Project Apprisal SCBA & Environment2

download Project Apprisal SCBA & Environment2

of 35

Transcript of Project Apprisal SCBA & Environment2

  • 7/27/2019 Project Apprisal SCBA & Environment2

    1/35

    15 October 2013

    Social Cost Benefit Analysis

    Also called Economic Analysis Developed for evaluating investment projects

    from the point of view of the society (oreconomy) as a whole.

    Primarily for evaluating public investments. Why this methodology? Once we agree with

    SCB, it helps in decision-making

    deciding whether a particular project should go aheador not.

    comparing different projects

  • 7/27/2019 Project Apprisal SCBA & Environment2

    2/35

    15 October 2013

    Increasing Emphasis

    Growing importance of public investmentsin developing countries

    Aids in evaluating individual projects withinthe planning framework (i.e. nationaleconomic objectives) & broaden allocationof resources to various sectors.

    Reasons for the difference between socialcosts and monetary costs

  • 7/27/2019 Project Apprisal SCBA & Environment2

    3/35

    15 October 2013

    Reasons for difference between social cost& benefits and monetary costs & benefits

    1. Market imperfection resulting in marketprices not reflecting social values e.g.

    Large Projects likely to yield significantsecondary benefits to the economy.

    Counting only the primary benefits is not OK

    Rationing of a commodity valuation like

    control over its price and distributionincluding capital, interest & rates

  • 7/27/2019 Project Apprisal SCBA & Environment2

    4/35

    15 October 2013

    Reasons

    2. Externalities Both costs and benefits todifferent people, groups in the societyare taken into account E.g.

    Large dam resulting in environmentalpollution, deforestation, mosquito breeding,ecological imbalance, displacement etc.

    Infrastructure facilities like roads coming up,installation of telephone lines

  • 7/27/2019 Project Apprisal SCBA & Environment2

    5/35

    15 October 2013

    Examples of difference

    A township coming up due to the project

    Employment opportunities in an otherwisenon-industrial area

    A road or telephone line being laid

    A petrol bunk coming up due to the project

    A project closes down due to nonviability &hence the canteen outside the campushas to close down

  • 7/27/2019 Project Apprisal SCBA & Environment2

    6/35

    15 October 2013

    Reasons

    3. Concern for Wealth Distribution For public investments

    4. Merit Wants

    = Goals & preferences not expressed in the marketplace but believed by policy makers to be in thelarger interest

    have long-term social and economic benefits.

    E.g. rural telecommunication network, airconnection with low density destinations, prioritysector lending etc

    Merit goods and non merit goods

  • 7/27/2019 Project Apprisal SCBA & Environment2

    7/35

    15 October 2013

    SCBA approaches

    SCBA is not a technique (for measuring) like NPV etcbut it is an approach

    Basically two approaches for SCBA viz.: UNIDO Approach and

    Little Mirrlees Approach United Nations Industrial Development Organization

    Primary objective is promotion & acceleration ofindustrial development in developing countries andcountries with economies in transition.

    Practical Project Appraisal by UNIDO (1978)

    Tries to quantify the social impact

  • 7/27/2019 Project Apprisal SCBA & Environment2

    8/35

    15 October 2013

    UNIDO Approach

    Calculate usual financial profitability of project asmeasured at market pries.

    Shadow price the resources

    Obtain the net benefit of the project on savings and

    investments. Adjust for the impacts of the project on savings and

    investment.

    Adjust for the impact of the project on income

    distribution. Adjust for the impact of project on merit goods and

    demerit goods whose social values differ from theireconomic values.

  • 7/27/2019 Project Apprisal SCBA & Environment2

    9/35

    15 October 2013

    Shadow pricing?

    The opportunity cost of a scarce resource

    Maximum price that management is willing to pay for anextra unit of a given limited resource

    Measure of the contribution foregone by failing to have

    one more unit of scare capacity in a particular situation. A shadow price is, in a way, an OPPORTUNITY COST

    Resources in excess supply have a shadow price of zero.

    Over time

    When foreign exchange is rationed, the shadow price of foreignexchange becomes the relevant exchange rate decisions.

    Benefits and costs are measured in terms of shadow prices ofinputs and outputs instead of in actual market prices

  • 7/27/2019 Project Apprisal SCBA & Environment2

    10/35

    15 October 2013

    How to calculate shadow prices

    Shadow prices = market prices under perfectmarket conditions; how to calculate otherwise?

