project
description
Transcript of project
Version 1.0
Folding Carton Operations (FCO) Business Requirements Gathering
Prepared by:SANDY KUMAR
ERP Solutions
FCO Status Report
Change History
Document Version
Document Version Date Revised By Requestor Description(s) of Change
1.0 05/24/2012 SKUMAR Creation
Document Change Management and Distribution ProcedureChanges will be applied to this document according to the following procedure:
1. Direct all change requests to the author of this document.
2. Each change request will be considered. If accepted, the change will be incorporated into a new draft of this document.
3. The new draft of this document will be circulated for review by appropriate staff.
4. Approval of the new draft will be by concurrence of those individuals participating in the review.
5. Once concurrence is achieved, the draft becomes the new version of this document, replacing any existing and previous versions.
6. New versions of this document are to be distributed to appropriate staff or made accessible on-line for reference. Notification of a new version will be communicated to appropriate individuals.
1
FCO Status Report
Project Status Template
General Information
Project Name Date
Folding Carton Operations (FCO) Business Requirements Gathering
05/28/2012
Organization
MVW
Contact Phone Email Fax
Melvin Shaffer [email protected]
Project Manager Phone Email Fax
Sandy Kumar 3182676119 [email protected] N/A
Submitted To Period Beginning Period Ending
05/29/2012 06/01/2012
Key Questions Explanation (if Yes)
1. Has the project scope of work changed? Yes No
2. Will upcoming target dates be missed? Yes No
3. Does the team have resource constraints? Yes No
4. Are there issues that require management attention?
Yes No
Mebane ,NC
2
FCO Status Report
Summary Project Status Based on the color legend below, indicate green, yellow, or red for the reporting periods of each item. Any item classified as red or yellow requires an explanation in the comment boxes that follow this section. Additional priority items can be added to the list for status reporting.
Select one color in each of the Reporting Period columns to indicate your best assessment of:
Last Reporting Period [MM/DD/YYYY]
This Reporting Period [MM/DD/YYYY]
1. Overall Project Status Red Yellow Green Red Yellow Green
2. Schedule Red Yellow Green Red Yellow Green
3. Budget (capital, overall project hours)
Red Yellow Green Red Yellow Green
4. Scope Red Yellow Green Red Yellow Green
5. Quality Red Yellow Green Red Yellow Green
Red Yellow Green Red Yellow Green
Color Legend
Red Project has significant risk to baseline cost, schedule, or project deliverables.Current status requires immediate management involvement.
Yellow Project has a current or potential risk to baseline cost, schedule, or project deliverables.Project Manager will manage risks based on risk mitigation planning.
Green Project has no significant risk to baseline cost, schedule, or project deliverables.
Milestones Planned and Accomplished
Milestone Original Date Revised Date Actual Date
All resources are located and started workshops
05/29/2012 05/29/2012
Workshops have started namely 05/29/2012 05/29/2012
Atlanta & Richmond
3
FCO Status Report
Summary Project Status Based on the color legend below, indicate green, yellow, or red for the reporting periods of each item. Any item classified as red or yellow requires an explanation in the comment boxes that follow this section. Additional priority items can be added to the list for status reporting.
Select one color in each of the Reporting Period columns to indicate your best assessment of:
Last Reporting Period [MM/DD/YYYY]
This Reporting Period [MM/DD/YYYY]
1. Overall Project Status Red Yellow Green Red Yellow Green
2. Schedule Red Yellow Green Red Yellow Green
3. Budget (capital, overall project hours)
Red Yellow Green Red Yellow Green
4. Scope Red Yellow Green Red Yellow Green
5. Quality Red Yellow Green Red Yellow Green
Red Yellow Green Red Yellow Green
Color Legend
Red Project has significant risk to baseline cost, schedule, or project deliverables.Current status requires immediate management involvement.
Yellow Project has a current or potential risk to baseline cost, schedule, or project deliverables.Project Manager will manage risks based on risk mitigation planning.
Green Project has no significant risk to baseline cost, schedule, or project deliverables.
Milestones Planned and Accomplished
Milestone Original Date Revised Date Actual Date
All resources are located and started workshops
05/29/2012 05/29/2012
Workshops have started namely 05/29/2012 05/29/2012
Germany
4
FCO Status Report
Summary Project Status : Based on the color legend below, indicate green, yellow, or red for the reporting periods of each item. Any item classified as red or yellow requires an explanation in the comment boxes that follow this section. Additional priority items can be added to the list for status reporting.
