Progress Of Ceiling Per Floors

9
CLIENT: Zabeel Investement L.I.C Planning Departement Package No. : D0469 Early Planned Start Early Planned Finish Tower N4 Basement 2 09-Jan-08 20-Feb-08 22.06% 0.00% Behind Basement 1 26-Dec-07 06-Feb-08 54.41% 0% Behind Ground 12-Dec-07 23-Jan-08 100.00% 1% Behind Level 1 13-Aug-07 24-Sep-07 100% 1% Behind Level 2 05-Sep-07 17-Oct-07 100% 0% Behind Level 3 17-Sep-07 29-Oct-07 100% 0% Behind Level 4 29-Sep-07 10-Nov-07 100% 0% Behind Level 5 13-Oct-07 24-Nov-07 100% 0% Behind Level 6 28-Oct-07 09-Dec-07 100% 0% Behind Level 7 12-Nov-07 24-Dec-07 100% 0% Behind Level 8 27-Nov-07 08-Jan-08 100% 0% Behind Level 9 12-Dec-07 23-Jan-08 100.00% 0% Behind Level 10 27-Dec-07 07-Feb-08 51.49% 0% Behind Level 11 12-Jan-08 23-Feb-08 12% 0% Behind Level 12 27-Jan-08 09-Mar-08 0% 0% On Scedule Level 13 06-Feb-08 19-Mar-08 0% 0% On Scedule Level 14 17-Feb-08 30-Mar-08 0% 0% On Scedule Level 15 27-Feb-08 09-Apr-08 0% 0% On Scedule Early Planned Dates Of Ceiling Works Month : 26 January 2008 Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Ceiling Performance Progress Status Anantara Palm Jumeirah and Tiara Residences Progress Of Ceiling Works