    Concepts to be understood for this purpose1. Numeraire unit of account for expressing

    input and output e.g. which currency toexpress, which time frame for comparison,whether costs at current values or constantvalues etc.

    2. Tradability generally international pricerepresents better price than the controlleddomestic price. Free import and exportequalises prices

  • 7/27/2019 Project Apprisal SCBA & Environment2

    11/35

    15 October 2013

    Basis for shadow prices

    3. Non-tradable Inputs and outputs e.g. when import price >domesticcost of production or export price < domestic cost of production.

    For such items, value should be measured in terms of what domesticconsumes are willing to pay

    4. Taxes impact of tax on price estimate is subjective. To beincluded when the project consumes inputs which are in fixedsupply by diverting from other producers

    5. Externalities It is not deliberately created by the project sponsor but is an

    incidental outcome of legitimate economic activity. It is beyond the control of the persons who affected by it, for better or

    for worse.

    It is not traded in the market place. An external effect may be positive or negative.

  • 7/27/2019 Project Apprisal SCBA & Environment2

    12/35

    15 October 2013

  • 7/27/2019 Project Apprisal SCBA & Environment2

    13/35

    15 October 2013

    Export Parity Price for Sugar(for project in Central area of Mozambique)

    Shadow Price Variable US$/Tonne World price of sugar exported FOB from Beira 264 Less transport costs from mill to docks 12 Net value per tonne of sugar at mill 252 Net value of cane at mill (10 % of sugar price) 25.2

    Less cane processing costs at mill 7 Less transport costs from project area 3 Delivered mill economic price for cane at project area in US$ 15.2

    Expected economic price of cane at project area (local currency) 220 Actual financial price of cane in project area (local currency) 200 Conversion factor (220/200) 1.10

  • 7/27/2019 Project Apprisal SCBA & Environment2

    14/35

    15 October 2013

    Import Parity Price of Maize(for project in Central area of Mozambique)

    Shadow Price Variable US$/Tonne Import price of rice from Johannesburg, South Africa 127 Bagging and loading in Durban 15 Freight, insurance and customs Durban to Maputo 30 Total CIF (Customs, Insurance and Freight) at Maputo 172 Unloading and storage in Maputo 3 Total in-store price in Maputo 175 Less transport and bagging to project area (200 km away) 25 Expected economic farm gate price at project area in US$ 150

    Expected economic farm gate price at project area (local currency) 1900 Actual financial farm gate price at project area (local currency) 1800

  • 7/27/2019 Project Apprisal SCBA & Environment2

    15/35

    15 October 2013

    Little- Mirrlees Approach

    This also involves shadow prices and the usualmathematical arrival of result like NPV

    Differs from UNIDO approach in UNIDO approach measures cost & benefit in

    domestic currency whereas this measures ininternational prices

    UNIDO approach measures costs and benefits interms of consumption where here it is measured interms of uncommitted social income

    Little and Mirrlees has an elaborate methodology forcalculating shadow prices of non-trade-ables

    Unlike the five stages of UNIDO, the Little andMirrlees procedure is relatively more practical

  • 7/27/2019 Project Apprisal SCBA & Environment2

    16/35

    15 October 2013

    Differences

    Little and Mirrlees emphasise ongenerating savings and hence it suggeststhe use of accounting rate of interest to

    calculate NPV.

    UNIDO Guidelines, on the other hand, donot make any adjustment for consumption

    and saving impact of project investment

  • 7/27/2019 Project Apprisal SCBA & Environment2

    17/35

    15 October 2013

    Accounting rate of return

    Subjective

    Chosen such that only a few of the best amongthe lot is cleared

    The future social profit of all projects should bediscounted using the same accounting rate ofreturn

    Should be chosen such that it balances between

    investments made and funds available for suchinvestments

    Mathematical risk based rate is not the criterion

  • 7/27/2019 Project Apprisal SCBA & Environment2

    18/35

    15 October 2013

    Applications

    Divide each input into tradeable (i.e. merchandise related), labour(i.e. service related) and residual (i.e. others). Each (public)organisation will use a specify social conversion factor (SCF) orproportion of T, L, R for each asset. E.g. if the T, L, R of building given as 0.5, 0.25 & 0.25 respectively.

