Transcript of Project Controls Expo – 13th Nov 2013- "The Key Role of the Cost Engineer Achieving an Integrated...
Copyright @ 2011. All rights reserved
The Key Role of the Cost Engineer Achieving an Integrated Work Process through a Holistic Mindset
by
Martin van Vliet
Project Controls Expo – 13th Nov 2013 Twickenham Stadium, London
Copyright @ 2011. All rights reserved
About Martin van Vliet
Cost Engineer/Sales Engineer at Cost Engineering Consultancy
Degree:
Civil Engineer
Years of Experience:
As a Cost Engineer and a Sales Engineer with over 17 years of experience in the field of cost estimating and cost engineering.
Professional Field:
Member of the DACE
Chairman of DACE Labor Productivity Norms Workgroup
Team leader for planning, budgeting, contracting, cost estimating and management reporting for the services department. Software implementations and development and perform functional and technical specifications, requirement assessments, give training on the job and do presentations and showcases.
Copyright @ 2011. All rights reserved
Agenda
What is Cost Engineering?
Cost Estimating
Cost Control
Challenges of the Modern Cost Engineer
Achieving an Integrated Work Process through a Holistic Mindset
Copyright @ 2011. All rights reserved
What is Cost Engineering?
AACEI defines Cost Engineering as:
“That area of engineering practice where engineering judgment and experience are utilized in the application of scientific principles and techniques to the problems of cost estimating, cost control and profitability”.
Copyright @ 2011. All rights reserved
What is Cost Engineering?
The Profession of Cost Engineering: Applying methods and techniques for:
Cost Estimating
Cost control
Planning
Contracting / Tendering
Quantity survey
Risk Assessment
Value Engineering
Copyright @ 2011. All rights reserved
Is Cost Engineering a Science?
Copyright @ 2011. All rights reserved
Is Cost Engineering a Science?
Some advise: Keep it simple, Cost Engineering is not “Rocket Science”
But it requires discipline!
Copyright @ 2011. All rights reserved
Cost Is Everything
“It costs time” “It costs resources”
“ It costs money”
Everything invested
in assets and projects
is a Cost
Copyright @ 2011. All rights reserved
Cost Estimating
Copyright @ 2011. All rights reserved
What is Cost Estimating?
Copyright @ 2011. All rights reserved
Can we predict the future based on the past?
Past performance is no
guarantee for future results
Copyright @ 2011. All rights reserved
What Is Cost Estimating?
“An evaluation of all the costs of the elements of a project or effort as defined by an agreed-upon scope.” (AACE 10S-90)
Cost Estimate
Involves assumptions and unknowns
Involves probabilities (and therefore ranges of costs)
Involves a given scope
Contingency covers variability within the defined scope - not changes in scope
Copyright @ 2011. All rights reserved
Project Life Cycle
Project
initiation note
± 40% Screening estimate
Economics
Step 1
Feasibility study
± 25% Study
estimate
Economics
Step 2
Development plan
± 25% Budget
estimate
Economics
Step 3
initial execution
plan
Initial commit.
plan
Basis for design
Project specification
± 10% Control
estimate
commit. plan
Economics
Step 4
Operations reference
plan
Project execution
plan
Detailed design
Materials procurement
Construction Commission.
start-up handover
Approval Approval
Review
Approval
Review
Approval
Identical to
Execution phase
Abandon project
Commit. & cost control
Contract control
Purchase order control
Reporting
Operations reference
plan
Close out
Project debrief
Change control
± 5% Counter estimate
Step 5
Identification phase Definition phase Execution phase Operational
phase Abandon
phase
Step 6 Step 7
Identical to
Execution phase
Copyright @ 2011. All rights reserved
What Is Accuracy?
An estimate should not be regarded as a single point number (or cost)
An estimate is a range of potential cost outcomes, and associated probabilities of occurrence
Thus – the accuracy range of an estimate is a probabilistic assessment of how far a project’s final actual cost can be expected to vary from the estimate
The range is driven by risks
Copyright @ 2011. All rights reserved
Cost Estimating Classification (AACEI)
Level of Project
definition
End Usage Methodology Expected Accuracy
Range
Preparation
Effort
5
4
3
2
1
Estimate
Level
0% to 2%
1% to 15%
10% to 40%
30% to 70%
50% to 100%
Concept
Screening
Study or Feasibility
Budget,
Authorization or
Control
Control or Bid /
Tender
Check Estimate or
Bid / Tender
Capacity factored
Parametric
Models, Judgment or
analogy
Equipment factored
or Parametric
Models
Semi-detailed unit cost
with assembly level line
items
Detailed Unit Cost with
Forced Detailed take-
off
Detailed Unit Cost with
Detailed
take-off
L: -20% to -50%
H: +30% to +100%
L: -15% to -30%
H: +20% to +50%
L: -10% to -20%
H: +10% to +30%
L: -5% to -15%
H: +5% to +20%
L: -3% to -10%
H: +3% to +15%
1
2 to 4
3 to 10
4 to 20
5 to 100
Copyright @ 2011. All rights reserved
Accuracy Level of the Estimate
Study
Type
C
Class4
90/10
Order of magnitude
D
Class5
Bas
e
~2-8% ~1-5%
Budget
Type
B
Class3/2
Control
Estimate
Class1
+40%
+10%
-25%
- 10%
Base
50/50
Base
10/90
90/10
Zero baseline
Base
90/10
90/10
50/50
Base
Bas
e
Copyright @ 2011. All rights reserved
What Defines the Accuracy of a Cost Estimate?
