scope statement describes the business need, justification, requirements, and current boundaries for the project. It

    provides important information about project requirements that are considered during Estimating Costs.

    69. Question

    ohn, a project manager, for Code Crashers Inc. has been assigned a project where he must lead a group of inexperienced programmers in developing a

    software package that creates Material Safety Data Sheets (MSDS) for a chemical company. This is very similar to a project that his colleague, Peter, worked on

    in 2006, with some junior programmers. If John needs to come up with a rough order of magnitude estimate, what tool or technique should he use?

    Bottom Up Estimating

    Parametric Estimating

    Analogou s Estimating

    Three-point estimate

    Incorrect

    Analogous estimating is the correct choice. This technique relies on parameters from a similar previous project and is a gross value estimating approach. It

    is also generally less accurate. [PMBOK 5th edition, Page 204]

    70. Question

    A project to construct 10 buildings in sequence, is estimated to cost $ 500,000 with a project timeline of 6 months. During a review after 3 months, the projectmanager finds that only 4 buildings are ready. The Actual Cost is $ 200,000. The Schedule Performance Index (SPI) of the project would then be:

    1.25

    0 .8

  • 8/10/2019 Project Cost Management Questions

    20/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 20/29

    Cannot be determined since the data is insufficient

    1

    Incorrect

    SPI = EV / PV. Earned Value = (4 / 10) * 500,000 = 200,000 since 4 buildings are completed out of 10. Planned Value = (5 / 10) * 500,000 = 250,000 since 5 of 10

    buildings were expected to be completed. Hence SPI = 200,000 / 250,000 = 4 / 5 = 0.8 [PMBOK 5th Edition, Page 219]

    71. Question

    You are a Project Manager for Groceries R US, a supermarket chain, and are currently working on a project to build a new outlet. The planned values (PV) for

    the foundation and the frame are $150,000 and $500,000. After five months, you do a performance measurement analysis. You are currently not ahead of

    schedule. The actual costs for the foundation and frame were $175,000 and $650,000 up to this point where 100% of the foundation is complete and only

    80% of the frame is complete. Which value represents the cost performance index (CPI) to two decimal places at this point in the project?

    1.19

    0.67

    0.84

    1.5

    Incorrect

    Get the total for the actual costs by adding the $175,000 and $650,000 for the foundation and frame. The total is $825,000. Now calculate earned value. We

    need to identify all of the activities that have been completed or partially completed as of the measurement date. If partially completed, we calculate the

    fractional value of the budgeted cost for the activity by the percent completion. Add together the budgeted cost for completed or partially completed work

    activities, INCLUDING any work that has been performed ahead of schedule. We are told that we are not ahead of schedule. So there is nothing to include

    for the ahead o f schedule category. 100% of the foundation is complete and only 80% of the frame is complete. So we add 100% of $150,000 and 80% of

    500,000, which is $400,000, together to get a total earned value of $550,000. Now find the CPI by taking the total for EV $550,000 up to this point and

    dividing it by the total of the actual cost $825,000 for the same time period. The result for CPI is 0.67. [PMBOK 5th edition, Page 219]

    72. Question

    Your project is running slightly over budget. You mention this to another project manager, who suggests you shift some of your expenses to indirect costs

    that are not charged to your project budget. What do you do?

    Examine project expenses to see if any are indirect expenses that could be taken off your project.

    Reestimate the project.

    Use your reserves.

    Fast track the project.

    Incorrect

    You should use your project reserves to cover the budget overruns. Project managers are required to d isclose accurate and truthful information about

    their projects. Masking an expense or otherwise using a half-truth to cover a budget overrun is a violation of the PMI Code. [Reference - PMBOK 5th

    edition, page 206 & PMI Code o f Ethics and Professional Conduct, Page 2, 4, 5]

    73. Question

    You are a project manager of a project. Till today you have actually completed $34,000 of work and based on the cost plan it should have been $50,000. What

    is Schedule Variance (SV) in this case?

