Progress Tracking Sheet-Steel Piping Hydro Testing Testing Reinstated Item Man hour Weighting 20% 45% 25% 10% 1 TP-001 A 950.0 532 0.08 100% 100% 100% 100% 100% 0.084 2 TP-002 A 1700.0 952 0.15 100% 100% 100% 0% 90% 0.136 3 TP-003 A 980.0 549 0.09 100% 100% 100% 0% 90% 0.078 4 TP-004 A 1370.0 767 0.12 100% 100% 100% 0% 90% 0.110 5 TP-005 B 2200.0 1100 0.17 100% 100% 100% 0% 90% 0.157 6 TP-006 B 2950.0 1475 0.23 56% 56% 29% 0% 44% 0.102 7 TP-007 B 800.0 400 0.06 0% 0% 0% 0% 0% 0.000 8 TP-008 B 1050.0 525 0.08 57% 57% 0% 0% 37% 0.031 Progress Summary by Project Area-Piping Hydro Testing Man hour Weighting A 5000 2800 0.44 92% 40.8% B 7000 3500 0.56 52% 29.0% Total 12000 6300 1.00 69.9% Preparation Done Clear Punch List TestPack No Project Area Quantity (Meter) Individual Progress Overall Progress Project Area Quantity (Meter) Progress by Area Overall Progress Progress is updated using data from Test Pack Tracker Sheet

description

tracking sheet

Transcript of Progress Tracking Sheet for Piping Hydrotesting

Progress Tracking SheetProgress Tracking Sheet-Steel Piping Hydro TestingPreparation DoneTestingReinstatedClear Punch ListItemTestPack NoProject AreaQuantity (Meter)Man hourWeighting20%45%25%10%Individual ProgressOverall Progress1TP-001A950.05320.08100%100%100%100%100%0.0842TP-002A1700.09520.15100%100%100%0%90%0.1363TP-003A980.05490.09100%100%100%0%90%0.0784TP-004A1370.07670.12100%100%100%0%90%0.1105TP-005B2200.011000.17100%100%100%0%90%0.1576TP-006B2950.014750.2356%56%29%0%44%0.1027TP-007B800.04000.060%0%0%0%0%0.0008TP-008B1050.05250.0857%57%0%0%37%0.031Progress Summary by Project Area-Piping Hydro TestingProject AreaQuantity (Meter)Man hourWeightingProgress by AreaOverall ProgressA500028000.4492%40.8%B700035000.5652%29.0%Total1200063001.0069.9%
Progress is updated using data from Test Pack Tracker Sheet
Test Pack Tracker SheetProgress updating SectionProgress Calculation SectionItemIso Drawing NoTestpack NoSystem NameWorkpackProject AreaPipe Length(m)Man HourPreparation DoneTestingReinstatedClear Punch ListPreparation DoneTestingReinstatedClear Punch List1ISO-01TP-001TP-001AWP-001A30016810-Jan-1010-Jan-1010-Jan-1015-Jan-103003003003002ISO-02TP-001TP-001AWP-001A20011210-Jan-1020-Jan-1022-Jan-1025-Jan-102002002002003ISO-03TP-001TP-001AWP-001A45025210-Jan-1020-Jan-1022-Jan-1025-Jan-104504504504504ISO-04TP-002TP-002AWP-001A60033610-Jan-1020-Jan-1022-Jan-1025-Jan-106006006006005ISO-05TP-002TP-002AWP-001A50028010-Jan-1020-Jan-1022-Jan-1025-Jan-105005005005006ISO-06TP-002TP-002AWP-001A60033610-Jan-1020-Jan-1022-Jan-1025-Jan-106006006006007ISO-07TP-003TP-003AWP-001A50028010-Jan-1020-Jan-1022-Jan-1025-Jan-105005005005008ISO-08TP-003TP-003AWP-001A48026910-Jan-1020-Jan-1022-Jan-1025-Jan-104804804804809ISO-09TP-004TP-004AWP-002A69038610-Jan-1020-Jan-1022-Jan-1025-Jan-1069069069069010ISO-10TP-004TP-004AWP-002A68038110-Jan-1020-Jan-1022-Jan-1025-Jan-1068068068068011ISO-11TP-005TP-005BWP-002B75037510-Jan-1020-Jan-1022-Jan-1025-Jan-1075075075075012ISO-12TP-005TP-005BWP-002B80040010-Jan-1020-Jan-1022-Jan-1025-Jan-1080080080080013ISO-13TP-005TP-005BWP-002B65032510-Jan-1020-Jan-1023-Jan-10650650650014ISO-14TP-006TP-006BWP-003B85042510-Jan-1020-Jan-1023-Jan-10850850850015ISO-15TP-006TP-006BWP-003B80040010-Jan-1020-Jan-108008000016ISO-16TP-006TP-006BWP-003B65032517ISO-17TP-006TP-006BWP-003B65032518ISO-18TP-007TP-007BWP-004B80040019ISO-19TP-008TP-008BWP-005B45022516ISO-16TP-008TP-008BWP-005B60030010-Jan-1020-Jan-1060060000Progress Summary (work step) by TestPack levelItemTestPack NoProject AreaLength (meter)Preparation DoneTestingReinstatedClear Punch List0.51TP-001A950100%100%100%100%2TP-002A1700100%100%100%100%3TP-003A980100%100%100%100%4TP-004A1370100%100%100%100%5TP-005B2200100%100%100%70%6TP-006B295056%56%29%0%7TP-007B8000%0%0%0%8TP-008B105057%57%0%0%