Process Guidelines

87
Doc. N°: WIP-SIPS-PCS-001 Rev.: A Date: 08/02/08 WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES Page 1 of 87 WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES WIP-SIPS-PCS-001 08/02/08 A First Issue RM PCS GP PCS GP ENG Date Revision Description of Revision Prepared by Checked by Approved by

description

Process Guidelines

Transcript of Process Guidelines

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 1 of 87

    WORK IMPROVEMENT PLAN

    PROCESS DESIGN GUIDELINES

    WIP-SIPS-PCS-001

    08/02/08 A First Issue RM PCS GP

    PCS GP

    ENG

    Date Revision Description of Revision Prepared by Checked by Approved by

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 2 of 87

    REVISION RECORDING

    Date Revision Description of Revision Prepared by Checked by Approved by

    08/02/08 A First Issue RM PCS GP

    PCS

    GP ENG

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 3 of 87

    TABLE OF CONTENTS

    1. INTRODUCTION.......................................................................................................................4 2. RESPONSIBILITY ....................................................................................................................4 3. SCOPE......................................................................................................................................4 4. PHYSICAL PROPERTIES........................................................................................................5 5. FORMULA ................................................................................................................................6 6. INSULATION SPECIFICATION FOR PIPING..........................................................................9 7. MATERIALS OF CONSTRUCTION .......................................................................................10 8. SELECTION OF THERMODYNAMIC MODEL IN HYSYS.....................................................11 9. PIG LAUNCHER AND RECEIVER.........................................................................................14 10. PUMP SELECTION AND SYSTEM DESIGN.........................................................................16 11. VESSEL SELECTION AND SIZING.......................................................................................25 12. HEAT EXCHANGERS ............................................................................................................28 13. COLUMNS & TOWERS..........................................................................................................34 14. COMPRESSORS AND VACUUM EQUIPMENT....................................................................36 15. SAFETY SYSTEM & PSV DESIGN........................................................................................38 16. PIPE SIZING ...........................................................................................................................43 17. SELECTION OF VALVES ......................................................................................................48 18. FLARE SYSTEM ....................................................................................................................57 19. HEAT TRANSFER FLUID (HTF) SYSTEM DESIGN .............................................................71 20. COOLING WATER SYSTEM DESIGN...................................................................................72 21. REFRIGERATION SYSTEMS ................................................................................................74 22. CHILLED WATER SYSTEM...................................................................................................75 23. CHILLED BRINE SYSTEM.....................................................................................................76 24. DM WATER SYSTEM.............................................................................................................77 25. STEAM SYSTEM....................................................................................................................78 26. PLANT & INSTRUMENT AIR SYSTEM .................................................................................80 27. NITROGEN GENERATION SYSTEM ....................................................................................82 28. INCINERATOR SYSTEM .......................................................................................................83 29. EFFLUENT TREATMENT SYSTEM.......................................................................................84 30. PROCESS CONTROLS .........................................................................................................86 31. REFERENCE ..........................................................................................................................87

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 4 of 87

    1. INTRODUCTION

    This guideline generally outlines the methods for designing the process systems.

    2. RESPONSIBILITY The design engineer shall be responsible for carrying out the Process system design. The respective lead engineer shall counter check the correctness of calculations and design.

    3. SCOPE This guideline covers the following subjects in detail: 1) Formulas 2) Material of construction 3) Storage tank selection and sizing 4) Vessel selection and sizing 5) Pump selection and sizing 6) Line sizing and selection 7) Control valve selection and sizing 8) Compressor selection 9) Safety valve relief load calculation and selection 10) Raw water / service water / potable water system design 11) Cooling water system design 12) Chilled water / chilled brine system design 13) DM water system design 14) Steam & condensate system design 15) Service and Instrument air system design 16) Nitrogen generation / storage system design 17) Oxygen storage and system design 18) Diesel / Fuel oil / LSHS storage and handling system design 19) Flare system design and selection 20) Chemicals storage and handling system design 21) Process control

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 5 of 87

    4. PHYSICAL PROPERTIES

    Property Units Water Organic Liquids Steam Air Organic Vapors

    KJ/kg C 4.2 1.0 - 2.5 2.0 1.0 2.0 - 4.0 Heat Capacity Btu/lb F 1.0 0.239 - 0.598 0.479 0.239 0.479 - 0.958

    kg/m 1000 700 - 1500 1.29@STP Density

    lb/ft 62.29 43.6 - 94.4 0.08@STP

    KJ/kg 1200 - 2100 200 - 1000 Latent Heat

    Btu/lb 516 - 903 86 - 430

    W/m C 0.55 - 0.70 0.10 - 0.20 0.025 - 0.070 0.025 - 0.05 0.02 - 0.06 Thermal Cond. Btu/h ft F 0.32 - 0.40 0.057 - 0.116 0.0144 - 0.040 0.014 - 0.029 0.116 - 0.35

    Viscosity cP 1.8 @ 0C **See Below 0.01 - 0.03 0.02 - 0.05 0.01 - 0.03

    0.57 @ 50C

    0.28 @ 100C

    0.14 @ 200C

    Prandtl Number 1 - 15 10-1000 1.0 0.7 0.7 - 0.8

    ** Viscosities of organic liquids vary widely with temperature

    Liquid density varies with temperature by: 3.0)( TTCL

    Gas density can be calculated by:

    TRZPMW

    G

    =

    Boiling Point of Water as a Function of Pressure:

    ( ) 25.0910= PTbp ; Tbp in C ; P in MPa

    Density of Metals

    Metal Density (kg/m)

    Aluminum 3500

    Carbon Steel 7800

    Galvanized Iron 6000

    Stainless Steel 8000

    Titanium 4000

    FRP 2000

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 6 of 87

    5. FORMULA

    5.1 VOLUME AND SURFACE AREA

    Volume and surface area for different shapes and sections are:

    Section Volume Surface area

    Sphere D/ 6 D

    Hemi-head D / 12 D/ 2

    S.E.head D / 24 1.084D

    Ellipsoidal head D l / 6 2R + (l2/ e) ln ((1+ e)/(1 e))

    100 60% F& D head 0.08467D 0.9286D

    F & D head 2R K / 3 R ( 1+ l2/ R (2 l/R))

    Cone D l / 12 Dl / 2cos

    Truncated cone ( l (D + D d + d) ) / 12 ((D + d)/2) sqrt (l+((D d)/2))

    30 Truncated cone 0.227(D d) 1.57(D d)

    Cylinder D l / 4 Dl

    .

    Where l = Height of cone, depth of head or length of cylinder = one- half apex angle of cone D = Large diameter of cone / diameter of head or cylinder R = Radius r = Knuckle radius of F & D head L = Crown radius of F & D head h = Partial depth of horizontal cylinder K,C = Coefficients d = Small diameter of truncated cone V = Volume

    2

    2

    1

    211

    Rle

    Rr

    RL

    RL

    RLK

    =

    +

    =

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 7 of 87

    5.2 PARTIAL VOLUME FOR HORIZONTAL VESSELS

    Volume of cylinder (V1)

    )}cos({Rh-1 )cos(

    )cos()sin(3.57

    21

    =

    =

    =

    ADegrees

    RLV

    Volume of Head (V2) (both heads)

    ( )hRhV = 3215.022

    Total Volume (V) 21 VVV +=

    5.3 PARTIAL VOLUME FOR VERTICAL VESSELS

    Volume of cylinder (V1)

    hDV 21 4

    =

    Volume of Head (V2) (one head)

    ( )DRhV = 3215.02

    Total Volume (V) 21 VVV +=

    5.4 WETTED AREA FOR HORIZONTAL VESSELS

    Wetted area of cylinder (A1)

    ( ) LRhArRA = )/1cos(21 Wetted area of heads (A2) (heads are assumed to be hemispherical) (two heads)

    =

    RHRRA 12 22

    Total wetted area (A) 21 AAA +=

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 8 of 87

    5.5 WETTED AREA FOR VERTICAL VESSELS Wetted area of cylinder (A1) hDA = 1 Wetted area of heads (A2) (heads are assumed to be hemispherical) (one head) 22 2 RA = Total wetted area (A) 21 AAA += Where D = Diameter of the vessel (m) R = Radius of the vessel = D/2 (m) L = Length of the vessel (m) h = Height of liquid from vessel bottom (m) A1 = Wetted area of cylindrical portion (m) A2 = Wetted area of heads (m) A = Total wetted area of the vessel (m) V1 = Partial volume of cylindrical portion (m) V2 = Partial volume of heads (m) V = Total liquid volume of the vessel (m)

    5.6 TWO PHASE DENSITY AND VISCOSITY The density and viscosity of mixed phase fluid is found by the following method:

    ( )

    )1(

    )1(

    /

    +=

    +=

    +=

    glh

    glh

    gll QQQ

    Where Q = Volumetric flow rate (m/h) l = Liquid g = Gas or vapor h = Mixed phase or homogenous phase = Density (kg/m) = Viscosity (cP)

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 9 of 87

    6. INSULATION SPECIFICATION FOR PIPING

    6.1 INSULATION THICKNESS FOR HOT SERVICE

    The maximum fluid temperature (C) is shown as a function of the insulation thickness and pipe size.

    Insulation Thickness (mm) 0 25 40 50 65 80 90 100 115 125 140 150 165 180 190 200

    Nominal Pipe Size Maximum Fluid Temperature (C)

    1/2 7 68 230 456 723 760

    1 7 61 205 409 653 760

    1 7 48 150 302 491 707 760

    2 7 45 134 269 439 635 760

    2 7 42 122 244 398 579 760

    3 7 40 111 221 361 526 710 760

    4 7 37 100 195 319 465 629 760

    6 7 35 86 164 265 386 524 676 760

    8 7 34 79 147 236 343 465 599 745 760

    10 7 33 75 136 216 312 422 544 676 760

    12 7 32 72 129 203 292 393 506 629 760

    14 7 32 70 125 196 281 379 487 605 731 760

    16 7 32 68 121 188 268 360 462 573 692 760

    18 7 31 67 117 181 258 345 442 548 661 760

    20 7 31 66 114 176 249 333 426 527 635 750 760

    Over 24 and flat surface 7 31 64 110 167 236 314 400 494 594 701 760

    To obtain the correct insulation thickness, read across from the correct pipe diameter to a tabulated process temperature that is greater or equal to the actual temperatures. Read up for the insulation thickness. For example a 16 diameter pipe operating at 190C will require 80 mm of insulation.