    Then the financial cost of building of Rs 10 lacs is = social value of

    building is T of 5, L of 2.5 and R of 2.5 If the SCF for land is 0.66, convert the financial cost of land of Rs 20

    lacs into social value of Rs 13.2 lacs (it cannot have L & R) Convert every asset cost into social value at the SCF given or split them

    into T, L, R Arrive at the total of T, L & R for the whole project cost

    At SCF, convert the total of L & R into social value equivalent. Total of this figure and T gives the social value of the projectcomponents compared to its financial cost.

    Using this calculate NPV etc

  • 7/27/2019 Project Apprisal SCBA & Environment2

    19/35

    The capital outlay on a new project isestimated to be as follows;

    The working capital requirement of theproject is Rs.159lakh(CIF value

    Rs.125lakh)

    15 October 2013

    Rs. In lakh

    LandBuildingsImported equipment (CIF value Rs.120 lakh)Indigenous equipment (CIF value Rs.300lakh)

    Engineering and know-how fees

    530150375

    20

  • 7/27/2019 Project Apprisal SCBA & Environment2

    20/35

    The estimated annual profitability of the project is as follows;

    The annual value of output of CIF prices is Rs.1,300lakh

    The CIF value of imported raw material is Rs.200 lakh per annum. The effective tax rate for the firm is 34%.

    15 October 2013

    ( Rs. In lakh)

    Sales revenue

    Imported raw materialIndigenous raw material

    1800

    2201,000

    LabourSalariesRepairs and maintenance

    Water, fuel, etcElectricityOther overhead

    100505

    152010

  • 7/27/2019 Project Apprisal SCBA & Environment2

    21/35

    Social conversion factors(SCF) or proportions of tradablecomponents(T), labour(L) and residual( R) to be used for variousitems are as follows;

    Ignoring salvage value of fixed and current assets and assuming aproject life of 5 years, calculate the Economic Rate of Return (ERR)for the project. Assume that the conversion factors for tradable,labor and residual components are 1/1.5, 0.5, 0.5 respectively.

    15 October 2013

    Item SCF or ProportionsLandBuildingsIndigenous equipmentEngineering and know-how feesLabour

    SalariesRepairs and maintenanceWater, fuel, etcElectricityIndigenous raw materials and storeOther overhead

    SCF=1/1.5Proportion T=0.5, L=0.25, R=0.25SCF=0.7SCF=1.5SCF=0.5

    SCF=0.8SCF=1/1.5Proportions T=0.5, L=0.25, R=0.25Proportions T=0.71, L=0.13, R=0.16SCF=0.8SCF=1/1.5

  • 7/27/2019 Project Apprisal SCBA & Environment2

    22/35

    Social cost associated with Initial outlay

    15 October 2013

    Item Financial cost

    Basis ofconversion

    Trade ablevalue abinitio

    T L R

    LandBuilding

    ImportedEquipmentIndigenousEquipmentEngineering& know-howWorkingCapital

    530

    150

    375

    20

    159

    SCF=1/1.5T=0.5,L=0.25, R=0.25

    CIF value

    CIF Value

    SCF=1.5

    CIF value

    3.33

    120

    300

    30

    125

    15 7.5 7.5

    578.33 15 7.5 7.5

  • 7/27/2019 Project Apprisal SCBA & Environment2

    23/35

    Tradable value ab initio 578.33

    Social cost of trade able component(15/1.5)Social cost of labour component (7.5x0.5)Social cost of residual component (7.5x0.5)

    103.753.75

    Total social cost of initial outlay 595.83

    15 October 2013

  • 7/27/2019 Project Apprisal SCBA & Environment2

    24/35

    Conversion of financial operating costsinto social costs

    15 October 2013

    Item Financial cost

    Basis ofconversion

    Trade ableab initio

    T L R

    Imported RM

    Indigenous RMLabourSalariesRepairs & MtenWater, Fuel,etc

    Electricity

    Other overhead

    220

    100010050515

    20

    10

    CIF value

    SCF=0.8SCF=0.5SCF=0.8SCF1/1.5T=0.5,L=0.25, R=0.25T=0.71,L=0.13,R=0.16SCF=1/1.5

    200

    80050403.33

    6.67

    7.5

    14.2

    3.75

    2.6

    3.75

    3.2

    1,100 21.7 6.35 6.95

  • 7/27/2019 Project Apprisal SCBA & Environment2

    25/35

    Annual Social Cost of Operation

    Social net benefit per year=Rs.1300-Rs.1121.13=Rs178.87

    Economic rate of return(r )

