PROGRESS REPORT TWG 2- UNCEN SEMARANG 11 th OF JULY, 2011

description

PROGRESS REPORT TWG 2- UNCEN. SEMARANG 11 th OF JULY, 2011. Introduction. Legal Basis UU No 30 Tahun 2007 UU No 10 Tahun 1997 UU No 22 Tahun 2001 UU No 17 Tahun 2007 UU No 4 Tahun 2009 UU No 9 Tahun 2009 UU No 32 Tahun 2009. 2. Current Renewable Energy Development. - PowerPoint PPT Presentation

Transcript of PROGRESS REPORT TWG 2- UNCEN

Page 1: PROGRESS REPORT TWG 2- UNCEN

PROGRESS REPORT TWG 2- UNCEN

SEMARANG11th OF JULY, 2011

Page 2: PROGRESS REPORT TWG 2- UNCEN

Introduction

Legal Basis • UU No 30 Tahun 2007 • UU No 10 Tahun 1997• UU No 22 Tahun 2001• UU No 17 Tahun 2007• UU No 4 Tahun 2009• UU No 9 Tahun 2009• UU No 32 Tahun 2009

Page 3: PROGRESS REPORT TWG 2- UNCEN

2. Current Renewable Energy

Development

Page 4: PROGRESS REPORT TWG 2- UNCEN

2.1 Current Energy Policy

• National Energy Policy

Page 5: PROGRESS REPORT TWG 2- UNCEN

• Papua Province Energy Policy through some programs:

a. Villagers empowerment.b. Energy Self-supporting Villagec. Forest conservationd. Illuminating Papuae. Green Economic Zone of Mambramof. Green Economic Zone of Timikag. Food Development and Integrated Energy

Zone of Merauke

Page 6: PROGRESS REPORT TWG 2- UNCEN

6

II MAIN RENEWABLE ENERGY DEVELOPMENT PROGRAM PROGRAM

A. ZONA EKONOMI HIJAU MAMBERAMO

B. ZONA EKONOMI HIJAU TIMIKA

C. KAWASAN PENGEMBANGAN PANGAN DAN ENERGI TERPADU MERAUKE

D. RESPEK – PNPM MANDIRI

A

B

C

Page 7: PROGRESS REPORT TWG 2- UNCEN

2.2 Current Renewable Energy Development

Tabel 2.1 Energy Production from renewable energy utilities

Jenis Energi Produksi Energi ( SBM/th)

Solar Energi 775,04Energi Air 36.536,85BBN 34.871,09

Page 8: PROGRESS REPORT TWG 2- UNCEN

SOLAR ENERGY UTILITIESYear Units Capacity Energy Production

(wp) For one year (kWh))2006 322 3.220,00 9.402

2007 1.650,00 18.125,00 52.925

2008 3.839,00 156.557,50 457.148

2009 7.049,00 258.313 754.273

2010 400 18.000,00 52.560

TOTAL 12.538,00 432.995,00 1.264.345

Page 9: PROGRESS REPORT TWG 2- UNCEN

Hydro Energy Utilities,2010Capacity (Kw) Energy Production

( MWh) SBM per Year

Grid 2040 11.760,3 7.209,06

Off Grid 8.760,0 47.843,04 29.327,78

Total 10799,995 59.603,3 36.536,85

Page 10: PROGRESS REPORT TWG 2- UNCEN

Bio Fuel Utilities ( Jathropa ),2010NO District Regency

Plantation Area

(ha)Production

( liter )

1 Kemtuk Jayapura 3

26.640,0

2 Sarmi Jayapura 5

44.400,0

3 Biak Numfor Biak Numfor 300

2.664.000,0

4 Merauke Merauke 467

4.146.960,0

Total 475

6.882.000,0

Page 11: PROGRESS REPORT TWG 2- UNCEN

Papua Energy Consumtion,2010( With Freeport )

NO JENIS ENERGI KONSUMSI ENERGI

SBM%

1 Avtur 342.214,33 4,10%

2 Avgas 66,64 0,0%

3 Premium 954.631,91 11,43%

4 Kerosene 374.362,73 4%

5 Fuel Oil 3.268.582,47 39,13%

6 LPG 7.228,86 0,09%

7Oli Bekas

44.449,32 0,53%

8Batubara

3.290.204,00 39,39%

9Reewable Energy

72.182,99 0,9%

Total 8.353.923,23 100%

8,35 juta SBM

Page 12: PROGRESS REPORT TWG 2- UNCEN

Papua Energy Consumtion,2010( Without Freeport )

NO JENIS ENERGI KONSUMSI ENERGI PROSENTASI (SBM)

1 Avtur 263.161

12,45%2 Avgas 67

0,00315%3 Premium 954.632

45,15%4 Kerosen 374.363

18%5 Fuel Oil 442.783

20,94%6 LPG 7.229

0,3419%7 EBT 72.183

3,414%

Total

2.114.417,92 100%

Page 13: PROGRESS REPORT TWG 2- UNCEN

Kampung Mandiri Energi ,Papua,2010(Energy Self Support Village

No Kabupaten Distrik Kampung

Basis -KME

Pemanfaatan Awal

1 Biak Numfor Oridek Wadibu Jarak Pagar

Penerangan

2 Biak Numfor Biak Timur

Sundey Biogas Memasak ,Penerangan

3 Pegunungan Bintang

Kiwirok Okik PLTMH

Pemenuhan kebutuhan listrik skala rumah tangga

Page 14: PROGRESS REPORT TWG 2- UNCEN

3RENEWABLE ENERGY DEVELOPMENT

OPPORTUNITY

Page 15: PROGRESS REPORT TWG 2- UNCEN

Table 3.1 Renewable Energy Potential and Current Utilization

Page 16: PROGRESS REPORT TWG 2- UNCEN

Table 3.2 Renewable Energy Development Opportunities

Page 17: PROGRESS REPORT TWG 2- UNCEN

PETA POTENSI PLTA PAPAU ( Sumber=BAPEDA,2011 )

