    WLR3 Product Establishment

    A breakdown of the steps required to

    launch WLR3 services

    18th December 2006.

  • 8/8/2019 Product Establishment

    2/23

    WLR3 Product Establishment - Web Conference-Call 2

    Contents

    Introduction

    Summary of Product Establishment

    CP ORT Criteria

    PE: A Step-By-Step Guide

    CP Test: Some Useful Information

    Next Steps & Contact Information

  • 8/8/2019 Product Establishment

    3/23

    WLR3 Product Establishment - Web Conference-Call 3

    Introduction to WLR3 Product Establishment

    WLR3 is a new product offering from Openreach requiring afundamentally new method of connectivity which delivers a multitude ofbenefits to Communication Providers (CPs)

    Openreach has developed a WLR3 Product Establishment (PE)process that allows CP and Third Party Integrators to familiarise

    themselves with and meet the required standards for the new systemsand processes associated with WLR3 Analogue

    These slides provide an overview of the process by which a CP canbecome a provider of WLR3 on the Equivalence ManagementPlatform.

    This information is intended for those CPs who have already registeredtheir interest in becoming a WLR3 provider. Those CPs who have notyet registered are invited to do so through the Customer ReceptionTeam or their existing Communications Business Manager (CBM).

  • 8/8/2019 Product Establishment

    4/23

    WLR3 Product Establishment - Web Conference-Call 4

    Registration for WLR3

    By registering their interest, a CP enters into Phase 0.

    This preliminary stage, which occurs prior to the formal start of PE,

    provides the CP with an introduction to the WLR3 product and to the

    Product Establishment process. It also offers the CP the opportunity to

    take advantage of support from Openreach (e.g. WLR3 seminars)

    The completion of Phase 0 activities will enable Openreach to offer the

    CP a formal PE start date based on the readiness of both parties.

    CPs who are already registered and who wish to formally commence

    Product Establishment may do so by following the next stepsinformation provided at the end of the presentation.

  • 8/8/2019 Product Establishment

    5/23

    WLR3 Product Establishment - Web Conference-Call 5

    EMP WLR Product Establishment Process

    Phase 0: CP Registration

    This phase is required for the CP to register their interest in WLR3 with Openreach, to fully understand the

    prerequisites to Product Establishment and to ensure the readiness of both parties prior to beginning PE Phase 1.

    At the end of Phase 0, the CP will be asked to demonstrate its readiness against CP ORT 0 criteria and will

    subsequently be assigned a Phase 1a start date.

    Phase 1: Enrolment and Set-up

    The CP Enrolment Phase represents the formal start of the PE process. During this stage the CP PE plan is

    developed and Openreach resources are assigned to support the activities.

    Phase 1a: CP Enrolment Commercial Contracts, Gathering of Customer Technical and Financial information, PE milestone

    planning

    Phase 1b: CP Set-up Building the CP on the EMP components (e.g.B2B Gateway)

    Phase 2: CP Test Phase 2a: Connectivity Testing

    Phase 2b: Functionality Testing

    Phase 3: Live Verification and Ramp Up

    Phase 0:

    CPRegistration

    Phase 1b:

    CP Set-up

    Phase 2a:

    ConnectivityTest

    Phase 1a:

    CP Enrolment

    Phase 2b:

    FunctionalityTest

    Phase 3:

    Live

    Verification &

    Ramp Up

  • 8/8/2019 Product Establishment

    6/23

    WLR3 Product Establishment - Web Conference-Call 6

    CP ORT Gates: An introduction to the concept

    CP ORT is a series of tests and checks (Gateways) to ensure that the CP isready and able to proceed through the various stages of ProductEstablishment, eventually, launch as a WLR3 provider.

    CP ORT gates are not designed to delay a CPs progress through ProductEstablishment, rather to ensure that each stage can be completed as smoothlyas possible.