    -$16,000

    $34,000

    $23,000

    $16,000

  • 8/10/2019 Project Cost Management Questions

    21/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 21/29

    Incorrect

    Schedule Variance (SV): Any difference between the scheduled completion of an activity and the actual completion of that activity. SV = EV PV SV = $34,000

    $50,000 = -$16,000

    74. Question

    A projects financial management reserve is identified in which process:

    Determine Budget

    Estimate Costs

    Control Costs

    Estimate Activity Resources

    Incorrect

    The Management Contingency Reserve is identified in the Determine Budget process. [PMBOK 5th edition, Page 213]

    75. Question

    The Cost Performance Baseline is a time-phased budget and is used as a basis to measure, monitor, and control overall cost performance of the project. It is

    usually displayed in the form of:

    Pie-chart

    An S-curve

    A Z curve

    An inverted S curve.

    Incorrect

    The correct response is S curve. The Cost Performance Baseline is a time-phased budget and is used as a basis to measure, monitor, and control overall

    cost performance of the project. It is usually displayed in the form of: an S curve and is developed by summing estimated costs by period. [PMBOK 5th

    edition, Page 213

    76. Question

    The Actual Cost (AC) is the total cost actually incurred and recorded in accomplishing work performed for an activity or work breakdown structure

    component. What is the upper limit for the AC?

    The Actual Cost (AC) is limited to the Planned Value (PV).

    50% over and above the Planned Value (PV)

    100% over and above the Planned Value (PV)

    There is no upper limit for the Actual Cost (AC)

    Incorrect

    There is no limit to the Actual Cost (AC). Whatever is spent to achieve the Earned Value (EV) is measured as the Actual Cost. [PMBOK 5th edition, Page 218]

    77. Question

    You are the project manager for Gleeson Associates. You are working together with a junior project manager on a project. You are currently discussing

    performance measurement analysis with her. You explain to her exactly the different variables involved. You tell her all of the following statements are true

    about the cost variance EXCEPT?

  • 8/10/2019 Project Cost Management Questions

    22/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 22/29

    It is always a po sitive value

    It is used to determine whether or not the project is meeting the planned costs

    It is calculated by the following formula: Cost Variance = Earned Value - Actual Cost.

    Its tendency is to decrease as the project is nearing the end.

    Incorrect

    The cost variance can be a negative value, zero, or a positive value depending on the earned value and actual costs. A negative cost variance indicates that

    the actual cost of the work was more than the amount of work being completed. [PMBOK 5th edition, Page 218]

    78. Question

    Your project has a budget of $240,000 and is expected to last for 1 year, with the work and budget spread evenly across all months. The project is now in the

    fourth month, the work is on schedule, but you have already spent $120,000 of the project budget. What is your COST Variance in this case?

    $240,000

    $40,000

    None

    -$40,000

    Incorrect

    Cost Variance = Earn Value Actual Cost Earn Value = (Total Cost/total project months) * total months completed = ($240,000 / 12)*4=$80,000 CV = $80,000-

    $120,000 = -$40,000

    79. Question

    You are the project manager of a Project. Your project will cost your organization $50,000 to complete over the next 3 months. Once the project is completed,

    the deliverables will let the company earn $5000 per month. What is the time to recover the costs of the project?

    2 Years

    1 Year

    10 Months

    3 Years

    Incorrect

    This is calculated by d ividing the ROI of $5000 per month into the project cost. 50000/5000 = 10 months

    80. Question

    As part of EVM, a project manager is calculating the to-complete performance index (TCPI) based on EAC. The data that he has is: the budget at completion

    for the project is $ 100,000. The earned value for the project is $ 25,000. The actual costs to date are 40,000 and the estimate at completion is $ 115,000. What

    is the TCPI that he will obtain?

    1

    0.9

    1.1

    0

    Incorrect

    TCPI based on EAC = (BAC-EV)/(EAC-AC) = (100000 25000) / (115000 40000) = 75000/75000 = 1 [PMBOK 5th edition, Page 221]

  • 8/10/2019 Project Cost Management Questions

    23/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 23/29

    81. Question

    Your company has been hired to configure software at 500 workstations. All workstations need equal time to configure. The contract for the project is set at a

    fixed cost, and the incentive based on how fast the project work is going to be completed. Management has requested that you study the work method to

    determine a faster, less costly, and a better method to complete the project. This scenario is an example of _________.

    Time Constraint

    Schedule Constraint

    Learning Curve

    Value Analysis

    Incorrect

    Value Analysis is a systematic approach to find less costly ways to complete the same work. A and B are incorrect, as this situation does not describe a

    specific time or cost constraint. D is incorrect: the learning curve happens as the project team completes the work.

