Project Apprisal SCBA & Environment2
-
Upload
shyam-le-grand -
Category
Documents
-
view
258 -
download
1
Transcript of Project Apprisal SCBA & Environment2
-
7/27/2019 Project Apprisal SCBA & Environment2
1/35
15 October 2013
Social Cost Benefit Analysis
Also called Economic Analysis Developed for evaluating investment projects
from the point of view of the society (oreconomy) as a whole.
Primarily for evaluating public investments. Why this methodology? Once we agree with
SCB, it helps in decision-making
deciding whether a particular project should go aheador not.
comparing different projects
-
7/27/2019 Project Apprisal SCBA & Environment2
2/35
15 October 2013
Increasing Emphasis
Growing importance of public investmentsin developing countries
Aids in evaluating individual projects withinthe planning framework (i.e. nationaleconomic objectives) & broaden allocationof resources to various sectors.
Reasons for the difference between socialcosts and monetary costs
-
7/27/2019 Project Apprisal SCBA & Environment2
3/35
15 October 2013
Reasons for difference between social cost& benefits and monetary costs & benefits
1. Market imperfection resulting in marketprices not reflecting social values e.g.
Large Projects likely to yield significantsecondary benefits to the economy.
Counting only the primary benefits is not OK
Rationing of a commodity valuation like
control over its price and distributionincluding capital, interest & rates
-
7/27/2019 Project Apprisal SCBA & Environment2
4/35
15 October 2013
Reasons
2. Externalities Both costs and benefits todifferent people, groups in the societyare taken into account E.g.
Large dam resulting in environmentalpollution, deforestation, mosquito breeding,ecological imbalance, displacement etc.
Infrastructure facilities like roads coming up,installation of telephone lines
-
7/27/2019 Project Apprisal SCBA & Environment2
5/35
15 October 2013
Examples of difference
A township coming up due to the project
Employment opportunities in an otherwisenon-industrial area
A road or telephone line being laid
A petrol bunk coming up due to the project
A project closes down due to nonviability &hence the canteen outside the campushas to close down
-
7/27/2019 Project Apprisal SCBA & Environment2
6/35
15 October 2013
Reasons
3. Concern for Wealth Distribution For public investments
4. Merit Wants
= Goals & preferences not expressed in the marketplace but believed by policy makers to be in thelarger interest
have long-term social and economic benefits.
E.g. rural telecommunication network, airconnection with low density destinations, prioritysector lending etc
Merit goods and non merit goods
-
7/27/2019 Project Apprisal SCBA & Environment2
7/35
15 October 2013
SCBA approaches
SCBA is not a technique (for measuring) like NPV etcbut it is an approach
Basically two approaches for SCBA viz.: UNIDO Approach and
Little Mirrlees Approach United Nations Industrial Development Organization
Primary objective is promotion & acceleration ofindustrial development in developing countries andcountries with economies in transition.
Practical Project Appraisal by UNIDO (1978)
Tries to quantify the social impact
-
7/27/2019 Project Apprisal SCBA & Environment2
8/35
15 October 2013
UNIDO Approach
Calculate usual financial profitability of project asmeasured at market pries.
Shadow price the resources
Obtain the net benefit of the project on savings and
investments. Adjust for the impacts of the project on savings and
investment.
Adjust for the impact of the project on income
distribution. Adjust for the impact of project on merit goods and
demerit goods whose social values differ from theireconomic values.
-
7/27/2019 Project Apprisal SCBA & Environment2
9/35
15 October 2013
Shadow pricing?
The opportunity cost of a scarce resource
Maximum price that management is willing to pay for anextra unit of a given limited resource
Measure of the contribution foregone by failing to have
one more unit of scare capacity in a particular situation. A shadow price is, in a way, an OPPORTUNITY COST
Resources in excess supply have a shadow price of zero.
Over time
When foreign exchange is rationed, the shadow price of foreignexchange becomes the relevant exchange rate decisions.