Select one color in each of the Reporting Period columns to indicate your best assessment of:
Last Reporting Period [MM/DD/YYYY]
This Reporting Period [MM/DD/YYYY]
1. Overall Project Status Red Yellow Green Red Yellow Green
2. Schedule Red Yellow Green Red Yellow Green
3. Budget (capital, overall project hours)
Red Yellow Green Red Yellow Green
4. Scope Red Yellow Green Red Yellow Green
5. Quality Red Yellow Green Red Yellow Green
Red Yellow Green Red Yellow Green
Color Legend
Red Project has significant risk to baseline cost, schedule, or project deliverables.Current status requires immediate management involvement.
Yellow Project has a current or potential risk to baseline cost, schedule, or project deliverables.Project Manager will manage risks based on risk mitigation planning.
Green Project has no significant risk to baseline cost, schedule, or project deliverables.
Milestones Planned and Accomplished
Milestone Original Date Revised Date Actual Date
Austria
5
FCO Status Report
Summary Project Status -Based on the color legend below, indicate green, yellow, or red for the reporting periods of each item. Any item classified as red or yellow requires an explanation in the comment boxes that follow this section. Additional priority items can be added to the list for status reporting.
Select one color in each of the Reporting Period columns to indicate your best assessment of:
Last Reporting Period [MM/DD/YYYY]
This Reporting Period [MM/DD/YYYY]
1. Overall Project Status Red Yellow Green Red Yellow Green
2. Schedule Red Yellow Green Red Yellow Green
3. Budget (capital, overall project hours)
Red Yellow Green Red Yellow Green
4. Scope Red Yellow Green Red Yellow Green
5. Quality Red Yellow Green Red Yellow Green
Red Yellow Green Red Yellow Green
Color Legend
Red Project has significant risk to baseline cost, schedule, or project deliverables.Current status requires immediate management involvement.
Yellow Project has a current or potential risk to baseline cost, schedule, or project deliverables.Project Manager will manage risks based on risk mitigation planning.
Green Project has no significant risk to baseline cost, schedule, or project deliverables.
Milestones Planned and Accomplished
Milestone Original Date Revised Date Actual Date
All resources are located and started workshops
05/29/2012 05/29/2012
Workshops have started namely 05/29/2012 05/29/2012
Czechslovakia
6
FCO Status Report
Summary Project Status Based on the color legend below, indicate green, yellow, or red for the reporting periods of each item. Any item classified as red or yellow requires an explanation in the comment boxes that follow this section. Additional priority items can be added to the list for status reporting.
Select one color in each of the Reporting Period columns to indicate your best assessment of:
Last Reporting Period [MM/DD/YYYY]
This Reporting Period [MM/DD/YYYY]
1. Overall Project Status Red Yellow Green Red Yellow Green
2. Schedule Red Yellow Green Red Yellow Green
3. Budget (capital, overall project hours)
Red Yellow Green Red Yellow Green
4. Scope Red Yellow Green Red Yellow Green
5. Quality Red Yellow Green Red Yellow Green
Red Yellow Green Red Yellow Green
Color Legend
Red Project has significant risk to baseline cost, schedule, or project deliverables.Current status requires immediate management involvement.
Yellow Project has a current or potential risk to baseline cost, schedule, or project deliverables.Project Manager will manage risks based on risk mitigation planning.
Green Project has no significant risk to baseline cost, schedule, or project deliverables.
Milestones Planned and Accomplished
Milestone Original Date Revised Date Actual Date
All resources are located and started workshops
05/29/2012 05/29/2012
Workshops have started 05/29/2012 05/29/2012
All Locations
7
FCO Status Report
Milestones Planned and Not AccomplishedFor each item listed, provide a corresponding explanation of the effect of this missed item on other target dates and provide the plan to recover from this missed item.
MilestoneLocation
Original Date Revised DateEffect on Other Dates/Plan
Milestones Planned for Next Period
Milestone Original Date Revised Date
Risks Management
Major Risk Events High/Medium/Low Risk Mitigation
Additional Comments
8