    595.83=178.87PVIFA(r,5)

    r= 15.27%

    15 October 2013

    Trade able value ab initio

    Social cost of trade able component (21.7/1.5)Social cost of labour component (6.35x0.5)Social cost of residual component (6.95x0.5)

    1,100

    14.473.183.48

    1121.13

  • 7/27/2019 Project Apprisal SCBA & Environment2

    26/35

    15 October 2013

    ERP

    = Effective rate of protection

    = {VA @ domestic prices VA @ intl prices}/VA @ intlprices

    VA = value added = selling price input cost

    (exclude tax elements which are characteristic of domesticprice)

    Take FOB of export item and CIF of imported item

    ERP = 0 = no protection to domestic industry, >0 = protection exists,

  • 7/27/2019 Project Apprisal SCBA & Environment2

    27/35

    15 October 2013

    DRC

    Domestic resources cost

    = VA @ domestic prices X exchange rate

    VA @ intl prices DRC = (ERP +1) X Exchange rate

    That means any positive value of ERP results inspending more for a project than if import had

    been permitted. Conflict of interest viz.: domestic Vs forex

    position

  • 7/27/2019 Project Apprisal SCBA & Environment2

    28/35

    15 October 2013

    Environmental Appraisal

    Conflict of interest between industrialgrowth and heritage preservation

    Controlled industrial growth

    Governmental control

    Central and State regulations

    Competition among States Increased public awareness

  • 7/27/2019 Project Apprisal SCBA & Environment2

    29/35

    15 October 2013

    Types

    Land

    Air

    Water Noise

    General environment

  • 7/27/2019 Project Apprisal SCBA & Environment2

    30/35

    15 October 2013

    Specific Cases

    Coco Cola plant in Kerala

    Alang Ship-breaking industry

    Biocon Garment industries of Tirupur

    Low count yarn spinning units

    Ganesh Chathurthi

  • 7/27/2019 Project Apprisal SCBA & Environment2

    31/35

    15 October 2013

    Sources

    Tanneries Chemicals

    Distilleries, sugar, BTindustries

    Organic substances

    Hardware units,photographic units

    Heavy metals

    Drugs and

    pharmaceuticals

    Chemicals into air and

    waterFabric dyeing units Heavy chemicals

    Cement Fly ash

  • 7/27/2019 Project Apprisal SCBA & Environment2

    32/35

    15 October 2013

    Remedies

    Solid, liquid and gaseous forms

    Pollution control equipments

    Technology, cost, process,

    Treatment

    Air, water, noise

    Primary and secondary Large captive waste disposal area

    Areas earmarked for hazardous products

  • 7/27/2019 Project Apprisal SCBA & Environment2

    33/35

    15 October 2013

    Financial Implications

    Non-availability of suitable technology

    Institutions clearance only after this

    Yearly monitoring Environmental audit

    Inspections etc

    Increased cost Possible delay

  • 7/27/2019 Project Apprisal SCBA & Environment2

    34/35

    15 October 2013

    Construction Projects

    Environmental clearance from the Ministry ofEnvironment & Forest (MoEF), GoI

    Covers new construction projects

    viz. new township, industrial township, settlementcolonies, commercial colonies, hotel complexes,hospitals and office complexes with

    Projects that serve 1,000 persons or above

    Discharging sewage of 50,000 liters per day or above. With an investment of Rs.50 cores or above.

  • 7/27/2019 Project Apprisal SCBA & Environment2

    35/35

    15 October 2013

    Procedure for obtainingenvironmental clearance

    Preparation of Rapid Environment Impact Assessmentreport.

    Application for consent to establish & Public Hearing toState Pollution Control Board (SPCB.)

    Attending Public Hearing held by SPCB. Securing consent to establish from SPCB. Application to MoEF, Government of India, for

    Environmental Clearance. Presentation to MoEF, New Delhi.

    Securing Environmental Clearance from MoEF,Government of India. Application to SPCB for Consent to Operate. Securing consent to operate from SPCB