Project # 3-3
Transcript of Project # 3-3
GCRC-SOP 7th Year International Workshop
Project # 3-3
Project 3-3: Risk and reliability analysis for efficient design supports
1. Research Background
2. Research Purpose
3. Summary of Research Results
4. Topic1• Risk/reliability based design support system
5. Topic2• Application of SIL technique
6. Conclusion & Future work
1/38
Requirements of research
There are various risks such as oil and gas leakage, fire,
explosion, equipment failure in offshore-plant
(United States, 2015.3*)
Risk and reliability analysis Safety design
Reducing the risk, accident prevention is
needed.
2/38Project 3-3: Risk and reliability analysis for efficient design supports
How to ensure safety Risk based design: Design a system with low risk to reduce damage
based on risk analysis Reliability based design: Safety system reduce accidents caused by
failure in system
Reliability analysis
Design Reliable system
Risk analysisRisk control
optionSafety system
Risk-based
Reliability based
SIL verification
3/38Project 3-3: Risk and reliability analysis for efficient design supports
Whole period Risk/reliability-based design technology
• 1st stage Establishment of basis of core technology for system risk/reliability analysis Application of system risk/reliability analysis technique
• 2nd stage : Development of risk/reliability-based design support system
7th year (2017) Requirement analysis of risk/reliability based design support system Application of SIL (Safety Integrity Level) technique
Safety system with basic process control system SIL verification method
4/38Project 3-3: Risk and reliability analysis for efficient design supports
2nd stage
Development of risk/reliability-based design support system
1year- Requirement analysis of risk/reliability based design support system
- Application of SIL (Safety Integrity Level) technique
2year
- Establishment of risk/reliability DB
- Modularization of risk/reliability based design factor
3year
- Application of design/analysis/validation integrated concept
- Development of risk/reliability based integrated design support system
4year- Application of simulation for risk/reliability based design support system
validation
Purpose by year
5/38Project 3-3: Risk and reliability analysis for efficient design supports
Topic 1 Risk/reliability based design support system
Cost-benefit analysis
p gReliability based optimal design
Fuzzy-based analysis
Risk based optimal design
HAZID analysis
Concept
Overall safety requirements
Hazard and risk analysis
Overall scope definition
Safety requirements allocation
11
2
3
4
5
Overall planning
Overall installationand commissioning
12
Overall safety validation13
Overall operation, maintenance and repair
14
Decommissioning or disposal
16
Overall modification and retrofit
15
Safety life cycle – IEC 61508
6/38
System analysis
Topic 2 Application of SIL (Safety Integrity Level) technique
• SIL verification• FPSO protection relay system, LNG bunkering ESD system
Protection relay system of FPSO ESD system of LNG bunkering
Results of SIL verification
7/38Project 3-3: Risk and reliability analysis for efficient design supports
Results of Topic 1
Fuzzy-based risk assessment
Qualitative, Quantitative risk assessment
HAZID, HAZOP analysis
Risk/reliability based optimum arrangement
Establishment of basis of core technology for system risk/reliability analysis
Application of system risk/reliability analysis technique
Cost-benefit analysis
Requirement analysis of risk/reliability based design support system
SIL verification 1st year
Phast, Flacs, PFD results etc.
Definition of risk/reliability-based Input features
Configuration of deep learning algorithm
Check the risk/reliability results using SILS modeling validation, etc.