    6.2 INSULATION MATERIAL Up to 343C (650F), magnesia is most used From 871C to 1037C (1600F 1900F) a mixture of asbestos and diatomaceous

    earth is used Ceramic refractories are used for higher temperatures Cryogenic equipment -129C (-200F) employs insulation with fine pores in which air is

    trapped

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 10 of 87

    7. MATERIALS OF CONSTRUCTION

    Material Advantage Disadvantage

    Carbon Steel Low cost, easy to fabricate, abundant, most common material. Resists most alkaline environments well.

    Very poor resistance to acids and stronger alkaline streams. More brittle than other materials, especially at low temperatures.

    Stainless Steel

    Relatively low cost, still easy to fabricate. Resist a wider variety of environments than carbon steel. Available is many different types.

    No resistance to chlorides and resistance decreases significantly at higher temperatures.

    254 SMO (Avesta)

    Moderate cost, still easy to fabricate. Resistance is better over a wider range of concentrations and temperatures compared to stainless steel.

    Little resistance to chlorides, and resistance at higher temperatures could be improved.

    Titanium

    Very good resistance to chlorides (widely used in seawater applications). Strength allows it to be fabricated at smaller thicknesses.

    While the material is moderately expensive, fabrication is difficult. Much of cost will be in welding labor.

    Pd stabilized Titanium

    Superior resistance to chlorides, even at higher temperatures. Is often used on sea water application where Titanium's resistance may not be acceptable.

    Very expensive material and fabrication is again difficult and expensive.

    Nickel Very good resistance to high temperature caustic streams. Moderate to high expense. Difficult to weld.

    Hastelloy Alloy Very wide range to choose from. Some have been specifically developed for acid services where other materials have failed.

    Fairly expensive alloys. Their use must be justified. Most are easy to weld.

    Graphite One of the few materials capable of withstanding weak HCl streams.

    Brittle, very expensive, and very difficult to fabricate. Some stream components have been known to diffusion through some types of graphites.

    Tantalum Superior resistance to very harsh services where no other material is acceptable. Extremely expensive, must be absolutely necessary.

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 11 of 87

    8. SELECTION OF THERMODYNAMIC MODEL IN HYSYS

    Application Type Model Applicable Range Remarks OIL & GAS

    Peng-Robinson (PENG-ROB)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present. Reservoir

    Systems

    Equations of state for high pressure hydrocarbon applications

    Redlich-Kwong-Soave (RK-

    SOAVE)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present.

    Peng-Robinson (PENG-ROB)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present Platform

    Separation

    Equations of state for high pressure hydrocarbon applications Redlich-Kwong-Soave (RK-

    SOAVE)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

    Peng-Robinson (PENG-ROB)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present Transportation of

    oil and gas by pipeline

    Equations of state for high pressure hydrocarbon applications Redlich-Kwong-Soave (RK-

    SOAVE)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

    REFINERY

    Braun K-10 (BK10)

    Suited for vacuum and low pressure

    applications

    Applicable range is 133 -800oK. Can be

    used up to 1100oK

    Gives fast and acceptable answers. Should be use as a first attempt only. This model should not be used for systems containing Hydrogen.

    Chao-Seader (CHAO-SEA)

    < 140 atm 200-533oK

    This model should not be used for systems containing Hydrogen. If light ends dominate, Equation of State models can be used.

    Low Pressure applications (up to several atm) eg: Vacuum tower & crude tower

    Petroleum Correlation Models

    Grayson < 210 atm 200-700oK

    This model should be used for systems containing Hydrogen. If light ends dominate, Equation of State models can be used.

    Chao-Seader (CHAO-SEA)

    < 140 atm 200-533oK

    This model should not be used for systems containing Hydrogen. If light ends dominate, Equation of State models can be used. Petroleum

    Correlation Models

    Grayson < 210 atm 200-700oK

    This model should be used for systems containing Hydrogen. If light ends dominate, Equation of State models can be used.

    Peng-Robinson (PENG-ROB)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

    Medium Pressure applications (up to several tens of atm) Coker Main Fractionator FCC Main Fractionator

    Equation Of State Models Redlich-Kwong-

    Soave (RK-SOAVE)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 12 of 87

    Petroleum Correlation Models Grayson < 210 atm 200-700

    oK

    This model should be used for systems containing Hydrogen. If light ends dominate, Equation of State models can be used

    Peng-Robinson (PENG-ROB)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

    Hydrogen Rich Applications eg: Reformer, Hydrofiner, Hydrotreaters & Hydro-Desulfurisers

    Equation Of State Models Redlich-Kwong-

    Soave (RK-SOAVE)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

    Peng-Robinson (PENG-ROB)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present Lube Oil Unit,

    De-Asphalting Unit

    Equation Of State Models Redlich-Kwong-

    Soave (RK-SOAVE)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

    GAS PROCESSING

    Peng-Robinson (PENG-ROB)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present Hydrocarbon separations De-

    methanizer C3-splitter

    Equation Of State Models Redlich-Kwong-

    Soave (RK-SOAVE)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

    Peng-Robinson (PENG-ROB)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present Cryogenic gas

    processing Equation Of State Models Redlich-Kwong-

    Soave (RK-SOAVE)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

    Peng Robinson MHV2 equation

    of state (PRMHV2)

    Accurate up to 150 bar

    All Temperatures

    Can be used for mixture of polar and non polar components

    Peng Robinson Wong-Sandler

    Equation Of State (PRWS)

    Accurate up to 150 bar

    All Temperatures

    Can be used for mixture of polar and non polar components

    Predictive Soave-Redlich-Kwong (PSRK)

    All Pressures

    All Temperatures

    Can be used for mixture of polar and non polar components

    Redlich Kwong MHV2 equation

    of state (RKSMHV2)

    Accurate up to 150 bar

    All Temperatures

    Can be used for mixture of polar and non polar components

    Gas Dehydration with glycols

    Flexible and Predictive Equation of State Model

    Redlich Kwong Wong-Sandler

    Equation Of State (RKSWS)

    Accurate up to 150 bar

    All Temperatures

    Can be used for mixture of polar and non polar components

    PETROCHEMICALS Chao-Seader (CHAO-SEA)

    < 140 atm 200-533oK

    This model should not be used for systems containing Hydrogen. Ethylene Plant

    Main Fractionator

    Petroleum Correlation Models

    Grayson < 210 atm 200-700oK This model should be used for systems containing Hydrogen.

    Ethylene Plant Light Hydrocarbon

    Equation Of State Models

    Peng-Robinson (PENG-ROB)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 13 of 87

    Separation Train Redlich-Kwong-

    Soave (RK-SOAVE)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

    Peng-Robinson (PENG-ROB)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present Ethylene Plant

    Quench Tower Equation Of State Models Redlich-Kwong-

    Soave (RK-SOAVE)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

    NRTL

    Low pressures up to 10

    atm.

    No component should be close

    to its critical temperature.

    UNIFAC

    Low pressures up to 10

    atm.

    No component should be close

    to its critical temperature.

    Aromatics (eg: BTX Extraction) Liquid Activity Coefficients

    UNIQUAC

    Low pressures up to 10

    atm.

    No component should be close

    to its critical temperature.

    Peng-Robinson (PENG-ROB)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

    Substituted hydrocarbons, VCM Plant & Acrylo Nitrile Plant

    Equation Of State Models Redlich-Kwong-

    Soave (RK-SOAVE)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

    NRTL

    Low pressures up to 10

    atm.

    No component should be close

    to its critical temperature.

    UNIFAC

    Low pressures up to 10

    atm.

    No component should be close

    to its critical temperature.

    Ether Production eg: MTBE, ETBE, TAME

    Liquid Activity Coefficients(very sensitive to parameters)

    UNIQUAC

    Low pressures up to 10

    atm.

    No component should be close

    to its critical temperature.

    Peng-Robinson (PENG-ROB)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present Equation Of State

    Models Redlich-Kwong-Soave (RK-

    SOAVE)

    All Pressures

    All Temperatures

    Should not be used if polar components such as Alcohols are present

    NRTL

    Low pressures up to 10

    atm.

    No component should be close

    to its critical temperature.

    UNIFAC

    Low pressures up to 10

    atm.

    No component should be close

    to its critical temperature.

    Ethyl Benzene and Styrene Plants

    Liquid Activity Coefficients

    UNIQUAC

    Low pressures up to 10

    atm.

    No component should be close

    to its critical temperature.