Benefits and costs are measured in terms of shadow prices ofinputs and outputs instead of in actual market prices
-
7/27/2019 Project Apprisal SCBA & Environment2
10/35
15 October 2013
How to calculate shadow prices
Shadow prices = market prices under perfectmarket conditions; how to calculate otherwise?
Concepts to be understood for this purpose1. Numeraire unit of account for expressing
input and output e.g. which currency toexpress, which time frame for comparison,whether costs at current values or constantvalues etc.
2. Tradability generally international pricerepresents better price than the controlleddomestic price. Free import and exportequalises prices
-
7/27/2019 Project Apprisal SCBA & Environment2
11/35
15 October 2013
Basis for shadow prices
3. Non-tradable Inputs and outputs e.g. when import price >domesticcost of production or export price < domestic cost of production.
For such items, value should be measured in terms of what domesticconsumes are willing to pay
4. Taxes impact of tax on price estimate is subjective. To beincluded when the project consumes inputs which are in fixedsupply by diverting from other producers
5. Externalities It is not deliberately created by the project sponsor but is an
incidental outcome of legitimate economic activity. It is beyond the control of the persons who affected by it, for better or
for worse.
It is not traded in the market place. An external effect may be positive or negative.
-
7/27/2019 Project Apprisal SCBA & Environment2
12/35
15 October 2013
-
7/27/2019 Project Apprisal SCBA & Environment2
13/35
15 October 2013
Export Parity Price for Sugar(for project in Central area of Mozambique)
Shadow Price Variable US$/Tonne World price of sugar exported FOB from Beira 264 Less transport costs from mill to docks 12 Net value per tonne of sugar at mill 252 Net value of cane at mill (10 % of sugar price) 25.2
Less cane processing costs at mill 7 Less transport costs from project area 3 Delivered mill economic price for cane at project area in US$ 15.2
Expected economic price of cane at project area (local currency) 220 Actual financial price of cane in project area (local currency) 200 Conversion factor (220/200) 1.10
-
7/27/2019 Project Apprisal SCBA & Environment2
14/35
15 October 2013
Import Parity Price of Maize(for project in Central area of Mozambique)
Shadow Price Variable US$/Tonne Import price of rice from Johannesburg, South Africa 127 Bagging and loading in Durban 15 Freight, insurance and customs Durban to Maputo 30 Total CIF (Customs, Insurance and Freight) at Maputo 172 Unloading and storage in Maputo 3 Total in-store price in Maputo 175 Less transport and bagging to project area (200 km away) 25 Expected economic farm gate price at project area in US$ 150
Expected economic farm gate price at project area (local currency) 1900 Actual financial farm gate price at project area (local currency) 1800
-
7/27/2019 Project Apprisal SCBA & Environment2
15/35
15 October 2013
Little- Mirrlees Approach
This also involves shadow prices and the usualmathematical arrival of result like NPV
Differs from UNIDO approach in UNIDO approach measures cost & benefit in
domestic currency whereas this measures ininternational prices
UNIDO approach measures costs and benefits interms of consumption where here it is measured interms of uncommitted social income
Little and Mirrlees has an elaborate methodology forcalculating shadow prices of non-trade-ables
Unlike the five stages of UNIDO, the Little andMirrlees procedure is relatively more practical
-
7/27/2019 Project Apprisal SCBA & Environment2
16/35
15 October 2013
Differences
Little and Mirrlees emphasise ongenerating savings and hence it suggeststhe use of accounting rate of interest to
calculate NPV.
UNIDO Guidelines, on the other hand, donot make any adjustment for consumption
and saving impact of project investment
-
7/27/2019 Project Apprisal SCBA & Environment2
17/35
15 October 2013
Accounting rate of return
Subjective
Chosen such that only a few of the best amongthe lot is cleared
The future social profit of all projects should bediscounted using the same accounting rate ofreturn
Should be chosen such that it balances between
investments made and funds available for suchinvestments
Mathematical risk based rate is not the criterion
-
7/27/2019 Project Apprisal SCBA & Environment2
18/35
15 October 2013
Applications
Divide each input into tradeable (i.e. merchandise related), labour(i.e. service related) and residual (i.e. others). Each (public)organisation will use a specify social conversion factor (SCF) orproportion of T, L, R for each asset. E.g. if the T, L, R of building given as 0.5, 0.25 & 0.25 respectively.