Development of risk/reliability-based design support system
GCRC 1st stage
2nd year
3nd year
4nd year
Establishment of risk/reliabilityresult based DB
Modularization of risk/reliability based design factor
risk/reliability based design support system validation
Development of risk/reliability based integrated design support system
GCRC 2nd stage
System analysis
9/38Project 3-3: Risk and reliability analysis for efficient design supports
Analysis of risk/reliability based design support system System analysis (Model based systems engineering)
Requirements diagram
Usecase diagram
10/38Project 3-3: Risk and reliability analysis for efficient design supports
Analysis of risk/reliability based design support system System analysis (Model based systems engineering)
• IEC 61508-5 standard defines key calculations for evaluating SIL
Block Definition Diagram – Knowledge model
11/38Project 3-3: Risk and reliability analysis for efficient design supports
Analysis of risk/reliability based design support system System analysis (Model based systems engineering)
Activity Diagram
12/38Project 3-3: Risk and reliability analysis for efficient design supports
Analysis of risk/reliability based design support system System analysis (Model based systems engineering)
Block Definition Diagram - SIL verification and PFD calculation model
Sensor Logic solver
Final element
Tripsignal
Abnormalsignal
13/38Project 3-3: Risk and reliability analysis for efficient design supports
SIL (Safety Integrity Level)
Process safety system
IEC 61508
IEC 61511
• IEC 61508: Functional safety of electrical/electronic/programmable electronic safety-related systems
• IEC 61511: Functional safety - Safety instrumented systems for the process industry sector
• 070 – Norwegian oil and gas application of IEC 61508 and IEC61511 in the Norwegian petroleum industry: Review and analysis report to apply SIL-related IEC standards to petroleum industry
14/38Project 3-3: Risk and reliability analysis for efficient design supports
BPCS, SIS & SIF BPCS (Basic Process Control System) SIS (Safety Instrumented System) SIF (Safety Instrumented Function)
Logic Solver
Final Element
Sensor
SIS, SIF, SIL Relationship
Logic SolverSensor Final Element
SIF
15/38Project 3-3: Risk and reliability analysis for efficient design supports
SIL & PFDAVG Safety Integrity Level : SIL
• SIL : 1~4, large number is safer PFD : Probability of Failure on Demand
Source : IEC 61508-2 Table 2
16/38
Relationship of SIL and PFDAVG
Project 3-3: Risk and reliability analysis for efficient design supports
SIL Verification To confirm that the current system design satisfies the target SIL
Example of process safety system
Requirement(Target SIL)
Designer(Result SIL)
SIL2
SIL2
SIL3
SIL3
SIL1
SIL2
SIL1
SIL3SIL3
SIL2SIL3
SIL2SIF
SIF
SIF
SIF
SIF
SIF
Target SIL ≤ Result SIL
17/38Project 3-3: Risk and reliability analysis for efficient design supports
SIL Verification Flowchart
Check the target SIL
IEC 61511
Target SIL determination
Definition of safety instrumented function (SIF)
System selection
Risk-based safety system analysis(HAZID, HAZOP, LOPA, etc.)
Calculation of PFD for result SIL Design change
SIF determination
Target SIL ≤ Result SIL
Calculation of PFD for result SIL
No
Yes
18/38Project 3-3: Risk and reliability analysis for efficient design supports
Results of Topic 2
Case study
Case study 1
Case study 2
FPSO
LNG bunkeringSemi-submersible
LNG fueled ship
20/38Project 3-3: Risk and reliability analysis for efficient design supports
System selection AGBAMI FPSO
• Operating from 2008 at Nigeria Agbami• Operated by Chevron, product 70,000 barrels Oil/day, Capacity of 2.15 million
barrels
Agbami FPSO
Agbami oil field at Nigeria Sea
- Case study 1 -Protection relay system of FPSO
21/38Project 3-3: Risk and reliability analysis for efficient design supports
Safety system analysis AGBAMI FPSO power system (75MW-Topside)
• Protection relay system as SIF and protection zone• Generator, transformer, circuit breaker, motor, motor control center
Single line of power system Simplified power system