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 14 of 87

    9. PIG LAUNCHER AND RECEIVER

    Typical diameters of Major Barrel and Pipework:

    Pipeline diameter Bypass line Kicker line Balance line Drain line Major barrel

    4 3 2 2 2 6

    6 4 2 2 2 8

    8 4 6 4 2 2 10

    10 6 4 2 2 12

    12 6 8 4 2 2 16

    14 6 10 4 2 2 16

    16 8 12 6 4 4 18

    18 10 12 8 4 4 20

    20 10 16 8 4 4 24

    24 12 18 8 4 4 28

    28 16 20 10 4 4 32

    30 16 24 10 4 4 36

    32 16 24 10 4 4 36

    36 18 28 12 4 4 40

    38 20 28 12 4 4 42

    40 20 32 12 4 4 44

    42 20 36 16 4 4 46

    48 24 36 18 4 4 52

    56 32 40 20 4 4 60

    Kiker line

    BL AL

    LAUNCHER

    Kiker line

    BR

    AR

    RECEIVER

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 15 of 87

    Barrel lengths for Intelligent Pigs:

    Approx. minimum barrel length (m) (Notes 1 & 2)

    Launcher Receiver Pipeline diameter

    Approx. maximum tool length

    (m) (Note 2)

    Approx. maximum

    tool weight (kg)

    (Note 3) AL BL AR BR

    4 2.8 60 2.8 0.5 2.8 2.8

    6 2.8 90 2.8 1.5 2.8 2.8

    8 3.9 170 4.1 1.5 3.9 3.9

    10 4.3 300 4.3 1.5 4.3 4.3

    12 4.3 365 4.3 1.5 4.3 4.3

    14 4.8 380 4.8 1.5 4.8 4.8

    16 5.1 700 5.1 1.5 5.1 5.1

    18 5.1 810 5.1 1.5 5.1 5.1

    20 5.1 840 5.1 1.5 5.1 5.1

    24 5.7 1600 5.7 1.5 5.7 5.7

    28 5.8 2000 5.8 1.5 5.8 5.8

    30 6.0 2000 6.0 1.5 6.0 6.0

    32 6.6 2270 6.6 1.5 6.6 6.6

    36 6.6 3560 6.6 1.5 5.3 6.6

    38 6.6 3600 6.6 1.5 5.5 6.6

    40 6.6 4090 6.6 1.5 5.5 6.6

    42 6.6 4550 6.6 1.5 6.4 6.6

    48 6.6 Note 4 6.6 1.5 6.6 6.6

    56 6.6 Note 4 6.6 1.5 6.6 6.6

    NOTES: 1) Refer the figure above for details 2) The lengths are extreme figures. To be checked with supplier for accurate dimensions 3) The weight is indicative for the pig only, excluding the weight of lifting/loading trolley 4) To be checked with supplier

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 16 of 87

    10. PUMP SELECTION AND SYSTEM DESIGN

    10.1 PUMP SELECTION

    Service Type of Pump Very high head at low flow Reciprocating Metering small flows (< 1 m/h) Reciprocating (plunger or diaphragm) Viscous fluid (> 1000 cP) Rotary gear or screw Non-Newtonian fluid Screw Suspension of crystals or fragile solids Rotary lobe Entrained gas (> 2 vol%) Rotary or diaphragm

    Centrifugal pumps: Single stage for 3.4 - 1134 m/h (15 - 5000 GPM) & 152 m maximum head Multi Stage for 4.6 - 2500 m/h (20 - 11,000 GPM) & 1675 m maximum head Efficiencies of 45% at 23 m/h (100 GPM), 70% at 113 m/h (500 GPM), 80% at 2270 m/h

    (10,000 GPM). Axial pumps can be used for flows of 4.6 - 22680 m/h (20 - 100,000 GPM) Expect heads up to 12 m and efficiencies of about 65-85% Rotary pumps can be used for flows of 0.23 - 1134 m/h (1 - 5000 GPM) Expect heads up to 15,200 m (50,000 ft) and efficiencies of about 50 - 80% Reciprocating pumps can be used for 2.3 - 22680 m/h (10 - 100,000 GPM) Expect heads up to 300,000 m (1,000,000 ft). Efficiencies:70% at 7.46 kW (10 hp), 85% at 37.3 kW (50 hp) and 90% at 373 kW (500 hp)

    10.2 PUMP PERFORMANCE WITH IMPELLER AND SPEED CHANGE

    Diameter change

    3

    1

    212

    2

    1

    212

    1

    212

    =

    =

    =

    DD

    BHPBHP

    DD

    HH

    DD

    QQ

    Speed change

    3

    1

    212

    2

    1

    212

    1

    212

    =

    =

    =

    NN

    BHPBHP

    NN

    HH

    NN

    QQ

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 17 of 87

    Dia & Speed change

    3

    1

    2

    1

    212

    2

    1

    2

    1

    212

    1

    2

    1

    212

    =

    =

    =

    NN

    DD

    BHPBHP

    NN

    DD

    HH

    NN

    DD

    QQ

    10.3 EFFECT OF VISCOSITY ON PUMP PERFORMANCE

    Alternate for centrifugal pump (rotary pump) to be considered when fluid viscosity is above 220 cSt (or 2500 SSU). Small pumps become impractical above 220 cSt.

    Generally centrifugal pumps are limited to about 4000 SSU max. viscosity Correction factors to head, capacity and efficiency should be applied when viscosity is

    above 70 SSU. Viscosity correction calculation:

    Viscous capacity (gpm) Qvis = Qwater* Cq Cq=0.95-0.9 @200-1000 cSt Viscous head (ft) Hvis = Hwater* Ch Ch=0.85-0.95 @200-1000 cSt Viscous efficiency Evis = Ewater* Ce Ce=0.55-0.75 @200-1000 cSt Correction factors (Cq,Ch,Ce)

    BHP @normal service = (Q*H*SG)/(2.31*1750*E) BHP @viscous service = (Qvis*Hvis*SG)/(2.31*1750*Evis)

    10.4 EFFECT OF VAPOR OR GASES

    1) Most centrifugal pumps can handle up to 3 vol. of vapor per 100 vol. of liquid with the max.

    limit at 7 - 8%. 2) If vapor is suspected in the pump suction area, specify any of the following:

    - Self-priming type pump - Increase suction pressure - Specify low speed pump - Specify that pump casing should be capable of accepting an oversize impeller to

    counter the resulting loss in head and capacity. 10.5 MINIMUM FLOW BYPASS

    1) Single stage pumps, bypass = 15 - 25 % Multistage pumps, bypass = 25 - 35 % Worthington suggests 30 gpm per 100 HP 2) The temperature rise in a turbine regenerative pump is much greater than in a conventional

    centrifugal pump, since the HP input increases as the flow rate thro the turbine pump is decreased, where as the HP input to a centrifugal pump decreases as flow is reduced. Consequently a turbine pump is always provided with bypass and also a relief valve

    3) The increase in liquid temperature at low flow rates may be calculated by assuming that all the HP shown on the pump curve at the desired capacity is being converted to heat, except that which is used to deliver the small capacity (by the following formulae).

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 18 of 87

    ( )

    CpSgQSgHQBHP

    T fromcurve

    =

    33.84.42000252.0

    At shut-off

    ( )

    CpWBHP

    T shutoffat

    =

    4.42

    Where T = Temp diff (F), Q = gpm, H = head (ft), Sg = Specific gravity; Cp = Specific heat capacity (Btu/lbF), W = weight of fluid in pump (lb) 4) Minimum flow orifice sizing can be done by the following formulae:

    = Sg

    PdKQ 28.29

    Where Q = gpm, K = orifice disc coef =0.65, d = orifice dia (inch), P = pres. drop (psi), Sg = Specific Gravity

    10.6 MINIMUM NPSH FOR CENTRIFUGAL PUMPS

    Pump capacity (m/h) NPSHr (m) Pump capacity (m/h) NPSHr (m) Up to 11.4 1.5 159 - 227 3.7 4.3 11.4 22.7 1.8 227 - 455 4.3 6.1 22.7 45.5 2.1 2.4 454 - 568 6.1 7.3 45.5 - 91 2.7 3.0 > 568 7.6 91 - 159 3.0 3.7

    Required NPSH can be reduced as follows:

    - Use a double suction pump - Use a slower speed - Use smaller pumps in parallel - Use an oversize pump - Use impeller with inducer

    10.7 PUMP CENTERLINE ELEVATION FOR CENTRIFUGAL PUMPS

    Pump capacity (m/h) Centerline

    Elevation (m) Pump capacity (m/h) Centerline

    Elevation (m) Up to 45.5 0.76 227 - 2270 1.1 45.5 227 0.91 2270 - 4545 1.4

    10.8 CENTRIFUGAL PUMP EFFICIENCY

    Pump capacity (m/h) Efficiency (%) Pump capacity (m/h) Efficiency (%) Up to 11.4 20 40% 45.5 114 50 75% 11.4 22.7 30 50% 114 - 227 60 80% 22.7 45.5 35 65% 227 - 1136 70 82%

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 19 of 87

    10.9 CENTRIFUGAL PUMP MOTOR RATING

    Shaft Power (BkW) Motor Rating Up to 22.4 1.25 x BkW 22.4 74.6 1.15 x BkW

    > 74.6 1.10 x BkW 10.10 STEAM TURBINE DRIVEN CENTRIFUGALPUMPS

    Shaft Power (BkW) Efficiency (%) Shaft Power (BkW) Efficiency (%) 37.3 33 373 58 74.6 37 746 64

    149.2 45

    10.11 PRESSURE DROP FOR EQUIPMENT AND PIPIING

    Equipment / Piping Item Pressure Drop (bar) Exchangers / Air coolers / Double pipes 0.7 Pump suction screen 0.07 Rotary & turbine flow meters 0.5 Flow orifice 0.2

    Pressure drop Pressure drop Pump suction 0.23 - 0.68 bar/km Pump discharge Carbon Steel Pipe Alloy Steel Pipe

    0 - 57 m/h 5.7 22.6 bar/km 13.6 33.9 bar/km 57 - 159 m/h 3.4 15.8 bar/km 13.6 33.9 bar/km

    > 159 m/h 2 9.1 bar/km 4.5 15.8 bar/km

    Higher velocity is considered for bigger pipes and for higher operating pressures. 10.12 MULTIPLYING FACTOR FOR EQUIVALENT LENGTH

    Pipe dia Approx. straight length (m) 30 60 150

    up to 3" 1.9 1.6 1.2 4" 2.2 1.8 1.3 6" 2.7 2.1 1.4

    8" and above 3.4 2.4 1.6

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 20 of 87

    10.13 PUMP SEALS

    In order to prevent leakage of pump fluid through the clearance between the pump shaft and casing, two types of sealing device are generally used in pumps namely; (1) Gland Packing; (2) Mechanical Seal Gland Packing: This is a simple packing by a sealing device which is a rope like material wound between the pump shaft and casing. Frequent changeover of packing is required to prevent leakage. This is used for domestic and water applications where leakage is not a concern. Mechanical Seals Single mechanical seals are generally used to arrest leakage, without frequent maintenance. Double mechanical seals are sometimes preferred in toxic, flammable and corrosive services. 1) Packed seal (Mechanical seal) Packed seal does not require an external flushing liquid if the pumped liquid has lubricating

    properties at the seal conditions. An external flushing system is required for the following: - For vacuum service to prevent air intake. - For abrasive containing fluids. - For handling volatile fluids which vaporize at operating conditions and present a fire

    hazard. - For pumping toxic or corrosive liquids.

