Procurement - Lecture13 260414
-
Upload
tauseefkhan -
Category
Documents
-
view
219 -
download
1
description
Transcript of Procurement - Lecture13 260414
Lecture #13April 18, 2023
1
RFP
CASE STUDY:CROWNAUTOMOBILECOMPANY
2
Crown Automobile Company is trying to complete the testing on a new model mid-sized car that it needs to stay competitive with other automobile companies. The Project Manager, Sue Montgomery, is nervous because of the fact that the project was originally scheduled for completion of testing and start of production last month. The primary problem with the testing is the malfunctioning of a computerized monitoring system that is supposed to indicate problems that should be corrected by the driver of the car. The computerized monitoring system was procured from the Automotive Control Systems Company.
The technical specifications for the monitoring system was prepared by the Crown engineering group. Since the engineering group lacked expertise in this area, the engineer responsible for preparing this specification worked closely with a sales representative from Automotive Control Systems in preparing the performance requirements for the specification. The specification was issued to the Crown procurement group without review from other project groups.
The Crown procurement group could only find two companies that were willing to bid on the RFP for the contract. The contract was awarded to Automotive Control Systems since its bid was twenty percent less than the other bid. After the first computerized monitoring system was delivered, the manufacturing group responsible for assembling the prototype car had difficulty in installing the system resulting in several costly modifications. The testing group experienced numerous difficulties in getting the monitoring system to detect routine problems.
Sue Montgomery called a meeting with the engineering, procurement, manufacturing, and testing groups working on the project to determine a way to resolve the problems. The procurement representative stated that he believes the contract technical specification is not complete and requires revision to obtain a monitoring system that works properly. The manufacturing group representative states that the contract specification should be revised to obtain a monitoring system that is less expensive and time consuming to install. The testing group is of the opinion that shop testing requirements should have been included in the original specification to demonstrate that the system functions properly prior to delivery. Answer the following questions as if you are Sue Montgomery.
3
Why scenarios?
Decision Making
Common Sense
Acquired Knowledge
4
Process of solving
What is the problem?◦What is the symptom?◦What is the cause?
What is creating the problem?What are the possible solutions?What is the BEST solution?
5
Crown Automobile CompanyWhat is the problem?
◦“The primary problem with the testing is the malfunctioning of a computerized monitoring system that is supposed to indicate problems that should be corrected by the driver of the car.”
What is creating the problem?What are the possible solutions?What is the BEST solution?
6
1 – How can the engineering group at this point develop more comprehensive technical requirements for the computerized monitoring system? Should the engineering group have taken a different approach in obtaining the necessary technical input for the specifications prior to their release?
At this point, Engineering group can consolidate the feedback of all manufacturing, testing and procurement groups. This would result as a more comprehensive technical requirements. Engineering should have taken the same kind of approach in the beginning. Rather than consulting with only one supplier, they should have explored the features of all the available solutions in the market and procurement group could help them in doing so. On top of that they should have revised technical requirements multiple times through the reviews of all the in-house important stakeholders like manufacturing, testing, project management and obviously procurement
7
2 – Should the fact that only two bidders were willing to bid on the RFP have indicated that there are problems with the technical specifications?
Yes, it indicates that most probably technical requirements were compiled on the basis of a vendor's existing solution. It can also be deducted on the basis of the fact that Automotive Control System's sales representative worked very closely for formulating the specifications. 8
3 – What input should have been received from the procurement group when the specification for this contract was in draft form?
Procurement could provide the list of suppliers for computerized monitoring system. They could also help in arranging meetings with different suppliers, so that engineering group would have a fair idea of all the systems available in the market. This could help in documenting technical specifications that would be based on Crown Automobile needs, rather than technology of one vendor
9
4 – What input should have been received from the manufacturing group when the specification was in draft form?
Manufacturing group could mainly provide input regarding installation, storage and maintenance of the system. As this feedback wasn't incorporated therefore installation was very challenging and it also resulted in blown up cost.
10
5 – What input should have been received from the testing group when the specification was in draft form?