Influences on the estimate
Scope definition
Knowledge of the cost engineer
Tools
Database
Risk
Systemic Risk
Project Specific Risk
Market influences
Copyright @ 2011. All rights reserved
Baseline of Cost Control
“Measurements are the key. If you cannot measure it, you cannot control it. If you cannot control it, you cannot manage it. If you cannot manage it, you cannot improve it.” - James H. Harrington
Copyright @ 2011. All rights reserved
Budgets are Always Under Pressure
What happens with too much pressure?
Copyright @ 2011. All rights reserved
Cost Control
Copyright @ 2011. All rights reserved
Cost Control
Copyright @ 2011. All rights reserved
What Is Cost Control?
There are two processes used for controlling the costs of the project.
1. Change Management – a formal process that identifies any requested (or un-requested) changes to the contract.
2. Forecasting – predictions of the costs at completion for any cost elements in progress or not yet started.
Copyright @ 2011. All rights reserved
All changes shall be documented, regardless if no net change in schedule or cost
has happened.
Don’t run and hide !!!
Change Management
Copyright @ 2011. All rights reserved
What Is Forecasting?
Forecasts are much like estimates. Whereas an estimate is always for future activities and assets, forecasts are predictions of the costs at completion for cost elements in progress.
Copyright @ 2011. All rights reserved
Earned Value, Budget & Schedule Forecasting
0
200
400
600
800
1000
1200
1400
1600
1800
1-apr 7-apr 14-apr 21-apr 28-apr 5-mei 12-mei 19-mei 26-mei 2-jun 9-jun 16-jun 23-jun
Budget Earned Actual
BCWS (Budgeted cost of
work scheduled) ACWP
(Actual cost of
work performed)
Budget plan
BCWP (Budgeted cost of
work performed
Copyright @ 2011. All rights reserved
Challenges of the Modern
Cost Engineer
A day in the office
Telephone rings…..
A business partner !!!!
Copyright @ 2011. All rights reserved
Business
Planning
Feasibility
Planning
Project
Planning
Execution Start-up
Inv
olv
em
en
t
Process Engineering
Project
Control Estimating
Project Director Construction Operations
/Commissioning Business
Feedback/Learning/Knowledge Engineering
Detailed Engineering
/Procurement
Involvement Process for Technical Projects
Copyright @ 2011. All rights reserved
Money
Business Case
Process Engineers
Engineering
Quality
Time / Schedule
Environment
Safety
Cost Engineers
Project Lead
Process Flow
Data sheets
Sub Contractors
Health
Regulation
Contractors
Permits
Government
Risk Assessment
Discipline Engineers
Involvement Process for Technical Projects
Copyright @ 2011. All rights reserved
Current approach to deal with complexity (over the wall syndrome)
Copyright @ 2011. All rights reserved
Common Problem with Current Approach
Potential of Decisions to
Influence Value
Potential of Changes to
Destroy Value
Project Life Cycle (Better Scope Definition/Time)
Copyright @ 2011. All rights reserved
Better Scope Definition Drives Better Absolute, Bottom-Line Cost Performance
Front End Loading (FEL)
Perc
en
tag
e A
bo
ve o
r B
elo
w
Ind
ustr
y A
vera
ge C
ost
-10%
-5%
0%
5%
10%
15%
20%
3 3,5 4 4,5 5 5,5 6 6,5 7 7,5 8 8,5 9FEL Index
From: Hollmann, John K., Best Owner Practices For
Project Control, 2002 AACE Transactions
5% Lower Cost = 1% Better ROE
SCREENING POOR FAIR GOOD BEST
Copyright @ 2011. All rights reserved
Less than 30% of Projects Achieve All Business Objectives
Perc
en
t T
hat
Ach
ieve
Ob
jecti
ve
As Reported by IPA, Inc.
Copyright @ 2011. All rights reserved
Achieving an Integrated Work Process through a Holistic
Mindset
Copyright @ 2011. All rights reserved
From only calculating to…
Copyright @ 2011. All rights reserved
… What-if Analysis
Copyright @ 2011. All rights reserved
Regression Analysis
Copyright @ 2011. All rights reserved
Key Metrics Analysis
Copyright @ 2011. All rights reserved
From Just Estimating, to…
Copyright @ 2011. All rights reserved
… Solution in 4D or 5D Interfacing (BIM)
Copyright @ 2011. All rights reserved
Estimating Cycle: The Ideal Scenario
Copyright @ 2011. All rights reserved
From Specialist to All-Round Cost Engineer
Mixing all different ideas together
Copyright @ 2011. All rights reserved
Continuous Improvement Cycle
A process for collecting, maintaining, and analyzing project historical information so that it is ready for use in an effective form by each functional process
Empirical information is the most fundamental project planning resource available
It is manifested in the form of quantified and documented historical data and information
The purpose is not to repeat history, but to learn from it (continuous improvement)
Copyright @ 2011. All rights reserved
Typical Integrated Work Process
Copyright @ 2011. All rights reserved
Integrated Work Process
Copyright @ 2011. All rights reserved
Suddenly, a heated
exchange took place
between the King and the
project manager
What was objective?
“dig a ditch next to the
castle wall”
or
“defend the castle from
attack”
Copyright @ 2011. All rights reserved
Questions?