    82. Question

    Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days. What is the PERT weighted average?

    6.3

    4

    6.1

    6

    Incorrect

    Optimistic = tO, most likely = tM, Pessimistic = tP. PERT weighted average = (tO + 4*tM + tP)/6 = (3+4*6+9)/6 = 36/6 = 6

    83. Question

    Your project has a budget of $12,000 and is expected to last for 1 year, with the work and budget spread evenly across all months. The project is now in the

    fourth month, but till now total spending for this project is $5,000. What is Variance at Completion in this case?

    $13,000

    -$5,000

    $12,000

    -$3,000

    Incorrect

    Earn Value = (Total Cost / total project months) * total months completed = ($12,000 / 12) * 4 = $4,000 Variance at Completion = BAC EAC CPI = EV (Earned

    Value) / AC (Actual Cost) = $4000/$5000 = .8 Estimate at Completion (EAC) = BAC/CPI = $12,000 / .8 = $1500 Variance at Completion = $12,000 $15,000 = -

    $3,000

    84. Question

    A project manager is analyzing the relationship between the consumption of project funds and the physical work being accomplished for such expenditures.

    In which pro ject management process would this be done?

    Determine Budget

    Control Costs

    Estimate Costs

  • 8/10/2019 Project Cost Management Questions

    24/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 24/29

    Manage Costs

    Incorrect

    Control Costs is the process o f monitoring the status of a project to update the project budget and managing changes to the cost baseline. Much of the

    effort of cost control involves analyzing the relationship between the consumption of project funds to the physical work being accomplished for such

    expenditures. [PMBOK 5th edition, Page 215]

    85. QuestionYou are working for FALCON highway construction agency as a project cost estimator. The agency started a highway construction project which is in its

    planning phase. The rough order of magnitude (ROM) cost estimate for the project is expected to be between 3 and 5 million dollars in the planning phase

    with a ROM of -25% to +25%. What will be the ROM estimate in the execution phase if it changes to -10% to +10%?

    Between 3.6 and 4.4 million dollars

    Between 3.1 and 4.1 million dollars

    Between 3.9 and 4.1 million dollars

    Between 3.4 and 4.4 million dollars

    Incorrect

    Since the Rough Order o f Magnitude (ROM) in the planning phase is -25% to +25%, the estimated mean value is 4 million dollars. If the estimates narrows

    down to -10% to +10% it becomes 3.6 to 4.4 million dollars. [PMBOK 5th edition, Page 201]

    86. Question

    Which estimating technique is most accurate?

    Analogous estimating

    Parametric modelling

    Bo ttom-up estimating

    None of the above

    Incorrect

    Bottom-up estimating: Estimating the cost of individual work items and then rolling up the costs to arrive at a project total is more accurate.

    87. Question

    Variance thresholds for monitoring cost performance are typically expressed as _______________ from the baseline plan.

    Negative deviation

    Positive deviation

    Percentage deviation

    Average deviation

    Incorrect

    Variance thresholds for monitoring cost performance are usually expressed as percentage deviations from the baseline plan. [PMBOK 5th Edition, Page

    199]

    88. Question

    A variance threshold for costs or other indicators to indicate the agreed amount of variation allowed is called:

  • 8/10/2019 Project Cost Management Questions

    25/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 25/29

    Upper control limits

    Control thresholds

    Upper specification limit

    Cost overrun

    Incorrect

    Control thresholds are variance thresholds for costs or other indicators such as person days and indicate the agreed amount of variation allowed.

    [PMBOK 5th edition, Page 148]

    89. Question

    Contingency Reserves are estimated costs to be used at the discretion of the project manager to deal with:

    Anticipated but not certain events.

    Anticipated and certain events

    Scope creep

    Unanticipated events

    Incorrect

    Contingency Reserves are estimated costs to be used at the discretion o f the project manager to deal with anticipated, but not certain events. These are

    also called as Known unknowns. [PMBOK 5th edition, Page 206]

    90. Question

    You are the project manager for a project. The customer has requested that you factor in after-project costs, such as maintenance and service. This is an

    example of which one of the following?