One key feedback from the testing group is to include shop testing requirements. If it would have been included in the original technical requirements, it could have solved a lot of problems. Other than that, they could have demanded for supplier test representatives to support testing after the installation in system 11
6 – What course of actions will you take?
First thing is to compile all of the technical specifications based on different groups feedback. This process of review should be repeated multiple times but on war footings. Once a comprehensive and all-inclusive requirements are finalized then as a Project Manager I would like to perform following steps, while keeping the sponsor(s) in loop:
1. Engage Automotive Control System again to negotiate a price on the basis of this new set of requirements. It should be cheaper than generating a lot of change requests.
2. Perform a complete bidding process based on these newly formulated requirements
3. Prepare and present the cost benefit analysis of both options (price restructure with existing supplier and going with the new supplier) to sponsor(s) and senior management. On the basis of their feedback, I would rework the entire project plan with updated costs and schedule.
12
RFP
13
RFP: Technical & Management RequirementsTechnical StandardsSpecificationsQuality RequirementsSchedule RequirementsCost RequirementsOther Management
Requirements
14
Schedule Requirements against Contract PricingFixed, unit and target price contracts
require specific completion datesCost reimbursable contracts with
schedule incentive fees can also require a complete definition of schedule requirements
Cost reimbursable contracts with a fixed fee or a percentage fee don’t require a detailed definition of schedule requirements
15
Schedule RequirementsSchedule Completion
Requirements
Schedule Monitoring Requirements
Schedule Incentive Fee Requirements
Responsibilities for Schedule Requirements
16
SCHEDULE COMPLETION REQUIREMENTS
17
Engineered Materials ContractsRequire a substantial amount of detailed workIf buyer develops the detailed design then buyer
should include when the detailed drawings and specifications will be released to supplier
Supplier’s timelines are critical, if it is responsible for a portion of detailed design
Procurement of raw material is another important factor; should be part of RFP (delivery sequence & dates)
RFP specifies how much time is required for buyer inspections
RFP should define dates for providing quality documentation such as material test reports
18
Example: Engineered Material
Buyer •Award Structural Steel Contract
Buyer •Provide Detailed Drawings
Supplier •Procure Structural Steel•Fabricate Columns
Buyer •Inspect Columns
Supplier •Ship Columns
19
Engineered Equipment ContractsRFP defines the date when the suppler will be
released to begin its detailed design workRFP defines the required completion dates for
supplier produced technical documents for activities like licensing and foundation design
RFP specifies the time required for buyer approval
RFP requires that suppliers provide lead times to procure materials
RFP requests a schedule for equipment testing
20
Engineered Equipment Contracts (Contd…)RFP specifies the required
delivery date based on project schedule. This date shouldn’t be earlier than required for installation
RFP specifies the dates when the testing is scheduled to take place at buyer’s premises for supplier’s representative availability
21
Example: Engineered Equipment
Buyer •Award Contract
Buyer •Release Supplier to Begin Design
Supplier •Prepare Detailed Design
Buyer •Approve Detailed Design
Supplier •Procure Materials•Fabricate Solution
Buyer •Inspect Solution
22
Engineering ServicesSchedule dates for completing
technical documents should be included in RFP
Scheduled completion dates for design packages are included in RFP
RFP should include dates of documents/activities that are required for licensing submittals
Dates for completing the design work are also included
23
Example: Engineering Services
Buyer •Award Contract
Supplier •Conceptual Design•Prepare Detailed Specifications
Buyer •Approve Design
Supplier •Submit Licensing Package
Supplier •Submit Design Packages•Submit Drawing Packages
Buyer •Acceptance Test
24
Construction ServicesCompletion dates for activities
that restrain the start of construction contractor activities are included in RFP
The integration of the construction and testing process schedules determines the dates for completion of the construction activities
25
Example: Construction Services
Buyer •Award Contract
Supplier •Receive Drawings•Install structure
Buyer •Inspect structure
Supplier •Install Equipment
Buyer •Test Equipment
26
27
thanK yoU
28