    The CP ORT Gateways ensure minimum criteria are met before progression tonext stage

    A Gateway may occur partway through a PE phase to enable the followingphase to commence in parallel

    Each CP ORT Gateway is an assessment which will result in appropriateOpenreach recommendations that the CP progresses into the next stage

    6 CP ORT Gateways (CP ORT0 CP ORT5) will be executed to provideauthorisation to proceed to the next stage of Product Establishment

  • 8/8/2019 Product Establishment

    7/23WLR3 Product Establishment - Web Conference-Call 7

    CP Operational Readiness Testing (CP ORT)

    CP ORT is a series of gateways completed during Product Establishment at several

    intervals to assess the degree of readiness of the CP for entry to the following phase or

    activity

    Please note that the diagram below is for demonstration purpose and is not

    representative of the timescales between the gates.

  • 8/8/2019 Product Establishment

    8/23WLR3 Product Establishment - Web Conference-Call 8

    There are 6 CP ORT gateways

    0:CP Readiness & Entry into WLR3 Product Establishment (P0 to P1a) Assessment of CP readiness for entry into Product Establishment

    1:Entry into CP Testing (P1b to P2a) Ensuring all commercial, test planning and test set-up activities on both the CP and Openreach

    sides prior to commencing CP Testing

    2: Entry into Live Verification (P2b to P3) Ensuring all commercial, launch planning and live set-up activities on both the CP and Openreach

    sides Ensuring the CP has completed at least the mandatory level of testing against the Openreach test

    environment prior to entering Live Verification

    3: Entry into Ramp-Up (P3) Ensuring the mandatory levels of Live Verification activities have completed prior to entry into

    Ramp-Up

    4: Entry into Hand Over to BAU (P3) Ensuring the ramp-up target has been achieved and that Openreach operations are ready toaccept the CP in question prior to handing over to BAU

    5: Acceptance by BAU, CP Launched (P3 complete) Acknowledgement from BAU that the CP has been accepted into live operations and has been

    declared as Launched as a WLR3 provider on Openreach EMP

  • 8/8/2019 Product Establishment

    9/23

    The PE Process - A step-by-step guide

    WLR3 Product Establishment

    A breakdown of the steps required to launch

    WLR3 services

  • 8/8/2019 Product Establishment

    10/23WLR3 Product Establishment - Web Conference-Call 10

    Phase 1a:

    CP Enrolment

    Phase 1b:

    CP Set-up

    Phase 2a:

    Connectivity

    Test

    Phase 2b:

    Functionality

    Test

    Phase 3:

    Live

    Verification &

    Ramp Up

    WLR3 Product Establishment Process

    Phase 0:

    CP

    Registration

    CP Signs NDA

    CP Completes

    Registration

    Questionnaire

    CP Completed CP

    ORT 0 Test

    CP Education

    (Product

    Documents)

    CP Attends WLR3

    Seminar

    CP selects data forCP ORT 0 test

    Openreach inform

    CP of PE Start

    Date

    CP Dashboard

    Activated

    PE Milestone

    Planning

    CP Receives

    Generic Test Pack

    Complete CRD

    CP Credit Check

    (New CPs only) *

    WLR3 Contract

    CP Build on EMP

    Components

    CP Transition

    Planning

    CP Test Planning

    Connect to On-

    Ramp

    Environment

    Test Digital

    Certificated

    Test ebXML

    Payload & Schema

    Connect to CP

    Test Environment

    Execute Test

    Cases

    Resolve Issues

    Re-submit Tests

    Resolve manualintervention

    Submit successful

    test data to

    Openreach

    Confirm CP Setup

    Execute Live

    Verification

    Execute Volume

    Ramp-Up

    * A New CP is a communication provider who does not have an

    active subscription to the current WLR product. A CP may be

    required to pay a deposit based on the outcome of the Credit check

  • 8/8/2019 Product Establishment

    11/23WLR3 Product Establishment - Web Conference-Call 11

    WLR3 Product Establishment Process

    Key Activities

    CP Registers interest to deploy WLR3 with Openreach

    CP and Openreach sign Non Disclosure Agreement

    CP complete registration questionnaire. This will provide key information to Openreach andenable the CP to identify areas where support may be required

    CP is supported through familiarisation of WLR3 Product and PE Process through: Reviewing documents provided on Openreach.co.uk

    Attending CP WLR3 Seminars

    Ad-hoc support provided by Openreach Business and Engagement Managers

    CP informs Openreach of the date they wish to demonstrate their readiness against the CPORT 0 Criteria

    CP provides demonstration of readiness against the CP ORT 0 Criteria

    Following the successful completion of CP ORT 0, Openreach inform CP of the start date forthe beginning of PE Phase 1a.