Transcript of Progress Of Ceiling Per Floors

Page 1: Progress Of Ceiling Per Floors

CLIENT: Zabeel Investement L.I.C

Planning Departement

Package No. : D0469

Early Planned Start Early Planned Finish

Tower N4

Basement 2 09-Jan-08 20-Feb-08 22.06% 0.00% Behind

Basement 1 26-Dec-07 06-Feb-08 54.41% 0% Behind

Ground 12-Dec-07 23-Jan-08 100.00% 1% Behind

Level 1 13-Aug-07 24-Sep-07 100% 1% Behind

Level 2 05-Sep-07 17-Oct-07 100% 0% Behind

Level 3 17-Sep-07 29-Oct-07 100% 0% Behind

Level 4 29-Sep-07 10-Nov-07 100% 0% Behind

Level 5 13-Oct-07 24-Nov-07 100% 0% Behind

Level 6 28-Oct-07 09-Dec-07 100% 0% Behind

Level 7 12-Nov-07 24-Dec-07 100% 0% Behind

Level 8 27-Nov-07 08-Jan-08 100% 0% Behind

Level 9 12-Dec-07 23-Jan-08 100.00% 0% Behind

Level 10 27-Dec-07 07-Feb-08 51.49% 0% Behind

Level 11 12-Jan-08 23-Feb-08 12% 0% Behind

Level 12 27-Jan-08 09-Mar-08 0% 0% On Scedule

Level 13 06-Feb-08 19-Mar-08 0% 0% On Scedule

Level 14 17-Feb-08 30-Mar-08 0% 0% On Scedule

Level 15 27-Feb-08 09-Apr-08 0% 0% On Scedule

Early Planned Dates Of Ceiling Works

Month : 26 January 2008

Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks

Ceiling Performance

Progress Status

Anantara Palm Jumeirah and Tiara Residences

Progress Of Ceiling Works

Page 2: Progress Of Ceiling Per Floors

CLIENT: Zabeel Investement L.I.C

Planning Departement

Package No. : D0469

Early Planned Start Early Planned Finish

Tower N3

Basement 2 22-Jan-08 03-Mar-08 6% 0% Behind

Basement 1 08-Jan-08 18-Feb-08 24.63% 0% Behind

Ground 25-Dec-07 04-Feb-08 61.94% 0% Behind

Level 1 23-Sep-07 03-Nov-07 100% 3% Behind

Level 2 04-Oct-07 14-Nov-07 100% 0% Behind

Level 3 16-Oct-07 26-Nov-07 100% 0% Behind

Level 4 28-Oct-07 08-Dec-07 100% 0% Behind

Level 5 08-Nov-07 19-Dec-07 100% 0% Behind

Level 6 20-Nov-07 31-Dec-07 100% 0% Behind

Level 7 02-Dec-07 12-Jan-08 100.00% 0% Behind

Level 8 13-Dec-07 23-Jan-08 100.00% 0% Behind

Level 9 25-Dec-07 04-Feb-08 62.12% 0% Behind

Level 10 06-Jan-08 16-Feb-08 30.30% 0% Behind

Level 11 17-Jan-08 27-Feb-08 6% 0% Behind

Level 12 29-Jan-08 10-Mar-08 0% 0% On Scedule

Level 13 09-Feb-08 20-Mar-08 0% 0% On Scedule

Level 14 19-Feb-08 31-Mar-08 0% 0% On Scedule

Level 15 01-Mar-08 13-Apr-08 0% 0% On Scedule

Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks

Early Planned Dates Of Ceiling Works

Progress Status

Month : 26 January 2008

Ceiling Performance

Anantara Palm Jumeirah and Tiara Residences

Progress Of Ceiling Works

Page 3: Progress Of Ceiling Per Floors

CLIENT: Zabeel Investement L.I.C

Planning Departement

Package No. : D0469

Early Planned Start Early Planned Finish

Tower N2

Basement 2 29-Jan-08 11-Mar-08 0% 0% On Scedule

Basement 1 15-Jan-08 26-Feb-08 6% 0% Behind

Ground 01-Jan-08 12-Feb-08 41% 0% Behind

Level 1 23-Sep-07 04-Nov-07 100% 1% Behind

Level 2 07-Oct-07 18-Nov-07 100% 0% Behind

Level 3 18-Oct-07 29-Nov-07 100% 0% Behind

Level 4 04-Nov-07 16-Dec-07 100% 0% Behind

Level 5 15-Nov-07 27-Dec-07 100% 0% Behind

Level 6 27-Nov-07 08-Jan-08 100% 0% Behind

Level 7 09-Dec-07 20-Jan-08 100.00% 0% Behind

Level 8 20-Dec-07 31-Jan-08 83.46% 0% Behind

Level 9 01-Jan-08 12-Feb-08 41.35% 0% Behind

Level 10 13-Jan-08 24-Feb-08 6% 0% Behind

Level 11 24-Jan-08 06-Mar-08 2% 0% Behind

Level 12 05-Feb-08 18-Mar-08 0% 0% On Scedule

Level 13 17-Feb-08 30-Mar-08 0% 0% On Scedule

Level 14 28-Feb-08 10-Apr-08 0% 0% On Scedule

Level 15 15-Mar-08 26-Apr-08 0% 0% On Scedule

Early Planned Dates Of Ceiling Works

Month : 26 January 2008

Ceiling Performance

Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Progress Status

Anantara Palm Jumeirah and Tiara Residences

Progress Of Ceiling Works

Page 4: Progress Of Ceiling Per Floors