- Case study 1 -Protection relay system of FPSO
22/38Project 3-3: Risk and reliability analysis for efficient design supports
Definition of Safety Instrumented Function Power system of AGBAMI FPSO
• 11kV, 690V• Supply the 11kV, 690V to loads by transformer• BUS-A, B, C, F, G : 11kV• BUS-D, E : 690V• 3 Generators• 6 Transformers• 31 Circuit breakers• 6 Electrical loads• Protection zone -> SIF
- Case study 1 -Protection relay system of FPSO
23/38Project 3-3: Risk and reliability analysis for efficient design supports
Definition of Safety Instrumented Function Composition and operation
• Power line current detection by current transformer• Over current detection by relay• Circuit breaker trips by relay -> power line shutdown
CT
CT
CT
OCR
OCR
OCR
CB
RBD of protection relay system
Sensor Logic Solver Final Element
Power linecurrent Trip signal
Over Current Relay (OCR)Current Transformer (CT) Circuit Breaker (CB)
- Case study 1 -Protection relay system of FPSO
24/38Project 3-3: Risk and reliability analysis for efficient design supports
Target SIL and result SIL Target SIL determination
Calculation of PFD for result SIL
Device Failure rate ( PFDAVG Type
CT (Current Transformer) 6.9635x10-6 3.0500x10-2 Sensor
OCR (Over Current Relay) 2.2831x10-8 1.0000x10-4 Logic Solver
CB 11kV (Circuit Breaker) 4.1096x10-7 1.8000x10-4 Final Element
CB 690V (Circuit Breaker) 3.0822x10-7 1.3500x10-4 Final ElementFailure rate Source : IEEE 2007, IEEE 2012, exida 2015
Proof Test Interval = 1 year Proof Test Coverage = 1
(*Ref: 070-Norwegian Oil and Gas Application of IEC 61508 and IEC 61511in the Norwegian petroleum industry, Norsok Standard)
- Case study 1 -Protection relay system of FPSO
25/38Project 3-3: Risk and reliability analysis for efficient design supports
Result of SIL
1.829E-031.829E-031.829E-031.829E-031.829E-031.829E-031.829E-03
1.097E-023.657E-03
1.097E-024.136E-034.136E-03
3.657E-033.207E-03
3.657E-033.657E-03
1.097E-025.486E-03
1.097E-02
0.0E+00 2.0E-03 4.0E-03 6.0E-03 8.0E-03 1.0E-02 1.2E-02
19181716151413121110987654321
PFDAVG
Pro
tect
ion
Zone
SIL2 SIL1SIL3, 4
- Case study 1 -Protection relay system of FPSO
ResultSIL
26/38Project 3-3: Risk and reliability analysis for efficient design supports
• Fuel tank: 130 m
• LNG bunkering time :
50min(before 15, during 25,
after 10min)
• Fuel flow rate : 320 m /h• Storage capacity : 2,000 m
• Fuel line dia. : DN150
• Gas recovery line dia. : DN80LNG Bunkering vessel
LNG fuelled ship
Bunkering connection
System selection LNG ship-to-ship bunkering ESD system
Emergency shutdown system
- Case study 2 -LNG bunkering ESD system
27/38Project 3-3: Risk and reliability analysis for efficient design supports
Safety system analysis FMEA Results
• Definition of safety instrumented function through FMEA
- Case study 2 -LNG bunkering ESD system
FMEA of LNG Bunkering- Bunker Operation -
No. Item Name Failure Effect
Sev
CauseOcc
Det
RPN
Control
1 Fire on Board Fire on the vessel
fire will be extinguished bycrew according commonprocedures, bunkering will bestopped by ESD, normaldisconnection or emergencyrelease, bunker vessel willleave receiving vessel.
4 e.g. fire in accommodation 3 1 1
2 fire detection system
2Rupture of Filling Line Rupture of pipe
hose of composite design,LNG spill on receiving andbunker vessel, big gas cloud,gas alarm, ESD initiated,bunkering stopped, structuraldamage of the vessels couldnot be excluded, ignition ofgas cloud can not be excluded,
5 e.g. material failure 2 1 1
0 gas detection system
3Loss of connection
Unintended disconnection LNG spill, large gas cloud 5 5 e.g. ERC will not
be activated 3 1 15 gas detection system
4 OverpressureOver pressurization of storage tanks
if critical pressure is reachedsafety valves will open andgas will be vented toatmosphere
4e.g. loss of overpressureprotection
4 2 32
Pressure monitoring system of storage tanks
28/38Project 3-3: Risk and reliability analysis for efficient design supports
Definition of Safety Instrumented Function The function to prevent dangerous work or to take action to mitigate