    Indicative Timescales: Variable based on CP schedules.

    CP ORT Gate: CP ORT 0 CP Ready to Process with PE.

    Phase 1a:

    CP Enrolment

    Phase 1b:

    CP Set-up

    Phase 2a:

    Connectivity

    Test

    Phase 2b:

    Functionality

    Test

    Phase 3:

    Live

    Verification &

    Ramp Up

    Phase 0:

    CP

    Registration

    CP Signs NDA

    CP Completes

    Registration

    Questionnaire

    CP Completed CP

    ORT 0 Test

    CP Education

    (Product

    Documents)

    CP Attends WLR3

    Seminar

    CP selects data forCP ORT 0 test

    Openreach inform

    CP of PE Start

    Date

  • 8/8/2019 Product Establishment

    12/23WLR3 Product Establishment - Web Conference-Call 12

    CP ORT Gateway 0: Criteria Detail

    CP Readiness & Entry into WLR3 Product Establishment

    Assessment of CP readiness for entry into Product Establishment

    Gateway 0 Criteria covers: CP Registration of Interest

    Via email or the OR website

    CP Engagement Questionnaire enable the CP to identify key decisions and capabilities which must be advanced prior toformally commencing PE

    CP Deployment Model CP Direct: The CP connects its own OSS directly to the EMP Gateway

    CP via SI: The CP utilises a SI solution which has previously been tested with the EMP

    CP via Bureau: The CP uses a 3rd Party Managed Service which is already connected to the

    EMP. The CP OSS (if applicable) has no direct connection with the EMP. Key Milestones Identified

    Anticipated start date for connectivity testing

    Anticipated start date for functional testing

    Anticipated live / launch date

  • 8/8/2019 Product Establishment

    13/23WLR3 Product Establishment - Web Conference-Call 13

    Phase 1a:

    CP Enrolment

    Phase 1b:

    CP Set-up

    Phase 2a:

    Connectivity

    Test

    Phase 2b:

    Functionality

    Test

    Phase 3:

    Live

    Verification &

    Ramp Up

    EMP WLR3 Product Establishment Process

    Phase 0:

    CP

    Registration

    CP Dashboard

    Activated

    PE Milestone

    Planning

    WLR3 Contract

    Complete CRD

    CP Credit Check

    (New CPs only)

    CP Receives

    Generic Test Pack

    Summary

    The CP Enrolment Phase is the first stage in the PE process. During this stage the CP PE plan is

    developed and Openreach resources are assigned to support the activities.

    Key Activities

    CP Dashboard Activation: A CP tracking dashboard is activated upon entry into PE Phase 1a. This will

    be visible to both the CP and the Openreach PE staff throughout the PE Process.

    Milestone Planning: The CP, supported by the Openreach PE Delivery Manager, plans out the activities

    required for the completion of PE against the generic plan. This will be supported by a CP-facing PE

    Dashboard

    Complete CRD: Using a form provided, the CP submits commercial and technical information to

    Openreach for the purposes of CP Enrolment and Set-Up (Phase 1b)

    CP Credit Check: A credit check is required for all CPs who do not have an active subscription to the

    current WLR3 product. Following this, a CP may be required to pay a deposit.

    WLR3 Contract: CPs sign and return the Conditions for Wholesale Line Rental 3 to Openreach

    Indicative Timescales:

    4 weeks

    CP ORT Gate:

    Not applicable

  • 8/8/2019 Product Establishment

    14/23WLR3 Product Establishment - Web Conference-Call 14

    Phase 1a:

    CP Enrolment

    Phase 1b:

    CP Set-up

    Phase 2a:

    Connectivity

    Test

    Phase 2b:

    Functionality

    Test

    Phase 3:

    Live

    Verification &

    Ramp Up

    EMP WLR3 Product Establishment Process

    Phase 0:

    CP

    Registration

    CP Build on EMP

    Components

    CP Transition

    Planning

    CP Test Planning

    Summary Upon completion of the CP Enrolment Phase, the CIO Customer Engagement Team works with

    the CP to ensure that the CP is provisioned on the Equivalence Management Platform andassociated test environments. The CP will use this time for test planning as well as progressingwith high level plans around transitions (the eventual migration of existing customers from WLR2to WLR3).