CLIENT: Zabeel Investement L.I.C

Planning Departement

Package No. : D0469

Early Planned Start Early Planned Finish

Tower N1

Basement 2 02-Feb-08 15-Mar-08 0% 0% On Scedule

Basement 1 19-Jan-08 01-Mar-08 6% 0% Behind

Ground 05-Jan-08 16-Feb-08 33.08% 0% Behind

Level 1 29-Sep-07 10-Nov-07 100% 0% Behind

Level 2 15-Oct-07 26-Nov-07 100% 0% Behind

Level 3 27-Oct-07 08-Dec-07 100% 0% Behind

Level 4 07-Nov-07 19-Dec-07 100% 0% Behind

Level 5 19-Nov-07 31-Dec-07 100% 0% Behind

Level 6 01-Dec-07 12-Jan-08 100.00% 0% Behind

Level 7 12-Dec-07 23-Jan-08 100.00% 0% Behind

Level 8 24-Dec-07 04-Feb-08 66.92% 0% Behind

Level 9 05-Jan-08 16-Feb-08 33.08% 0% Behind

Level 10 16-Jan-08 27-Feb-08 6% 0% Behind

Level 11 28-Jan-08 10-Mar-08 0% 0% On Scedule

Level 12 09-Feb-08 22-Mar-08 0% 0% On Scedule

Level 13 19-Feb-08 01-Apr-08 0% 0% On Scedule

Level 14 01-Mar-08 12-Apr-08 0% 0% On Scedule

Level 15 11-Mar-08 22-Apr-08 0% 0% On Scedule

Early Planned Dates Of Ceiling WorksCeiling Performance

Month : 26 January 2008

Progress StatusEarly Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks

Anantara Palm Jumeirah and Tiara Residences

Progress Of Ceiling Works

Page 5: Progress Of Ceiling Per Floors

CLIENT: Zabeel Investement L.I.C

Planning Departement

Package No. : D0469

Early Planned Start Early Planned Finish

Tower S1

Basement 2 02-Jan-08 13-Feb-08 38% 0% Behind

Basement 1 19-Dec-07 30-Jan-08 86.47% 0% Behind

Ground 05-Dec-07 16-Jan-08 100.00% 0% Behind

Level 1 29-Aug-07 10-Oct-07 100% 8% Behind

Level 2 12-Sep-07 24-Oct-07 100% 2% Behind

Level 3 26-Sep-07 07-Nov-07 100% 4% Behind

Level 4 08-Oct-07 19-Nov-07 100% 2% Behind

Level 5 20-Oct-07 01-Dec-07 100% 2% Behind

Level 6 31-Oct-07 12-Dec-07 100% 0% Behind

Level 7 12-Nov-07 24-Dec-07 100% 0% Behind

Level 8 24-Nov-07 05-Jan-08 100% 0% Behind

Level 9 05-Dec-07 16-Jan-08 100.00% 0% Behind

Level 10 17-Dec-07 28-Jan-08 92.48% 0% Behind

Level 11 29-Dec-07 09-Feb-08 48.87% 0% Behind

Level 12 09-Jan-08 20-Feb-08 21.80% 0% Behind

Level 13 21-Jan-08 03-Mar-08 6% 0% Behind

Level 14 02-Feb-08 15-Mar-08 0% 0% On Scedule

Level 15 13-Feb-08 26-Mar-08 0% 0% On Scedule

Month : 26 January 2008

Ceiling PerformanceEarly Planned Dates Of Ceiling Works

Progress StatusEarly Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks

Anantara Palm Jumeirah and Tiara Residences

Progress Of Ceiling Works

Page 6: Progress Of Ceiling Per Floors

CLIENT: Zabeel Investement L.I.C

Planning Departement

Package No. : D0469

Early Planned Start Early Planned Finish

Tower S2

Basement 2 01-Jan-08 11-Feb-08 42.86% 0% Behind

Basement 1 18-Dec-07 28-Jan-08 90.98% 0% Behind

Ground 04-Dec-07 14-Jan-08 100.00% 0% Behind

Level 1 02-Sep-07 13-Oct-07 100% 7% Behind

Level 2 13-Sep-07 24-Oct-07 100% 7% Behind

Level 3 25-Sep-07 05-Nov-07 100% 3% Behind

Level 4 07-Oct-07 17-Nov-07 100% 2% Behind

Level 5 18-Oct-07 28-Nov-07 100% 2% Behind

Level 6 30-Oct-07 10-Dec-07 100% 2% Behind

Level 7 11-Nov-07 22-Dec-07 100% 0% Behind

Level 8 22-Nov-07 02-Jan-08 100% 0% Behind

Level 9 04-Dec-07 14-Jan-08 100.00% 0% Behind

Level 10 16-Dec-07 26-Jan-08 96.99% 0% Behind

Level 11 27-Dec-07 06-Feb-08 53.38% 0% Behind

Level 12 08-Jan-08 18-Feb-08 24.81% 0% Behind

Level 13 20-Jan-08 01-Mar-08 6% 0% Behind

Level 14 31-Jan-08 12-Mar-08 0% 0% On Scedule

Level 15 12-Feb-08 24-Mar-08 0% 0% On Scedule

Early Planned Dates Of Ceiling Works

Month : 26 January 2008

Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Progress Status

Ceiling Performance

Anantara Palm Jumeirah and Tiara Residences

Progress Of Ceiling Works

Page 7: Progress Of Ceiling Per Floors

CLIENT: Zabeel Investement L.I.C

Planning Departement