    2) Seal piping

    - Seal cooler duty can be estimated by for a seal fluid flow of 0.5 m/h per seal. - For dead end seals the seal fluid flow can be 0.23 m/h per seal - Seal fluid pressure can be 0.7 1.72 bar above packing box pressure.

    Turbine or pump seal, gland, stuffing box cooling water rate shall be 1-2 m/h.

    Refer API-610 to understand more about the type of flushing plans for each service.

    10.14 CONTROL VALVE PRESSURE DROP FOR CENTRIFUGAL PUMPS

    1) Minimum pressure drop for a control valve is 0.7 bar @design flow rate. 2) Generally CV loss shall be taken as 25% of the total system friction loss or 10% of

    operating pressure 3) More detailed approach for CV pressure drop is:

    sfv dPBdPAdP +=

    Where: dPv = Control valve pressure drop

    dPf = Frictional pressure drop of system dPs = Pressure differential due to static head of system A, B = Multiplication factors (as given below) Qd = Design / rated flow rate Qm = Maximum process flow rate

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 21 of 87

    Pump Over design Factor (Qd / Qm) A B

    0 - 5 % 0.294 0.059 10% 0.468 0.094 15% 0.658 0.132 20% 0.875 0.175 25% 0.950 0.200

    10.15 PUMP SYSTEM CURVE Where:

    dPv = Control valve pressure drop at maximum flow Qm dPo = Control valve pressure drop at full open condition at design flow Qd

    10.16 PUMP CALCULATION

    Hso

    Hd

    dPv

    dPf

    dPs

    dPo

    Qmin Qn Qm Qd

    Pa

    dPf1H1

    H2

    dPf2

    Pb

    PS

    Pd

    H3

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 22 of 87

    Where: Pa = Suction vessel minimum operating pressure (barg)

    Pb = Discharge vessel maximum operating pressure (barg) Pv = Vapor pressure of fluid at maximum operating temperature (bara) Ps = Pump suction pressure (barg) Pd = Pump discharge pressure (barg) Sg = Specific Gravity of the fluid at operating conditions dPf1 = Suction piping frictional loss (bar) dPf2 = Discharge piping frictional loss (bar) H1 = Suction vessel minimum liquid level (LSLL) elevation (m) (bar) H2 = Pump suction nozzle elevation (m) (bar) H3 = Discharge vessel maximum liquid level (LSHH) elevation (m) (bar)

    To convert elevation in meters to pressure unit = H / 10.2 * Sg (in bar) Suction pressure (Ps) = Pa + H1 H2 dPf1 (barg) Discharge pressure (Pd) = Pb + H3 H2 + dPf2 (barg) Pump differential pressure (DP) = Pd Ps (bar) Pump head (h) = DP *10.2 / Sg (m) Available NPSH (NPSHa) = (Pa + 14.7) Pv dPf1 + (H1 - H2) (bara)

    = NPSHa *10.2 / Sg (m)

    General considerations: 1) RVP is lower than the True vapor pressure (TVP or Absolute vapor pressure) of

    hydrocarbon liquids. Correction chart is used to find out TVP from RVP at operating temperature. TVP is used for pump calculations

    2) Calculated NPSHa - 1 m (less 1 m) should be given in the process datasheet. The difference between vendor NPSHr and datasheet NPSHa should not be less than 1 m.

    3) In absence of data pump suction elevation can be considered as 0.6 m for smaller pumps and 1.0 m for larger pumps (> 200 m/h).

    4) In absence of data take 0.1 bar line loss for suction piping or 0.05 bar for smaller pumps. 5) Spare single stage pumps in service over 260C and spare multistage pumps in service

    over 200C must be kept warm for quick start-up, by providing a bypass around check valve. Needle valve to be provided for the bypass.

    6) Pumping capacity over design: Column overhead pumps 20% Product and transfer pumps 10% Design pressure of pump = Design pressure of suction vessel (PSV set) + Max. suction static

    head + Max. pump differential pressure Pump Power calculation

    Power estimates for pumping liquids

    BkW = { Flow (m/h) x Head (m) x Sp.Gr. } / {367 x Efficiency} BHP = { Flow (US gpm) x Head (ft) x Sp. Gr. } / {3960 x Efficiency} **Efficiency expressed as a fraction in these relations

    An equation developed for efficiency based on the GPSA Engineering Data Book is:

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 23 of 87

    Efficiency = 80-0.2855F+0.000378FG-0.000000238FG^2+0.000539F^2-0.000000639(F^2)G + 0.0000000004(F^2)(G^2) Where; Efficiency is in fraction form, F = developed head (ft), G = flow (gpm)

    Ranges of applicability are F = 15 - 91 m and G = 23 230 m/h 10.17 PUMP OVERDESIGN FACTOR

    Service Over design Factor Service Over design Factor Product 10% Sour water drain 25% Reflux 15% Intermittent 0%

    Circulating reflux 5% Utilities 10% 10.18 RECIPROCATING PUMP

    a) Simplified formulas for sizing dampers (for pump speeds up to 100 rpm)

    Pump type Damper volume, US Gallons Simplex, single-acting V = 5 x discharge rate in gpm / rpm Simplex, double-acting V = 2.5 x discharge rate in gpm / rpm Duplex, double-acting V = 1.3 x discharge rate in gpm / rpm

    Triplex, single & double-acting V = 0.45 x discharge rate in gpm / rpm

    For pump speeds above 100 rpm multiply the above volumes by (Pump rpm / 100).

    b) Calculation of line shock pressure due to valve closure

    The magnitude of line shock can be calculated by the following formula:

    g

    vVVSgP P

    =144

    )(

    Where,P = Increase in pressure due to shock (psi) Vp = Velocity of pressure wave propagation in pipe (approx 4000 ft/s in small

    pipes) Sg = Specific gravity of liquid (lb/ft) V = Velocity of liquid in pipe before valve closure (ft/s) v = Velocity of liquid in pipe at an interval equivalent to the time that a

    pressure wave will travel up the pipe and back after the valve starts closing (ft/s)

    G = Acceleration of gravity, 32 (ft/s)

    Example:- A 3" line 1000 ft long is carrying water at a pressure of 250 psi and at a velocity of 10 ft/s is suddenly shut-off by a valve closing in 0.3 sec. Assuming that the velocity of the pressure wave in the pipe is approx 4000 ft/s, it would take 0.5 sec for the wave to travel up the pipe and back. This is slower than the time required for the valve to close and consequently v (the velocity thro the valve after the pressure wave has made one complete cycle) is equal to zero.

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 24 of 87

    P = 62.5 * 4000 * (10 - 0) / (144 * 32.2) = 540 psi

    Total surge pressure = Original pressure in pipe + shock pressure = 250 + 540 = 790 psi In general water hammer will occur when the total surge pressure exceeds twice the static pressure. Therefore, in the above example, water hammer will occur.

    c) Calculation of damper volume required to reduce shock

    Dampers to absorb the shock of fast closing valves are mounted just upstream of the valve. To calculate the minimum surge volume, the following equation may be used.

    ( )( )

    =

    12

    2 )005.0(004.0PP

    TLPRA

    Where, A = Surge volume required (US gpm)

    R = Pipe flow rate (US gpm) T = Normal closing time of valve in sec. (T=0 for instantaneous closure

    valves) L = Length of pipe (ft) P1 = Actual flow pressure at the inlet of valve (source pres. - line DP) (psi) P2 = Upper pressure limit which the surge should be limited to in absorbing

    the decelerating flow on valve closure. This should be set at 1.5 times the static pressure in the line when the valve is closed and the liquid is at rest (psi)

    Example: In a 3"-40 sch line 1000 ft long water @ 230 gpm at 10 ft/s is flowing at 250 psi. Fric. Drop is 4.5 psi/100ft. Valve closure time is 0.3 sec.

    P1 = 250 - (4.5*1000/100) = 205 psi P2 = 250 * 1.5 = 375 psi A = 0.004 * 230 * 375 * (0.005 * 1000 - 0.3) / (375-205) = 9.5 gallons.

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 25 of 87

    11. VESSEL SELECTION AND SIZING 11.1 STORAGE TANKS CAPACITY

    1) For fixed and roofless tanks the working capacity should be the volume between the top of

    the suction nozzle and the maximum safe working level in the tank. 2) For floating roof tanks the working capacity should be the volume between the maximum

    highest safe position for the roof and the minimum allowed position for the roof. 3) For study purposes the working capacity will be multiplied by 1.05 for fixed roof tanks and

    1.10 for floating roof tanks to obtain nominal tank capacities for cost estimating purposes.

    11.2 TYPE OF ROOF

    U.S. environmental protection agency requires the following for storage of hydrocarbon in petroleum refineries: 1) Hydrocarbons with a natural vapor pressure of 1.5 psia (0.103 bara) or less at storage

    temperature may be stored in a freely vented fixed roof tank 2) Hydrocarbons with a natural vapor pressure between 1.5 psia to 11.0 psia (0.103 bara to

    0.76 bara) at storage temperature may be stored in floating roof tanks 3) Hydrocarbons with a natural vapor pressure in excess of 11.0 psia (0.76 bara) at storage

    temperature should be stored in a fixed roof tank with a vapor recovery or refrigeration system.

    4) The flammability of the stored material, regulations governing the emission of the vapor to the atmosphere together with cost of the product lost due to evaporation, should be considered.

