Program Evaluaperttion Review Technique 4707

download Program Evaluaperttion Review Technique 4707

of 29

Transcript of Program Evaluaperttion Review Technique 4707

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    1/29

    Program Evaluation Review Technique

    (PERT)

    Report by:

    Raymund N. Sanchez

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    2/29

    Content of the Presentation

    Definition

    Differences between PERT & CPM

    Purpose Historical Perspective

    Terminologies

    Creating a PERT/CPM diagram

    Schedule Duration Crash Probabilistic Time Estimates

    uncertainty of activities and paths

    path probabilities

    Problem Exercises

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    3/29

    Definition

    A method to analyze the tasks involvedin completing a given project.

    Focus is paid to the time needed tocomplete each task, and identifying theminimum time needed to complete the

    total project.

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    4/29

    Purpose

    To simplify the planning and scheduling oflarge and complex projects.

    To incorporate uncertainty in the sense that itwas possible to schedule a project notknowing precisely the details and duration'sof all the activities.

    Event-oriented technique rather than start-and completion-oriented.

    Used more in R&D-type projects where Cost

    is not a major factor but Time is.

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    5/29

    PERT & CPM Similarities

    Both follow the same steps and use networkdiagrams

    Both are used to plan the scheduling ofindividual activities that make up a project

    They can be used to determine theearliest/latest start and finish times for eachactivity

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    6/29

    PERT & CPM Differences

    PERT is probabilistic whereas CPM isdeterministic

    In CPM, estimates of activity duration arebased on historical data

    In PERT, estimates are uncertain and we talkof ranges of duration and the probability thatan activity duration will fall into that range

    CPM concentrates on Time/Cost trade off.

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    7/29

    Historical Background

    PERT was invented by Booz Allen Hamilton, Inc. undercontract to the United States Department of Defense'sUS Navy Special Projects Office in 1958

    A part of the Polaris mobile submarine-launchedballistic missile project. This project was a directresponse to the Sputnik crisis

    CPM was developed by the dupont company &

    Remington-Rand-Univac Used for large construction projects

    Each were unaware of the others existence until the1960s

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    8/29

    Terminologies

    PERT event: is a point that marks the start or completion of one(or more) tasks. It consumes no time, and uses no resources.It marks the completion of one (or more) tasks. It is not

    reached until all of the activities leading to that event havebeen completed.

    Predecessor event: an event (or events) that immediatelyprecedes some other event without any other events intervening.

    It may be the consequence of more than one activity. Successor event: an event (or events) that immediately follows

    some other event without any other events intervening. It may bethe consequence of more than one activity.

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    9/29

    Terminologies

    PERT activity: is the actual performance of a task. It consumestime, it requires resources (such as labor, materials, space,machinery), and it can be understood as representing the time,

    effort, and resources required to move from one event to another.A PERT activity cannot be completed until the event preceding it

    has occurred. Optimistic time (O): the minimum possible time required to

    accomplish a task, assuming everything proceeds better than isnormally expected

    Pessimistic time (P): the maximum possible time required toaccomplish a task, assuming everything goes wrong (but

    excluding major catastrophes).

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    10/29

    Terminologies

    Most likely time(M): the best estimate of the time required toaccomplish a task, assuming everything proceeds as normal.

    Expected time (TE): the best estimate of the time required to

    accomplish a task, assuming everything proceeds as normal (theimplication being that the expected time is the average time thetask would require if the task were repeated on a number ofoccasions over an extended period of time).

    Critical Path: the longest possible continuous pathway takenfrom the initial event to the terminal event. It determines the totalcalendar time required for the project; and, therefore, any timedelays along the critical path will delay the reaching of theterminal event by at least the same amount.

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    11/29

    Terminologies

    Lead time: the time by which a predecessor event must becompleted in order to allow sufficient time for the activities thatmust elapse before a specific PERT event is reached to be

    completed. Lag time: the earliest time by which a successor eventcan follow

    a specific PERT event.

    Slack: the slackof an event is a measure of the excess time and

    resources available in achieving this event. Positive slackwouldindicate ahead of schedule; negative slack would indicate

    behind schedule; and zero slackwould indicate on schedule.

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    12/29

    Terminologies

    Early Start (ES): maximum EF of all predecessor activities,unless the activity in question is the the first activity, wherein ESis 0

    Early Finish (EF): ES plus task duration

    Late Start (LS): LF minus task duration

    Late Finish (LF): minimum LS on all successor activities, unlessthe activity is the last activity, wherein LF equals EF

    Activity on Arrow (AOA): a type of PERT diagram wherein theactivities are written on the arrows

    Activity on Node (AON): a type of PERT diagram wherein theactivities are written on the nodes

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    13/29

    Creating a PERT Diagram

    STEPS 1: Determine the tasks that the project requires and the

    order in which they must be completed Determine the optimistic, most likely, and pessimistic

    time of each task

    Compute for the Expected time using the formula

    Te=(O+4M+P)/6 Determine whether to use AOA or AON diagrams

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    14/29

    Activity Predecessor Optimistic

    (a)

    Normal

    (m)

    Pessimistic

    (b)