    Key Activities CP is set up on EMP components

    CP Test Planning: Against the CP Test Scenarios document (see slides 18-20)

    CP Transition Planning: Existing CPs engage with Openreach to plan the transition of existingassets from the current systems to EMP. The transition of these assets will occur after thecompletion of the PE Process. Note that Transitions do not need to occur immediately afterProduct Establishment and the CP may choose to wait once entering Business As Usual forWLR3.

    Indicative Timescales: 2 weeks

    CP ORT Gate: CP ORT 1: Successful completion of criteria allows entry into Test phases

  • 8/8/2019 Product Establishment

    15/23

    WLR3 Product Establishment - Web Conference-Call 15

    Phase 1a:

    CP Enrolment

    Phase 1b:

    CP Set-up

    Phase 2a:

    Connectivity

    Test

    Phase 2b:

    Functionality

    Test

    Phase 3:

    Live

    Verification &

    Ramp Up

    EMP WLR3 Product Establishment Process

    Phase 0:

    CP

    Registration

    Connect to On-

    Ramp

    Environment

    Test Digital

    Certificated

    Test ebXML

    Payload & Schema

    Summary Phase 2a tests and assures the connectivity with the TEST WLR EMP environment, including

    testing firewall access, digital certificates and validation of the CPs XML schema.

    Key Activities Once CP ORT1 is completed and all mandatory requirements on the checklist have been

    successfully met, the CP commences the CP connectivity test, specifically to: Establish connectivity to BT On-Ramp system through Firewalls

    Test Digital Certificates

    Test ebXML schema

    Test ebXML Payload

    Resolve faults and confirm completion of connectivity testing.

    Indicative Timescales: 2 weeks

    CP ORT Gate: Not applicable

  • 8/8/2019 Product Establishment

    16/23

    WLR3 Product Establishment - Web Conference-Call 16

    Phase 1a:

    CP Enrolment

    Phase 1b:

    CP Set-up

    Phase 2a:

    Connectivity

    Test

    Phase 2b:

    Functionality

    Test

    Phase 3:

    Live

    Verification &

    Ramp Up

    EMP WLR3 Product Establishment Process

    Phase 0:

    CP

    Registration

    Connect to CP

    Test Environment

    Execute Test

    Cases

    Resolve Issues

    Re-submit Tests

    Resolve manual

    intervention

    Submit successful

    test data to

    Openreach

    Summary Once the connectivity testing is complete, the CP commences functional testing in order to test

    fulfilment and assurance scenarios against the CP Test Environment.

    Key Activities Run test cases developed from the supported test scenarios provided in the Generic Test Pack

    Identify root cause of issues CP manages faults against their own system through to resolution

    CP re-submits tests

    Resolve an manual interventions and ensure the order is put back on the automated route.

    CP submits the output data of the mandatory test scenarios to Openreach in order todemonstrate successful completion of CP Functionality Testing.

    Indicative Timescales:

    6 weeks

    CP ORT Gate: CP ORT 2 Entry into Live Verification. This checkpoint ensures that all mandatory tests have

    been completed and passed.

  • 8/8/2019 Product Establishment

    17/23

    WLR3 Product Establishment - Web Conference-Call 17

    Execute Live

    Verification

    Phase 1a:

    CP Enrolment

    Phase 1b:

    CP Set-up

    Phase 2a:

    Connectivity

    Test

    Phase 2b:

    Functionality

    Test

    Phase 3:

    Live

    Verification &

    Ramp Up

    EMP WLR3 Product Establishment Process

    Phase 0:

    CP

    Registration

    Confirm CP Setup

    Execute Volume

    Ramp-Up

    Summary After the Phase 2 test phase, the CP is required to go through Phase 3 - Live Verification to test

    progression of single orders in controlled fashion on Live platform and ramp-up to BAU volumes insupported and structured fashion

    Finally, upon completion of Phase 3, the CP has completed PE and moves on to Business As Usual.