    11.3 TYPE OF STORAGE VESSELS

    1) For less than 3.8 m (1000 gallons) vertical tanks on legs can be used. 2) Between 3.8 m and 38 m (1000 to 10,000 gallons) horizontal tanks on concrete supports

    can be used. 3) Beyond 38 m (10,000 gallons) vertical tanks on concrete pads can be used. 4) Liquids with low vapor pressures, tanks with floating roofs can be used. 5) Raw material feed tanks are often specified for 30 days feed supplies 6) Storage tank capacity should be at 1.5 times the capacity of mobile supply vessels. 7) For example, 28.4 m (7500 gallon) tanker truck, 130 m (34,500 gallon) rail cars 8) Liquid drums are usually horizontal. Gas/Liquid separators are usually vertical 9) Optimum Length/Diameter ratio is usually 3, range is 2.5 to 5

    11.4 HOLDUP TIME

    1) Holdup time is 5 minutes for half full reflux drums and gas/liquid separators 2) Design for a 5-10 minute holdup for drums feeding another column 3) For drums feeding a furnace, a holdup of 30 minutes is a good estimate 4) Knockout drum in front of compressors should be designed for a holdup of 10 times the

    liquid volume passing per minute.

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 26 of 87

    11.5 VELOCITY CRITERIA 1) Liquid/Liquid separators should be designed for settling velocities of 2-3 inch/min (0.00085

    m/s to 0.0013 m/s) 2) Gas velocities in gas/liquid separators

    ( )1= V

    LkVelocity

    Where k = 0.35 with horizontal mesh deentrainers 0.167 with vertical mesh deentrainers 0.1 without mesh deentrainers Velocity is in ft/s A 6 (150 mm) mesh pad thickness is very popular for such vessels

    3) For positive pressure separations, disengagement spaces of 6-18 (150 mm to 450 mm) before the mesh pad and 12 inches (300 mm) after the pad are generally suitable

    11.6 DESIGN CONDITIONS

    1) The design pressure for atmospheric storage tanks is +100 mmWC (or full of water) / -50 mmWC

    2) Design pressure is 10% or 0.69 bar to 1.7 bar above the maximum operating pressure, whichever is greater, as applicable

    3) The maximum operating pressure is taken as 1.7 bar (25 psi) above the normal operation pressure, as applicable

    4) For vacuum operations, design pressures are 1 barg (15 psig) to full vacuum 5) For systems with maximum operating temperature (MOT) between -30C and 345C,

    design temperatures is typically MOT + 15C (to 25C as applicable). Above this range the margin increases

    6) Minimum design temperature is 0C to 5C less than the minimum operating temperature 7) Minimum wall thicknesses for maintaining tank structure are:

    6.4 mm (0.25 in) for 1.07 m (42 in) diameter and under 8.1 mm (0.32 in) for 1.07 m - 1.52 m (42-60 in) diameter 9.7 mm (0.38 in) for diameters over 1.52 m (60 in)

    8) Allowable working stresses are taken as 1/4 of the ultimate strength of the material

    11.7 MECHANICAL DESIGN

    1) Thickness calculation based on pressure and radius is given by: (Pressure) * (outer Radius)

    Thickness = (Allowable stress) * (Weld Efficiency) 0.6 (Pressure)

    Where : pressure = psig, radius = inch, stress = psi, corrosion allowance = inch ** Weld efficiency can usually be taken as 0.85 for initial design work 2) Guidelines for corrosion allowances are as follows: 0.35 in (9 mm) for known corrosive

    fluids, 0.15 in (4 mm) for non-corrosive fluids, and 0.06 in (1.5 mm) for steam drums and air

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 27 of 87

    receivers

    3) Generally 1.5 mm to 3.0 mm is considered as the minimum corrosion allowance (CA) for Carbon Steel equipment/piping while Nil corrosion allowance is considered for Stainless Steel and non-metallic equipment/piping

    11.8 SIZING EXPLOSION HATCHES

    e

    WW '3600 =

    Where W = Required relieving capacity (lb/h) W' = Weight of air and gas in the vessel (lb) e = Time to attain maximum pressure (sec)

    Time to attain maximum pressure for mixture of gases and air at 1 atm & 150F is 0.01 sec for H2, 0.045 sec for ethane, 0.056 for propane, 0.06 for hexane and naphtha, 0.0117 for acetylene, 0.06 for benzene, 0.10 for toluene. The required open area, A, to discharge the relieving capacity, W, using a discharge coefficient of 0.8 is:

    1245

    /PMTZWA

    =

    Where A = Discharge area (in) P1 = Relieving pressure (psia) T = Initial temperature (R) Z = Compressibility factor, at P1 & T M = Mixture MW

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 28 of 87

    12. HEAT EXCHANGERS

    Some of the important design tips for heat exchanger design are: 1) Fluids that are corrosive, fouling, scaling, high pressure drop or under high pressure are

    usually placed in tube side 2) Hot, viscous and condensing fluids are typically placed on the shell side 3) Pressure drops are about 1.5 psi (0.1 bar) for boiling/vaporization and 3-10 psi (0.2-0.7 bar)

    for other services 4) The minimum approach temperature for shell and tube exchangers is about 20F (10 C)

    for fluids and 10F (5C) for refrigerants. 5) Cooling tower water is typically available at a maximum temperature of 90F (30C) and

    should be returned to the tower no higher than 115F (45C) 6) Double pipe heat exchangers may be a good choice for areas from 100 to 200 ft2 (9.3-18.6

    m2) 7) Spiral heat exchangers are often used to slurry interchangers and other services containing

    solids 8) Plate heat exchanger with gaskets can be used up to 320F (160C) and are often used for

    interchanging duties due to their high efficiencies and ability to "cross" temperatures. 9) For the heat exchanger equation, Q = UAF (LMTD), use F = 0.9 when charts for the LMTD

    correction factor are not available 10) Shell and Tube heat transfer coefficient for estimation purposes can be found in many

    reference books 11) Most commonly used tubes are (19 mm) outer diameter on a 1 triangular spacing at 16

    ft (4.9 m) long 12) A 1 ft (300 mm) shell will contain about 100 ft2 (9.3 m2) A 2 ft (600 mm) shell will contain about 400 ft2 (37.2 m2) A 3 ft (900 mm) shell will contain about 1100 ft2 (102 m2) 13) Typical velocities in the tubes should be 3-10 ft/s (1-3 m/s) for liquids and 30-100 ft/s (9-30

    m/s) for gases

    12.1 DESIGN MARGINE The following design margins shall be adopted as applicable: 1) Heat exchangers shall be designed with 10% margin on area while using the normal heat

    duty. 2) While designing heat exchangers, 10% margin on normal duty shall be considered and the

    exchanger shall be designed with minimum over design factor (say 2% to 5%) on area. 3) If the design duty (10% to 15% over design factor) is used for sizing the heat exchangers,

    then the exchanger shall be designed with minimum over design factor (say 2% to 5%) on area.

    12.2 EVAPORATORS

    1) When the boiling point rise is appreciable, the economic number of effects in series with forward feed is 4-6.

    2) When the boiling point rise is small, minimum cost is obtained with 8-10 effect in series.

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 29 of 87

    12.3 HEAT EXCHANGER DETAILS 1) TEMA shell types: 2) Baffle cut orientation; parallel, perpendicular and 45 with reference to shell nozzle 3) Tube length : Length up to the tangent point of the outermost tube for U-tubes. The length

    in the tube sheets should be included. Effective area is excluding the tube sheet. 4) Shell inlet nozzle location 5) U-tube nozzle location

    Parallel0

    Perpendicular90

    45

    U-tube exchanger

    Overall tube length

    Total tube length

    code 0

    VerticalHorizontal

    code 2

    code 1

    Code 0, normal Code 1, in front of Code 2, behind U

    ACU

    TEMA X TEMA G TEMA H

    TEMA J21 TEMA J12 TEMA E

    TEMA K

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 30 of 87

    6) Shell side inlet nozzle location: Normally it is assumed to be at the tube channel end.

    Distance from tangent point to last baffle: Generally the last baffle is placed at the at the tangent point of the U-tube

    7) Tube arrangement 8) Impingement device: An impingement plate will be added if the inlet nozzle pV value is

    greater than TEMA standards (1500 lb/ft s or 2232 kg/m s) 9) Adding a shell in parallel: If pressure drop limitations are not met at the maximum shell

    diameter permitted, a unit can be added in parallel. 10) Adding a shell in series: If a pure counter flow exchanger has been selected, a shell can be

    added in series only if the required heat duty can not be achieved at the maximum permitted shell diameter. For multi-tube pass exchangers shells in series can be added if the F-factor is less than 0.7

    11) Temperature cross: When the outlet temp of the cold fluid is higher than the outlet temp of

    hot fluid, it is called the temperature cross. For small exchangers, temperature cross does not have much effect on the type of shells. But for large exchangers shells in series to be used.

    12) Baffle design: Baffle window cut should be between 17% to 35%. Baffle spacing should be

    20% to 100% of shell ID. For no-tube-in-window exchangers, the ratio of window velocity to cross-flow velocity should normally be 2 to 3. For double segmental baffles (for low pres drop service), baffle spacing should not be too small to avoid ineffective shell side flow patterns.

    13) No-tube-in-windows baffle cut design: The baffle cut shall be limited between 15 - 30% of

    shell diameter 14) Baffle cut out of window: The portion of the baffle which is continuous into the window acts

    as a sealing strip in the window to force the fluid into the bundle. Continuous baffles should be considered for pull-through floating heads.

    Code Y, shell inlet at tube channel end

    Code N, shell inlet at tube end

    Flow

    30

    Pitch

    Triangular Pitch

    45

    Pitch

    Rotated Square Pitch

    60

    Pitch

    Rotated Triangular Pitch

    90Pitch

    Square Pitch

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 31 of 87

    12.4 HTRI SHELL SIDE FLOW FRACTIONS This is for shells with single phase fluid flow. The shell flow is broken down into 5 major streams. 1) B-stream : Main cross flow stream through the bundle. B should be at least 60% of the total

    flow for turbulent flow and 40% for laminar flow. If the baffle spacing is too narrow, more flow will be forced into the A, C and E streams, thereby decreasing the heat transfer.