Then the financial cost of building of Rs 10 lacs is = social value of
building is T of 5, L of 2.5 and R of 2.5 If the SCF for land is 0.66, convert the financial cost of land of Rs 20
lacs into social value of Rs 13.2 lacs (it cannot have L & R) Convert every asset cost into social value at the SCF given or split them
into T, L, R Arrive at the total of T, L & R for the whole project cost
At SCF, convert the total of L & R into social value equivalent. Total of this figure and T gives the social value of the projectcomponents compared to its financial cost.
Using this calculate NPV etc
-
7/27/2019 Project Apprisal SCBA & Environment2
19/35
The capital outlay on a new project isestimated to be as follows;
The working capital requirement of theproject is Rs.159lakh(CIF value
Rs.125lakh)
15 October 2013
Rs. In lakh
LandBuildingsImported equipment (CIF value Rs.120 lakh)Indigenous equipment (CIF value Rs.300lakh)
Engineering and know-how fees
530150375
20
-
7/27/2019 Project Apprisal SCBA & Environment2
20/35
The estimated annual profitability of the project is as follows;
The annual value of output of CIF prices is Rs.1,300lakh
The CIF value of imported raw material is Rs.200 lakh per annum. The effective tax rate for the firm is 34%.
15 October 2013
( Rs. In lakh)
Sales revenue
Imported raw materialIndigenous raw material
1800
2201,000
LabourSalariesRepairs and maintenance
Water, fuel, etcElectricityOther overhead
100505
152010
-
7/27/2019 Project Apprisal SCBA & Environment2
21/35
Social conversion factors(SCF) or proportions of tradablecomponents(T), labour(L) and residual( R) to be used for variousitems are as follows;
Ignoring salvage value of fixed and current assets and assuming aproject life of 5 years, calculate the Economic Rate of Return (ERR)for the project. Assume that the conversion factors for tradable,labor and residual components are 1/1.5, 0.5, 0.5 respectively.
15 October 2013
Item SCF or ProportionsLandBuildingsIndigenous equipmentEngineering and know-how feesLabour
SalariesRepairs and maintenanceWater, fuel, etcElectricityIndigenous raw materials and storeOther overhead
SCF=1/1.5Proportion T=0.5, L=0.25, R=0.25SCF=0.7SCF=1.5SCF=0.5
SCF=0.8SCF=1/1.5Proportions T=0.5, L=0.25, R=0.25Proportions T=0.71, L=0.13, R=0.16SCF=0.8SCF=1/1.5
-
7/27/2019 Project Apprisal SCBA & Environment2
22/35
Social cost associated with Initial outlay
15 October 2013
Item Financial cost
Basis ofconversion
Trade ablevalue abinitio
T L R
LandBuilding
ImportedEquipmentIndigenousEquipmentEngineering& know-howWorkingCapital
530
150
375
20
159
SCF=1/1.5T=0.5,L=0.25, R=0.25
CIF value
CIF Value
SCF=1.5
CIF value
3.33
120
300
30
125
15 7.5 7.5
578.33 15 7.5 7.5
-
7/27/2019 Project Apprisal SCBA & Environment2
23/35
Tradable value ab initio 578.33
Social cost of trade able component(15/1.5)Social cost of labour component (7.5x0.5)Social cost of residual component (7.5x0.5)
103.753.75
Total social cost of initial outlay 595.83
15 October 2013
-
7/27/2019 Project Apprisal SCBA & Environment2
24/35
Conversion of financial operating costsinto social costs
15 October 2013
Item Financial cost
Basis ofconversion
Trade ableab initio
T L R
Imported RM
Indigenous RMLabourSalariesRepairs & MtenWater, Fuel,etc
Electricity
Other overhead
220
100010050515
20
10
CIF value
SCF=0.8SCF=0.5SCF=0.8SCF1/1.5T=0.5,L=0.25, R=0.25T=0.71,L=0.13,R=0.16SCF=1/1.5
200
80050403.33
6.67
7.5
14.2
3.75
2.6
3.75
3.2
1,100 21.7 6.35 6.95
-
7/27/2019 Project Apprisal SCBA & Environment2
25/35
Annual Social Cost of Operation
Social net benefit per year=Rs.1300-Rs.1121.13=Rs178.87