POTENSIAL 6S. Yadowal (Apalapsili)

g (m/dt)Q (m3/dt)

h (m)P (MW)

9,81286,60100,00244,60

POTENSIAL 1S. Idenburg(Yahukimo)

g (m/dt)Q (m3/dt)

h (m)P (MW)

9,81800,00100,00682,78

POTENSIAL 5S. Angolah (Tolikara)

g (m/dt)Q (m3/dt)

h (m)P (MW)

9,81204,71100,00174,71

POTENSIAL 4S. Vanden Wiligen

(Kembu)

g (m/dt)Q (m3/dt)

h (m)P (MW)

9,81184,24100,00157,24

POTENSIAL 2S. Nabuabu

(Yapen Waropen)

g (m/dt)Q (m3/dt)

h (m)P (MW)

9,81346,00100,00295,30

POTENSIAL 3S. Taniku(Masirei)

g (m/dt)Q (m3/dt)

h (m)P (MW)

9,81128,00100,00109,24

POTENSIAL 7S. Apauwar

(Pantai Barat)

g (m/dt)Q (m3/dt)

h (m)P (MW)

9,81203,00100,00173,25

ALTERNATIF 1S. Mamberamo Tengah

(Burmeso)

g (m/dt)Q (m3/dt)

h (m)P (MW)

9,813.850,00

47,001.544,35

Kawasan Industri Bonggrang

Jalur Transmisi 227 Km BONGGRANG

SARMI

BURMESO

17

Page 18: PROGRESS REPORT TWG 2- UNCEN

Tabel 3.3 Projection of Renewable Energy Utilization

Page 19: PROGRESS REPORT TWG 2- UNCEN

4. RENEWABLE ENERGY DEVELOPMENT ACTION PLAN

Page 20: PROGRESS REPORT TWG 2- UNCEN

Table 4.1 Target Of Renewable Energy Development

Page 21: PROGRESS REPORT TWG 2- UNCEN

ACTION PLAN OF HYDRO POWER

Page 22: PROGRESS REPORT TWG 2- UNCEN

ACTION PLAN OF PLTM/PLTMH

Page 23: PROGRESS REPORT TWG 2- UNCEN

ACTION PLAN OF JATHROPA PLANTATION ( BIODIESEL )

Page 24: PROGRESS REPORT TWG 2- UNCEN

ACTION PLAN OF BIOETHANOL DEVELOPMENT

Page 26: PROGRESS REPORT TWG 2- UNCEN

ACTION PLAN OF BIOGAS DEVELOPMENT

Page 27: PROGRESS REPORT TWG 2- UNCEN

ACTION PLAN OF SOLAR ENERGY DEVELOPMENT

Page 28: PROGRESS REPORT TWG 2- UNCEN

IMPLEMENTATION STRATEGY

Page 29: PROGRESS REPORT TWG 2- UNCEN

I.Empowering the such institutions

• Empowering such institutions as Dinas, private sectors, academic as well as establishing Regional Energy Council

Page 30: PROGRESS REPORT TWG 2- UNCEN

II. Conducting energy diversification to maximize the energy resources in Papua

1) Developing and improving the hydro power potentials as electricity.

2) Developing the bio-fuel from such Papua local plants as sago, nyamplung, nipah, coconut, etc.

3) Diversifying the power plants among others by interconnected plants.

Page 31: PROGRESS REPORT TWG 2- UNCEN

III. Improving the people empowerment in Renewable Energy Development Management

1) Maximizing the local energy potentials utilization.2) Developing Energy Self-Support Village.3) Developing the energy specific region.4) Developing energy entrepreneurship capability.5) Socialization on renewable energy continuously to

all the society.6) Improving the business and industry opportunity

in renewable energy field.

Page 32: PROGRESS REPORT TWG 2- UNCEN

III. Supporting the private investment for renewable energy development

1. Publishing and fixing the regional regulation related to the renewable energy development.

2. Developing the local markets for renewable energy development.

3. Legalizing the regional regulation on lands exploitation.

Page 33: PROGRESS REPORT TWG 2- UNCEN

IV. Improving the energy supply and utilization

1) Improving energy efficiency on energy supplier.2) Improving energy efficiency on energy-consuming

devices.3) Improving energy efficiency on energy users.

Page 34: PROGRESS REPORT TWG 2- UNCEN

V. Improving human resources capacity and technology application

1. Developing the budget mechanism research and renewable energy development.2. Developing and fixing the renewable energy curriculum in the higher education institutions

and vocational schools.3. Certifying the expertise on renewable energy.4. Conducting the standard competency on renewable energy.

Page 35: PROGRESS REPORT TWG 2- UNCEN

VI. Minimizing the carbon emission in the power plants and using the environmentally friendly energy.

Page 36: PROGRESS REPORT TWG 2- UNCEN

4.4 Usulan Skema Pendanaan untuk Pengembangan Energi Terbarukan di Papua

Skema pendanaan yang diusulkan pada dasarnya terdiri dari

a. Subsidi Tarif (Harga)b. Kredit Investasic. Pembebasan Pajak Impor Komponen

(Pembayaran Pajak Impor Komponen Oleh Pemerintah)

d. Rabat.