    2) C-stream : Bundle to shell cross flow bypass stream. C should not normally exceed 10%.

    Additional sealing strips can be incorporated to decrease this flow fraction. Although this stream is partially effective for heat transfer, a high C-stream flow fraction, especially for pure cross flow shells ("X"), can lead to a severe delta correction to the mean temp difference

    3) F-stream : Tube pass partition bypass stream. F should not normally exceed 10%.

    Additional seal rods can be incorporated to decrease this flow fraction. Although this stream is partially effective for heat transfer, a high C-stream flow fraction, is not recommended. To block the F-stream flow fraction, program assumes one seal rod of a diameter equal to the tube diameter for each 6 tube rows of cross flow in the exchanger

    4) A-stream : Tube-to-baffle hole leakage stream. A-stream is large in narrow baffle spacing

    where large TEMA clearances apply. However, the A-stream is fairly effective thermally. It will decrease for multi-segmental baffles. Fouling layers might seal this A-stream. The design should be examined by giving a zero tube-to-baffle clearance and the built-up fouling layer thickness for a safe design from a pres drop stand point.

    5) E-stream : Baffle-to-shell leakage stream. E-stream is highly ineffective thermally because

    it does not contact the heat transfer surface; but, since it mixes poorly with the other streams, it can cause distortions of the temp profile. If E-stream is more than 15%, double segmental baffle or other modifications should be tested. If E-stream causes (ST program only) low delta correction factor (< 0.8), corrective action is required.

    F-stream seal rods: Allocate one seal rod of the tube diameter for each 6 rows in cross flow

    in the exchanger Sealing strips: These are metal strip or rod placed between the shell and the bundle which

    has the effect of forcing the bundle bypass C-stream back into the bundle.

    Window

    Baff le

    A

    B

    E

    A

    C

    E

    A A

    FCC

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 32 of 87

    12.5 SHELL SIDE ANNULAR DISTRIBUTOR

    Thermal correction factor "F" = (TUBE) x (BAFFLES) x (F/G) x (HOT/COLD); where TUBE is the uncorrected F-factor based on the no of tube passes, shell style and temp BAFFLES is the correction when there are few baffles. (F/G) is the correction for thermal leakage through longitudinal baffle for TEMA "F","G","H" shells. (HOT/COLD) is the correction for nonconstant overall h.t.coeff due to diff in the h.t.coeff at the hot and cold ends. Effective MTD = (LMTD) x F x (DELTA): where DELTA is the profile distortion due to the E- and C-stream leakage

    12.6 SHELL SIDE HEAT TRANSFER LIMIT If there is spare shell side pres drop available, the shell side coefficient can be increased by various methods: 1) Changing the shell type to "F" or "G" can increase the shell side velocity and h.t.coefficient.

    But the mean temperature difference may increase. 2) Reducing the tube pitch 3) Decreasing the tube size to accommodate more tubes in a smaller shell 4) Considering finned tubes 5) If DELTA is lower than 0.85, adding a shell in series gives best result, or using sealing

    strips might improve the performance

    12.7 TUBE SIDE HEAT TRANSFER LIMIT If there is spare tube side pressure drop available, the tube side coefficient can be increased by various methods: 1) Changing the tube length 2) Decreasing tube diameter 3) When in laminar flow switching the tube side fluid to shell side usually results in a more

    efficient design 4) Increasing the tube pitch, gives less tubes in the given shell ID

    Length

    Clearance

    Slot area

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 33 of 87

    12.8 LIQUID DRIVING HEAD FOR THERMOSIPHON EXCHANGERS 1) For horizontal thermosiphon reboilers, most recirculating type feed systems can be

    designed with kettle type since the height of the outlet piping entering the column is above the liquid level in the column as shown in figure.

    2) For thermosiphon reboiler systems for which the reboiler outlet piping enters the distillation

    column at a height below the liquid level in the trap-out tray as shown in figure the piping should be checked to ensure that the liquid level does not cover the exit nozzle.

    3) For horizontal thermosiphon reboiler designs, the reboiler exit weight fraction should be

    limited to 0.5 to avoid tube wall dry out. 4) For an effective design, most of the available loop pressure drop is used across the

    reboiler. As a rule of thumb, this should be around 60 - 70%. However, the inlet and outlet piping design may change this requirement.

    Liquid Driving Head (Static Head)

    HG

    D F

    B E

    A

    C

    C

    Nozzle pipe

    Main pipe

    Main pipe

    Header pipe

    Vapor+Liquid

    Recirculating Feed System

    Vapor+ Liquid

    Once through Feed System

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 34 of 87

    13. COLUMNS & TOWERS 13.1 GENERAL DESIGN RULES

    1) For ideal mixtures, relative volatility can be taken as the ratio of pure component vapor

    pressures 2) Tower operating pressure is most often determined by the cooling medium in condenser or

    the maximum allowable reboiler temperature to avoid degradation of the process fluid 3) For sequencing columns:

    Perform the easiest separation first (least trays and lowest reflux) If relative volatility or feed composition varies widely, take products off one at time as

    the overhead If the relative volatility of components does vary significantly, remove products in order

    of decreasing volatility If the concentrations of the feed vary significantly but the relative volatility does not,

    remove products in order of decreasing concentration. 4) The three most common types of trays are valve, sieve, and bubble cap. Bubble cap trays

    are typically used when low-turn down is expected or a lower pressure drop than the valve or sieve trays can provide is necessary

    5) Bubble cap trays are used only when a liquid level must be maintained at low turn down ratio; they can be designed for lower pressure drop than either sieve or valve trays.

    6) The optimum Kremser absorption factor is usually in the range of 1.25 to 2.00

    13.2 TRAY COLUMNS/TOWERS 1) The most economic number of trays is usually about twice the minimum number of trays 2) The minimum number of trays is determined with the Fenske-Underwood Equation 3) Typically, 10% more trays than calculated are specified for a tower 4) Tray spacings should be from 18 to 24 (450 to 600 mm), with accessibility in mind 5) Peak tray efficiencies usually occur at linear vapor velocities of 2 ft/s (0.6 m/s) at moderate

    pressures, or 6 ft/s (1.8 m/s) under vacuum conditions. 6) Pressure drop per tray is of the order of 3 of water or 0.1 psi (0.007 bar) 7) Tray efficiencies for distillation of light hydrocarbons and aqueous solutions are usually in

    the range of 60-90% while gas absorption and stripping typically have efficiencies closer to 10-20%

    8) Sieve tray holes are 0.25 to 0.50 in. diameter with the total hole area being about 10% of the total active tray area

    9) Valve trays typically have 1.5 diameter holes each with a lifting cap. 12-14 caps/square foot of tray is a good benchmark. Valve trays usually cost less than sieve trays

    10) The most common weir heights are 2 and 3 (50 to 80 mm) and the weir length is typically 75% of the tray diameter

    11) For towers that are at least 3 ft (0.9 m) in diameter, 4 ft (1.2 m) should be added to the top for vapor release and 6 ft (1.8 m) should be added to the bottom to account for the liquid level and reboiler return

    12) Limit tower heights to 175 ft (53 m) due to wind load and foundation considerations 13) The Length/Diameter ratio of a tower should be no more than 30 and preferably below 20 14) Liquid redistributors are needed every 5-10 tower diameters with pall rings but at least

    every 20 feet (6.1 m). The number of liquid streams should be 3-5 /ft in towers larger than 3 ft dia, and more numerous in smaller towers

    15) A rough estimate of reboiler duty as a function of tower diameter is given by: Q = 0.5 D for pressure distillation Q = 0.3 D for atmospheric distillation Q = 0.15 D for vacuum distillation

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 35 of 87

    Where Q = Reboiler duty (Million Btu/h) D = Tower diameter (ft)

    13.3 REFLUX DRUMS 1) The most economic reflux ratio usually is between 1.2 Rmin and 1.5 Rmin 2) Reflux pumps should be at least 25% over designed 3) Reflux drums are almost always horizontally mounted and designed for a 5 min holdup at

    half of the drum's capacity. A take off pot for second liquid phase such as water in hydrocarbon systems, is sized for a linear velocity of that phase of 0.5 ft/s (0.15 m/s) with minimum diameter of 16 (400 mm)

    13.4 PACKED TOWERS 1) Packed towers almost always have lower pressure drop than comparable tray towers 2) Packing is often retrofitted into existing tray towers to increase capacity or separation 3) For gas flow rates of 500 ft/min (14.2 m/min) use 1 in (2.5 cm) packing, for gas flows of

    2000 ft/min (56.6 m/min) or more, use 2 in (5 cm) packing 4) Ratio of tower diameter to packing diameter should usually be at least 15 5) Due to the possibility of deformation, plastic packing should be limited to an unsupported

    depth of 10-15 ft (3-4 m) while metallic packing can withstand 20-25 ft (6-7.6 m) 6) Liquid distributor should be placed every 5-10 tower diameters (along the length) for pall

    rings and every 20 ft (6.5 m) for other types of random packing 7) For redistribution, there should be 8-12 streams per sq. foot of tower area for tower larger

    than 3 feet in diameter. They should be even more numerous in smaller towers 8) Packed columns should operate near 70% flooding 9) Height Equivalent to Theoretical Stage (HETS) for vapor-liquid contacting is 1.3-1.8 ft (0.4-

    0.56 m) for 1 in pall rings and 2.5-3.0 ft (0.76-0.90 m) for 2 in pall rings

    13.5 DESIGN PRESSURE DROPS

    Service Pressure drop (in H2O/ft packing) Absorbers and Regenerators Non-Foaming Systems 0.25 - 0.40 Moderate Foaming Systems 0.15 - 0.25 Fume Scrubbers Water Absorbent 0.40 - 0.60 Chemical Absorbent 0.25 - 0.40 Atmospheric or Pressure Distillation 0.40 - 0.80 Vacuum Distillation 0.15 - 0.40 Maximum for Any System 1.0

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 36 of 87

    14. COMPRESSORS AND VACUUM EQUIPMENT

    The following chart is used to select the type of compressor:

    1) Fans should be used to raise pressure about 3% (12 or 300 mm water), blowers to raise to less than 2.75 barg (40 psig), and compressors to higher pressures

    2) The theoretical reversible adiabatic power is estimated by:

    [ ]

    aaPP

    TRZmPower1)/( 12

    1

    =

    where: T1 = Inlet temperature; R = gas constant; Z1 = Compressibility; m = molar flow rate

    ( )

    aPPTTCvCpk

    kka

    ==

    =

    )/(/

    /1

    1212

    T2 = Outlet temperature for adiabatic reversible flow

    3) Exit temperatures should not exceed 204C (400F) 4) For diatomic gases (Cp/Cv = 1.4) this corresponds to a compression ratio of about 4 5) Compression ratios should be about the same in each stage for a multistage unit,

    n

    n

    PP

    Ratio/1

    1

    = with n stages.