    Project Spin off

    Life Cycle costs

    Scope Creep

    Operations

    Incorrect

    The after-project costs are known as Life Cycle costs.

    91. Question

    You are the Project Manager for JTs Lumber Yard. You are trying to forecast estimates for the last phase of the project you are currently working on. Based

    on the performance of the project to date, which formula can be used to estimate the total value of the project when completed assuming similar variances

    will not occur?

    SV = EV - PV

    ETC = (BAC - EV)/CPI

    CPI = EV/AC

    EAC = AC + BAC - E V

    Incorrect

    The formula EAC = AC + BAC EV is used to determine the total value of the project when completed assuming similar variances will not occur for the

    uncompleted project activities. [PMBOK 5th edition, Page 220]

  • 8/10/2019 Project Cost Management Questions

    26/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 26/29

    92. Question

    Analogous Cost Estimating is which of the following?

    Bottom-up estimating

    Generally accurate

    Generally less accurate

    Uses statistical relationship between historical data and other variables

    Incorrect

    Analogous cost estimating is generally deemed less accurate than other methods of estimation. [PMBOK 5th edition, Page 204]

    93. Question

    Lucy is currently preparing a high-level cost estimate for her project in the initiation phase. Given the limited detail available to her, what would you expect

    the range of her estimate to be and what would you call such an estimate?

    -25 to +25 %, Rough Order of Magnitude

    -5 to +10 %, Narrow

    -1 to +1 %, Definitive

    -25 to +75 %, Rough Order of Magnitude

    Incorrect

    During the initial stages of the project, the level of information available will be limited. Hence the Rough Order of Magnitude (ROM) estimate is usually

    prepared and has an accuracy range of -25% to +75%. [PMBOK 5th edition, Page 201]

    94. Question

    Your company has been hired to configure software at 500 workstations. All workstations need equal time to configure. You calculate the time to configure

    each workstation as 5 hours. The cost for labor is calculated at $500 for each workstation. Your Project Sponsor disagrees with your labor estimate. Why is it

    so?

    You have not factored in all of the effort applied to the work.

    You have not considered the law of diminishing returns.

    You haven't completed one workstation yet, so you don't know how long the work will actually take

    You have not considered the learning curve.

    Incorrect

    As the project team completes more and more units, the time to configure a workstation should take less and less time.

    95. Question

    Which of the following statement is true about Control Costs ?

    Monitoring cost performance to detect variances from the plan

    Recording all appropriate changes accurately against the cost baseline

    Influencing the factors that create changes to the cost baseline

    A ll

  • 8/10/2019 Project Cost Management Questions

    27/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 27/29

    Incorrect

    96. Question

    Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days. What is the Triangular Distribution (tE) ?

    6.3

    4

    6.1

    6

    Incorrect

    Optimistic = tO, most likely = tM, Pessimistic = tP. Triangular Distribution = (tO + tM + tP)/3 = (3+6+9)/3 = 18/3 = 6

    97. Question

    Your Vice President has asked you what the Estimate at Completion is go ing to be for a small project you are working on. You were g iven a budget of $30,000,

    and to date you have spent $20,000 but only completed $10,000 worth of work. You are sure that the future work will be accomplished at the planned rate.

    $40,000

    $60,000

    $30,000

    $10,000

    Incorrect

    If the future work will be accomplished at the planned rate, then then Estimate at Completion (EAC) will be AC+BAC-EV. Budget at Completion (BAC) is

    $30,000, Earned Value (EV) is $10,000 and Actual Cost (AC) is $20,000. Hence the EAC is $40,000. [PMBOK 5th edition, Page 224]

    98. Question

    You are a project manager of a project. Till today you have actually completed $34,000 of work, but based on the cost plan it should have been $50,000. What

    is percentage Schedule Variance (SV) in this case?

    -16%

    28%

    -32%

    32%

    Incorrect

    Schedule Variance (SV): Any difference between the scheduled completion of an activity and the actual completion of that activity. SV % = (EV PV) / PV SV %

    = ($34,000 $50,000) / $50,000 = -32%

    99. Question

    You are aware that cost and schedule risks are prevalent in your project. You want to compare the planned project performance with its actual performance.

    What should you perform to provide this information?