Economic rate of return(r )
595.83=178.87PVIFA(r,5)
r= 15.27%
15 October 2013
Trade able value ab initio
Social cost of trade able component (21.7/1.5)Social cost of labour component (6.35x0.5)Social cost of residual component (6.95x0.5)
1,100
14.473.183.48
1121.13
-
7/27/2019 Project Apprisal SCBA & Environment2
26/35
15 October 2013
ERP
= Effective rate of protection
= {VA @ domestic prices VA @ intl prices}/VA @ intlprices
VA = value added = selling price input cost
(exclude tax elements which are characteristic of domesticprice)
Take FOB of export item and CIF of imported item
ERP = 0 = no protection to domestic industry, >0 = protection exists,
-
7/27/2019 Project Apprisal SCBA & Environment2
27/35
15 October 2013
DRC
Domestic resources cost
= VA @ domestic prices X exchange rate
VA @ intl prices DRC = (ERP +1) X Exchange rate
That means any positive value of ERP results inspending more for a project than if import had
been permitted. Conflict of interest viz.: domestic Vs forex
position
-
7/27/2019 Project Apprisal SCBA & Environment2
28/35
15 October 2013
Environmental Appraisal
Conflict of interest between industrialgrowth and heritage preservation
Controlled industrial growth
Governmental control
Central and State regulations
Competition among States Increased public awareness
-
7/27/2019 Project Apprisal SCBA & Environment2
29/35
15 October 2013
Types
Land
Air
Water Noise
General environment
-
7/27/2019 Project Apprisal SCBA & Environment2
30/35
15 October 2013
Specific Cases
Coco Cola plant in Kerala
Alang Ship-breaking industry
Biocon Garment industries of Tirupur
Low count yarn spinning units
Ganesh Chathurthi
-
7/27/2019 Project Apprisal SCBA & Environment2
31/35
15 October 2013
Sources
Tanneries Chemicals
Distilleries, sugar, BTindustries
Organic substances
Hardware units,photographic units
Heavy metals
Drugs and
pharmaceuticals
Chemicals into air and
waterFabric dyeing units Heavy chemicals
Cement Fly ash
-
7/27/2019 Project Apprisal SCBA & Environment2
32/35
15 October 2013
Remedies
Solid, liquid and gaseous forms
Pollution control equipments
Technology, cost, process,
Treatment
Air, water, noise
Primary and secondary Large captive waste disposal area
Areas earmarked for hazardous products
-
7/27/2019 Project Apprisal SCBA & Environment2
33/35
15 October 2013
Financial Implications
Non-availability of suitable technology
Institutions clearance only after this
Yearly monitoring Environmental audit
Inspections etc
Increased cost Possible delay
-
7/27/2019 Project Apprisal SCBA & Environment2
34/35
15 October 2013
Construction Projects
Environmental clearance from the Ministry ofEnvironment & Forest (MoEF), GoI
Covers new construction projects
viz. new township, industrial township, settlementcolonies, commercial colonies, hotel complexes,hospitals and office complexes with
Projects that serve 1,000 persons or above
Discharging sewage of 50,000 liters per day or above. With an investment of Rs.50 cores or above.
-
7/27/2019 Project Apprisal SCBA & Environment2
35/35
15 October 2013
Procedure for obtainingenvironmental clearance
Preparation of Rapid Environment Impact Assessmentreport.
Application for consent to establish & Public Hearing toState Pollution Control Board (SPCB.)
Attending Public Hearing held by SPCB. Securing consent to establish from SPCB. Application to MoEF, Government of India, for
Environmental Clearance. Presentation to MoEF, New Delhi.
Securing Environmental Clearance from MoEF,Government of India. Application to SPCB for Consent to Operate. Securing consent to operate from SPCB