    6) Efficiencies for reciprocating compressors are:

    - 65% at compression ratios of 1.5 - 75% at compression ratios of 2.0 - 80-85% at compression ratios between 3 and 6

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 37 of 87

    7) Efficiencies of large centrifugal compressors handling 2.8 to 47 m/s (6000-100,000 acfm)

    at suction is about 76-78% 8) Flash gas compressors typically have an overall compressor ratio in the range 5 to 10 9) For compressors, the brake horsepower per stage can be determined from

    ( ) ( )

    =

    11

    0857.0

    111 k

    k

    s

    dsgkk

    skav PP

    kk

    ETQ

    ZZBHP

    Where BHP = Brake horsepower per stage Qg = Volume of gas (MMscfd) Ts = Suction temperature (R) Zs = Suction compressibility factor Zd = Discharge compressibility factor Zav = (Zs + Zd) / 2 E = Efficiency % High speed reciprocating units use 70% Low speed reciprocating units use 78% Centrifugal units - use 75% K = Ratio of specific heat, Cp/Cv Ps = Suction pressure of stage (psia) Pd = Discharge pressure of stage (psia)

    14.1 VACUUM PUMPS

    1) Reciprocating piston vacuum pumps are generally capable of vacuum to 1 torr (1 mmHg

    absolute) 2) Rotary piston types can achieve vacuums of 0.001 torr 3) Single stage Jet ejectors are capable of vacuums up to 100 torr, 2-stages to 10 torr, 3-

    stages to 1 torr, and 5-stages to 0.05 torr 4) A three stage ejector requires about 100 lb steam/lb air (100 kg steam/kg air) to maintain a

    pressure of 1 torr 5) Air leakage into vacuum equipment can be approximated as follows:

    3/2VkLeakage =

    Where k = 0.20 for P >90 torr, 0.08 for 3 < P < 20 torr, and 0.025 for P < 1 torr

    V = equipment volume (ft) Leakage = air leakage into equipment (lb/h)

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 38 of 87

    15. SAFETY SYSTEM & PSV DESIGN 15.1 SAFETY SYSTEM CONFIGURATION

    1) For direct discharge of fluids to atmosphere, they should be in the vapor state, below their

    auto ignition temperature, and should meet one of the following requirements:- Flammable vapors of MW less than 28.9 (MW of air). Flammable vapors heavier than air with MW less than 70 but with minimum discharge

    velocity of 500 fps (152 m/s), based on maximum capacity of the relief valve Vapors of any MW that are non-flammable, non-toxic and non-condensable

    2) In all other cases relieved fluids should be disposed to a flare system. 3) Boilers having more than 47 m of water heating surface or electric boilers having a power

    input of more than 500 kW shall have 2 or more PSV. 4) For electric boilers the minimum relieving capacity shall be 1.6 kg/hr/kW input 5) For Boilers, if additional PSV are used the highest pressure setting shall not exceed the

    MAWP by more than 3%. When multiple PSV are installed, the difference between the highest and lowest set pressure should not be greater than 10% of the highest set pressure.

    6) For Pressure vessels, if additional PSV are used the highest pressure setting shall not exceed 105% of MAWP. For multiple PSV, one of which is installed for fire exposure only, this particular valve may be set at a pressure not exceeding 110% of MAWP

    7) Fire exposure protection of vessels by water spray @ 0.05 - 0.2 gpm/ft of total vessel area. Fire exposure is considered for a wetted area up to 25 ft (7.62 m) from grade. Average or normal liquid level to be considered for vessels, High liquid level for columns, surge drums and KO drums. 50% of storage tank height or 25 ft (7.62 m) from grade, which ever is higher.

    8) For flare fire relief load, consider plot area between 2000-5000 ft (186-465 m). Use 2500 ft (232 m) for a paved drained surface in a plant where NFPA required fire fighting equipment is available.

    9) If fire proofing insulation is not provided, environmental factor (F) should be = 1.0

    15.2 SAFETY VALVE BACK PRESSURE 1) Super imposed back pressure = pressure at PSV discharge before valve opening 2) Builtup back pressure = pressure at PSV discharge header after valve opening. 3) Conventional PSV shall be used when the superimposed back pressure varies over a

    range not exceeding 10% of the set pressure (gauge). However the performance of PSV at builtup back pressure to be studied by the vendor before selecting the PSV

    4) Balanced type PSV can be used for >10% superimposed back pressure. However when builtup back pressure exceeds 30-50% of set pressure, capacity of PSV for vapors and gases starts to fall below the theoretical capacity. With liquids, the capacity reduction starts at 15% of set pressure. The fall in capacity depends on overpressure, type and make of PSV.

    5) Pilot operated relief valves are used when operating pressure is very close to set pressure or when set pressure is below 10-15 psig (0.7 1.0 barg)

    15.3 SAFETY VALVE RELIEF LOAD CALCULATION PSVs relief load can be calculated by considering the following major failure scenarios:

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 39 of 87

    1) Blocked outlet 2) Gas blow by case 3) Inadvertent valve opening 4) Reflux failure 5) Tube rupture 6) Fire case 7) Reverse flow 8) Thermal relief case.

    15.3.1 Blocked Outlet

    Blocked outlet case can occur when the control valves at the outlet of the vessel close at the same time due to the stoppage of instrument air supply or plant shut down. The relief quantity shall be the design flow rate to the vessel.

    15.3.2 Fire Case The amount of heat absorbed by a vessel open to fire is markedly affected by the type of fuel feeding the fire. The following equivalent formulas are used to evaluate the condition where there are prompt firefighting efforts and drainage of flammable materials away from the vessels are available: 18.021000 = AFq 82.021000 AFQ = Where adequate drainage & firefighting equipment do not exist, the following equation should be used: 82.034500 AFQ =

    Where q = Average unit heat absorption (Btu/h/ft of wetted surface) Q = Total heat absorption (input) to the wetted surface (Btu/h) F = Environmental factor (Values for various type of installation are given in

    Table 5 in API 521 page 25) A = Total wetted surface (ft)

    The discharge area for pressure relief devices on vessels containing super critical fluids, gases or vapors exposed to open fires can be estimated by using the following equation.

    1

    ''PAFA =

    = 6506.01

    25.11 )(1406.0'

    TTT

    KCF w

    D

    The relief load can calculated directly, in pounds per hour.

    = 1506.1

    1

    25.11

    1)(

    '1406.0T

    TTAPMW w

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 40 of 87

    Where A = Effective discharge area of the valve (in) A = Exposed surface area of the vessel (ft) F = PSV Factor (= 0.01 min. or 0.045 if value is not known) P1 = Upstream relieving pressure (psia) P1 = PSV set pressure + allowable over pressure + atmospheric pressure C = Cp/Cv KD = Coefficient of discharge (=0.975 max) M = Molecular weight of the gas TW = Vessel wall temperature (R) (for CS vessels = 1100F) T1 = Gas temperature (R) at the upstream relieving pressure, determined from

    the following relation. nn TPPT = )/( 11

    Where Pn = Normal operating gas pressure (psia) Tn = Normal operating gas temperature (R)

    Air Coolers For air coolers heat absorption equation becomes 0.121000 AFQ = Total bare tube area to be considered instead of finned area, since fins are burned out in the first few minutes of fire. Water spray nozzles are some times mounted below the tubes in case of fire. API 520 recommends a minimum of 0.05 - 0.2 gpm/ft water spray rate.

    15.3.3 Inadvertent Valve Opening

    116

    =PXYFN

    WCP

    V

    KK XF

    XY

    =3

    1

    Where W = Mass to be relieved (kg/h)

    6N = Constant (27) PF = Geometric factor Y = Downstream pressure (bara) X = Ratio of pressure drop P1 = Upstream pressure (bara)

    1 = Upstream gas density (kg/m)

    15.3.4 Thermal Expansion

    As per API RP 521, the relieving capacity requirements for hydraulic expansion cases will be very small as relieving fluid will be liquid. Therefore X 1 nominal pipe size relief valve is commonly used

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 41 of 87

    Cold fluid blocked in and continuous heat input from hot fluid. Two conditions can occur: Cold fluid remains liquid and expands cQBWL /= Cold fluid vaporizes

    LQTTTT

    Wav

    bpV /)(

    )(

    1

    1

    =

    Where WL, Wv = weight of liquid or vapor relieved (lb/h) Q = Normal exchanger duty (Btu/h) L = Latent heat of vaporization at relieving conditions (Btu/lb) T1 = Hot side inlet temperature (F) Tbp = Cold side boiling temperature at relieving pressure (F) Tav = Average of inlet and outlet temperature of cold side during normal

    operation (F) c = Specific heat of cold medium (Btu/lb F ) B = Coefficient of expansion of cold medium (1/F)

    Fluid API Expansion Coef. Fluid API Expansion Coef.Oil 3 to 34.9 0.0004 Oil 79 to 88.9 0.0008 Oil 35 to 50.9 0.0005 Oil 89 to 93.9 0.00085 Oil 51 to 63.9 0.0006 Oil =>94 0.0009 Oil 64 to 78.9 0.0007 Water 0.0001