    Te(a+4m+b)/6

    A --- 2 4 6 4.00B --- 3 5 9 5.33

    C A 4 5 7 5.17

    D A 4 6 10 6.33

    E B, C 4 5 7 5.17

    F D 3 4 8 4.50

    G E 3 5 8 5.17f

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    15/29

    Start

    F

    C

    GE

    D

    B

    A

    Finish

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    16/29

    Creating a PERT Diagram

    STEPS 2: Determine the ES & EF of each activity by:

    Start at the beginning moving towards the end ES & EF for the start activity is always 0 since they are

    milestones

    Use the EF of the predecessor activity as the ES of thecurrent activity

    EF of an activity is computed by adding its ES with itsduration

    For activities with 2 or more predecessor activities, usethe predecessor with the higher EF as the ES of the

    current activity

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    17/29

    Start

    ES:0

    EF:0

    F

    D:4.5

    ES:10.33

    EF:14.83

    CD:5.17

    ES:4

    EF:9.17

    G

    D:5.17

    ES:14.34

    EF:19.51

    E

    D:5.17

    ES:9.17

    EF:14.34

    D

    D:6.33

    ES:4

    EF:10.33

    BD:5.33

    ES:0

    EF:5.33

    A

    D:4

    ES:0

    EF:4

    Finish

    D:0

    ES:19.51

    EF:19.51

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    18/29

    Creating a PERT Diagram

    STEPS 3: Determine the LS & LF of each activity by:

    Start at the end and work towards the beginning The LF for the finish activity is equal to EF since it is the

    last activity in the project. Since duration is 0, LS is equalto LF

    Use the LS of the successor activity as the LF of the

    current activity

    LS of an activity is computed by subtracting its LF with itsduration

    For activities with 2 or more successor activities, use the

    successor with the lower LS as the LF of the currentactivity

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    19/29

    Start

    D:0

    ES:0

    EF:0

    LS:0

    LF:0

    F

    D:4.5

    ES:10.33

    EF:14.83

    LS:15.01

    LF:19.51

    C

    D:5.17ES:4

    EF:9.17

    LS:4

    LF:9.17

    GD:5.17

    ES:14.34

    EF:19.51

    LS:14.34

    LF:19.51

    ED:5.17

    ES:9.17

    EF:14.34

    LS:9.17

    LF:14.34

    D

    D:6.33

    ES:4

    EF:10.33

    LS:8.68

    LF:15.01

    B

    D:5.33

    ES:0

    EF:5.33

    LS:3.84

    LF:9.17

    A

    D:4

    ES:0

    EF:4

    LS:0

    LF:4

    Finish

    D:0

    ES:19.51

    EF:19.51

    LS:19.51

    LF:19.51

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    20/29

    Creating a PERT Diagram

    STEPS 4: Compute for the critical path by adding the duration's

    of various paths for all activities Determine if any activities have slack by subtracting the

    activitys LF & EF

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    21/29

    Critical Path

    Critical Path: A-C-E-G

    Path A-D-F = 14.83 work days

    Path A-C-E-G = 19.51 work days

    Path B-E-G = 15.67 work days

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    22/29

    Slack

    Activity LF-EF Total

    A 4 - 4 0

    B 9.17 5.33 3.84

    C 9.17 9.17 0

    D 15.01 10.33 4.68

    E 14.34 14.34 0

    F 19.51 14.83 4.68

    G 19.51 19.51 0

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    23/29

    Gantt Chart

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    24/29

    Schedule Duration Crash

    Crash : an effort to reduce the overall time duration ofa project by employing one or all of the followingtechniques

    Adding resources (human or otherwise)

    Increasing work hours (overtime or weekends)

    Lessening quality

    A trade-off between shorter task duration and higher

    task costs

    If the cost savings on a delay penalty are higher thanthe incremental cost of reducing the project duration,then the crashing is justified.

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    25/29

    Activity Uncertainty

    Standard Deviation of an activity is estimated as onesixth of the difference between the pessimistic andoptimistic time estimates

    Variance is determined by squaring the standarddeviation

    The size of the variance reflects the degree ofuncertainty associated with the activitys time. The

    larger the variance, the greater the uncertainty.

    Standard Deviation = tp - to

    6

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    26/29

    Path Uncertainty

    Standard Deviation of a path can also be computed to

    know the uncertainty of a particular path.

    SD of Path= variances of activities ona path

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    27/29

    Path Probability

    The probability that a given path will be completed in aspecified length of time can be determined using thefollowing formula:

    Z = Specified Time - Path Mean

    Path Standard Deviation

    If the value of Z is 2.50 more, treat the path probabilityas 100%. If the value of Z is less than 2.50, use thetable of values under the standardized normal curve.

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    28/29

    Sample ProblemActivity Description Predecessor Duration

    A Receive production authorization --- 0

    BDetermine parts requirements

    A 2C Determine required resources B 4D Determine material availability C 5E Determine labor availability C 3

    F Determine equipment availability C 5G Prepare operation schedule D, E, F 8H Prepare & issue shop forms G 7I Manufacture the equipment H 31J Deliver the equipment I 4

  • 7/30/2019 Program Evaluaperttion Review Technique 4707

    29/29