Package No. : D0469

Early Planned Start Early Planned Finish

Tower S3

Basement 2 26-Dec-07 06-Feb-08 55% 0% Behind

Basement 1 12-Dec-07 23-Jan-08 100.00% 0% Behind

Ground 28-Nov-07 09-Jan-08 100% 0% Behind

Level 1 06-Aug-07 17-Sep-07 100% 7% Behind

Level 2 22-Aug-07 03-Oct-07 100% 8% Behind

Level 3 05-Sep-07 17-Oct-07 100% 0% Behind

Level 4 19-Sep-07 31-Oct-07 100% 0% Behind

Level 5 03-Oct-07 14-Nov-07 100% 0% Behind

Level 6 17-Oct-07 28-Nov-07 100% 0% Behind

Level 7 31-Oct-07 12-Dec-07 100% 0% Behind

Level 8 14-Nov-07 26-Dec-07 100% 0% Behind

Level 9 28-Nov-07 09-Jan-08 100% 0% Behind

Level 10 12-Dec-07 23-Jan-08 100.00% 0% Behind

Level 11 26-Dec-07 06-Feb-08 54.89% 0% Behind

Level 12 07-Jan-08 18-Feb-08 26.32% 0% Behind

Level 13 21-Jan-08 03-Mar-08 6% 0% Behind

Level 14 04-Feb-08 17-Mar-08 0% 0% On Scedule

Level 15 18-Feb-08 31-Mar-08 0% 0% On Scedule

Month : 26 January 2008

Ceiling Performance

Progress Of Ceiling Works

Early Planned Dates Of Ceiling Works

Progress Status

Anantara Palm Jumeirah and Tiara Residences

Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks

Page 8: Progress Of Ceiling Per Floors

CLIENT: Zabeel Investement L.I.C

Planning Departement

Package No. : D0469

Early Planned Start Early Planned Finish

Tower H1

Basement 3 29-Jan-08 10-Mar-08 0% 0% On Scedule

Basement 2 17-Jan-08 27-Feb-08 4% 0% Behind

Basement 1 03-Jan-08 13-Feb-08 27.37% 0% Behind

Ground 20-Dec-07 30-Jan-08 85.39% 0% Behind

Mezzanine 06-Dec-07 16-Jan-08 100.00% 0% Behind

Level 1 23-Aug-07 03-Oct-07 100% 0% Behind

Level 2 06-Sep-07 17-Oct-07 100% 0% Behind

Level 3 20-Sep-07 31-Oct-07 100% 0% Behind

Level 4 04-Oct-07 14-Nov-07 100% 0% Behind

Level 5 18-Oct-07 28-Nov-07 100% 0% Behind

Level 6 01-Nov-07 12-Dec-07 100% 0% Behind

Level 7 13-Nov-07 24-Dec-07 100% 0% Behind

Level 8 25-Nov-07 05-Jan-08 100% 0% Behind

Level 9 06-Dec-07 16-Jan-08 100.00% 0% Behind

Level 10 20-Dec-07 30-Jan-08 86.03% 0% Behind

Level 11 03-Jan-08 13-Feb-08 26.82% 0% Behind

Level 12 17-Jan-08 27-Feb-08 4% 0% Behind

Level 13 31-Jan-08 12-Mar-08 0% 0% On Scedule

Level 14 14-Feb-08 26-Mar-08 0% 0% On Scedule

Level 15 26-Feb-08 07-Apr-08 0% 0% On Scedule

Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Progress Status

Month : 26 January 2008

Early Planned Dates Of Ceiling WorksCeiling Performance

Progress Of Ceiling Works

Anantara Palm Jumeirah and Tiara Residences

Page 9: Progress Of Ceiling Per Floors

CLIENT: Zabeel Investement L.I.C

Planning Departement

Package No. : D0469

Early Planned Start Early Planned Finish

Tower H2

Basement 3 28-Jan-08 09-Mar-08 0% 0% On Scedule

Basement 2 16-Jan-08 26-Feb-08 7% 0% Behind

Basement 1 05-Jan-08 14-Feb-08 25.14% 0% Behind

Ground 24-Dec-07 03-Feb-08 72.78% 0% Behind

Mezzanine 12-Dec-07 22-Jan-08 100.00% 0% Behind

Level 1 04-Sep-07 15-Oct-07 100% 0% Behind

Level 2 18-Sep-07 29-Oct-07 100% 0% Behind

Level 3 04-Oct-07 14-Nov-07 100% 0% Behind

Level 4 17-Oct-07 27-Nov-07 100% 0% Behind

Level 5 31-Oct-07 11-Dec-07 100% 0% Behind

Level 6 14-Nov-07 25-Dec-07 100% 0% Behind

Level 7 28-Nov-07 08-Jan-08 100% 0% Behind

Level 8 12-Dec-07 22-Jan-08 100.00% 0% Behind

Level 9 26-Dec-07 05-Feb-08 60.00% 0% Behind

Level 10 07-Jan-08 17-Feb-08 20.67% 0% Behind

Level 11 19-Jan-08 28-Feb-08 4% 0% Behind

Level 12 30-Jan-08 11-Mar-08 0% 0% On Scedule

Level 13 11-Feb-08 23-Mar-08 0% 0% On Scedule

Level 14 23-Feb-08 03-Apr-08 0% 0% On Scedule

Level 15 05-Mar-08 15-Apr-08 0% 0% On Scedule

Progress StatusEarly Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks

Month : 26 January 2008

Ceiling PerformanceEarly Planned Dates Of Ceiling Works

Anantara Palm Jumeirah and Tiara Residences

Progress Of Ceiling Works