    15.3.5 Tube failure and leakage Tube failure is considered a viable contingency when the design pressure of the low pressure side is less than 2/3 rd (=67%) of design pressure of high pressure side. However, if the high pressure side of the exchanger operates at 1000 psig (69 barg) or more and contains a vapor or liquid that can flash or result in vaporization of liquid on the low pressure side, complete tube failure should be considered, regardless of the pressure differential. Install a PSV, if the piping and downstream equipment on the low pressure side do not have the capacity to handle material leaked from high pressure side without exceeding 110% of the equipment design pressure. A tube failure is considered to be a sharp break in one tube. The high pressure fluid flows through both openings, which is equal to twice the cross section area of a single tube. Following equation can be used to calculate the flow from high to low pressure sides. = PCdWL (256.12

    2

    Where WL = Relieving rate. (kg/h)

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 42 of 87

    d = Tube inside diameter (mm) C = Orifice coefficient P = Differential pressure (Operating pressure of high pressure side (bara) -

    Relieving pressure of PSV (1.1 times set pressure of PSV) (bara) = Density of high pressure fluid (kg/m)

    For a discharge coef. of 0.7, Cp/Cv=1.33 and twice the cross sectional area of one tube

    Sg

    PPdqL

    2128.41

    =

    TZ

    MPdqV = 1

    2385

    Where qL, qv = Quantity of liquid (gpm) or vapour (lb/h) d = tube inside diameter (inch) M = MW P1 = normal high pressure side (psig) Sg = specific gravity P2 = 1.1 times low pressure design pressure (psig) Z = compressibility factor T = vapor temperature (R) at operating conditions

    If the calculated discharge exceeds the normal total flow in the high pressure side, the latter flow should be used. Possible flash of liquid to vapor shall be taken into account due to both pressure reduction and mixing of a volatile fluid with a hot fluid. Valves on low pressure side provided only for isolation may be assumed fully open, control valves in a position equivalent to the minimum normal flow unless the valve could automatically close due to the emergency situation.

    15.4 SETTLE-OUT PRESSURE

    In high pressure oil & gas handling facilities the compressor suction KO drum has to be designed based on settle-out pressure. In case of compressor trip the suction and discharge shutdown valves will close and the gas from high pressure discharge side will flow through the recycle control valve to the suction side. A new settle-out condition is reached. The settle-out pressure is calculated by the following formula:

    21

    2211 )()(VV

    VPVPPs +

    +=

    Where Ps = Settle-out pressure (barg) P1 = Suction side pressure before settle-out (barg) P2 = Discharge side pressure before settle-out (barg) V1 = Suction side volume (including KO drum, piping, etc) (m) V2 = Discharge side volume (including KO drum, piping, etc) (m)

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 43 of 87

    16. PIPE SIZING

    The major criteria for line sizing are velocity and pressure drop 1) Liquid lines should be sized for a velocity of (5+D/3) ft/s and a pressure drop of 2.0 psi/100

    ft of pipe at pump discharge. At the pump suction, size for (1.3+D/6) ft/s and a pressure drop of 0.4 psi/100 ft of pipe. **D = pipe diameter (inch)

    2) Steam or gas lines can be sized for 20D ft/s and pressure drops of 0.5 psi/100 ft of pipe 3) Limits on superheated, dry steam or gas line should be 61 m/s (200 ft/s) and a pressure

    drop of 0.1 bar/100 m (0.5 psi/100 ft) of pipe. Saturated steam lines should be limited to 37 m/s (120 ft/s) to avoid erosion.

    4) For turbulent flow in commercial steel pipes, use the following:

    =

    DMP

    20000

    2.0

    Where:P = Frictional pressure drop (psi/100 ft) M = Mass flow (lb/h) = Viscosity (cP) = Density (lb/ft) D = ID of pipe (inch) For smooth heat exchanger steel tubes replace 20000 with 23000

    5) For two phase flow, an estimate often used is Lockhart and Martinelli. First, the pressure

    drops are calculated as if each phase exist alone in the pipe, then

    5.0

    =G

    L

    PP

    X

    Now the total pressure drop can be calculated by one of the following:

    LG

    L

    GGLLTOTAL

    YXY

    XXYWhere

    PYorPYP

    =

    ++=

    =

    2

    68.078.1 65.05.126.4

    6) Control valves require at least 0.7 bar (10 psi) pressure drop for sufficient control 7) Flange ratings include 10, 20, 40, 103, and 175 bar (150, 300, 600, 1500, and 2500 psig) 8) Globe valves are most commonly used for gases and when tight shutoff is required. Gate

    valves are common for most other services. 9) Screwed fitting are generally used for line sizes 2 inches and smaller. Larger connections

    should utilize flanges or welding to eliminate leakage. 10) Pipe Schedule Number = 1000 P/S (approximate) where P is the internal pressure rating in

    psig and S is the allowable working stress of the material is psi. Schedule 40 is the most common.

    11) About 15% margin in flow should be considered in general for line sizing 12) For fuel oil and heating oil, lines to be sized for 25% margin on flow 13) Pump suction lines should be checked for NPSH requirement. More critical if the liquid is at

    its saturation temperature

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 44 of 87

    14) 100% margin is desirable for pump suction lines 15) Pump suction line is generally one (or) two sizes higher than the discharge line 16) Liquid overflow line size shall be at least one size higher than the largest liquid inlet line to

    that equipment 17) Most of the time, the line size is same as that of the vessel nozzle 18) For pumps and compressors, the connected pipeline (inlet and outlet) sizes are generally

    higher than those of the equipments 19) Safety valve inlet line sizing is based on a pressure drop corresponding to about 3% of the

    set pressure (in absolute) 20) Minimum velocity of 1 m/sec is preferred for water services and liquids carrying suspended

    solid 21) The pressure downstream of PSV, shall not exceed 10% of the PSV set pressure for

    conventional safety valves. For balanced type valves it is preferable to limit this pressure to 40% of the set pressure

    22) For free draining line, sizing should be less than 1 m/sec velocity

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 45 of 87

    Recommended Velocity and Pressure Drop for Process Liquids (not Water)

    SL. NO. Type of Service Recommended Velocity (m/s) Max. Allowable Pressure

    drop (bar/km) 1. General recommendation 1.5 - 4.5 9.0 2. Laminar flow 1.2 - 1.5 ---

    3.

    Turbulent flow Liquid density (kg/m)

    320 800 1600

    3.0 - 4.5 1.8 - 3.0 1.5 - 2.5

    --- --- ---

    4. Pump suction

    Boiling liquid Non-boiling liquid

    0.6 - 1.8 1.2 - 2.4

    1.1 2.2

    5.

    Pump discharge (m/h) < 57

    57 - 159 > 159

    1.8 - 2.4 2.4 - 3.0 3.0 - 4.5

    13.5 9.0 4.5

    6. Liquid flow on gravity 0.9 2.4 0.9 7. Vessel / Column Inlet 1.2 - 1.8 --- 8. Outlet (+vortex breaker) 1.0 0.9 9. Outlet to reboilers 0.3 - 1.2 0.33

    10. Liquid from total condenser 0.9 - 1.8 1.1 11. Liquid to/from chillers 1.2 - 1.8 --- 12. Refrigerant liquid 0.6 - 1.2 0.9 13. Self venting lines (max velocity) 0.18 ---

    NOTE :

    The velocity higher than 3.0 m/sec for any line should be used only after due consideration for velocity limitations.

    Recommended Velocity and Pressure Drop for Steam Services

    Type of Service Recommended Velocity (m/s) Max. Allowable Pressure

    Drop (bar/km) Steam Headers : Saturated

    Superheated Steam Pressure 0 - 3.5 barg

    3.5 10 barg 10 20 barg 20 barg and above

    60 (max) 75 (max)

    0.57 1.1 2.2 3.4

    Process steam piping (saturated) 30 - 50 --- Boiler steam piping (superheated) 35 - 100 6.8 Steam lines to Turbine (superheated) 35 - 100 6.8 Steam lines to Turbine exhaust header --- 3.4 Turbine exhaust to header ( > atm) --- 1.1 Driving steam to pumps & recip. equip. 3.8 - 4.6 ---

  • Doc. N: WIP-SIPS-PCS-001

    Rev.: A Date: 08/02/08

    WORK IMPROVEMENT PLAN PROCESS DESIGN GUIDELINES

    Page 46 of 87

    Recommended Velocity and Pressure Drop for Water (Condensate)

    SL. NO. Type of Service Recommended Velocity (m/s) Max. Allowable Pressure

    drop (bar/km)

    1.

    General service

    Pipe diameter < 1 2 4 6 8 10 12 16

    20 and above

    0.6 - 5.0

    0.6 - 0.9 0.9 - 1.3 1.5 - 2.0 2.0 - 2.7 2.4 - 3.0 3.0 - 3.6 3.0 - 4.3 3.0 - 4.6 3.0 - 4.8

    4.5

    4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5

    2. Pump suction 1.2 - 2.1 --- 3. Pump discharge 1.5 - 3.0 --- 4. Boiler feed water 2.4 - 4.5 --- 5. Condensate from condenser 0.9 - 1.5 --- 6. Process water 0.6 - 1.5 5.5

    7. Cooling water (once thro, brackish/sea) 3.6 - 4.9 4.5

    8. Cooling water (circulating, clean) 1.5 - 3.0 5.0

    9. Water drain lines (gravity flow) 1.2 - 2.1 ---

    Recommended maximum Velocity for Special Liquids or Materials

    Sl. No. Type of Service Recommended

    Maximum Velocity (m/s)

    1.

    Carbon steel pipe with

    Phenolic water Concentrated H2SO4 Salt water Caustic solution (low temp.)

    0.9 1.2 1.8 1.2

    2. Stainless steel pipe with CO2 -rich amine liquid 3.0

    3. Cement pipe with salt water 4.5 4. Coal Tar enamel lined pipe with salt water 4.5

    5. Plastic pipe or rubber lined pipe with

    Liquid in general Liquid with suspended solids

    3.0

    0.9 (min. velocity)