    Reserve analysis

    Variance and trend analysis

    Risk audit

  • 8/10/2019 Project Cost Management Questions

    28/29

    3/3/2014 Project Cost Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project- cost-management-questions/ 28/29

    Risk reassessment

    Incorrect

    Variance and trend analysis are used to evaluate the differentials between planned and actual costs, schedules, and performance criteria. A variety of

    statistical techniques, such as Earned Value (EV) technique, are used to analyze these variances. [PMBOK 5th edition, Page 222]

    100. Question

    Your project has a budget of $240,000 and is expected to last for 1 year, with the work and budget spread evenly across all months. The project is now in the

    fourth month, the work is on schedule, but you have spent $120,000 of the project budget. What is your COST Variance percentage in this case?

    40%

    -50%

    50%

    None

    Incorrect

    Cost Variance = Earn Value Actual Cost Earn Value = (Total Cost/total project months) * total months completed = ($240,000 / 12) * 4 = $80,000 CV =

    $80,000 $120,000 = -$40,000 CV % = CV / EV = -$40,000/$80,000 = -50%

    101. Question

    Martin is the project manager of a project that is in an early phase. He needs to estimate costs but finds that he has a limited amount of detailed information

    about the project. Which of the following estimation techniques would be least suited to his requirements?

    Top-down Estimating

    Bottom-up Estimating

    Budgetary Estimating

    Analogous Estimating

    Incorrect

    Bottom-up estimating is a technique that can be applied only when there is a sufficient amount of detail available to the project manager. [PMBOK 5th

    edition, Page 205]

    102. Question

    A project manager is estimating project costs and needs to decide whether the estimates will include only direct costs, or whether the estimates will also

    include indirect costs. In which of the following phases does this decision need to take place?

    Determine Budget

    Estimate Costs

    Define Scope

    Plan Expenses

    Incorrect

    This is done in the Estimate Costs process. The pro ject manager works in accordance with the organizations guidelines and decides whether the estimates

    will be limited to direct project costs only or whether the estimates will also include indirect costs. Indirect costs are those that cannot be traced to one

    specific project, and are usually allocated equitably over multiple projects. [PMBOK 5th edition, Page 202]

    103. Question

  • 8/10/2019 Project Cost Management Questions

    29/29

    3/3/2014 Project Cost Management Questions

    RETURN TO TOP OF PAGE COPYRIGHT 2014 LOG OUT

    Which of the following statement is true about Work Breakdown Structure (WBS)?

    It is used to organize the cost estimates and to ensure that the cost of all identified work has been estimated.

    It identifies the project elements that require resources.

    A ll

    It provides the relationship among all the components of the project and the project deliverable.

    Incorrect

    Work breakdown structure (WBS): It identifies the project elements that require resources, used to organize the cost estimates and to ensure that the cost

    of all identified work has been estimated, and provides the relationship among all the components o f the project and the project deliverable.

    104. Question

    You have elected to use parametric modelling while Estimating Costs for the project. Which one of the following is an example of parametric modelling?

    Historical information from a similar project

    Estimates based on top-down budgeting

    Estimates built from bottom-up based on the WBS

    $10 per pound

    Incorrect

    $10 per pound is an example of parametric modelling. Parametric modelling: Using project characteristics (or parameters) in a mathematical model to

    predict costs (e.g., price per square foot). B is incorrect, as historical information is analogous, not parametric. C is incorrect; bottom-up estimating is not a

    parametric modelling. D is incorrect, top-down budgeting is related to analogous estimating .

    105. Question

    The Budget at Completion (BAC) for a project is $50,000. The Actual Costs (AC) to date are $10,000. The Earned Value (EV) is $7,000. At this stage, the project

    management team did a manual bottom-up summation of costs and forecast an Estimate to Complete (ETC) of $50,000. What is the Estimate at Completion

    (EAC) for the project?

    $57,000

    $40,000

    $60,000

    $53,000

    Incorrect

    When a bottom-up manual forecasting has been done for the ETC, the calculation for EAC is g iven by: EAC = AC + bottom-up ETC Hence, EAC = 10,000 +

    50,000 = $60,000. Note that the BAC is no longer viable at this stage. [PMBOK 5th edition, Page 220]

    http://www.pmpden.com/wp-login.php?action=logout&_wpnonce=261e5bf05d