    Key Activities

    Confirm CP set up on the live environment Execute Live Verification: The CP places orders in the Live environment in a controlled manner (initially

    one at a time, gradually increasing order volumes). The CP is supported by the SMC during this phase.This stage is followed by CP ORT 3.

    Execute Volume Ramp-Up: The CP places orders in increasing volumes until full production volumesare reached. This stage is followed by CP ORT 4.

    CP Is handed over to Business As Usual operational teams. This stage is followed by CP ORT 5.

    Indicative Timescales: Variable

    CP ORT Gate: CP ORT 3: Entry into Ramp-Up this checkpoint ensures that the CP is ready to commence volume

    ramp-up to full production volume CP ORT 4: Entry into Handover to BAU this checkpoint ensures that the CP is ready to go through to

    full, live operation. CP ORT 5: Acceptance by BAU. PE Complete.

  • 8/8/2019 Product Establishment

    18/23

    CP Testing - Some useful information

    WLR3 Product Establishment

    A breakdown of the steps required to launch

    WLR3 services

  • 8/8/2019 Product Establishment

    19/23

    WLR3 Product Establishment - Web Conference-Call 19

    CP Test: Generic Test Pack

    We have developed a set of generic test scenarios which will be madeavailable to the CP

    The CP test environment (covered later in this pack) is intended to support all

    of these test scenarios

    Of the listed scenarios, a subset are marked as mandatory for all CPs

    undertaking Phase 2b Functionality testing.

    A CP may also test against as many optional scenarios as they wish within the

    confines of the test window as specified in the CP test plan

    The CP is required to develop their own test cases against the chosen

    scenarios

    At the end of the test period, the CP is required to demonstrate compliance

    against the test scenarios before progressing to the next PE Phase.

  • 8/8/2019 Product Establishment

    20/23

    WLR3 Product Establishment - Web Conference-Call 20

    Self-Test Management Process and Procedures: Planning and

    Execution

    Identify Test Scenarios for CP

    test (including Mandatory

    Scenarios)

    CP

    Openre

    ach

    TestSu

    pport

    Team

    Openre

    ach

    Test

    Environ

    ment

    suppo

    rt

    Provide Generic Test

    Scenarios Pack (including

    mandatory tests)

    During Phase 1a/1b

    CE and Setup

    Support and Maintain Mini-EMP Environment

    Develop test cases and data on CP

    OSS

    Support CP where required

    OR

    CP

    Determine whether CP

    requires functional test

    During Phase 2a:

    Connectivity Testing

    Phase 2b:

    Functionality Testing

    Connect to Mini-EMP

    Run Test Cases

    Provide evidence of

    successful tests for

    mandatory criteria

  • 8/8/2019 Product Establishment

    21/23

    Next Steps for registered CPs

    WLR3 Product Establishment

    A breakdown of the steps required to launch

    WLR3 services

  • 8/8/2019 Product Establishment

    22/23

    WLR3 Product Establishment - Web Conference-Call 22

    Next Steps for registered CPs

    CPs should review the CP ORT 0 Documentation and also ensure that they are familiar

    with all other EMP and WLR3 Product documentation

    CPs who are ready to do so should then contact their Business Manager and nominate thedate by which they will be able to demonstrate compliance to CP ORT 0

    CPs will then be requested to provide confirmation that they have met to the CP ORT 0

    readiness criteria on that date

    If successful, the CP will be informed of their PE Start date the date at which they willbegin the CP Enrolment activities within Phase 1a

    Further information and WLR3 product documentation, including the CP ORT 0 criteriadocument, can be found at: http://www.openreach.co.uk/orpg/products/wlr/wlr3/wlr3.do

    For any queries, please contact your Business Manager.

    http://www.openreach.co.uk/orpg/products/wlr/wlr3/wlr3.dohttp://www.openreach.co.uk/orpg/products/wlr/wlr3/wlr3.do
  • 8/8/2019 Product Establishment

    23/23

    WLR3 Product Establishment

    A breakdown of the steps required to

    launch WLR3 services