dangerous accidents
- Case study 2 -LNG bunkering ESD system
29/38Project 3-3: Risk and reliability analysis for efficient design supports
Definition of Safety Instrumented Function Emergency shutdown function 'SIF-1 ~ 4’
• Consists of 4 scenarios (SIF-1~4) RBD (Reliability Block Diagram)
'SIF-1’ deck fire 'SIF-2’ pipe rupture during fueling
'SIF-3’ LNG bunkering connection broken'SIF-4’ overpressure in the LNG storage tank
- Case study 2 -LNG bunkering ESD system
30/38Project 3-3: Risk and reliability analysis for efficient design supports
(*Ref: 070-Norwegian Oil and Gas Application of IEC 61508 and IEC 61511 in the Norwegian petroleum industry, Norsok Standard)
Target SIL – Minimum SIL Requirements*- Case study 2 -
LNG bunkering ESD system
31/38Project 3-3: Risk and reliability analysis for efficient design supports
Calculation of PFD for result SIL (1/2) PFDAVG (Average Probability of Failure on Demand)
• PFDAVG that can cause an accident due to failure of normal operation of SIF
Σ Σ + Σ
Devices failure rate Relationship of SIL and PFDAVG
- Case study 2 -LNG bunkering ESD system
32/38Project 3-3: Risk and reliability analysis for efficient design supports
Calculation of PFD for result SIL (2/2) Deriving the SIL of the LNG bunkering ESD system
• SIL check by deriving PFDAVG value of 'SIF-1', 'SIF-2', 'SIF-3', and 'SIF-4‘• Comparing the PFDAVG, which is the result of SIL calculation, with the target SIL,
confirming the satisfaction of Target SIL 2
Function PFDAVG Result SIL
SIF-1 6.081E-03 SIL 2
SIF-2 6.059E-03 SIL 2
SIF-3 5.973E-03 SIL 2
SIF-4 6.985E-03 SIL 2
6.081E-03 6.059E-03 5.973E-036.985E-03
-0.001
0.001
0.003
0.005
0.007
0.009
0.011
0.013
0.015
SF-1 SF-2 SF-3 SF-4
SIF-1
SIF-2
SIF-3
- Case study 2 -LNG bunkering ESD system
PFD
AVG
33/38Project 3-3: Risk and reliability analysis for efficient design supports
Conclusion Risk/reliability based design support system
• Performed system analysis: requirement diagram, usecase diagram, 17 Block definition diagrams, 6 activity diagrams, 4 sequence diagrams
• Established SIL verification algorithm Protection relay system
• Defined 19 protection zones as SIFs and calculated the PFDAVG by RBD• 15 protection zones satisfied target SIL 2• Protection zone 1,3,10,12 were calculated SIL 1• Design change should be done to four protection zones
LNG bunkering ESD system• Defined four SIFs based on FMEA for LNG bunker operation: deck fire, pipeline
rupture, broken connection, overpressure of the storage tank• All SIFs satisfied target SIL 2
35/38Project 3-3: Risk and reliability analysis for efficient design supports
Future work• 2 year
Establishment of risk/reliability result based DB Modularization of risk/reliability based design factor
• 3 year Application of design/analysis/validation integrated concept Development of risk/reliability based integrated design support system
• 4 year Application of simulation for risk/reliability based design support system
validation
36/38Project 3-3: Risk and reliability analysis for efficient design supports
Publications International Journal (SCI)
• Min-jae Jung, Byeong-cheol Park, Jeong-hoon Bae, Sung-chul Shin, ‘PAUT-based defect detection method for submarine pressure hulls’, InternationalJournal of Naval Architecture and Ocean Engineering, 2092-6782, 2017.06.
• Jae-chul Lee, Ji-ho Jeong, Philip Wilson, Soon-sup Lee, Tak-kee Lee, Jong-HyunLee, Sung-chul Shin, A study on multi-objective optimal design of derrickstructure: Case study, International Journal of Naval Architecture and OceanEngineering, 2092-6782, 2017.09.
Conference Presentation• ‘2017 The society of naval architects of KOREA spring conference, 2 paper• ‘2017 The Korean society of industry convergence autumn conference, 1 paper• ‘2017 The society of naval architects of KOREA autumn conference, 3 paper• ‘2017 Naval ship technology & weapon systems seminar, 1 paper• ‘2017 International Symposium on Ocean Science and Technology, 1 paper
Education MS Graduate
• Hyung-Sik Kim
37/38Project 3-3: Risk and reliability analysis for efficient design supports